Professional Documents
Culture Documents
1
CONTENT PAGE
1. Project background
3. Development Progress
5. Next step
2
1. Project Description
1.1. Layout of the development
1.1.1. The proposed site is located at Lot 28532 to Lot 28580 and part of government
Land, Jalan Sri Mawar 2, Mukim Setul, Seremban District, Negeri Sembilan Darul
Khusus with an area of 2.71 acres.
The total number of lots under this development is 40 lots of double storey terrace
houses. The components of the proposed development on the site are as shown
in the table below:
Land Use Unit Area (acres) %
Double Storey Terrace House 40 1.219 44.8
Compact Electrical Substation 1 0.008 0.3
Sewerage Treatment Plan 1 0.114 4.2
Green Area - 0.336 12.4
Roads - 1.042 38.3
Total Land Use 42 2.719 100.0
The building plan and landscape plan have been approved from Majlis
Perbandaran Nilai (MPN) earlier. Jabatan Bomba dan penyelamat has endorsed
3
the drawings on February 2017. The resubmission on the building plan is
required as the internal layout of the house has been revised. The initiative was
taken place to improve the quality of the saleable area.
3. Development progress
3.1. Current progress
3.1.1. Revised Building Plan Approval
3.1.1.1. Approved. Dated 27th Feb 2023.
4
Bill No.2+3 Bill No.5
Bill No.1 Bill No.4 Vol 1- Main Building Works Vol 2- M&E Works
Tenderers Main Building Works Prime Cost & Corrected Tender Sum
Preliminaries Ext & Infrastructure & Infrastructure Works (Refer M&E Tender Report for Analysis)
(Type A & B) Provisional Sum
(A) (B) (C) (D) (E) = (A) + (B) + (C) + (D) (F) (G) = (E) + (F)
Consultant’s
517,480.57 BASE 7,514,950.05 BASE 2,037,661.28 BASE 797,000.00 BASE 10,867,091.90 BASE 934,360.00 BASE 11,801,451.90 BASE
Estimate
Tenderer B 372,500.00 -28% 7,621,988.10 +1% 2,190,735.10 +8% 782,000.00 -2% 10,967,223.20 +1% 1,637,930.00 +75% 12,605,153.20 +7%
Group A
Tenderer A 960,000.00 +86% 7,472,478.06 -1% 2,562,105.12 +26% 792,000.00 -1% 11,786,583.18 +8% 1,133,940.40 +21% 12,920,523.58 +9%
Tenderer C 726,000.00 +40% 8,804,298.90 +17% 2,465,333.70 +21% 802,000.00 +1% 12,797,632.60 +18% 1,103,664.00 +18% 13,901,296.60 +18%
Group B
Tenderer D 651,868.00 +26% 8,888,751.40 +18% 2,378,050.10 +17% 807,000.00 +1% 12,725,669.50 +17% 1,335,702.00 +43% 14,061,371.50 +19%
Tenderer E 1,544,358.50 +198% 10,017,588.50 +33% 2,702,600.90 +33% 807,000.00 +1% 15,071,547.90 +39% 1,314,086.40 +41% 16,385,634.30 +30%
Group C
Tenderer F 1,164,285.00 +125% 10,987,727.15 +46% 2,743,224.12 +35% 792,000.00 -1% 15,687,236.27 +44% 1,840,128.50 +97% 17,527,364.77 +49%
Table 2: The breakdown of corrected tender sum for Volume 1- Main Building Works & Infrastructure and Volume 2- M&E Works.
Tenderer B - Their prices for Main Building are very competitive, being 1% variance from QS Estimate. Their Preliminaries appear low (28%
lower than QS Estimate) while their prices for Infrastructure Works appears slightly (+8%) higher than QS Estimate. Their prices for M&E works
are very high being 75% higher than M&E Engineer’s Estimate.
Tenderer A - Their prices for Main Building are very competitive, being 1% variance from QS Estimate. Their Preliminaries, Infrastructure
Works and M&E Works are high, being 86%, 26% and 21% higher than QS/M&E Estimate respectively.
Tenderer C & D - Both tender prices for Main Building Works are very close, being at RM8.8M or 17% and 18% higher than QS Estimate.
Their Preliminaries are 40% and 26% higher than QS Estimate respectively. As for Infrastructure Works, they are varying between 17% and
21% higher than QS Estimate. Their M&E Prices are 18% and 43% higher than M&E Engineer Estimate.
Tenderer E & F - Their tender sum is significantly higher than the QS Estimate and other available tenders by nearly RM5M. Their pricing for
each bill is generally 30% higher compared to QS Estimate. It will be prudent to exclude Tenderer E & F's tender from consideration and focus
on the remaining tenders that are more in line with the QS Estimate and other available tenders.
5
From the summary above, the tender clarification to be proceed with 4 lowers tender sum in a range from RM12.6M to RM14M.
Tenderer A - Their revised tender at RM 12,578,353.22 is the lowest tender. Their revised tender is RM 342,170.36 lower than their original
tender sum (RM 12,920,523.58). Their revised tender is RM776,901.32 or 7% higher than Consultant Estimate and 20% than PTT budget.
Tenderer B - Their revised tender at RM 13,193,710.70 is the second lowest tender. Their revised tender is RM 588,557.50 higher than their
original tender sum (RM 12,605,153.20). Tenderer B did not omit hoarding and gate (amounting to RM103,050) in their revised tender despite it
was highlighted in the tender questionnaire that the hoarding and gate had been erected on site. Their revised tender sum exclude hoarding and
gate is at RM 13,090,660.70 is RM 512,307.48 higher than the lowest tender and RM 1,289,208.80 higher than Consultant Estimate and
RM 2,565,665.70 than PTT budget.
Tenderer C - Their revised tender prices at RM 13,507,762.20 is the second higher tender. Their revised tender is RM 503,071.50 lower than their
original tender sum (RM 13,901,296.60). Their revised tender is 14% higher than Consultant Estimate and 28% than PTT budget.
Tenderer D - Their revised tender prices at RM 13,558,300.00 is the higher tender. Their revised tender is RM 399,534.40 lower than their original
tender sum (RM 14,061,371.50). Their revised tender is 15% higher than Consultant Estimate and 29% than PTT budget.
7
3.1.3.3 Completed Building Work Quality
The visit to the existing project on 12th May 2023 is one of the Tender
Valuation processes to assess the quality of work by the team on
completed project by Tenderers.
Tenderer A Tenderer B Tenderer C Tenderer D
No Architectural Score Scale Score Scale Score Scale Score Scale
Evaluation Criteria
8
3.2. Sale and Marketing and APDL permit
3.2.1. The Developer License has been approved by KPKT.
3.2.2. The Advertisement Permit (AP) with condition has been approved by KPKT on
10th May 2023.
3.2.3. The AP approval with condition is to open HDA account and to deposited
RM533,160 into the account. We are in the midst to open HDA account. Upon
account opening, will resubmit back to KPKT for final approval. Targeted final
AP approval by 15th June 2023.
3.2.4. For bank end financing, we have submitted application to 6 end-financier
(Maybank Berhad, Hong Leong Bank Berhad, Public Bank Berhad, Bank
Simpanan Nasional, Affin Bank and RHB Bank).
3.2.5. MBB, HLBB, PBB, BSN & RHB are required AP for their final approval. Besides,
9
AFBB is pending valuation on the development.
3.2.6. Status of Marketing material
5. Next step
5.1 PTTD to negotiate with tenderers to meets the PT estimate before award.
5.4 To get at least 30% of SPA signing from purchaser before start construction work.
5.4 To continue with dealing with authority on STP and Taman’s naming.
10
APPENDIX 1
11
CADANGAN PEMBANGUNAN YANG MENGANDUNGI 40 UNIT RUMAH
TERES DUA TINGKAT :
A) 36 UNIT JENIS A 20' X 60'
B) 4 UNIT JENIS B 20' X 55' - 60'
C) 1 UNIT PENCAWANG ELEKTRIK PADAT 23' X 13'
D) 1 UNIT LOJI KUMBAHAN
DI ATAS LOT 33079 HINGGA 33120 DAN SEBAHAGIAN TANAH
KERAJAAN, TAMAN SERI MAWAR, MUKIM SETUL (BANDAR BARU
MANTIN), DAERAH SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS
UNTUK TETUAN PTT DEVELOPMENT SDN. BHD.( DAHULU DIKENALI
SEBAGAI HOOVER BUILDERS SDN. BHD.)
CONTRACT : VOLUME 2 OF 2
FOR SUPPLY, DELIVERY, INSTALLATION,TESTING, COMMISSIONING
AND MAINTENANCE OF MECHANICAL & ELECTRICAL WORKS
EMPLOYER ARCHITECT
M&E ENGINEERS
CT PERUNDING
28-2, JALAN RAHANG JAYA 1,
PUSAT PERNIAGAAN RAHANG JAYA
70100 SEREMBAN, N.S.D.K.
TEL : 06-765 6237 FAX : 06-679 1954
MAY 2023
TABLE OF CONTENTS
1.0 PREAMBLE
1.1 Tender Clarification No.1
1.2 Addendum No.1
APPENDICES
Appendix A Comparison of Tender Price
All Four (4) tender documents are examined for completeness in terms of their offers and
the findings are summarized as follows:-
Tenderer ‘B’ and ‘D’ didnot submitted the Schedule of Unit Rate as requested by the
Tender.
All the tenderers have submitted the Schedule of Technical Data as requested by the
Tender Document except Tenderer ‘D’
The tender of Tenderer ‘A’ with a tender price of RM 1,111,905.00 is the second
lowest of the Four Tenders received.There is a decrease of Tender price of RM30,195.00
compare with Original Tender Prices The following were noted in the Tender:
Description Remarks
Items are found to be high:-
• 2.0 – Electrical Works Tenderer to review and revised the
• 4.0 Street Lighting & Landscape Tender Price.
Lighting Works
3.3.2 Technical
Tenderer ‘A’ has submitted the Schedule of Technical Data as requested by the Tender.
The tender of Tenderer ‘D’ with a tender price of RM 1,277,628.00 is the third highest of
the Four Tenders received. There is a decrease of Tender price of RM58,074.00
compare with Original Tender Prices. The following were noted in the Tender:
Description Remarks
Tenderer did not submit the details of the Tenderer required to submit the
prices details of Revised Tender Price.
3.5.2 Technical
The Schedule of Technical Data submitted are not submitted. They should be requested to
submit the schedule.
4.0 Street Lighting & Landscape Lighting Works 175,000.00 201,773.00 178,200.00 212,316.00 207,042.00
4.1 Landscape Lighting 25,000.00 22,539.00 148,300.00 22,800.00 39,457.00
4.2 Street Lighting 150,000.00 179,234.00 29,900.00 189,516.00 167,585.00
5.0 Internal Cold Water Plumbing Work 192,000.00 216,964.00 248,000.00 230,400.00 237,600.00
5.1 Double Storey Terrace House Intermediate Type A/B (36 Unit)172,800.00 195,267.60 223,200.00 207,360.00 213,840.00
5.2 Double Storey Terrace House Corner Type A/B (4 Unit) 19,200.00 21,696.40 24,800.00 23,040.00 23,760.00
6.0 Internal Sanitary Plumbing Work 160,000.00 185,320.00 76,000.00 228,000.00 202,400.00
6.1 Double Storey Terrace House Intermediate Type A/B (36 Unit)144,000.00 166,788.00 68,400.00 205,200.00 182,160.00
6.2 Double Storey Terrace House Corner Type A/B (4 Unit) 16,000.00 18,532.00 7,600.00 22,800.00 20,240.00
1,103,664.00
Overall Discount -70,152.00
SOP-1
SCHEDULE OF PRICE
SOP-3
SCHEDULE OF PRICE
SOP-5
SCHEDULE OF PRICE
3.5 To supply and install concrete pole to TM requirement 7 No. 1,567.50 10,972.50 800.00 5,600.00
3.6 Testing and Commissioning of the whole system Lump Sum 3,080.00 3,500.00
3.7 Any other items not mentioned above but may be
necessary in order to implement and complete the
complete telephone system
a)
b)
Sub-total to be carried forward to Page SOP-1 48,367.00 30,950.00 0.00 0.00
SOP-1
SCHEDULE OF PRICE
SOP-7
SCHEDULE OF PRICE
SOP-9
SCHEDULE OF PRICE
SOP-11
APPENDIX B : COMPARISON OF TENDER TECHNICAL OF DATA
Tenderer 'A' Tenderer 'B' Tenderer 'C' Tenderer 'D' Tenderer 'E' Tenderer 'F'
Item Description Unit Specification Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer
e) Gauge/Pressure Rating
e) Type/Model Round
3) Stop Cock
a) Manufacturer City Gkent City City/Eq To comply
Gkent
GKM
b) Country of manufacture China Local
e) Type/Model HD T Handle
TLV-1 CT
APPENDIX B : COMPARISON OF TENDER TECHNICAL OF DATA
Tenderer 'A' Tenderer 'B' Tenderer 'C' Tenderer 'D' Tenderer 'E' Tenderer 'F'
Item Description Unit Specification Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer
4) Ball Valve
a) Manufacturer City City/GKent City City/Eq To comply
Gkent
GKM
b) Country of manufacture Malaysia Local
e) Type/Model HD
d) Type/model 20mm-25mm
f) grade
1 UPVC Soil Pipe & Fittings to BS 4514 Cew Sin SAE SAE South Asia/ To comply
a) Manufacturer Bina Plastic Bina Plastic/EQ
South Asia
Excel
Exact
b) Country of manufacture Malaysia Local
e) Working pressure
2 UPVC waste Pipe & Fittings to BS 5355 Cew Sin SAE SAE South Asia/ To comply
a) Manufacturer Bina Plastic Bina Plastic/EQ
South Asia
Excel
Exact
b) Country of manufacture Malaysai Local
TLV-2 CT
APPENDIX B : COMPARISON OF TENDER TECHNICAL OF DATA
Tenderer 'A' Tenderer 'B' Tenderer 'C' Tenderer 'D' Tenderer 'E' Tenderer 'F'
Item Description Unit Specification Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer
c) Local Agent Open Market
e) Working pressure
3 UPVC Underground Soil Pipe & Fittings
to BS 4660 (Brown Pipe) Cew Sin SAE SAE South Asia/ To comply
a) Manufacturer Bina Plastic Bina Plastic/EQ
South Asia
Excel
Exact
b) Country of manufacture Malaysia Local
e) Working pressure
e) Working pressure
5 Vent Cowl
a) Manufacturer Cew Sin SAE SAE South Asia/ To comply
Bina Plastic Bina Plastic/EQ
South Asia
Excel
Exact
b) Country of manufacture Malaysia Local
6 Floor Trap
a) Manufacturer Cew Sin SAE South Asia/ To comply
Bina Plastic Bina Plastic/EQ
South Asia
Excel
Exact
Tenderer 'A' Tenderer 'B' Tenderer 'C' Tenderer 'D' Tenderer 'E' Tenderer 'F'
Item Description Unit Specification Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer
7 Gully Trap
a) Manufacturer SGW To comply
c) Local Agent
d) Type/model
150/150 mm
e) Material of body
SGW
8 Manholes Covers
a) Manufacturer ACI LYE ACI ACI/JCI/EQ To comply
JCI
Cast Iron Products
b) Country of manufacture
c) Local Agent
d) Type/model Light Duty
e) Material of body Cast Iron
TLV-4 CT
APPENDIX B : COMPARISON OF TENDER TECHNICAL OF DATA
Tenderer 'A' Tenderer 'B' Tenderer 'C' Tenderer 'D' Tenderer 'E' Tenderer 'F'
Item Description Unit Specification Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer
LOW VOLTAGE ELECTRICAL SYSTEM
1.0 LV Sub Switchboard/Distribution Board
a) Manufacturer EPS/ TERASAKI Federal SRS To comply
b) XLPE Insulated Armoured Cables Mega Mega Southern Cables Mega/EQ To comply
Manufacturer Thorn
Leader Cables
Power Cable
Universal Cables
Southern Cables
TLV-5 CT
APPENDIX B : COMPARISON OF TENDER TECHNICAL OF DATA
Tenderer 'A' Tenderer 'B' Tenderer 'C' Tenderer 'D' Tenderer 'E' Tenderer 'F'
Item Description Unit Specification Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer
5.0 CABLES INSTALLATION ACCESSORIES
b) UPVC. Conduit PVC Link PVC Link Wireman PVC Link/EQ To comply
TND Plastic
h) Cable Clamps
a) 13A Switch Socket Outlet Flush Mounted MK/Schneider Schneider/Vivace Schneider Schneider/EQ To comply
TLV-6 CT
APPENDIX B : COMPARISON OF TENDER TECHNICAL OF DATA
Tenderer 'A' Tenderer 'B' Tenderer 'C' Tenderer 'D' Tenderer 'E' Tenderer 'F'
Item Description Unit Specification Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer
8.0 LIGHT FITTINGS
c) Internal General Purpose Telephone Cable Southern Cable Southern Cable Southern Cable Southern/EQ To comply
Uniphone
Universal Cables
TLV-7 CT
CADANGAN PEMBANGUNAN PERUMAHAN YANG MENGANDUNGI:
(A) 36 UNIT 20’ X 60’ RUMAH TERES 2 TINGKAT JENIS A (B) 4 UNIT 20’ X 55’-60’ RUMAH TERES 2 TINGKAT JENIS B (C) 1
UNIT 23’ X 13’ PENCAWANG ELEKTRIK PADAT (D) 1 UNIT LOJI KUMBAHAN DI ATAS LOT 33079 HINGGA 33120 DAN
SEBAHAGIAN TANAH KERAJAAN, TAMAN SERI MAWAR, BANDAR BARU MANTIN, MUKIM SETUL, DAERAH SEREMBAN,
NEGERI SEMBILAN DARUL KHUSUS. UNTUK TETUAN PTT DEVELOPMENT SDN. BHD. (DAHULU DIKENALI SEBAGAI
HOOVER BUILDERS SDN BHD)
CONFIDENTIAL
REVISED TENDER EVALUATION REPORT
(392238-X)
3 – 2B, JALAN PJU 1/3F,
SUNWAYMAS COMMERCIAL CENTRE,
47301 PETALING JAYA
SELANGOR DARUL EHSAN, MALAYSIA TEL: +603
7805 1318 FAX: +603 7887 1618
Email: lai@mkscqs.com / waiming@mkscqs.com
CONTENT PAGE
EXECUTIVE SUMMARY 1
1.0 INTRODUCTION 2
2.0 TENDER CLARIFICATION MEETING & REVISED TENDER SUBMISSION 2
3.0 REVISED TENDER RESULTS 2
4.0 COMPARISON OF REVISED TENDER AGAINST ORIGINALTENDER AND 3
GENERAL OBSERVATIONS
5.0 COMPARISON OF REVISED TENDER AGAINST CONSULTANT ESTIMATE 5
EXECUTIVE SUMMARY
From the tender clarifications, of the four tenderers, three had reverted with price reductions of RM300k to
RM500k while one of them (Tender B) increased their price by RM600k instead.
From the revised prices in Table 3.1, Tender C & D will be higher than the lowest tender (Tender A) by nearly
RM1M or 8%. From commercial point of view, it will be prudent to exclude Group B tenderers from
consideration and focus on Group A tenderers.
Tender B did not respond positively to the tender clarifications and increased its price by some RM580,000.
Its Infrastructure & M&E Works were higher than Tender A by some RM300k and RM700k respectively.
Tender A is the current lowest tender. All the items are consistently priced. Its preliminaries is currently the
highest at RM912k equivalent to 7.3% of tender sum and may have rooms for further negotiations. If PTT
desired further price reductions, it will have to consider “restructuring the contractual arrangements,
terms & risks allocations”, such as:-
1 Supply of major building materials such as steel bars/concrete to contractor & assume the
escalation risks.
2 Considering award of Civil Works & M&E Works separately.
MKS 293.22 | 1
Confidential
MKS CQS Sdn Bhd
1.0 INTRODUCTION
1.1 The purpose of this report is to present the commercial analysis of the 4 revised tenders
received after tender clarification held on 18th April 2023 and to make the recommendations of
further actions to be taken to enable the Client to make considered decision. We will leave to
the Architect, Engineer, and Client to assess the technical, project management & financial
capabilities respectively of these tenderers.
2.1 The lowest 4 tenderers had been invited to Tender Clarification Meeting held on 18 th April 2023.
Tender questionnaires was issued to them after tender clarification meeting.
2.2 Revised tender submission was closed on 3rd May 2023. All 4 tenderers submitted their revised
tender via Email to Client Representative – Pn. Sharifah and QS – Ms. Tan Kai Xuan.
MKS 293.22 | 2
Confidential
MKS CQS Sdn Bhd
It is very unlikely that Group B tenderers could reduce their price further to match the lowest tender.
From commercial point of view, it will be prudent to exclude Group B tenderers from consideration
and focus on Group A tenderers.
4.1 Overall Comparison of revised tenders is in Attachment 1. The overall comparison of revised tender
for the 2 lowest tenders are summarised as follows: -
Tenderers Tenderer A Tenderer B
Volume Volume 1 Volume 2 Total Volume 1 Volume 2 Total
Original Corrected Tender Sum 11,786,583.18 1,133,940.40 12,920,523.58 10,967,223.20 1,637,930.00 12,605,153.20
Revised Corrected Tender Sum 11,466,448.22 1,111,905.00 12,578,353.22 11,410,820.70 1,782,890.00 13,193,710.70
Reductions/Additions (RM) -320,134.96 -22,035.40 -342,170.36 +443,597.50 +144,960.00 +588,557.50
(%) -3% -2% -3% +4% +9% +5%
Note : Volume 1- Main building works + Infrastructure works Volume 2 – M&E Works
4.2 The differences for Volume 1 – Main Building Works + Infrastructure Works are make-up of the
following: -
Items Tenderer A Tenderer B
1. Reduction of prices of items highlighted during tender interview and tender questionnaire. - 353,813.50 -113,400.00
2. Omission of Hoarding & Gate -101,750.40 -
3. Increase of prices of selected items by the tenderer +135,428.94 +556,997.50
Total -320,134.96 +443,597.50
Detail prices adjustment by the 2 lowest tenderers were identified and summarised in Attachment 2.
4.3 The detail evaluation for Volume 2 – M&E Works shall refer to M&E’s Revised Tender Report.
MKS 293.22 | 3
Confidential
MKS CQS Sdn Bhd
Tenderer A revised tender at RM 12,578,353.22 is the lowest tender. Their revised tender is RM 342,170.36
lower than their original corrected tender sum (RM 12,920,523.58). Their revised tender is RM776,901.32
or 6% higher than Consultant Estimate.
Tenderer A has made reduction of RM320,134.96 in Volume 1 – Main Building Works & Infrastructure Works
as summarised below: -
a) Price reduction to their overpricing items which have been highlighted to them during tender clarification
meeting, resulting a reduction of RM353,813.50.
b) Omission of hoarding and gate, resulting a reduction of RM101,750.40.
c) Increase prices of concrete and steel related works 6% and 3% respectively, resulting an addition of
RM135,428.94.
Tenderer B revised tender at RM 13,193,710.70 is the second lowest tender. Their revised tender is RM
588,557.50 higher than their original corrected tender sum (RM 12,605,153.20). Tenderer B did not omit
hoarding and gate (amounting to RM103,050) in their revised tender despite it was highlighted in our tender
questionnaire that the hoarding and gate had been erected on site. Their revised tender sum exclude hoarding
and gate is at RM 13,090,660.70 is RM 512,307.48 higher than the lowest tender and RM1,289,208.80 higher
than Consultant Estimate.
4.6 Tenderer B has made addition of RM443,597.50 in Volume 1 – Main Building Works & Infrastructure Works
as summarised below: -
a) Price reduction to their overpricing items which have been highlighted to them during tender clarification
meeting, resulting a reduction of RM113,400.00.
b) Increase prices of other items, resulting an addition of RM556,997.50, mainly from the items below:-
i. Roof covering (From RM80/m2 to RM110/m2), result an addition of RM96,480
ii. Site clearance works(From RM200,000 to RM370,000).
iii. Drainage crossing existing roads along (Addition of RM144,000)
MKS 293.22 | 4
Confidential
MKS CQS Sdn Bhd
5.2 From the above table, it is observed that tender prices for Main Building Works are very competitive
and very close to QS Estimate from +0.3% to +5%.
5.3 Their prices for Infrastructure Works and M&E Works are a lot higher than Consultant Estimate. The
Client may consider to award these works directly to the Infra-Works contractor and M&E contractor
to remove Main Contractor’s mark up for their profit, overhead and risk.
MKS 293.22 | 5
CADANGAN PEMBANGUNAN PERUMAHAN YANG MENGANDUNGI: (A) 36 UNIT 20’ X 60’ RUMAH TERES 2 TINGKAT JENIS A (B) 4 UNIT 20’ X 55’-60’ RUMAH TERES 2 TINGKAT JENIS B (C) 1 UNIT 23’ X 13’ PENCAWANG ELEKTRIK PADAT (D) 1 UNIT LOJI KUMBAHAN DI ATAS LOT 33079 HINGGA 33120 DAN SEBAHAGIAN TANAH KERAJAAN, TAMAN SERI MAWAR, BANDAR BARU MANTIN, MUKIM SETUL, DAERAH
SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS
1 2 3 4
QS Estimate
Tenderer A Tenderer B Tenderer C Tenderer D
Bill Description Amount (RM) Amount (RM) % Revised Amount (RM) % Original Amount (RM) % Revised Amount (RM) % Amount (RM) % Revised Amount (RM) % Amount (RM) % Revised Amount (RM) %
1 Preliminaries 517,480.57 960,000.00 186% 912,500.00 176% 372,500.00 72% 372,500.00 72% 726,000.00 140% 606,000.00 117% 651,868.00 126% 596,868.00 115%
2 Main Building Works (Type A) 6,797,041.44 6,755,432.12 99% 6,797,224.29 100% 6,879,993.60 101% 6,924,016.10 102% 7,954,268.00 117% 7,954,095.20 117% 8,027,041.80 118% 7,777,313.90 114%
Corner (3 Units) 649,584.93 646,292.94 99% 650,482.68 100% 646,197.00 99% 648,702.00 100% 757,846.20 117% 757,831.80 819,618.30 126% 777,731.39
Intermediate (29 Units) 5,360,413.07 5,318,780.38 99% 5,350,997.93 100% 5,432,285.80 101% 5,468,463.30 102% 6,266,743.40 117% 6,266,604.20 6,270,574.30 117% 6,066,304.84
End (4 Untis) 787,043.44 790,358.80 100% 795,743.68 101% 801,510.80 102% 806,850.80 103% 929,678.40 118% 929,659.20 936,849.20 119% 933,277.67
3 Main Building Works (Type B) 717,908.61 717,045.94 100% 724,816.97 101% 741,994.50 103% 758,924.50 106% 850,030.90 118% 850,030.90 118% 861,709.60 120% 825,971.20 115%
Corner (1 Units) 203,136.06 202,511.23 100% 204,641.15 101% 208,532.10 103% 212,884.60 105% 239,040.70 118% 239,040.70 257,148.10 127% 246,149.80
Intermediate (3 Units) 514,772.55 514,534.71 100% 520,175.82 101% 533,462.40 104% 546,039.90 106% 610,990.20 119% 610,990.20 604,561.50 117% 579,821.40
4 External & Infrastructure Works 2,037,661.28 2,562,105.12 126% 2,239,906.96 110% 2,190,735.10 108% 2,573,380.10 126% 2,465,333.70 121% 2,262,124.10 111% 2,378,050.10 117% 2,273,518.90 112%
5 Prime Cost And Provisional Sums 797,000.00 792,000.00 99% 792,000.00 99% 782,000.00 98% 782,000.00 98% 802,000.00 101% 802,000.00 101% 807,000.00 101% 807,000.00 101%
Sub - Total 10,867,091.90 11,786,583.18 108% 11,466,448.22 106% 10,967,223.20 101% 11,410,820.70 105% 12,797,632.60 118% 12,474,250.20 115% 12,725,669.50 117% 12,280,672.00 113%
Difference from Consultant Estimate (RM / %) BASE 919,491.28 8% 100,131.30 1% 1,930,540.70 18% 1,858,577.60 17%
6 Volume 2 - M&E Works 934,360.00 1,133,940.40 121% 1,111,905.00 119% 1,637,930.00 175% 1,782,890.00 191% 1,103,664.00 118% 1,033,512.00 111% 1,335,702.00 143% 1,277,628.00 137%
Overall Tender Sum 11,801,451.90 12,920,523.58 109% 12,578,353.22 107% 12,605,153.20 107% 13,193,710.70 112% 13,901,296.60 118% 13,507,762.20 114% 14,061,371.50 119% 13,558,300.00 115%
Difference from Consultant Estimate
BASE 1,119,071.68 9% 776,901.32 7% 803,701.30 7% 1,392,258.80 12% 2,099,844.70 18% 1,706,310.30 14% 2,259,919.60 19% 1,756,848.10 15%
(RM / %)
Difference from Previous (RM) - 342,170.36 -3% 588,557.50 5% - 393,534.40 -3% - 503,071.50 -4%
Attachment 1 |Revised Overal Comparison of Final Summary (Before / After Arith. Check)
Confidential
MKS CQS Sdn Bhd
CADANGAN MEMBINA DAN MENYIAPKAN PEMBANGUNAN PERNIAGAAN PHASE 4B, 2A, 2B DI ATAS LOT
43430, LOT 43422 SEHINGGA LOT 43429 DAN LOT 43406 SEHINGGA LOT PT43421 (DAHULUNYA DIKENALI
SEBAGAI LOT 4216, 4217, 4218) MUKIM RAWANG, DAERAH GOMBAK, MAJLIS PERBANDARAN SELAYANG,
SELANGOR DARUL EHSAN.
UNTUK TETUAN SYNERGY DEVELOPMENT SDN. BHD.
2.1 Tenderer A
Tenderer A
Volume 1 – Main Building Works + Infrastructure Works
(RM)
Original Corrected Tender Sum 11,786,583.18
Revised Corrected Tender Sum 11,466,448.22
Reductions / Additions -320,134.96
Bill No.1 Preliminaries -47,500.00
Bill No.2 & 3 Main Building Works + 49,563.30
Reduction of prices in:-
• Internal plastering works (From RM33.70/m2 to RM33/m2) -10,151.80
Increased of price in:
• All grades of vibrated reinforced concrete prices (+6% increase) +38,675.88
Grade 15 (From RM364/m3 to RM382/m3)
Grade 20 (From RM313/m3 to RM331/m3)
Grade 25 (From RM323.50/m3 to RM341.30/m3)
• Steel Reinforcements (From original average RM4.70/kg to RM5.02/kg; +3% increase) +44,367.30
• “Monier Nordica” roof covering & aluminium foil + 9,969.60
• Precast concrete coping/hood, Lintol +5,112.20
• Perimeter brick wall fencings, meter compartment, letter box +1,590.20
Bill No. 4 External & Infra Works -322,198.16
Reduction of prices in:-
• Site clearance & preparation -59,100.00
• Temporary hoarding (Total omission) -101,750.40
• Wash Trough, Pavement at site entrance -56,550.00
• Road hump, Provision machineries and labours to mill existing premix road [Road -53,922.20
Works]
• RC Grade 25 Staircase landing slab (For MS stairs) [Drainage Works] -59,572.00
• Connections to Individual Unit & Existing Main, Excavate existing premix road for -22,017.50
water pipe installation, hot tapping and tee-off connection of water pipe to existing
water pipes, Sterilisation, Flushing and Testing Pipelines [Water Reticulations]
Increased of price in:
• RC Concrete Grade 35 retaining wall (From RM348.40/m3 to RM366.20/m3), Grade +5,081.96
15 concrete base & Steel Reinforcements [Retaining Wall]
• Grade 15 lean concrete and mass concrete for drain bases, Grade 25 concrete for +9,749.50
sump, house entrance slab, drain cover slab [Drainage Works]
• 600mm x 600mm box culvert [ From RM59/m to RM261.50/m] [Drainage Works] +11,947.50
• Supply and lay 225mm VCP pipe pipe [Sewer] + 459.98
• Supply and lay 150mm MS Water pipe [Water] +8,475.00
Items remained unpriced, but shall deemed inclusive
Provisional of RM1,000/unit for water tank plinth -40,000.00
Field and laboratory test as requested by the Engineer -5,000.00
CADANGAN MEMBINA DAN MENYIAPKAN PEMBANGUNAN PERNIAGAAN PHASE 4B, 2A, 2B DI ATAS LOT
43430, LOT 43422 SEHINGGA LOT 43429 DAN LOT 43406 SEHINGGA LOT PT43421 (DAHULUNYA DIKENALI
SEBAGAI LOT 4216, 4217, 4218) MUKIM RAWANG, DAERAH GOMBAK, MAJLIS PERBANDARAN SELAYANG,
SELANGOR DARUL EHSAN.
UNTUK TETUAN SYNERGY DEVELOPMENT SDN. BHD.
2.2 Tenderer B
Tenderer B
Volume 1 – Main Building Works + Infrastructure Works
(RM)
Original Corrected Tender Sum 10,967,223.20
Revised Corrected Tender Sum 11,410,820.70
Reductions/Additions +443,597.50
Bill No.2 & 3 Main Building Works + 60,952.50
Reduction of prices in:-
• 600mm x 600mm Porcelain tiles (Living, Dining) (From original RM185/m2 to RM95/m2) -113,400.00
Increased of price in:
• “Monier Nordica” roof covering (From original RM80/m2 to RM110/m2) +96,480.00
• Additional items in roof, BRC in roof, water ponding test for roof slab +40,760.00
• 900mm High mild steel handrail and balustrades (From original RM200/m to RM300/m) +25,200.00
• Anti-termite soil treatment +7,900.00
• Excavation Works (Pad Footing, Ground Beam) +4,012.50
Bill No. 4 External & Infra Works +382,645.00
Increased of price in:
• Site clearance & preparation (From original RM200,000 to RM370,000) +170,000.00
• Wash trough, silt trap +14,000.00
• Premix road works +56,645.00
• Resurfacing of road works +10,000.00
• Drainage Works Provision (provision for machineries and labour to demolish existing +114,000.00
road side drains, machineries and labour to excavate existing premix road for box culvert
and sump construction, liaison with Authorities for permits, traffic diversion, connecting od
box culvert to existing roadside drain, cleaning, flushing, testing and commissioning)
• Provide machineries and labour to excavate existing premix road for sewer pipe and +7,000.00
manhole, liaison with Local Authorities for permits to work [Sewer]
• Liaison with local authorities for permits to work, hot tapping and tee-off connection of +11,000.00
water pipe to existing water pipes, sterilisation, flushing and testing pipelines
Items remained unpriced, but shall deemed inclusive
Profit and Attendance for STP Prime Cost Sum For record
Overall, we believe that all 3 tenderers’ building works quality and workmanship is of
respective quality and standards. In comparison, Tenderer A’s building work quality and
workmanship are the highest. Besides that, it is important to note that Tenderer A’s project
site personnel exhibits good knowledge of construction methods and works. The building
works quality and workmanship for Tenderer B are the second highest followed by tenderer
D. However, it is important to consider other factors, like the date of completion between
these 2 building does also play a part in factoring in the overall quality and workmanship.
CADANGAN PEMBANGUNAN YANG MENGANDUNGI 40 UNIT RUMAH
TERES DUA TINGKAT :
A) 36 UNIT JENIS A 20' X 60'
B) 4 UNIT JENIS B 20' X 55' - 60'
C) 1 UNIT PENCAWANG ELEKTRIK PADAT 23' X 13'
D) 1 UNIT LOJI KUMBAHAN
DI ATAS LOT 33079 HINGGA 33120 DAN SEBAHAGIAN TANAH
KERAJAAN, TAMAN SERI MAWAR, MUKIM SETUL (BANDAR BARU
MANTIN), DAERAH SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS
UNTUK TETUAN PTT DEVELOPMENT SDN. BHD.( DAHULU DIKENALI
SEBAGAI HOOVER BUILDERS SDN. BHD.)
CONTRACT : VOLUME 2 OF 2
FOR SUPPLY, DELIVERY, INSTALLATION,TESTING, COMMISSIONING
AND MAINTENANCE OF MECHANICAL & ELECTRICAL WORKS
EMPLOYER ARCHITECT
M&E ENGINEERS
CT PERUNDING
28-2, JALAN RAHANG JAYA 1,
PUSAT PERNIAGAAN RAHANG JAYA
70100 SEREMBAN, N.S.D.K.
TEL : 06-765 6237 FAX : 06-679 1954
APRIL 2023
TABLE OF CONTENTS
1.0 PREAMBLE
1.1 Tender Introduction
1.2 Scope of Tender
1.3 Invitation to Tender
1.4 Receipt of Tender
APPENDICES
Appendix A Comparison of Tender Price
All Six (6) tender documents are examined for completeness in terms of their offers and
the findings are summarized as follows:-
All The tenderers have submitted the Schedule of Unit Rate as requested by the Tender.
All the tenderers have submitted the Schedule of Technical Data as requested by the
Tender Document.
The tender of Tenderer ‘C’. with a tender price of RM 1,103,664.00 is the second lowest
of the Six Tenders received. The following were noted in the Tender:
Description Remarks
Items are found to be high:-
• 4.0 – Street Lighting & Landscape Tenderer to be highlighted on the
Lighting Works Tender Price.
• 5.0 – Internal Cold Water Plumbing
Works
• 6.0 – Internal Sanitary Plumbing Works
3.2.2 Technical
Tenderer ‘C’ has submitted the Schedule of Technical Data as requested by the Tender.
The tender of Tenderer ‘A’ with a tender price of RM 1,133,940.40 is the third lowest of
the Six Tenders received. The following were noted in the Tender:
Description Remarks
Items are found to be high:-
• 2.0 – Electrical Works Tenderer to review and revised the
Tender Price.
3.3.2 Technical
The tender of Tenderer ‘B’ with a tender price of RM 1,637,930.00 is the second highest
of the Six Tenders received. The following were noted in the Tender:
Description Remarks
Items are found to be high:-
• 2.0 – Electrical Works Tenderer to review and revised the
Tender Price.
3.6.2 Technical
Tenderer ‘B’ has submitted the Schedule of Technical Data as requested by the Tender.
The tender of Tenderer ‘F’ with a tender price of RM 1,840,128.50 is the highest of the
Six Tenders received. The following were noted in the Tender:
Description Remarks
Items are found to be high:-
• 5.0 – Internal Cold Water Plumbing Tenderer to review and revised the
Works Tender Price.
• 6.0 – Internal Sanitary Plumbing Works
3.7.2 Technical
Tenderer ‘F’ has submitted the Schedule of Technical Data as requested by the Tender.
2.0 Electrical Work 377,360.00 448,288.30 966,580.00 374,076.00 536,659.00 400,492.40 462,882.00
2.1 Double Storey Terrace House Intermediate Type A/B (36 Unit) 325,800.00 379,749.60 618,300.00 320,760.00 447,534.00 333,828.00 404,838.00
2.2 Double Storey Terrace House Corner Type A/B (4 Unit) 36,560.00 42,605.20 69,080.00 36,072.00 50,094.00 37,404.40 45,444.00
2.3 TNB Compact Substation 15,000.00 25,933.50 279,200.00 17,244.00 39,031.00 29,260.00 12,600.00
3.0 Telephone Work 30,000.00 38,872.00 29,150.00 39,072.00 60,260.00 24,090.00 35,700.00
4.0 Street Lighting & Landscape Lighting Works 175,000.00 207,276.10 178,200.00 212,316.00 216,453.00 187,594.00 168,346.50
4.1 Landscape Lighting 25,000.00 23,153.90 148,300.00 22,800.00 41,250.50 22,000.00 17,115.00
4.2 Street Lighting 150,000.00 184,122.20 29,900.00 189,516.00 175,202.50 165,594.00 151,231.50
5.0 Internal Cold Water Plumbing Work 192,000.00 208,804.00 288,000.00 230,400.00 248,400.00 374,220.00 555,200.00
5.1 Double Storey Terrace House Intermediate Type A/B (36 Unit) 172,800.00 187,131.60 259,200.00 207,360.00 223,560.00 336,600.00 499,680.00
5.2 Double Storey Terrace House Corner Type A/B (4 Unit) 19,200.00 21,672.40 28,800.00 23,040.00 24,840.00 37,620.00 55,520.00
6.0 Internal Sanitary Plumbing Work 160,000.00 203,400.00 136,000.00 228,000.00 211,600.00 315,040.00 572,000.00
6.1 Double Storey Terrace House Intermediate Type A/B (36 Unit) 144,000.00 183,060.00 122,400.00 205,200.00 190,440.00 283,536.00 514,800.00
6.2 Double Storey Terrace House Corner Type A/B (4 Unit) 16,000.00 20,340.00 13,600.00 22,800.00 21,160.00 31,504.00 57,200.00
(a)-(b) Arithmetical Error (RM) -8,160.00 0.00 0.00 0.00 0.00 34,083.00
% Ranking of Lowest (After Arith. Check)
2.74% 48.41% 0.00% 21.02% 19.07% 66.73%
Completion Period: 16 Months 48 Weeks Not indicated Not indicated 69.5 Weeks Not indicated
SOP-1
SUMMARY OF PRICES (BEFORE ARITHMETICAL CHECK)
PTE Tender 'A' Tender 'B' Tender 'C' Tender 'D' Tender 'E' Tender 'F'
Item Description Amount (RM) Amount (RM) Amount (RM) Amount (RM) Amount (RM) Amount (RM) Amount (RM)
2.0 Electrical Work 377,360.00 448,288.30 966,580.00 374,076.00 536,659.00 400,492.40 428,799.00
2.1 Double Storey Terrace House Intermediate Type A/B (36 Unit)325,800.00 379,749.60 618,300.00 320,760.00 447,534.00 333,828.00 404,838.00
2.2 Double Storey Terrace House Corner Type A/B (4 Unit) 36,560.00 42,605.20 69,080.00 36,072.00 50,094.00 37,404.40 11,361.00
2.3 TNB Compact Substation 15,000.00 25,933.50 279,200.00 17,244.00 39,031.00 29,260.00 12,600.00
3.0 Telephone Work 30,000.00 38,872.00 29,150.00 39,072.00 60,260.00 24,090.00 35,700.00
4.0 Street Lighting & Landscape Lighting Works 175,000.00 207,276.10 178,200.00 212,316.00 216,453.00 187,594.00 168,346.50
4.1 Landscape Lighting 25,000.00 23,153.90 148,300.00 22,800.00 41,250.50 22,000.00 17,115.00
4.2 Street Lighting 150,000.00 184,122.20 29,900.00 189,516.00 175,202.50 165,594.00 151,231.50
5.0 Internal Cold Water Plumbing Work 192,000.00 216,964.00 288,000.00 230,400.00 248,400.00 374,220.00 555,200.00
5.1 Double Storey Terrace House Intermediate Type A/B (36 Unit)172,800.00 195,267.60 259,200.00 207,360.00 223,560.00 336,600.00 499,680.00
5.2 Double Storey Terrace House Corner Type A/B (4 Unit) 19,200.00 21,696.40 28,800.00 23,040.00 24,840.00 37,620.00 55,520.00
6.0 Internal Sanitary Plumbing Work 160,000.00 203,400.00 136,000.00 228,000.00 211,600.00 315,040.00 572,000.00
6.1 Double Storey Terrace House Intermediate Type A/B (36 Unit)144,000.00 183,060.00 122,400.00 205,200.00 190,440.00 283,536.00 514,800.00
6.2 Double Storey Terrace House Corner Type A/B (4 Unit) 16,000.00 20,340.00 13,600.00 22,800.00 21,160.00 31,504.00 57,200.00
SOP-1
SCHEDULE OF PRICE
Tender 'A' Tender 'B' Tender 'C' Tender 'D' Tender 'E' Tender 'F'
Item Description Qty Unit Unit Rate (RM) Amount (RM)Unit Rate (RM) Amount (RM)Unit Rate (RM) Amount (RM)Unit Rate (RM) Amount (RM)Unit Rate (RM) Amount (RM)Unit Rate (RM) Amount (RM)
1.0 Preliminary
1.1.1 3 sets of shop drawings and working details. Lump Sum 6,300.00 5,000.00 5,400.00 550.00 10,000.00
1.1.2 Preparation of 1 set of 'as-built' tracing, 1 set Lump Sum 10,500.00 20,000.00 5,400.00 1,380.00 1,380.00 1,100.00 16,000.00
of Auto-CAD drawing files in Compact Disc (CD)
and 3 sets of O&M Manuals complete with as-
built drawings.
1.1.3 Liaison with relevant Authorities for Lump Sum 10,500.00 15,000.00 9,000.00 8,050.00 8,050.00 11,000.00 20,000.00
inspections and to obtain all approval and
certificates including payment of all necessary
inspection fees, notices, documentations,
Notes:
a) The quantities shown on this schedules are indicative and
intended to assist tenderer in working out their tender
price. The onus is on the tenderer to verify that the said
quantities shown on this schedule is correct by quantity
taking against the tender drawings
b) Liaison with authorities as stipulated above implies the
following:
i) For electrical work, submit necessary form and 13,225.00
documentation for TNB meter application, and assist client
to make relevant payment to TNB for meter deposit if
required.and other work as necessary
ii) For Telephone work, informing Telekom before starting 13,225.00
work, arranging for inspection after completion, prepare &
submit of As-built drawings to Telekom, obtaining of Letter
of Acceptance, and supporting letter for CFO application
and other work as necessary
iii) For street lighting work, liaison with Majlis Bandaraya 13,225.00
Seremban (MBS) including arranging for Street Lighting
inspection, and obtaining of supporting letters for
application of CCC is included in the scope of work of this
iv) For TNB work, liaison with Majlis Bandaraya Seremban 13,225.00
(MBS) including arranging for road excavation permit
inspection for TNB cable laying, and obtaining of supporting
letters for application of CCC is included in the scope of
work of this tender.
v) Signing of relevant CCC form are included in the scope of
work
Sub-total to be carried forward to Page SOP-1 27,300.00 40,000.00 19,800.00 62,330.00 12,650.00 46,000.00
SOP-1
SCHEDULE OF PRICE
Tender 'A' Tender 'B' Tender 'C' Tender 'D' Tender 'E' Tender 'F'
Item Description Qty Unit Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM)
2.0 Electrical work
2.1 Double Storey Terrace House Intermediate Type A/B
2.1.1 To supply and install 150mm underground HDPE pipe for TNB 1 No. 423.80 423.80 500.00 500.00 192.00 192.00 310.50 310.50 330.00 330.00 420.00 420.00
cable incoming to metering panel as per TNB requirement.
2.1.2 To supply and install TNB Metering Panel c/w busbar panel, 1 Lot
metal claded panel, necessary cabling, earthing and accessories 226.00 226.00 1,500.00 1,500.00 102.00 102.00 621.00 621.00 330.00 330.00 210.00 210.00
as per TNB requirement.
2.1.3 To supply and install cable Underground from TNB meter panel
using 1x2C-16mm2 +E PVC/SWA/PVC Cu. Cable c/w supports 1 Lot 1,118.70 1,118.70 2,000.00 2,000.00 744.00 744.00 1,265.00 1,265.00 880.00 880.00 756.00 756.00
and accessories to switchboard.
2.1.4 To supply and install cable Distribution Board as per drawing c/w 1 No. 1,107.40 1,107.40 2,000.00 2,000.00 1,020.00 1,020.00 1,207.00 1,207.00 2,090.00 2,090.00 1,207.50 1,207.50
all supports and accessories
2.1.5 Supply and install Ceiling/wall lighting point by using 2x1C-
1.5mm2+E PVC Cu. Cable in high impact UPVC conduit c/w 18 No. 101.70 1,830.60 95.00 1,710.00 108.00 1,944.00 92.00 1,656.00 66.00 1,188.00 115.50 2,079.00
supports, 10A one way light switch and other accessories to
2.1.6 Supply and install Wall Mounted lighting point by using 2x1C-
1.5mm2+E PVC Cu. Cable in high impact UPVC conduit c/w 1 No. 101.70 101.70 110.00 110.00 132.00 132.00 92.00 92.00 66.00 66.00 115.50 115.50
supports, 10A 2 way light switch and other accessories to
complete from switchboard.
2.1.7 Supply and install Ceiling Fan point by using 2x1C-1.5mm2+E
PVC Cu. Cable in high impact UPVC conduit c/w fan hook, 10A 7 No. 113.00 791.00 80.00 560.00 132.00 924.00 92.00 644.00 77.00 539.00 115.50 808.50
switches, supports and accessories from switchboard.
2.1.8 Supply and install Door Bell point c/w Switch by using 1x3C-
1.5mm2 PVC/SWA/PVC Cu. Cable Underground c/w excavation, 1 No. 339.00 339.00 450.00 450.00 264.00 264.00 207.00 207.00 242.00 242.00 315.00 315.00
back filling with proper compaction, supports, 2 pole light switch
and other accessories to complete switchboard.
2.1.9 Supply and install small power points by using 2x1C- 2.5mm 2 +E
PVC Cu. Cables in high impact UPVC conduit c/w 13A switch 11 No. 158.20 1,740.20 95.00 1,045.00 156.00 1,716.00 207.00 2,277.00 99.00 1,089.00 262.50 2,887.50
socket outlet and other accessories to complete from
2.1.10 Supply and install Water Heater point by using 2x1C- 4.0mm2+E
PVC Cu. Cables in concealed high impact UPVC conduit c/w 2 1 No. 372.90 372.90 550.00 550.00 336.00 336.00 563.50 563.50 275.00 275.00 378.00 378.00
pole switch socket outlet, supports and other accessories to
complete from switchboard.
Sub-total to be carried forward to next page 8,051.30 10,425.00 7,374.00 8,843.00 7,029.00 9,177.00
Sub-total brought from previous page 8,051.30 10,425.00 7,374.00 8,843.00 7,029.00 9,177.00
SOP-1
SCHEDULE OF PRICE
Tender 'A' Tender 'B' Tender 'C' Tender 'D' Tender 'E' Tender 'F'
Item Description Qty Unit Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM)
2.2.16 To supply and install SIRIM approved Fibre Wall Socket (FWS)
c/w SC-output connector mounted on 300mm from finish floor 1 No. 90.40 90.40 1,000.00 1,000.00 36.00 36.00 172.50 172.50 55.00 55.00 105.00 105.00
level to TM requirement
2.2.17 Testing and Commissioning of the whole system Lump Sum 340.00 1,000.00 96.00 402.50 220.00 157.50
2.2.18 Other items not mentioned but deemed necessary for satisfactory
completion of the works :-
a)
b)
Sub-total of 1 unit corner two storey terrace house 10,651.30 17,270.00 9,018.00 12,523.50 9,351.10 11,361.00
Sub-total of 4 unit to be carried forward to SOP-1 42,605.20 69,080.00 36,072.00 50,094.00 37,404.40 45,444.00
SOP-3
SCHEDULE OF PRICE
Tender 'A' Tender 'B' Tender 'C' Tender 'D' Tender 'E' Tender 'F'
Item Description Qty Unit Unit Rate (RM) Amount (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM)
3.5 To supply and install concrete pole to TM requirement 5 No. 1,695.00 8,475.00 800.00 4,000.00 1,080.00 5,400.00 2,875.00 14,375.00 1,430.00 7,150.00 945.00 4,725.00
3.6 Testing and Commissioning of the whole system Lump Sum 3,390.00 3,500.00 3,000.00 8,050.00 550.00 3,780.00
3.7 Any other items not mentioned above but may be
necessary in order to implement and complete the
complete telephone system
a)
b)
Sub-total to be carried forward to Page SOP-1 38,872.00 29,150.00 39,072.00 60,260.00 24,090.00 35,700.00
SOP-1
SCHEDULE OF PRICE
Tender 'A' Tender 'B' Tender 'C' Tender 'D' Tender 'E' Tender 'F'
Item Description Qty Unit Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM)
SOP-1
SCHEDULE OF PRICE
Tender 'A' Tender 'B' Tender 'C' Tender 'D' Tender 'E' Tender 'F'
Item Description Qty Unit Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM)
Sub-total of 1 unit intermediate two storey 5,198.10 7,200.00 5,760.00 6,210.00 9,350.00 13,880.00
Sub-total of 36 unit to be carried forward to 187,131.60 259,200.00 207,360.00 223,560.00 336,600.00 499,680.00
SOP-1
SCHEDULE OF PRICE
Tender 'A' Tender 'B' Tender 'C' Tender 'D' Tender 'E' Tender 'F'
Item Description Qty Unit Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM) Unit Rate (RM)
SOP-1
APPENDIX B : COMPARISON OF TENDER TECHNICAL OF DATA
Tenderer 'A' Tenderer 'B' Tenderer 'C' Tenderer 'D' Tenderer 'E' Tenderer 'F'
Item Description Unit Specification Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer
e) Gauge/Pressure Rating
e) Type/Model Round
3) Stop Cock
a) Manufacturer City City City/Eq To comply
Gkent
GKM
b) Country of manufacture Local
e) Type/Model HD T Handle
TLV-1 CT
APPENDIX B : COMPARISON OF TENDER TECHNICAL OF DATA
Tenderer 'A' Tenderer 'B' Tenderer 'C' Tenderer 'D' Tenderer 'E' Tenderer 'F'
Item Description Unit Specification Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer
c) Local Agent Open Market
e) Working pressure
3 UPVC Underground Soil Pipe & Fittings
to BS 4660 (Brown Pipe) Cew Sin SAE South Asia/ To comply
a) Manufacturer Bina Plastic Bina Plastic/EQ
South Asia
Excel
Exact
b) Country of manufacture Local
e) Working pressure
e) Working pressure
5 Vent Cowl
a) Manufacturer Cew Sin SAE South Asia/ To comply
Bina Plastic Bina Plastic/EQ
South Asia
Excel
Exact
b) Country of manufacture Local
6 Floor Trap
a) Manufacturer Cew Sin South Asia/ To comply
Bina Plastic Bina Plastic/EQ
South Asia
Excel
Exact
Tenderer 'A' Tenderer 'B' Tenderer 'C' Tenderer 'D' Tenderer 'E' Tenderer 'F'
Item Description Unit Specification Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer
LOW VOLTAGE ELECTRICAL SYSTEM
1.0 LV Sub Switchboard/Distribution Board
a) Manufacturer EPS/ TERASAKI Federal SRS To comply
b) XLPE Insulated Armoured Cables Mega Mega Southern Cables Mega/EQ To comply
Manufacturer Thorn
Leader Cables
Power Cable
Universal Cables
Southern Cables
TLV-5 CT
APPENDIX B : COMPARISON OF TENDER TECHNICAL OF DATA
Tenderer 'A' Tenderer 'B' Tenderer 'C' Tenderer 'D' Tenderer 'E' Tenderer 'F'
Item Description Unit Specification Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer Tenderer's Offer
8.0 LIGHT FITTINGS
c) Internal General Purpose Telephone Cable Southern Cable Southern Cable Southern Cable Southern/EQ To comply
Uniphone
Universal Cables
TLV-7 CT
CADANGAN PEMBANGUNAN PERUMAHAN YANG MENGANDUNGI:
(A) 36 UNIT 20’ X 60’ RUMAH TERES 2 TINGKAT JENIS A (B) 4 UNIT 20’ X 55’-60’ RUMAH TERES 2 TINGKAT JENIS B (C) 1
UNIT 23’ X 13’ PENCAWANG ELEKTRIK PADAT (D) 1 UNIT LOJI KUMBAHAN DI ATAS LOT 33079 HINGGA 33120 DAN
SEBAHAGIAN TANAH KERAJAAN, TAMAN SERI MAWAR, BANDAR BARU MANTIN, MUKIM SETUL, DAERAH SEREMBAN,
NEGERI SEMBILAN DARUL KHUSUS. UNTUK TETUAN PTT DEVELOPMENT SDN. BHD. (DAHULU DIKENALI SEBAGAI
HOOVER BUILDERS SDN BHD)
CONFIDENTIAL
TENDER EVALUATION REPORT
(392238-X)
3 – 2B, JALAN PJU 1/3F,
SUNWAYMAS COMMERCIAL CENTRE,
47301 PETALING JAYA
SELANGOR DARUL EHSAN, MALAYSIA TEL: +603
7805 1318 FAX: +603 7887 1618
Email: lai@mkscqs.com / waiming@mkscqs.com
CONTENT PAGE
EXECUTIVE SUMMARY 1
1.0 INTRODUCTION 2
2.0 CALLING OF TENDERS 3
3.0 TENDER RESULTS 3
4.0 ARITHMETICAL CHECKS & COMPLIANCE CHECK 4
5.0 EVALUATION OF TENDERED RATES/PRICES 5
6.0 OVERALL TENDER COMPARISON & GENERAL OBSERVATION 6-7
7.0 DETAIL COMMENTS ON TENDERER SUBMISSIONS 8-16
EXECUTIVE SUMMARY
1. 11 Contractors were invited to participate in this tender. 8 tenderers confirmed their participation and
collected the tender documents. However only 6 tenderers submitted their tender.
2. After arithmetical errors correction, the 6 tenders received ranged from RM12.6M to RM17.5M.
Difference From QS
Corrected Total
Revised Rank Tenderers Estimate
Tender Sum
(RM) (%)
Consultant’s Estimate 11,801,451.90 BASE
Group 1 Tenderer B 12,605,153.20 +803,701.30 +7%
A 2 Tenderer A 12,920,523.58 +1,119,071.68 +9%
Group 3 Tenderer C 13,901,296.60 +2,099,844.70 +18%
B 4 Tenderer D 14,061,371.50 +2,259,919.60 +19%
Group 5 Tenderer E 16,385,634.30 +4,584,182.40 +39%
C 6 Tenderer F 17,527,364.77 +5,725,912.87 +49%
4 The lowest tender, Tenderer B, there is an obvious pricing error of painting at RM75/m2 for Type A
while RM10.50/m2 for Type B and we have corrected it. Their prices for Preliminaries are low while
the pricing for M&E works are very high.
5 The 2nd lowest tender, Tenderer A, their prices for Preliminaries are very high (+96%) and prices for
infra-structure works & M&E Works high at +26% and +21% respectively. However, their pricing for
building works is the lowest, even lower than MKS PTE.
6 We believe clarification from tender interviews will be able to improve the tender results closer to the
PTE.
MKS 293.22| 1
Confidential
MKS CQS Sdn Bhd
1.0 INTRODUCTION
1.1 The purpose of this report is to present the commercial analysis of the 6 tenders received for this
project and to make the recommendations of further actions to be taken to enable the Client to
make considered decision. We will leave to the Architect and Client to assess the technical and
project management capabilities of these tenderers during tender clarifications.
2.1 A tender list comprising 11 Contractors were collectively provided by Client and Consultants, as
summarised in Attachment 1.
2.2 Letter of invitation to tender were issued to all the 11 Contractors from MKS CQS Sdn Bhd on 3rd
March 2023 and 21st March 2023. 8 out of 11 Contractors confirmed their interest to participate in
the tender. 3 Contractors declined to participate due to shortage of resources or tight on-going
project schedule.
2.3 Tender collection was at the office of MKS CQS Sdn Bhd, started from 3rd March 2023.
2.4 Site briefing was carried out on 13th March 2023 and attended by all tenderers that were invited.
Attendance list is attached in Attachment 2.
2.6 Tender closing was extended to 3rd April 2023 at the request of Khas Corporation & KESB
Engineering.
MKS 293.22| 2
Confidential
MKS CQS Sdn Bhd
2.7 Tender were opened at 9am on 4th April 2023 at Client’s office, in the presence of:-
PTT Development Sdn Bhd Pn Sharifah
Pn Norehan
3.1 Only 6 tenderers submitted base tender complying fixed completion period of 16 Months. There are 2
contractors who collected the tender documents did not submit their tenders.
3.3 Tenderer A, B and C submitted Tender Earnest Money of RM10,000 and are in the custody of Client.
3.4 Tenderer B submitted alternative tender with the same tender sum but with longer completion period
at 20 Months.
MKS 293.22| 3
Confidential
MKS CQS Sdn Bhd
4.1 The 6 tenders have been checked for any arithmetical errors, major pricing error, and incorporation of Tender Addendum A issued.
4.2 All tenderers have incorporated Tender Addendum A.
4.3 There were arithmetical errors in all 6 tenders. Tenderer B had obvious pricing errors that lead to major cost impact. Detail of Errors is in Attachment 3.
4.4 The errors and adjustments made are summarised as follows. The corrected tender sum will be utilised for evaluation purpose to enable “like-to-like” comparison.
Add Original Total Tender Total Arithmetical Obvious Pricing Corrected Total Revised
Rank Tenderers Remarks
A Sum Errors Errors Tender Sum Rank
1 √ Tenderer A 12,883,360.78 +37,162.80 12,920,523.58 2 Refer Attachment 3
Major pricing errors in Internal Painting to
2 √ Tenderer B 13,755,077.20 -307,425.00 -842,499.00 12,605,153.20 1
Walls (Type A) pricing. Refer Attachment 3
3 √ Tenderer C 13,900,402.20 +894.40 - 13,901,296.60 3 Refer Attachment 3
4 √ Tenderer D 14,032,954.00 +28,417.50 - 14,061,371.50 4 Refer Attachment 3
5 √ Tenderer E 16,450,976.10 -65,341.80 - 16,385,634.30 5 Refer Attachment 3
6 √ Tenderer F 17,514,016.65 +13,348.12 - 17,527,364.77 6 Refer Attachment 3
4.5 Tenderer B’s has major error amounting to RM 1,149,924.00 (Arithmetical Error - RM307,425 + Obvious Pricing Error - RM842,499) in their tender.
• Tenderer’s B has made a major arithmetical error due to transferring wrong amount for Sanitary Wares & Fittings in Collection Summary Page (Type A),
leading to an over-calculation of RM 271,795.00.
• Tenderer B’s obvious pricing errors were due to pricing of internal painting to walls (Type A) at RM75/m2 instead of RM10.50/m2 (Unit Rate in Type B),
leading to an over-calculation of RM842,499.00 for 13,062m2 wall area for Type A house units.
4.6 After errors adjustment, Tenderer B is the lowest tender available.
MKS 293.22 | 4
Confidential
MKS CQS Sdn Bhd
We have undertaken detail comparison of the prices submitted by the Tenderers as follows.
We have marked red those pricing that we consider to be high and green those items we consider
to be low.
MKS 293.22 | 5
CADANGAN MEMBINA DAN MENYIAPKAN PEMBANGUNAN PERNIAGAAN PHASE 4B, 2A, 2B DI ATAS LOT 43430, LOT 43422 SEHINGGA LOT 43429 DAN LOT 43406
SEHINGGA LOT PT43421 (DAHULUNYA DIKENALI SEBAGAI LOT 4216, 4217, 4218) MUKIM RAWANG, DAERAH GOMBAK, MAJLIS PERBANDARAN SELAYANG,
SELANGOR DARUL EHSAN.
UNTUK TETUAN SYNERGY DEVELOPMENT SDN. BHD.
CADANGAN MEMBINA DAN MENYIAPKAN PEMBANGUNAN PERNIAGAAN PHASE 4B, 2A, 2B DI ATAS LOT 43430,
LOT 43422 SEHINGGA LOT 43429 DAN LOT 43406 SEHINGGA LOT PT43421 (DAHULUNYA DIKENALI SEBAGAI
LOT 4216, 4217, 4218) MUKIM RAWANG, DAERAH GOMBAK, MAJLIS PERBANDARAN SELAYANG, SELANGOR
DARUL EHSAN.
UNTUK TETUAN SYNERGY DEVELOPMENT SDN. BHD.
7.1 Tenderer B
Tenderer B corrected tender at RM12,605,153.20 (from RM13,755,077.20) is the lowest tender. They have made
major error in transferring amount for Sanitary and Plumbing Works for Corner and Intermediate units in Bill No.2
Main Building Works (Type A), resulting over-calculation of RM271,795 and pricing error in internal painting to
wall in Bill No.2 Main Building Works (Type A), leading to over-calculation of RM842,499.00 (refer to 4.5). This
shall be clarified with them during the tender clarification meeting.
Tenderer B corrected tender is being RM803,701.30 or 7% higher than Consultant Estimate is summarised
as below:-
Item QS Estimate Tenderer A Difference (RM/%) Remarks
Volume 1- MBW 10,867,091.90 10,967,223.20 +100,131.30 +1% Refer item 7.1.1 – 7.1.3
Volume 2-M&E Works 934,360.00 1,637,930.00 +703,570.00 +75% Refer M&E Tender Report for Analysis
Corrected Tender Sum 11,801,451.90 12,605,153.20 803,701.30 +7%
7.1.1 Preliminaries
Tenderer B Preliminaries at RM372,500.00 or about 3% of their tender sum is considered low. Their
Preliminaries is about RM144,980.57 lower than QS Estimate. Listed below are items that were left unpriced.
These items shall be clarified with them during tender interview
MKS 293.22 | 8
Confidential
MKS CQS Sdn Bhd
CADANGAN MEMBINA DAN MENYIAPKAN PEMBANGUNAN PERNIAGAAN PHASE 4B, 2A, 2B DI ATAS LOT 43430,
LOT 43422 SEHINGGA LOT 43429 DAN LOT 43406 SEHINGGA LOT PT43421 (DAHULUNYA DIKENALI SEBAGAI
LOT 4216, 4217, 4218) MUKIM RAWANG, DAERAH GOMBAK, MAJLIS PERBANDARAN SELAYANG, SELANGOR
DARUL EHSAN.
UNTUK TETUAN SYNERGY DEVELOPMENT SDN. BHD.
Tenderer B’s Main Building Works is at RM 7,621,988.10 is RM 107,038.05 or 1% higher than QS Estimate. Items
listed below are major rates that appeared high: -
Overall
Tenderer’s Reasonable Approx.
Description Difference (RM) Impact
Rate (RM) Rate (RM) Qty
(RM)
Steel roof trusses system 80/m2 60/m2 +20.00 +33% 3,216 +64,320.00
Monier Nordica roof system (Covering, Fittings, Sisalation Avg 35/m2 Avg 85/m2 -50.00 -59% 3,216 -160,800.00
sheet,flashing, fascia board)
600mm x 600mm porcelain tiles; "Guocera,60T001A Olympus 185/m2 88/m3 +97.00 +110% 1,384 +134,248.00
Bone White (Polished)" to floor (Living, Dining)
9.5mm Thick plasterboard flat ceiling lining, exceeding 3.5m 75/m2 50/m2 +25.00 +50% 1,988 +49,700.00
n.e. 5.0m high
Supply and lay stamped concrete imprint 95/m2 55/m2 +40.00 +73% 1,532 +61,280.00
Internal painting to walls 10.50/m2 3.90/m2 +6.60 +169% 14,366 +94,815.60
External painting to Walls 15/m2 10/m2 +5.00 +50% 5,125 +25,625.00
External Structural Steel Staircase (Back of Houses) 500/no 2000/no -1,500 -75% 40 -60,000.00
Excavate pit for pad footing exceeding 1.5m n.e. 3m deep & 2.50/m3 28/m3 -25.50 -91% 1,605 -40,927.50
trench for ground beam n.e. 1.50m deep
Total Impact: +168,261.10
Tenderer B’s External and Infrastructure Works is at RM 2,190,735.10 is RM 153,073.82 or 8% higher than QS
Estimate. Items listed below are major rates that appeared high:-
Overall
Tenderer’s Reasonable Appro
Description Difference (RM) Impact
Rate (RM) Rate (RM) x. Qty
(RM)
Site Clearance And Preparation 200,000/sum 45,000/sum +155,000 +344% Sum +155,000.00
Excavate, trim, level and grade formation to required 12.50/m2 8/m2 +4.50 +56% 3,583 +16,123.50
cambers, gradients, falls and crossfalls required level and
cart away excess earth to make up level on site (Road)
100mm Broken straight lane line (Road) +50/m +4/m +46.00 +1150% 376 +17,296.00
150mm Unbroken edge line (Road) +65/m +4/m +61.00 +1525% 690 +42,090.00
Supply and lay 225mm diameter VCP sewer pipe (Sewer) 65/m 250/m -185.00 -74% 176 -32,560.00
Supply and construct standard precast concrete manhole; Avg 1,310/no Avg 4,800.no -3,490 -73% 5 -17,450.00
1.2m-1.6m (Sewer)
Total Impact: +180,499.50
MKS 293.22 | 9
Confidential
MKS CQS Sdn Bhd
CADANGAN MEMBINA DAN MENYIAPKAN PEMBANGUNAN PERNIAGAAN PHASE 4B, 2A, 2B DI ATAS LOT 43430,
LOT 43422 SEHINGGA LOT 43429 DAN LOT 43406 SEHINGGA LOT PT43421 (DAHULUNYA DIKENALI SEBAGAI
LOT 4216, 4217, 4218) MUKIM RAWANG, DAERAH GOMBAK, MAJLIS PERBANDARAN SELAYANG, SELANGOR
DARUL EHSAN.
UNTUK TETUAN SYNERGY DEVELOPMENT SDN. BHD.
They offer alternative tender with completion period at 20 Months at the same tender price.
7.2 Tenderer A
Tenderer A corrected tender at RM 12,920,523.58 (from RM 12,883,360.78) is the second lowest tender, being
RM 1,119,071.68 or 9% higher than Consultant Estimate is summarised as below:-
7.2.1 Preliminaries
Tenderer A Preliminaries at RM 960,000.00 or about 8% of their tender sum is considered high. Their
Preliminaries is the highest among the 4 lowest tenderers. Listed below are items that appeared high.
MKS 293.22 | 10
Confidential
MKS CQS Sdn Bhd
CADANGAN MEMBINA DAN MENYIAPKAN PEMBANGUNAN PERNIAGAAN PHASE 4B, 2A, 2B DI ATAS LOT 43430,
LOT 43422 SEHINGGA LOT 43429 DAN LOT 43406 SEHINGGA LOT PT43421 (DAHULUNYA DIKENALI SEBAGAI
LOT 4216, 4217, 4218) MUKIM RAWANG, DAERAH GOMBAK, MAJLIS PERBANDARAN SELAYANG, SELANGOR
DARUL EHSAN.
UNTUK TETUAN SYNERGY DEVELOPMENT SDN. BHD.
Tenderer A’s Main Building Works is at RM 7,472,478.06 is RM 41,609.32 or 1% lower than QS Estimate. Items
listed below are major rates that appeared high:-
Tenderer A’s External and Infrastructure Works is at RM 2,562,105.12 is RM 524,443.84 or 26% higher than QS
Estimate. Items listed below are major rates that appeared high:-
600mm Wide x 600mm depth precast box culvert 59/m 400/m -341.00 -81% 59 -20,119.00
MKS 293.22 | 11
Confidential
MKS CQS Sdn Bhd
CADANGAN MEMBINA DAN MENYIAPKAN PEMBANGUNAN PERNIAGAAN PHASE 4B, 2A, 2B DI ATAS LOT 43430,
LOT 43422 SEHINGGA LOT 43429 DAN LOT 43406 SEHINGGA LOT PT43421 (DAHULUNYA DIKENALI SEBAGAI
LOT 4216, 4217, 4218) MUKIM RAWANG, DAERAH GOMBAK, MAJLIS PERBANDARAN SELAYANG, SELANGOR
DARUL EHSAN.
UNTUK TETUAN SYNERGY DEVELOPMENT SDN. BHD.
7.3 Tenderer C
Tenderer C corrected tender at RM 13,901,296.60 (from RM 13,900,402.20) is the third lowest tender, being
RM 2,099,844.70 or 18% higher than Consultant Estimate is summarised as below: -
7.3.1 Preliminaries
Tenderer C Preliminaries at RM 726,000 or about 6% of their tender sum is considered reasonable. Listed
below are items that appeared high and may have rooms for improvements.
MKS 293.22 | 12
Confidential
MKS CQS Sdn Bhd
CADANGAN MEMBINA DAN MENYIAPKAN PEMBANGUNAN PERNIAGAAN PHASE 4B, 2A, 2B DI ATAS LOT 43430,
LOT 43422 SEHINGGA LOT 43429 DAN LOT 43406 SEHINGGA LOT PT43421 (DAHULUNYA DIKENALI SEBAGAI
LOT 4216, 4217, 4218) MUKIM RAWANG, DAERAH GOMBAK, MAJLIS PERBANDARAN SELAYANG, SELANGOR
DARUL EHSAN.
UNTUK TETUAN SYNERGY DEVELOPMENT SDN. BHD.
Tenderer C’s Main Building Works is at RM 8,804,298.90 is RM 1,289,348.85 or 17% higher than QS Estimate.
Items listed below are major rates that appeared high:-
Tenderer C’s External and Infrastructure Works is at RM 2,465,333.70 is RM 427,672.42 or 21% higher than QS
Estimate. Items listed below are major rates that appeared high: -
MKS 293.22 | 13
Confidential
MKS CQS Sdn Bhd
CADANGAN MEMBINA DAN MENYIAPKAN PEMBANGUNAN PERNIAGAAN PHASE 4B, 2A, 2B DI ATAS LOT 43430,
LOT 43422 SEHINGGA LOT 43429 DAN LOT 43406 SEHINGGA LOT PT43421 (DAHULUNYA DIKENALI SEBAGAI
LOT 4216, 4217, 4218) MUKIM RAWANG, DAERAH GOMBAK, MAJLIS PERBANDARAN SELAYANG, SELANGOR
DARUL EHSAN.
UNTUK TETUAN SYNERGY DEVELOPMENT SDN. BHD.
7.4 Tenderer D
Tenderer D corrected tender at RM 14,061,371.50 (from RM 14,032,954) is the fourth lowest tender, being
RM 2,259,919.60 or 19% higher than Consultant Estimate is summarised as below:-
Item QS Estimate Tenderer A Difference (RM/%) Remarks
Volume 1- MBW 10,867,091.90 12,725,669.50 +1,858,577.60 +17% Refer item 7.4.1 – 7.4.3
Volume 2-M&E Works 934,360.00 1,335,702.00 + 401,342.00 +43% Refer M&E Tender Report for Analysis
Corrected Tender Sum 11,801,451.90 14,061,371.50 + 2,259,919.60 +19%
7.4.1 Preliminaries
Tenderer D Preliminaries at RM 651,868.00 or about 5% of their tender sum is considered reasonable. Listed
below are items that appeared high.
Tenderer’s Price
BQ Ref Description
(RM)
1/33/A Constructional Plant High 150,000
1/45/D Safety and Health Measures High 64,000
1/16/C Workmen Accommodation High 60,000
1/53/A Dilapidation Survey High 25,000
Tenderer D’s Main Building Works is at RM 8,888,751.40 is RM 1,373,801.35 or 18% higher than QS Estimate.
Items listed below are major rates that appeared high:-
MKS 293.22 | 14
Confidential
MKS CQS Sdn Bhd
CADANGAN MEMBINA DAN MENYIAPKAN PEMBANGUNAN PERNIAGAAN PHASE 4B, 2A, 2B DI ATAS LOT 43430,
LOT 43422 SEHINGGA LOT 43429 DAN LOT 43406 SEHINGGA LOT PT43421 (DAHULUNYA DIKENALI SEBAGAI
LOT 4216, 4217, 4218) MUKIM RAWANG, DAERAH GOMBAK, MAJLIS PERBANDARAN SELAYANG, SELANGOR
DARUL EHSAN.
UNTUK TETUAN SYNERGY DEVELOPMENT SDN. BHD.
Tenderer D’s External and Infrastructure Works is at RM 2,378,050.10 is RM 340,388.82 or 17% higher than QS
Estimate. Items listed below are major rates that appeared high:-
CADANGAN MEMBINA DAN MENYIAPKAN PEMBANGUNAN PERNIAGAAN PHASE 4B, 2A, 2B DI ATAS LOT 43430,
LOT 43422 SEHINGGA LOT 43429 DAN LOT 43406 SEHINGGA LOT PT43421 (DAHULUNYA DIKENALI SEBAGAI
LOT 4216, 4217, 4218) MUKIM RAWANG, DAERAH GOMBAK, MAJLIS PERBANDARAN SELAYANG, SELANGOR
DARUL EHSAN.
UNTUK TETUAN SYNERGY DEVELOPMENT SDN. BHD.
MKS 293.22 | 16
ATTACHMENT 1
MKS 293.22
PRIVATE & CONFIDENTIAL [updated on 30.3.2023]
PROJECT:
CADANGAN PEMBANGUNAN PERUMAHAN YANG MENGANDUNGI: a) 36 UNIT 20’ X 60’ RUMAH TERES 2 TINGKAT JENIS A; b) 4 UNIT 20’ X 50’-60’ RUMAH TERES 2 TINGKAT JENIS B; c) 1 UNIT 23’ X
13’ PENCAWANG ELEKTRIK PADAT; d) 1 UNIT LOJI KUMBAHAN, DIATAS TANAH LOT 33079 HINGGA 33120 DAN SEBAHAGIAN TANAH KERAJAAN, TAMAN SERI MAWAR BANDAR BARU MANTIN,
MUKIM SETUL DAERAH SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS.
UNTUK TETUAN PTT DEVELOPMENT SDN BHD
List of Tenderers
CIDB Registration List of Similar Project Experience
Paid Up
No. Company Name Company Address & Contact Expiry Year of
Grade Capital Project title Value (RM)
Date Completion
A. Confirmed Participation
1 Dian Makmur Sdn Bhd No.23, Jalan 15/23, Seksyen 15, G7 10/12/22 RM 1,000,000 Proposed Second Malaysian Project, Finance, Design & Construction 1997 86,100,000
(231481-M) Taman Perindustrian Tiong of 2,100 Low Cost Housing Units for National Housing Development
Nam,40200 Shah Alam, Selangor Company
Darul Ehsan.
Tel: 03-5524 6612 Cadangan Projek Pembangunan Bagi Membina 215 Unit (Fasa 3d) 2020 29,100,000
Fax: 03-5524 6613 Bangunan Kediaman Yang Terdiri Dari: 215 Unit Rumah Teres 2
Email: dianmakmur95@gmail.com Tingkat Di Atas Pt 20814 (Hsd 241561), Taman Iringan Bayu, Mukim
Rantau, Daerah Seremban, Negeri Sembilan Darul Khusus Untuk
Tetuan Aspect Synergy Sdn. Bhd.
2 Khas Corporation Sdn No.17-4, Tingkat 3, Jalan SP 2/2, G7 14/02/23 RM 3,000,000 Cadangan Membina 2 Unit Rumah Contoh Sementara Bagi Cadangan 2012 1,550,000
Bhd (75545-W) Taman Serdang Perdana Section 2, Pembangunan Strata Title “Guard and Gated Community” Untuk 18
43300 Seri Kembangan, Selangor Blok Garden Villa (280 Unit) Diatas Lot 52339 (Dahulunya Lot 8853).
Darul Ehsan Taman Bukit Mewah 8, Lebuhraya Silk 19.80km, Mukim Kajang,
Tel: 03-8943 3399 Daerah Hulu Langat, Selangor Darul Ehsan Untuk Tetuan Metro
Fax: 03-8943 2299 Esquire (M) Sdn Bhd
Email: kl@khascorp.com.my
3 Muara Bernas (M) Sdn No 506, Jalan SJ 9/1 Taman G7 23/09/23 RM 5,000,000 Cadangan Membina Dan Menyiapkan Sebuah Bangunan Makmal 2012 4,051,636.20
Bhd(303010-T) Seremban Jaya 70450, Seremban, Marin Untuk Akedemi Tentera Malaysia (ATMA) Fasa 4 Di Kem Sg.
Negeri Sembilan Darul Khusus. Besi, Kuala Lumpur Untuk Kementerian Pertahanan Malaysia.
Tel: 06-678 5892
Fax:06-678 4795 Cadangan Pembangunan Infrastrukture bangunan “Leadership 2014 4,276,584
Email: muarabernas.sb@gmail.com Development Center-LDC” Di TNB Integrated Learning Solution Sdn
Bhd Di atas Lot 14608, Bandar Baru Bangi, Daerah Sepang, Selangor
D.E
1
PRIVATE & CONFIDENTIAL [updated on 30.3.2023]
CIDB Registration List of Similar Project Experience
Paid Up
No. Company Name Company Address & Contact Expiry Year of
Grade Capital Project title Value (RM)
Date Completion
4 KESB Kamal No 22, Jalan SG 3/2, Taman Sri G7 29/03/24 RM 2,000,000 Cadangan Membina Dan Menyiapkan Sebuah Banglo 1 Tingkat 2011 1,108,136.67
Engineering Sdn Gombak, 68100 Batu Caves, Selangor Beserta Loteng Di No. Lot 1736, Jalan Gajah 11 Kg. Kubu Gajah,
Bhd.(500292-X) Darul Ehsan. Seksyen U17, 40160 Shah Alam, Selangor.
Tel: 03-6186 2405 / 03-6178 2405
Email: inquiry@kesb.com.my
Cadangan Membina Sebuah Pusat Kawalan Integrasi Prasana (3 2017 21,315,228.51
Tingkat) Dengan Tempat Letak Kereta Terbuka Di PT8070, Kuala
Lumpur, Utuk Tetuan Prasana Negara Berhad
5 Semenanjung Teguh No. 76, Jalan Rimbunan Raya, Laman G7 18/10/24 RM 1,000,000 Cadangan Membina Dan Menyiapkan 250 Unit Rumah Teres Mampu 2020 10,350,000.00
Sdn. Bhd. (861399-P) Rimbunan, Batu 6 1/2, Jalan Kepong, Milik Serta Kerja-Kerja Berkaitan Dengannya Di Atas Tanah Kerajaan
52100 Kuala Lumpur. Di Kampung Tajin, Mukim Kuala Berang, Daerah Hulu Terengganu,
Tel: 03 6252 3399 Terengganu Darul Iman. (Pakej 1 & 2 - 180 Unit)
Fax: 03 6252 3996
Email: skfw88@gmail.com Cadangan Membina Dan Menyiapkan 95 Unit Rumah Teres Setingkat 2020 9,815,480.00
‘TYPEA’ Di Atas Lot PT6765-PT6859 Serta Kerja-Kerja Berkaitan Di
Kampung Bukit Keluang, Mukim Keluang, Daerah Besut,Terengganu
Darul Iman.
Cadangan Membina Dan Menyiapkan 103 Unit Rumah Teres Mampu 2019 6,998,395.00
Milik Di Atas Lot PT7014-PT7116 Serta Kerja-Kerja Berkaitan Di
Kampung Bukit Keluang, Mukim Keluang, Daerah Besut,Terengganu
Darul Iman.
` Cadangan Membina Dan Menyiapkan 36 Unit Rumah Sesebuah 2019 7,200,000.00
Setingkat Di Atas Lo tPT6685 - PT6716 Dan Lot PT7117-PT7120
Serta Kerja Kerja Berkaitan Di Kampung Bukit Keluang, Mukim
Keluang, Daerah Besut, Terengganu Darul Iman.
Cadangan Membina Dan Menyiapkan 154 Unit Rumah Teres 2019 16,341,500.00
Setingkat ‘Typeb’ Di Atas Lot Pt6860-Pt7013 Serta Kerja-Kerja
Berkaitan Di Kampung Bukit Keluang, Mukim Keluang, Daerah
Besut,Terengganu Darul Iman
2
PRIVATE & CONFIDENTIAL [updated on 30.3.2023]
CIDB Registration List of Similar Project Experience
Paid Up
No. Company Name Company Address & Contact Expiry Year of
Grade Capital Project title Value (RM)
Date Completion
5 Semenanjung Teguh Cadangan Membina Dan Menyiapkani 11 Unit Rumah Banglo Satu 2017 9,856,600.00
Sdn. Bhd. (861399-P) Tingkat (Typea) ,Ii) 19 Unit Rumah Banglo Satu Tingkat (Typeb) ,Iii) 4
[Cont’d] Unit Rumah Berkembar Satu Tingkat (Typea) ,Iv) 4 Unit Rumah
Berkembar Satu Tingkat (Typeb) , V) 2 Unit Rumah Berkembar Satu
Tingkat (Typec) ,Di, Bukit Gedup, Mukim Kuala Dungun,Terengganu.
6 Mk Megah Sdn Bhd No.36, Jalan Vista 1/9, Desa Vista, G1 09/06/24 Not Provided Pembinaan Rumah Banglo Setingkat Persendirian, Sg. Pelek Not Provided
(1352568-M) 43900 Sepang, Selangor. Selangor.
Tel: 011-5505 8345
Whatsapp: 018-3738 345 Pembinaan Rumah Sewa Sebanyak 10 Unit
Email:mktransbenamegah@gmail.com
Pembinaan Rumah Banglo Setingkat Persendirian, Di Sepang,
Selangor.
7 SH Aluminium No.132, Taman A.S.T. Tingkat Bawah, G1 04/03/23 RM100,000 Kiambang double storey terrace; 5 units Not Provided
(Seremban) Sdn Bhd Suite 7 Jalan Sungai Ujong, 70200
(951570-D) Seremban, Negeri Sembilan. Taman seroja single storey semi-d; 20 units
Tel: 019 – 660 7811
Email: sweethome811@gmail.com Taman Seroja Double storey bungalow; 2 units.
3
PRIVATE & CONFIDENTIAL [updated on 30.3.2023]
CIDB Registration List of Similar Project Experience
Paid Up
No. Company Name Company Address & Contact Expiry Year of
Grade Capital Project title Value (RM)
Date Completion
8 Transnational No. 31, Jalan Bukit Angkat, Kawasan G7 8/9/2023 RM750,000 65 units of single storey terrace houses, 95 units of double storey 2022 16,700,00
Builder Sdn Bhd Perusahaan Bukit Angkat, Kajang, terrace houses and 39 units of single storey semi-detached houses
(1425205-U) 43000 Selangor. (Taman Botanika Residen)
Tel: 012 386 5697 / 012 521 9392
E-mail: clement.toh@ktb.com.my 2,965 units of single storey terrace houses, 157 units of double storey 2021 427,300,000
edison.choo@ktb.com.my terrace houses and 1,492 units of single storey cluster houses
(Bandar Baru Setia Awan Perdana)
79 units of single storey terrace houses (Taman Permatang Permai) 2020 9,100,000
59 units of single storey terrace houses (Taman Lekir Damai) 2019 6,400,000
28 units of single storey semi-detached houses (Taman Anjung Lekir 2018 3,400,000
2)
14 units of single storey semi-detached houses and 1 unit of bungalow 2019 2,200,000
(Taman Lekir Bistari 2)
108 units of double storey terrace houses (Scientex Klebang) 2018 15,000,000
45 units of shop lots & a gated & guarded 108 units of semi-d, cluster 2013 18,000,000
house & 2-storey terrace house (Bercham Nova mixed development)
245 units of single storey terrace houses, 168 units of single storey On going 50,600,00
cluster houses
4
PRIVATE & CONFIDENTIAL [updated on 30.3.2023]
130 units of E7-1 for cadangan projek pembangunan perumahan yang 2017 27,845,018
mengandungi 204 units rumah teres 2 tingkat dan pencawang elektrik
di Bandar Springhill, Pekan Jemima Daerah Port Dickson, Negeri
Sembilan . Untuk tetuan West Synergy
Cadangan mendirikan 193 unit rumah teres 2&3 tingkat di Seremban 2018 47,109,648
Forest Heights, Mukim Ampangan Seremban. Untuk Sunrise MCL
Land Sdn Bhd.
2 UMP Holdings Sdn Bhd Persiaran Bandar Gambang, Off G7 03/08/25 RM4,500,000 Kolej Kediaman 4 UMP Hostel Development Not Provided
(644726-H) Lebuhraya Tun Razak, 26300
Gambang Kuantan, Pahang Darul Projek Perumahan Kolek Makmur Sejahtera
Makmur.
UMP Campus Rental
Commercial Block Development
5
ATTACHMENT 2
MKS 293.22
ATTACHMENT 3
MKS 293.22
SUMMARY OF ERRORS
1 Tenderer A
ORIGINAL TENDER SUM 12,883,360.78
CORRECTED CONTRACT SUM 12,920,523.58
37,162.80
A. Volume 1- Main Building Works
Now Read Should Read Difference
BQ Ref Description Remarks
Cor Int End Cor Int End Cor Int End
Bill No.2 Main Building Works (Type A)
2/13/2 20mm thk plastering to walls 0.00 0.00 6,138.00 0.00 0.00 6,240.30 0.00 0.00 102.30 Multiplication Error
2/15/1D Provisional sum for water tank plinth (RM1,000) 0.00 0.00 0.00 1,000.00 1,000.00 1,000.00 1,000.00 1,000.00 1,000.00 Not priced
TOTAL COST/UNIT 0.00 0.00 6,138.00 1,000.00 1,000.00 7,240.30 1,000.00 1,000.00 1,102.30
NO OF UNITS 3.00 29.00 4.00 3.00 29.00 4.00 3.00 29.00 4.00
SUB-TOTAL (RM) 0.00 0.00 24,552.00 3,000.00 29,000.00 28,961.20 3,000.00 29,000.00 4,409.20
TOTAL ERROR (RM) 24,552.00 60,961.20 36,409.20 (a)
Now Read Should Read Difference
BQ Ref Description Remarks
Cor Int End Cor Int End Cor Int End
Bill No.3 Main Building Works (Type B
3/11/1E C&S paving top 100mm high drop 50.40 50.40 28.80 28.80 -21.60 -21.60 Multiplication Error
3/15/1D Provisional sum for water tank plinth (RM1,000) 0.00 0.00 1,000.00 1,000.00 1,000.00 1,000.00 Not Priced
Not Not
TOTAL COST/UNIT 50.40 50.40 1,028.80 1,028.80 978.40 978.40 Not Applicable
Applicable Applicable
NO OF UNITS 1.00 3.00 1.00 3.00 1.00 3.00
SUB-TOTAL (RM) 50.40 151.20 1,028.80 3,086.40 978.40 2,935.20
TOTAL ERROR (RM) 201.60 4,115.20 3,913.60 (b)
BQ Ref Description Now Read Should Read Difference Remarks
Bill No.4 External & Infrastructure Works
4/4/2(A)C Provisional sum for field & lab test 0.00 5,000.00 5,000.00 Not Priced
TOTAL ERROR (RM) 0.00 5,000.00 5,000.00 (c )
2 Tenderer B
ORIGINAL TENDER SUM 13,755,077.20
CORRECTED CONTRACT SUM 12,605,153.20
-1,149,924.00
A. Volume 1- Main Building Works
Now Read Should Read Difference
BQ Ref Description Remarks
Cor Int End Cor Int End Cor Int End
Bill No.2 Main Building Works (Type A)
2/1/2C VRC Grade 25 to pad footing 0.00 0.00 2,745.00 0.00 0.00 3,050.00 0.00 0.00 305.00 Multiplication Error
2/1/2E VRC Grade 25 to ground beam 0.00 0.00 915.00 0.00 0.00 1,220.00 0.00 0.00 305.00 Multiplication Error
2/4/2A High tensile in RC ledge, 10mm diameter bar 104.00 0.00 0.00 96.00 0.00 0.00 -8.00 0.00 0.00 Multiplication Error
2/5/3E Supply and lay "Excel Floor", extra over for supply 0.00 432.00 0.00 0.00 414.00 0.00 0.00 -18.00 0.00 Multiplication Error
and lay pvc stairs nosing
2/8/10 Carried to collection summary 240.00 0.00 0.00 1,560.00 0.00 0.00 1,320.00 0.00 0.00 Key In Error
2/13/8 Prepare and apply externally "Nippon" to surfaces of 468.00 0.00 0.00 450.00 0.00 0.00 -18.00 0.00 0.00 Multiplication Error
asbestos free cement board
2.S/2 Collection Summary 15,843.00 11,364.00 0.00 3,169.00 3,169.00 0.00 -12,674.00 -8,195.00 0.00 Transferring Error
TOTAL COST/UNIT 16,655.00 11,796.00 3,660.00 5,275.00 3,583.00 4,270.00 -11,380.00 -8,213.00 610.00
NO OF UNITS 3.00 29.00 4.00 3.00 29.00 4.00 3.00 29.00 4.00
SUB-TOTAL (RM) 49,965.00 342,084.00 14,640.00 15,825.00 103,907.00 17,080.00 -34,140.00 -238,177.00 2,440.00
TOTAL COST (RM) 406,689.00 136,812.00 -269,877.00 (a)
Now Read Should Read Difference
BQ Ref Description Remarks
Cor Int End Cor Int End Cor Int End
Bill No.3 Main Building Works (Type B)
3/1/1D Hardcore bed , 100mm thk to receive ground slab 0.00 624.00 0.00 494.00 0.00 -130.00 Multiplication Error
3/1/1F Comcrete Grade 15,50mm thk blinding beneath ground beam 0.00 120.00 0.00 105.00 0.00 -15.00 Multiplication Error
3/1/5 Carried to Collection 5,264.00 4,634.00 6,746.00 5,850.00 1,482.00 1,216.00 Summation Error
3/3/1C VRC Grade 25 to 150mm thk suspended slab 1,368.00 0.00 1,330.00 0.00 -38.00 0.00 Multiplication Error
3/5/6A Handrail & Balustrades 1,400.00 1,400.00 1,600.00 1,600.00 200.00 200.00 Multiplication Error
3/8/2 Carried to Collection 180.00 0.00 1,560.00 0.00 1,380.00 0.00 Summation Error
3/8/4 Carried to Collection 0.00 3,700.00 Not 0.00 3,250.00 Not 0.00 -450.00 Summation Error
Not Applicable
3/9/4 Carried to Collection 1,708.00 1,708.00 Applicable 2,808.00 2,808.00 Applicable 1,100.00 1,100.00 Summation Error
3/12/5 Carried to Collection 2,345.00 2,285.00 1,845.00 1,785.00 -500.00 -500.00 Summation Error
3/16/3 RC Grade 25 Stip footing 800.00 0.00 750.00 0.00 -50.00 0.00 Multiplication Error
3.S/2 Collection Summary 19,955.00 12,702.00 3,169.00 3,169.00 -16,786.00 -9,533.00 Summation Error
TOTAL COST/UNIT 13,065.00 14,471.00 16,639.00 15,892.00 -13,212.00 -8,112.00
NO OF UNITS 1.00 3.00 1.00 3.00 1.00 3.00
SUB-TOTAL (RM) 13,065.00 43,413.00 16,639.00 47,676.00 -13,212.00 -24,336.00
TOTAL COST (RM) 56,478.00 64,315.00 -37,548.00 (b)
3 Tenderer C
ORIGINAL TENDER SUM 13,900,402.20
CORRECTED CONTRACT SUM 13,901,296.60
894.40
4 Tenderer D
ORIGINAL TENDER SUM 14,032,954.00
CORRECTED CONTRACT SUM 14,061,371.50
28,417.50
(c)
BQ Ref Description Now Read Should Read Difference Remarks
Final Summary
BS/FS/1 Total Carried to Form of Tender 13,225,954.00 13,225,954.40 0.40 Summation Error
TOTAL ERROR(RM) 0.40
(d)
TOTAL ERROR 28,417.50
(a) + (b) + (c) +(d)
6. Tenderer F
ORIGINAL TENDER SUM 17,514,016.65
CORRECTED CONTRACT SUM 17,527,364.77
13,348.12
Now Read Should Read Difference
BQ Ref Description Remarks
Cor Int End Cor Int End Cor Int End
Bill No.2 Main Building Works (Type A)
2/3/1 Total Carried To Collection 0.00 0.00 7,012.93 0.00 0.00 7,012.92 0.00 0.00 -0.01 Summation Error
2/3/1B VRC G25 to 150mm thk susp. slab 987.26 987.26 987.25 987.21 987.21 987.21 -0.05 -0.05 -0.04 Multiplication Error
2/3/1C VRC G25 to 150mm thk susp. slab 2,313.02 2,313.02 2,313.02 2,313.22 2,313.22 2,313.22 0.20 0.20 0.20 Multiplication Error
2/4/1B VRC G25 to 125mm thk roof slab/ Water tank slab 752.20 752.20 752.20 752.16 752.16 752.16 -0.04 -0.04 -0.04 Multiplication Error
2/4/1C VRC G25 to 150mm thk car porch roof slab and RC ledge 1,523.21 1,297.55 1,071.89 1,523.34 1,297.66 1,071.98 0.13 0.11 0.09 Multiplication Error
2/8/1A PRC G25 to Lintol 450.00 421.88 421.88 450.08 421.95 421.95 0.08 0.07 0.07 Multiplication Error
2/9/1A PRC G25 to Lintol 421.88 309.38 506.25 421.95 309.43 506.34 0.07 0.05 0.09 Multiplication Error
2/13/5B Concrete soffit, sides and soffit pf beam n.e. 3.5m 0.00 0.00 322.40 0.00 0.00 310.00 0.00 0.00 -12.40 Multiplication Error
2/16/3A 1600mm(H) perimeter brickwall fencing (Cor) 11,480.64 0.00 0.00 11,480.70 0.00 0.00 0.06 0.00 0.00 Multiplication Error
TOTAL COST/UNIT 17,928.21 6,081.29 13,387.82 17,928.66 6,081.63 13,375.78 0.45 0.34 -12.04
NO OF UNITS 3.00 29.00 4.00 3.00 29.00 4.00 3.00 29.00 4.00
SUB-TOTAL (RM) 53,784.63 176,357.41 53,551.28 53,785.98 176,367.27 53,503.12 1.35 9.86 -48.16
TOTAL COST (RM) 283,693.32 283,656.37 -36.95 (a)
Now Read Should Read Difference
BQ Ref Description Remarks
Cor Int End Cor Int End Cor Int End
Bill No.3 Main Building Works (Type B)
3/3/1B VRC G25 to 125mm thk susp. slab 846.23 752.20 846.18 752.16 -0.05 -0.04 Multiplication Error
3/3/1C VRC G25 to 150mm thk susp. slab 1,974.53 2,030.94 1,974.70 2,031.12 0.17 0.18 Multiplication Error
3/4/1B VRC G25 to 125mm thk roof slab/ Water tank slab 799.21 799.21 799.17 799.17 -0.04 -0.04 Multiplication Error
3/4/1C VRC G25 to 150mm thk car porch roof slab 1,071.89 1,071.89 1,071.98 1,071.98 0.09 0.09 Multiplication Error
3/4/4 Total Carried To Collection 0.00 955.00 0.00 955.40 0.00 0.40 Key In Error
3/4/13 Total Carried To Collection Summary 0.00 25,586.64 0.00 25,586.24 0.00 -0.40 Summation Error
3/8/1A PRC G25 to Lintol 337.50 337.50 337.56 337.56 0.06 0.06 Multiplication Error
Not Not
3/8/4B Single leaf timber flush door TYPE D4 0.00 446.40 0.00 892.80 0.00 446.40 Not Applicable Multiplication Error
Applicable Applicable
3/9/1A PRC G25 to Lintol 450.00 450.00 450.08 450.08 0.08 0.08 Multiplication Error
3/11/1D 25mm Thk screeded bed to drop, 50mm high 150.00 150.00 90.00 90.00 -60.00 -60.00 Multiplication Error
3/11/1E 25mm Thk screeded bed to drop, 100mm high 200.00 200.00 120.00 120.00 -80.00 -80.00 Multiplication Error
3/11/1F 25mm Thk screeded bed to skirting, 100mm high 4,200.00 4,200.00 2,520.00 2,520.00 -1,680.00 -1,680.00 Multiplication Error
3/16/3A 1600mm(H) perimeter brickwall fencing (Cor) 11,480.64 0.00 11,480.70 0.00 0.06 0.00 Multiplication Error
TOTAL COST/UNIT 21,510.00 36,979.78 19,690.37 35,606.51 -1,819.63 -1,373.27
NO OF UNITS 1.00 3.00 1.00 3.00 1.00 3.00
SUB-TOTAL (RM) 21,510.00 110,939.34 19,690.37 106,819.53 -1,819.63 -4,119.81
TOTAL COST (RM) 132,449.34 126,509.90 -5,939.44 (b)
BQ Ref Description Now Read Should Read Difference Remarks
Bill No.4 External & Infrastructure Works
4/4/4(A) D(A) VRC G25 to 150mm thk entrance concrete slab 14,216.58 14,217.84 1.26 Multiplication Error
4/4/5(A) F(A) 600mm x 300mm galvanised steel grating 24,960.00 19,200.00 -5,760.00 Multiplication Error
4/4/5(A) G(A) VRC G25 to 150mm thk drain cover slab 3,791.09 3,791.34 0.25 Multiplication Error
4/6/3 Total Carried To Collection 25,800.00 16,800.00 -9,000.00 Summation Error
TOTAL COST (RM) 68,767.67 54,009.18 -14,758.49 (c)
Now Read Should read Difference
BQ Ref Description Cor int Cor int Cor int Remarks
SOP-1(2.2) Electrical (Corner Type A/B) 11,361.00 45,444.00 34,083.00 0.00 Transferring error
TOTAL COST/UNIT 34,083.00 0.00
NO OF UNITS 4.00 36.00 4.00 36.00 1.00 1.00
SUB-TOTAL (RM) 34,083.00 0.00
TOTAL ERROR (RM) 34,083.00
(d)
TOTAL ERROR 13,348.12
(a) + (b) + (c ) + (d)
MKS 293.22
CADANGAN PEMBANGUNAN PERUMAHAN YANG MENGANDUNGI: (A) 36 UNIT 20’ X 60’ RUMAH TERES 2 TINGKAT JENIS A (B) 4 UNIT 20’ X 55’-60’ RUMAH TERES 2 TINGKAT JENIS B (C) 1 UNIT 23’ X 13’ PENCAWANG ELEKTRIK PADAT (D) 1 UNIT LOJI KUMBAHAN DI ATAS LOT 33079 HINGGA 33120 DAN SEBAHAGIAN TANAH
KERAJAAN, TAMAN SERI MAWAR, BANDAR BARU MANTIN, MUKIM SETUL, DAERAH SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS
UNTUK TETUAN PTT DEVELOPMENT SDN. BHD. (DAHULU DIKENALI SEBAGAI HOOVER BUILDERS SDN BHD)
1 2 3 4 5 6
QS Estimate
Tenderer B Tenderer A Tenderer C Tenderer D Tenderer E Tenderer F
Bill Description Amount (RM) Amount (RM) % Amount (RM) % Amount (RM) % Amount (RM) % Amount (RM) % Amount (RM) %
Volume 1 - Main Building Works
1 Preliminaries 517,480.57 372,500.00 72% 960,000.00 186% 726,000.00 140% 651,868.00 126% 1,544,358.50 298% 1,164,285.00 225%
2 Main Building Works (Type A) 6,797,041.44 6,879,993.60 101% 6,755,432.12 99% 7,954,268.00 117% 8,027,041.80 118% 9,045,902.40 133% 9,930,871.12 146%
Corner (3 Units) 649,584.93 646,197.00 99% 646,292.94 99% 757,846.20 117% 819,618.30 126% 872,094.30 134% 959,809.98 148%
Intermediate (29 Units) 5,360,413.07 5,432,285.80 101% 5,318,780.38 99% 6,266,743.40 117% 6,270,574.30 117% 7,137,935.30 133% 7,826,932.38 146%
End (4 Untis) 787,043.44 801,510.80 102% 790,358.80 100% 929,678.40 118% 936,849.20 119% 1,035,872.80 132% 1,144,128.76 145%
3 Main Building Works (Type B) 717,908.61 741,994.50 103% 717,045.94 100% 850,030.90 118% 861,709.60 120% 971,686.10 135% 1,056,856.03 147%
Corner (1 Units) 203,136.06 208,532.10 103% 202,511.23 100% 239,040.70 118% 257,148.10 127% 275,442.50 136% 301,815.88 149%
Intermediate (3 Units) 514,772.55 533,462.40 104% 514,534.71 100% 610,990.20 119% 604,561.50 117% 696,243.60 135% 755,040.15 147%
4 External & Infrastructure Works 2,037,661.28 2,190,735.10 108% 2,562,105.12 126% 2,465,333.70 121% 2,378,050.10 117% 2,702,600.90 133% 2,743,224.12 135%
5 Prime Cost And Provisional Sums 797,000.00 782,000.00 98% 792,000.00 99% 802,000.00 101% 807,000.00 101% 807,000.00 101% 792,000.00 99%
Sub - Total 10,867,091.90 10,967,223.20 101% 11,786,583.18 108% 12,797,632.60 118% 12,725,669.50 117% 15,071,547.90 139% 15,687,236.27 144%
Difference from Consultant Estimate (RM / %) BASE 100,131.30 1% 919,491.28 8% 1,930,540.70 18% 1,858,577.60 17% 4,204,456.00 39% 4,820,144.37 44%
6 Volume 2 - M&E Works 934,360.00 1,637,930.00 175% 1,133,940.40 121% 1,103,664.00 118% 1,335,702.00 143% 1,314,086.40 141% 1,840,128.50 197%
Overall Tender Sum 11,801,451.90 12,605,153.20 107% 12,920,523.58 109% 13,901,296.60 118% 14,061,371.50 119% 16,385,634.30 139% 17,527,364.77 149%
Difference from Consultant Estimate
BASE 803,701.30 7% 1,119,071.68 9% 2,099,844.70 18% 2,259,919.60 19% 4,584,182.40 39% 5,725,912.87 49%
(RM / %)
Difference from Lowest (RM) BASE 315,370.38 3% 1,296,143.40 10% 1,456,218.30 12% 3,780,481.10 30% 4,922,211.57 39%
UNTUK TETUAN PTT DEVELOPMENT SDN. BHD. (DAHULU DIKENALI SEBAGAI HOOVER BUILDERS SDN BHD)
1 2 3 4 5 6
QS Estimate
Tenderer A Tenderer B Tenderer C Tenderer D Tenderer E Tenderer F
Bill Description Amount (RM) Amount (RM) % Amount (RM) % Amount (RM) % Amount (RM) % Amount (RM) % Amount (RM) %
Volume 1 - Main Building Works
1 Preliminaries 517,480.57 960,000.00 186% 372,500.00 72% 726,000.00 140% 651,868.00 126% 1,544,358.50 298% 1,164,285.00 225%
2 Main Building Works (Type A) 6,797,041.44 6,719,022.92 99% 7,992,369.60 118% 7,954,095.20 117% 8,015,525.70 118% 9,115,204.20 134% 9,930,908.07 146%
Corner (3 Units) 649,584.93 643,292.94 99% 747,675.00 115% 757,831.80 117% 818,170.80 126% 865,605.00 133% 959,808.63 148%
Intermediate (29 Units) 5,360,413.07 5,289,780.38 99% 6,355,065.80 119% 6,266,604.20 117% 6,256,567.30 117% 7,204,539.60 134% 7,826,922.52 146%
End (4 Untis) 787,043.44 785,949.60 100% 889,628.80 113% 929,659.20 118% 940,787.60 120% 1,045,059.60 133% 1,144,176.92 145%
3 Main Building Works (Type B) 717,908.61 713,132.34 99% 779,542.50 109% 849,309.30 118% 851,423.60 119% 967,726.10 135% 1,062,795.47 148%
Corner (1 Units) 203,136.06 201,532.83 99% 221,744.10 109% 238,860.30 118% 254,215.10 125% 274,223.15 135% 303,635.51 149%
Intermediate (3 Units) 514,772.55 511,599.51 99% 557,798.40 108% 610,449.00 119% 597,208.50 116% 693,502.95 135% 759,159.96 147%
4 External & Infrastructure Works 2,037,661.28 2,557,105.12 125% 2,190,735.10 108% 2,465,333.70 121% 2,371,435.10 116% 2,702,600.90 133% 2,757,982.61 135%
5 Prime Cost And Provisional Sums 797,000.00 792,000.00 99% 782,000.00 98% 802,000.00 101% 1,335,702.00 168% 807,000.00 101% 792,000.00 99%
FS Error. Amount for PC Sum was inserted as M&E Sum
Sub - Total 10,867,091.90 11,741,260.38 108% 12,117,147.20 112% 12,796,738.20 118% 13,225,954.00 122% 15,136,889.70 139% 15,707,971.15 145%
Difference from Consultant Estimate (RM / %) BASE 874,168.48 8% 1,250,055.30 12% 1,929,646.30 18% 2,358,862.10 22% 4,269,797.80 39% 4,840,879.25 45%
6 Volume 2 - M&E Works 934,360.00 1,142,100.40 122% 1,637,930.00 175% 1,103,664.00 118% 807,000.00 86% 1,314,086.40 141% 1,806,045.50 193%
Overall Tender Sum 11,801,451.90 12,883,360.78 109% 13,755,077.20 117% 13,900,402.20 118% 14,032,954.00 119% 16,450,976.10 139% 17,514,016.65 148%
Difference from Consultant Estimate
BASE 1,081,908.88 9% 1,953,625.30 17% 2,098,950.30 18% 2,231,502.10 19% 4,649,524.20 39% 5,712,564.75 48%
(RM / %)
Difference from Lowest (RM) BASE 871,716.42 7% 1,017,041.42 8% 1,149,593.22 9% 3,567,615.32 28% 4,630,655.87 36%
MKS 293.22
CADANGAN PEMBANGUNAN PERUMAHAN YANG MENGANDUNGI: (A) 36 UNIT 20’ X 60’ RUMAH TERES 2 TINGKAT JENIS A (B) 4 UNIT 20’ X 55’-60’ RUMAH TERES 2
TINGKAT JENIS B (C) 1 UNIT 23’ X 13’ PENCAWANG ELEKTRIK PADAT (D) 1 UNIT LOJI KUMBAHAN DI ATAS LOT 33079 HINGGA 33120 DAN SEBAHAGIAN TANAH
KERAJAAN, TAMAN SERI MAWAR, BANDAR BARU MANTIN, MUKIM SETUL, DAERAH SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS
UNTUK TETUAN PTT DEVELOPMENT SDN. BHD. (DAHULU DIKENALI SEBAGAI HOOVER BUILDERS SDN BHD)
1 2 3 4 5 6
QS Estimate
Item Descriptions Tenderer B Tenderer A Tenderer C Tenderer D Tenderer E Tenderer F
Amount(RM) Amount(RM) Amount(RM) Amount(RM) Amount(RM) Amount(RM) Amount(RM)
1/56/5 Levels and Setting Out of Works 10,000 12,600.00 10,000.00 15,000.00 80,865.30 9,000.00
1/60/8&10 Site Agent / Site Staff 198,000 192,000.00 140,000.00 50,000.00 615,000.00 80,000.00
1/60/11 Variation, Provisional and Prime Cost Sum 96,000.00
1/62/18-20A Workmen Compensation & CAR Insurance 20,000 22,700.00 23,000.00 29,260.00 19,687.30 35,939.00
TOTAL 517,481 372,500.00 960,000.00 726,000.00 651,868.00 1,544,358.50 1,164,285.00
Tender Sum (-) Preliminaries 11,283,971.33 12,232,653.20 11,960,523.58 13,175,296.60 13,409,503.50 14,841,275.80 16,363,079.77
% of Preliminaries / Tender Sum 5% 3% 8% 6% 5% 10% 7%
MKS 293.22
CADANGAN PEMBANGUNAN PERUMAHAN YANG MENGANDUNGI: (A) 36 UNIT 20’ X 60’ RUMAH TERES 2 TINGKAT JENIS A (B) 4 UNIT 20’ X 55’-60’ RUMAH TERES 2 TINGKAT JENIS B (C) 1 UNIT 23’ X 13’ PENCAWANG ELEKTRIK PADAT (D) 1 UNIT LOJI KUMBAHAN DI ATAS LOT 33079 HINGGA 33120 DAN SEBAHAGIAN TANAH KERAJAAN, TAMAN SERI
MAWAR, BANDAR BARU MANTIN, MUKIM SETUL, DAERAH SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS
UNTUK TETUAN PTT DEVELOPMENT SDN. BHD. (DAHULU DIKENALI SEBAGAI HOOVER BUILDERS SDN BHD)
COMPARISON OF GENERAL SUMMARY OF BILL 2 MAIN BUILDING WORKS (TYPE A) Date: 4/11/2023
TOTAL COST (RM) 6,797,041.44 6,879,993.60 6,755,432.12 7,954,268.00 8,027,041.80 9,045,902.40 9,930,871.12
TOTAL COST (RM) 717,908.61 741,994.50 717,045.94 850,030.90 861,709.60 971,686.10 1,056,856.03
Attachment 6 | Comparison of General Summary Bill 2 And 3 - Main Building Works (Type A and B)
CADANGAN PEMBANGUNAN PERUMAHAN YANG MENGANDUNGI: (A) 36 UNIT 20’ X 60’ RUMAH TERES 2 TINGKAT JENIS A (B) 4 UNIT 20’ X 55’-60’ RUMAH TERES 2 TINGKAT
JENIS B (C) 1 UNIT 23’ X 13’ PENCAWANG ELEKTRIK PADAT (D) 1 UNIT LOJI KUMBAHAN DI ATAS LOT 33079 HINGGA 33120 DAN SEBAHAGIAN TANAH KERAJAAN, TAMAN
SERI MAWAR, BANDAR BARU MANTIN, MUKIM SETUL, DAERAH SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS
UNTUK TETUAN PTT DEVELOPMENT SDN. BHD. (DAHULU DIKENALI SEBAGAI HOOVER BUILDERS SDN BHD)
Attachment 6 | Comparison of General Summary Bill 4 And 5 - Prime Cost And Provisional Sum
ATTACHMENT 7
MKS 293.22
CADANGAN PEMBANGUNAN PERUMAHAN YANG MENGANDUNGI: (A) 36 UNIT 20’ X 60’ RUMAH TERES 2 TINGKAT JENIS A (B) 4 UNIT 20’ X 55’-60’ RUMAH TERES 2 TINGKAT JENIS B (C) 1 UNIT 23’ X 13’ PENCAWANG ELEKTRIK PADAT (D) 1 UNIT LOJI KUMBAHAN DI ATAS LOT 33079 HINGGA 33120 DAN SEBAHAGIAN TANAH KERAJAAN,
TAMAN SERI MAWAR, BANDAR BARU MANTIN, MUKIM SETUL, DAERAH SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS
UNTUK TETUAN PTT DEVELOPMENT SDN. BHD. (DAHULU DIKENALI SEBAGAI HOOVER BUILDERS SDN BHD)
UNTUK TETUAN PTT DEVELOPMENT SDN. BHD. (DAHULU DIKENALI SEBAGAI HOOVER BUILDERS SDN BHD)
Floor 300mm x 300mm ceramic tiles as "Guocera, Code: K1722D 120 M2 72.79 8,734.80 65.00 7,800.00 68.90 8,268.00 80.40 9,648.00 74.80 8,976.00 66.00 7,920.00 137.20 16,464.00
Tiles Manhattan Grey" or other approved equivalent to floor
(Washing Area)
11 8mm thick laminated timber flooring 2,092 M2 79.06 165,393.52 88.00 184,096.00 70.30 147,067.60 80.50 168,406.00 97.80 204,597.60 83.10 173,845.20 84.80 177,401.60
12 Screeding Works 7,601 M2 26.83 203,910.40 23.09 175,545.00 26.81 203,776.60 23.34 177,392.10 26.40 200,697.30 22.37 170,043.40 53.13 403,865.40
Wall 20mm Thick backing screed to receive wall tiles (Kitchen, 2,896 M2 28.30 81,956.80 20.00 57,920.00 22.60 65,449.60 22.10 64,001.60 17.80 51,548.80 19.40 56,182.40 51.40 148,854.40
Tiles
Floor Bath
25mm 1-3)
Thick screeded bed to floor to receive tiles including 2,577 M2 25.92 66,795.84 25.00 64,425.00 29.40 75,763.80 24.10 62,105.70 31.70 81,690.90 24.20 62,363.40 54.20 139,673.40
Tiles finish to falls and cross falls to bathroom (Living, Dining,
Kitchen, Bedroom 4, Washing Area, Bath 1-3)
25mm Thick screeded bed to floor to receive laminated 2,128 M2 25.92 55,157.76 25.00 53,200.00 29.40 62,563.20 24.10 51,284.80 31.70 67,457.60 24.20 51,497.60 54.20 115,337.60
timber flooring ( Study Area, Master Bedroom, Bedroom 2
& 3)
13 Skim Coat (Int + Ext) 4,053.00 M2 6.81 27,600.93 17.62 71,405.00 13.40 54,310.20 9.70 39,314.10 8.60 34,855.80 24.14 97,849.40 12.40 50,257.20
Int. Skim coat to Concrete soffit, sides and soffit of beams 2,992 M2 6.81 20,375.52 15.00 44,880.00 13.40 40,092.80 9.70 29,022.40 8.60 25,731.20 13.20 39,494.40 12.40 37,100.80
not exceeding 3.50m above floor level (Living, Dining,
Kitchen, Washing Area, Bedroom 3, Bedroom 4, Utility
1&2)
Ext. Concrete soffit, sides and soffit of beams not 1,061 M2 6.81 7,225.41 25.00 26,525.00 13.40 14,217.40 9.70 10,291.70 8.60 9,124.60 55.00 58,355.00 12.40 13,156.40
exceeding 3.50m above floor level (Car Porch, Utility 1,
Terrace, Apron)
14 Plastered Ceiling 2,384.00 M2 49.03 116,898.40 78.32 186,720.00 38.53 91,847.20 33.64 80,197.60 50.06 119,354.40 55.37 131,991.20 40.74 97,124.00
9.5mm Thick plasterboard flat ceiling lining, not exceeding 1,588 M2 47.52 75,461.76 75.00 119,100.00 36.50 57,962.00 31.80 50,498.40 49.50 78,606.00 55.00 87,340.00 36.70 58,279.60
3.50m high ( Master Bedroom, Bedroom 2, Study Area)
9.5mm Thick plasterboard flat ceiling lining, exceeding 400 M2 52.27 20,908.00 75.00 30,000.00 36.50 14,600.00 9.70 3,880.00 49.50 19,800.00 55.00 22,000.00 47.71 19,084.00
3.5m not exceeding 5.0m high (Study Area)
Water resistant plaster board ceiling lining, not exceeding 396 M2 51.84 20,528.64 95.00 37,620.00 48.70 19,285.20 65.20 25,819.20 52.90 20,948.40 57.20 22,651.20 49.90 19,760.40
3.50m high from floor level (Bath 1,Bath 2, Bath 3)
15 Supply and lay stamped concrete imprint 1,532 M2 55.00 84,260.00 95.00 145,540.00 48.60 74,455.20 69.00 105,708.00 86.30 132,211.60 121.50 186,138.00 110.70 169,592.40
TOTAL ARCHITECTURAL MAJOR ITEM 2,851,333.52 3,067,644.00 2,833,468.50 3,462,048.50 3,377,567.70 3,637,662.40 4,298,829.10
RM BASE 216,310.48 - 17,865.02 610,714.98 526,234.18 786,328.88 1,447,495.58
DIFFERENCE FROM QS ESTIMATE
% 7.6% -0.6% 21.4% 18.5% 27.6% 50.8%
12
Appendices (for Marketing)
Property roadshows at NSK Seremban 2
Agent reported there are total of 23 registrants during the roadshow. The next roadshow is at Econmart Mantin
(1/6/2023 – 15/6/2023)
13
APPENDIX 3
14
Development Key Schedule
Revised 2 as Revised 3 as
Description Baseline Date Remarks
17/04/2023 31/05/2023
Submission of the KM
Approved Approved Approved
(Kebenaran Merancang)
Submission of Building Resubmission due to revised
Approved Approved Approved
Plan layout and time frame issue.
Preparation of revised
July/Aug 2022 Completed Completed Completed
layour design
OSC (Online) submisson Lulus dengan syarat on 11th
on 12th October 2022 Dec 2022, and one of the
syarat to comply is obtained
OSC (Hard Copy) Building Plan approval by
submission target by 16th Bomba.
Revised submission of November 2022,
Building Plan Building Plan Approval from
Result obtained from Bomba received by 9th
OSC meeting is Lulus Jan 2023 and resubmit
dengan syarat on 11th building plan submission to
November 2022 Majlis Bandaraya Seremban.
Received by Consultant on
Approval of Building Plan 15th Jan 2023 21st February 2023 21st February 2023
27th February 23
Preparation for Marketing Nov – Dec 2022 Registration – Stage 2 is
material & Sales and targeted in Jan 2023
Marketing activities 15th Nov 2022 – 1st Mar Official launch targeted in 19th
2023 onwards March 2023
Submission of AP 16th Jan – 15th Feb 2023 15th March 2023 15th March 2023 Upon approval Building Plan &
Amended DL
15
10th May 2023
Approval of AP (with
Signing of Sales and Purchase
condition) 28th Feb 2023 3rd May 2023
Target Final Approval – Agreement (SPA) after
Final approval of AP
15th June 2023 the AP is obtained.
A detail drawing and
schematic is completed and
proceed for tender
documents.Preparation of
Details design 1st Nov – 31st Dec 2022 Completed Completed
contract strategy.Compiling
and screening the selective
tenderer for tender invitation.
BQ preparation for Tender 31st Dec – 4th Feb 2023 31st Dec – 4th Feb 2023 31st Dec – 4th Feb 2023 Completed
PT Estimate
Completed
Tender closing was extended
Tender period 6th Feb – 28th Feb 2023 7th March – April 2023 7th March – April 2023 to 3rd April 2023 at the request
of tenderers and Addendum
Evaluation and
1st Mar – 15th Mar 2023 3rd April – 17th April 2023 3rd April – 3rd May 2023
Clarification
Tender validity from 3rd May
Award process for 2023 – 30th august 2023
20th Mar – 27th Mar 2023 18th April – 10th May 2023 1st June – 1st July 2023
Contractor (120days - under clause 16 in
the Conditions of tendering)
15th May 2023 – 15th 15th July 2023 – 15th
September 2024 November 2024 Target to start on site (subject
Construction to start 30th Mar – 30th Apr 2023
(Duration to complete by (Duration to complete by to 30% of SPA signing).
16 months) 16 months)
16
PTT DEVELOPMENT SDN BHD
CASH BOOK FOR MANTIN PROJECT - SEKATA SRI MAWAR
PROPOSED RESIDENTIAL DEVELOPMENT AT TAMAN SRI MAWAR BANDAR BARU MANTIN, MUKIM SENTUL, DAERAH SEREMBAN NEGERI SEMBILAN DARUL KHUSUS
Date : as at 23/5/2023
Date Recipients Particulars In (RM) Out (RM) Closing Balance
17/04/2023 BALANCE B/F 773,005.00
18/05/2023 MKS CQS SDN BHD PC2 - QUANTITY SURVEYING CONSULTANCY SERVICES 27,348.00 745,657.00
18/05/2023 ARKITEK CKL PC3 - CONTRACT DOCUMENTATION (15%)-PROPOSED DEV OF 40 UNITS TERRACE HOUSES AT LOT 33079 TO 3179 29,415.00 716,242.00
716,242.00
- 56,763.00
-