1.0 INTRODUCTION
AIM 1.1
OBJECTIVE 1.2
SCOPE OF STUDY 1.3
CONTENT
2
2.0 PREPARATION OF PLANNING FEES
SCOPE OF WORK 2.1
PROJECT DETAILED 2.2
SCALE OF FEES 2.3
PROPOSED FEES 2.4
1.0 INTRODUCTION
Valuation for the conversion of land use, or more technically, change of category of land use or
express condition of title, is normally carried out by the Valuation and Property Services
Department of Malaysia (JPPH Malaysia).
Pursuant to Section 52 of the National Land Code 1965, all alienated lands are divided into
three (3) categories of land use i.e. “Agriculture”, “Building” and “Industry”. All landowners
must use the land in accordance with the category of land use and the express condition
stipulated in the title. Failure to do so is a breach of a condition of the land alienated and the
State Authority can forfeit the land. As such any landowner who intends to use his land for
another category of use other than the category stated in the title must apply to change the
category of land use accordingly. Sections 124 and 124A of the National Land Code and the
respective State Land Rules allow landowners to apply for such changes. The State Authority
will charge an additional premium on all applications approved for change of use. Then, in this
project, the developer needs to propose a change of land category and land subdivision under
section 124 (1) national land code1965, from agriculture to building for development of terrace
houses.
1.1 Aim
Change of land category form agriculture to building :
a) To the development of terrace house, apartment, facilities, infrastructure.
1.2 Objective
Need to change land use activity from agriculture to housing. This method needs to be
undertaken before implementing some agricultural land growth. Plan to be built is a terrace
house with 150 units in 22,200 square meters, 350 apartment units with 4 stores in 22,000
square meters, services and amenities. In this building the estimated floor space is 46,500
square meters, with 10 hectares of construction area.
▪ Planner
Planners involves overseeing all aspects of planning, including reviewing research on economic
and environmental impacts. Planners work with developers and with other communities on the
best way to turn proposals into reality that means recommending either the proposals be
rejected if research and analysis show that the project would not be beneficial or might actually
be detrimental.
▪ Architect
Project architects are working with the construction using AutoCAD, Sketchup, and other tools
to make the building more practical. Architect's area of work is designing and writing designs
for residential building projects. An urban designer can sometimes collaborate with engineers to
make sure that project are built in accordance with native principles codes and consumer
expectations cross.
▪ Landscape Architect
Landscape Architects integrate and apply knowledge of ecology, socio-cultural influences,
economics and aesthetics to create practical, imaginative, suitable and attractive environments.
Landscape Architects' talents are evident in the beauty and utility of our parks, natural areas,
gardens, urban squares, highways, neighborhoods and communities all around us. Landscape
architects scope of work include master planning, site preparation, landscape design, project
management and execution in a broad range of fields.
▪ Land Surveyor
Land surveyor scope of work are direct or conduct surveys in order to establish legal
boundaries for properties, based on legal deeds and titles, record the results of surveys,
including the shape, contour, location, elevation, and dimensions of land or land features and
also make exact measurements and determine property boundaries. Other than that, they need
to Provide data relevant to the shape, contour, gravitation, location, elevation, or dimension of
land or land features on or near the earth's surface for engineering, mapmaking, mining, land
evaluation, construction, and other purposes.
▪ Civil and Structural Engineer
Analyze survey reports, maps, drawings, blueprints, aerial photography, and other
topographical or geologic data to plan projects.Next prepare plan and design transportation or
hydraulic systems and structures, following construction and government standards, using
design software and drawing tools. Civil and structural engineer perform engineering duties in
planning, designing, and overseeing construction and maintenance of building structures, and
facilities, such as roads, railroads, airports, bridges, harbors, channels, dams, irrigation projects,
pipelines, power plants, water and sewage systems, and waste disposal units.
▪ Traffic Engineer
Traffic engineer scope of work are included develop plans for surface transportation projects,
according to established engineering standards and state or federal construction policy. Then
prepare designs, specifications, or estimates for transportation facilities and also plan
modifications of existing streets, highways, or freeways to improve traffic flow.
The project development is residential area within 10 hectares of total area. The type of
residential that will develop consists of terrace houses for 150 units complete with facilities and
infrastructure and apartment with 4 stores with total 350 units and also with complete facilities
and infrastructure
Type Of Project Unit Total Unit Per Sq.M 1 Unit Per Sq.M
Terrace House 150 22,200 148
Apartment(4Storey) 350 22,200 63.42
Facilities - 1,500 -
Infrastructure - 800 -
Total 7,250
SST 6% 435
File Registration Fee=RM50.00 100
Site Visit Charge Fee=RM50.00
Total 7,785
Total 64,877.66
a) On the basis of land area where the application for change of use (change of use, density for
residential and plot ratio for commercial, industrial and institutional or increase in height) is
made, the fees shall be:
Total 60,000
Total 75,000
c) Schedule of Payment for Preparation of Layout Plan for Planning Permission Application
Total 6,680,000
e) The schedule of payment for Preparation of Planning Permission Application for Erection of
Building
Prior to its establishment in May 1890 to administer Klang town, Klang Local Authority was
known as Klang Health Board. Its official boundary was set in 1895, which was later combined
with Port Swettenham in December 1945 to form Klang Municipal Board. Further change in
the administration came when Klang Town Council was established in 1954. With this new
administrative system Klang developed rapidly until 1971 when Port Klang, Kapar and Meru
were incorporated to form Klang District Council. With the enforcement of the Local
Government Act 1976 (Act 171) and the reorganisation of all local authorities, Klang District
Council was upgraded to Klang Municipal Council (KMC) on 1st January 1977.
7
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
Development control is the process by which authorities manage the extent and nature of
growth in local areas. In other terms, it is a process that authorities organize, plan and
implement local development plan control in line with the planning. It also required an
application permission in development control process that regulate the quality of environment
and physical planning.
In the first phase of planning process, any consultant and developer need to submit Form A
which is an application of the planning permission. Every application of planning permission is
necessary to follow every process that will be notified by an officer in the One Stop Centre
(OCS) division. One Stop Center is a new way to shorten the period of time for the approval of
land development as an alternative to speed up the approval process and directly land delivery
system procedures and processes of land development proposal on local authorities to disclose
towards a comprehensive service, fast and accurate and meet the needs of the public.
At the second phase, an officer in the OSC division will accept application of planning
permission that is to follow each process. The process starts from the beginning of the process
that you want to develop until a planning permission certificate is obtained. There are several
processes that the individuals need to go through in order to submit their application which is:
1. The individual need go to the district office to get all the information related to the site; and
2. Go to the planner section to list the area you want to build.
This process must pay a certain amount of fees before going to the next phase, which is to
report this document to the OSC department. The OSC shall provide such support for the
individual concerned to submit to the OSC meeting to ensure that the application is complied
with or not, if the application is not approved, the individual must re-process and repair the
defective amendment in the next meeting.
At the final phase, the application is passed and the planning permission certificate will be
granted by the planning department. This indicates that construction has already been approved.
But each planning permission certificate has an expired period in which construction is due to
commence on a specified date.
8
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
Making an application
Application is valid No
Yes
Publicity, neighbourhood
notification and consultations
applicable Pre-decision amendments
Delegated/committee decision
1
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
AGENCIES FUNCTION
1
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
1. Housing 50/unit
i. 100-unit first 45/unit
ii. 100-unit second 40/unit
iii. More than 200 unit 25/unit
iv. Low cost houses
2. Commercial and private institutions 50
i. 100 sq. first 45
ii. 75 sq. next 30
iii. 50 sq. next (include cemetery, mausoleum and crematorium)
3. Industry 50
i. 100 sq. first 30
ii. 75 sq. next 25
iii. 50 sq. next
4. Hotel/Homestay/Chalet/Motel/Service Apartment (support building 50/room or unit
activities using rates set for their respective types or development
component)
5. Petrol Station 500/unit
i. Regular Petrol station 800/unit
ii. Petrol station with service facilities
6. Golf Field (support building activities using rates set for their 1000/permission
respective types or development component
7. Infrastructure 2000/permission
i. Telecommunication tower 500/permission
ii. Oil pipe/ gas 500/permission
iii. Electric substations, main substations, electrical main intake 500/permission
iv. Sewerage station 500/permission
v. Solid system transit site/station (support building activities
using rates set for their respective types or development
component)
8. Other development 2/square
i. Parking lot 5/square
ii. Heavy parking site 1000/permission
iii. Private jetty (support building activities using rates set for 0.5/square
their
iv. respective types or development component)
2. Land Division
a) Residential 30/plot
i. Linked residential or bungalow plot 30/unit
ii. Residential plot for multi-layered development residential
without breakdown/broad zoning (the fee rate is based on
the allowable density)
b) Commercial
i. Shop house plot/linked office 50/plot
ii. Commercial complex plot/office/exhibition 500/plot
iii. Another trade plot (without any breakdown/broad zoning) 0.20/square meter
c) Industry
i. Linked industry plot 50/plot
ii. Free standing building industry plot 500/plot
iii. Another plot industry (without any breakdown/broad 0.10/square meter
zoning)
d) Agriculture 50/plot
i. Normal agriculture plot/ orchard/ commercial/ farms in all
colonies
ii. Normal agriculture plot/ orchard/ commercial/ farms in
Kecil Lojing colonies
v. To make changes to the layout plan or addition/ changes above a building that has planning
permission
In conclusion, the town and country planning system is a blueprint to regulate the development
and utilization of land in the public interest. It is an important resource for the conservation and
enhancement of the built and natural environment. Then, to develop the property, it's important
to make sure the owner knows the planning process and procedure. This is due to ensuring that
the job sequences and the development to be achieved run seamlessly and have not been
constrained by another party. In addition, to make it a possibility, the owner still has to provide
the specifications that the contractor can carry out and handle. It is also a compulsory measure
in which the developer and all involved parties must follow all the rules and guidelines
implemented by the authorities in order to meet the requirement and satisfy the need of all
parties.
4.0 REFERENCE
5.0 APPENDIX
5.1 Carta Alir Proses Permohonan
14
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
5.0 APPENDIX
5.2 Borang kebenarang merancang
15
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
16
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
17
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
18
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
19
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
20
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
21
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
22
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
23
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
24
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
25
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
26
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
27
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
28
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
29
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
30
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
31
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
32
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
33
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
34
TPS 584: PROFFESIONAL PRACTICE
PLANNING FEES & SUBMISSION
OF PLANNING PERMISSION TO LOCAL AUTHORITY
35
TPS 584: PROFFESIONAL PRACTICE