S. No.

Essential details Sought Reply


1. Form I Form I along with toposheet showing the sensitivity
is enclosed as Annexure I.
2. New Project/Expansion The project is a proposed Hotel project with Builtup
area 37,790.80 sq.m
3. In case of Expansion-Point wise compliance Not applicable, The project is a proposed Hotel
report of earlier EC duly certified by Project.
RSPCB/SEIAA/MoEF.
4. Location (maps showing general location / Location map enclosed as Annexure II.
specific location /project boundaries and
project site layout) along with KML file.
5. Size including Project area and gross builtup Project Summary enclosed as Annexure III.
area.
6. Affidavit regarding violation of EIA Affidavit regarding violation of EIA notification and
notification and regarding correctness of regarding correctness of submitted data & document
submitted data & document by project is enclosed as Annexure IV.
proponent —Annx.
7. Duly filled environment sensitivity portion of Form I along with toposheet showing the sensitivity
Form I clearly showing distance from is enclosed as Annexure I.
national / state boundary /protected areas /
sanctuaries/National park and it area falls
within 10 kms from boundary of
sanctuaries/National park a copy of
application submitted NBWL, New Delhi.
8. Partnership Deed/Directors list. List of Directors enclosed as Annexure V.
9. Disclosure of the consultant engaged Disclosure of the consultant engaged is enclosed as
including the sector and serial no. in the latest Annexure VI.
QCI/NABET list.
10. Mail id of PP arifkhan73@gmail.com
11. DCF certificate clearly showing distance DCF certificate clearly showing distance from Wild
from Wild life sanctuary (WLS)/National life sanctuary (WLS)/National Park is enclosed as
Park and NOC from NBWL if area falls Annexure VII.
within 10 Kms from boundary of wild life
Sanctuary/National Park.
12. Annexure G Annexure G enclosed as Annexure VIII
13. Water demand and source of water with copy The total water demand for the hotel project will be
of application submitted to CGWA for 433 KLD (fresh water: 241 KLD and the
withdrawal of ground water. recycled/reused water demand: 192 KLD). The fresh
water requirement will be sourced from Municipal
water supply. The letter for the supply of fresh water
has been submitted. Copy of the same is enclosed as
Annexure IX.
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

APPENDIX I
(See paragraph – 6)

FORM 1

I. Basic Information

S. No Item Details
1. Name of the Project/s : Proposed Hotel Project “JW. Marriott Udaipur”
Promoted by: Shri Madhav Hotels Pvt. Ltd.
2. S. No. in the schedule : 8(a) {Building and Construction projects ≥ 20,000 sq.
m. and <1,50,000 sq. m. of built-up area }
3. Proposed capacity/ area/ length/ : Total plot area : 10508 sq.m
tonnage to be handled/ Built up area : 37,790.80 sq.m
command area/ lease area/ The proposed project involves construction of Hotel
number of wells to be drilled project. The project will constitute of 230 guest
rooms, along with facilities like restaurant, BAR,
Banquet hall, Party Lawn etc. Details are as under :

S. No Particulars Details
1. No of Blocks 1 no.
2. No of Floors LB+UB+ GF+ Seventh Floor
3. Project facilities o Guest Rooms : 230nos.
o Restaurant : 1 no. ( 253 Pax)
o Banquet hall : 1 no. ( 1226pax)
o Ball room : 468 sq.m (361 Pax)
o Retail : 89 sq.m

4. New/Expansion/Modernization : New

5. Existing capacity/area etc : Not applicable


6. Category of project i.e. 'A' or 'B' : Category- B2
7. Does it attract the general : General conditions not applicable on projects listed
condition? If yes, please under Item 8 of Schedule of EIA Notification, 2006
specify. and its subsequent amendments thereof.

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

8. Does it attract the specific : Specific conditions are not applicable on projects
condition? If yes, please listed under item 8 of the schedule- EIA notification,
specify. 2006 and its subsequent amendments thereof.
9. Location
Plot/Survey/Khasra no. : Khasra no. 1360
Village/Area : Village Hawala Khurd
Tehsil : Girwa
District : Udaipur
State : Rajasthan
10. Nearest Railway station/ : As under:
Airport along with distance in Nearest Name Distance (aerial) &
kms. Direction
Railway Udaipur City Railway 6.6 KM SE
Station Ranapratap Nagar 7.7 KM ESE
Railway Station
Airport Maharana Pratap 22.5 KM E
Airport Udaipur

11. Nearest Town, City, District : Nearest District Headquarter: Collectorate– 4.54
Headquarters along with kms towards SSE.
distance in kms.
12. Village Panchayat, Zilla : Urban Improvement Trust, Udaipur – 2.92 km towards
Parishad, Municipal SSE
Corporation, Local body Address:
(Complete postal address with Urban Improvement Trust, Udaipur
telephone no. to be given) Moti Magri Rd, Moti Magri Scheme, Zinc Park,
Udaipur, Rajasthan 313001
13. Name of the applicant : Shri Madhav Hotels Pvt. Ltd.
14. Registered address : G-4, B-6B, Steerling Apartment Prithviraj Road C-
Scheme Jaipur
15. Address for correspondence:
Name : Mr. Arif Khan

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

Designation : Authorised Signatory


(Owner/Partner/CEO)
Address : G-4, B-6B, Steerling Apartment Prithviraj Road C-
Scheme Jaipur
Pin Code :
E-mail : arifkhan73@gmail.com
16. Details of alternative sites : No alternative site was examined.
examined, if any. Location of
these sites should be shown on a
Toposheet.
17. Interlinked projects : No
18. Whether separate application of : No
interlinked project has been
submitted?
19. If yes, date of submission : No
20. If no, reason : There is no interlinked project
21. Whether the proposal involves : No
approval/Clearance under: if yes,
details of the same and their
status to be given.
a. The Forest (Conservation)
Act, (1980)?
b. The Wildlife (Protection)
Act, 1972?
c. The C.R.Z. Notification,
1991?
22. Whether there is any : No
Government Order/ Policy
relevant/ relating to the site
23. Forest land involved (hectares) : No

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

24. Whether there is any litigation : No litigation is pending against the project in any
pending against the project court of law.
and/or land in which the project
is propose to be set up?
a. Name of the Court
b. Case No.
c. Orders/directions of the
court, if any and its relevance
with the proposed project.

II. Activity

1. Construction, operation or decommissioning of the Project involving actions, which


will cause physical changes in the locality (topography, land use, changes in water
bodies, etc.)

S. Information/Checklist Yes/ Details thereof (with approximate quantities/


No confirmation No rates, wherever possible) with source of
information data
1.1 Permanent or temporary No Land-use:
change in land use, land cover The project is coming up in the land duly allotted
or topography including for the hotel purpose. Copy of land documents
increase in intensity of land enclosed as Annexure.
use (with respect to local land
use plan)
Land cover:
Yes
There will be permanent change in the land cover
and the intensity of land use w.r.t. project site. The
site is mostly vacant and covered with perennial
vegetation.

The intensity of land cover will change from

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

presently vacant land to hotel project having a


footprint area of about 21.25 % (2234 sq. m.)
1.2 Clearance of existing land, No The existing land in industrial area, hence No
vegetation and buildings? clearance of existing land, vegetation or building is
envisaged for the project.
1.3 Creation of new land uses? Yes There will be change in land use. However, the
internal land use pattern will be as under:

S. No Particulars Permissible Proposed


1. Total Plot area 10508 sq.m
2. Built up Area 37,790.80 sq.m
3. Ground Coverage 40 % (4203.2 sq.m) 39.9 % (4192.69 sq.m )
4. BAR 2 2.18 (22942.80 sq.m)
5. Landscape Area - 2234 sq. m (21.25 %)
6. Paved areas including Parking - 4081.31 sq. m (38.84 %)

1.4 Pre-construction No There will be no physical impacts on the locality


investigations e.g. bore due to the soil testing or other pre-construction
houses, soil testing? investigations.
1.5 Construction works? Yes There will be construction of hotel project with 230
nos. of guest rooms and other facilities with the
gross built up area 37,790.80 sq.m. The impact on
physical environment will be temporary in terms of
fugitive emissions. Best construction practices will
be adhered to minimize the impacts. The same is
tabulated as under:

S. N. Guidance on Practices to reduce emission


1. Dust Suppressants Dust suppressants will be applied judiciously.
2. Design  Travelled distances will be minimized for delivery of materials
 Green building materials viz. fly ash bricks, RMC’s, etc. will be
used to the best possible extent.
3. Vehicles &  Engines & exhaust systems will be properly maintained.

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

Equipments  Low sulphur diesel (HSD) will be used.


 Idling time will be eliminated/ reduced to the maximum
4. Material Handling &  Foam suppression systems will be utilized.
Transfer systems  PM emissions from spills will be prevented.
 Material handling operations will be minimized.
5. Road Surfaces  On-site vehicle restrictions will be established.

1.6 Demolition works? No No demolition work is anticipated.


1.7 Temporary sites used for Yes Temporary store-rooms and site office will be built
construction works or housing during construction phase, which will be removed
of construction workers? later. The impact due to the same will be confined
to the construction phase only and thus can be
categorized as temporary.
Provisions of temporary housing facility for
construction workers will be provided. Adequate
infrastructural facilities such as sanitation
(including separate mobile toilets for male and
female workers), drinking water, crèche, cooking
fuel, cookers etc will be provided to construction
labours.
1.8 Above ground buildings, Yes The maximum height of the project will be 30 m
structures or earthworks (up to Mumty level).
including linear structures, cut
and fill or excavations Upto terrace level : 30 m
Upto Mumty level : 33.21 m
1.9 Underground works including No Not Applicable
mining or tunnelling?
1.10 Reclamation works? No Not Applicable
1.11 Dredging? No Not Applicable
1.12 Offshore structures? No Not Applicable
1.13 Production & manufacturing No Not Applicable

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

processes?
1.14 Facilities for storage of goods No During the operational phase, there will be well-
or materials? designated confined storage areas within the
building, which will not have impact on the
physical environment.
1.15 Facilities for treatment or Yes Construction phase:
disposal of solid waste or Construction waste
liquid effluents? There will be generation of 2268 MT construction
waste from the project which will be disposed as
per the C&D waste management Rules,
2016.Details elaborated in CP & EMP.

Municipal Solid waste


Approx 27 kg/day municipal solid waste will be
generated from the construction workers which will
be managed as per the Solid waste Management
Rules, 2016.

Post Construction Phase:


Municipal Solid waste:
The solid waste generated from the project
considering full occupancy will be mainly domestic
waste and estimated quantity of the same will be
approx 475 kg/day which will be managed as per
the Solid waste Management Rules, 2016.

Liquid effluent:
Total effluent generation : 245 KLD
Treatment: STP of capacity : 300 KLD
The waste management during construction & post

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

construction phase is detailed in CP& EMP.


1.16 Facilities for long term No There will be no facilities for long term housing of
housing of operational operational workers.
workers?
1.17 New road rail or sea traffic No There will be no new road and rail.
during construction or The impact in terms of traffic will be marginal due
operation? to the proposed project.
Details of the total parking facilities envisaged
within the project site is given as under:
Required Parking : 382 ECU
Proposed Parking : 392 ECU
1.18 New road, rail, air waterborne No There is no new rail, air-borne transport
or other transport infrastructure infrastructure required for the project.
including new or altered routes
and stations, ports, airports etc?
1.19 Closure or diversion of existing No Due to the upcoming project, there will be no
transport routes or closure or diversion of existing transport routes or
infrastructure leading to infrastructures leading to changes in traffic
changes in traffic movements? movements.
1.20 New or diverted transmission No There will be no diversion of transmission and
lines or pipelines? pipelines.
1.21 Impoundment, damming, No The project will not involve any impoundment,
culverting, realignment or other damming, culverting or realignment or other
changes to the hydrology of changes to the hydrology of watercourses or
watercourses or aquifers? aquifers.
1.22 Stream crossings? No None
1.23 Abstraction or transfers of Yes The daily fresh water demand to the tune of about
water from ground or surface 241 KLD will be met through Ground water
waters? supply.

However, provisions of capturing the maximum

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

surface runoff and providing recharge to the tune


of 5248 cu. m. per annum (maximum recharge)
will be done through the 4 rain water harvesting
pit.
1.24 Changes in water bodies or the Yes There will be increase in total surface run-off
land surface affecting drainage during post construction phase, which will be
or run-off? captured through well designed storm-water pipe
network of rain-water harvesting and will be used
for recharge of the aquifers.
1.25 Transport of personnel or Yes Construction:
materials for construction, There will be movement of personnel, materials
operation or decommissioning? and machineries during the construction phase.
The impact due to the movement of personnel will
be negligible as local people will be deployed.
Thus there will be contribution of marginal noise
& vehicular emissions which will be mitigated by
implementation of effective EMP. The same is
elaborated at point1.5, Form 1.

The construction work will be carried out during


non-peak seasons. Further, no work will be done
during the night hours.

Post Construction:
During commissioning, there will be
transportation of personnel and materials in and
out of the project regularly. There will be 392
ECU peak on road due to the project on
completion of project with 100% occupancy.
1.26 Long-term dismantling or No Restoration works for the project on long-term
decommissioning or restoration will be an ongoing activity which will not have

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

works? any impact on physical environment.


1.27 Ongoing activity during No There will be no decommissioning activity related
decommissioning which could to the project.
have an impact on the
environment?
1.28 Influx of people to an area in Yes During the post construction phase, there will be
either temporarily or regular influx of visitors, staff related personals.
permanently?
1.29 Introduction of alien species? No Only local plant species will be planted for the
green belt /landscaping.
1.30 Loss of native species or No -
genetic diversity?
1.31 Any other actions? No None

2. Use of Natural resources for construction or operation of the project (such as land,
water, materials or energy, especially any resources which are non-renewable or in
short supply):
S. Information/checklist Yes Details thereof (with approximate quantities/ rates,
No. confirmation /No wherever possible) with source of information data
2.1 Land especially undeveloped No The project is coming up on the land duly alloted for
or agricultural land (ha) the hotel purpose. The total plot area envisaged for the
project is about 10508 sq.m
2.2 Water (expected source & Yes As under:
competing users) unit: Demand Quantity Source
Fresh 241 KLD Ground water supply
Recycled 192 KLD STP treated water
Total 433KLD

2.3 Minerals (MT) Yes Bricks and stone (locally available in the market)
2.4 Construction material – Yes The approximate quantities of construction
stone, aggregates, sand/ soil materials to be used are as under:
(expected source – MT)

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

2.5 Forests and timber (source – Yes The use of wood in the project has been planned to the
MT) minimum extent possible. Wood with recycled content
such as MDF boards will be used to the extent
possible.
2.6 Energy including electricity Yes Energy:
and fuels (source, competing The estimated connected load for the project will be
users) Unit: fuel (MT), 3800 KW and maximum demand will be 11 KW,
energy (MW) which will be met from AVVNL Supply.

Source of supply 33 kV AVVNL GSS


Electrical Load Connected load : 3800 KW
Maximum demand : 1100 KW
Transformer Number 1
Capacity 1500 kVA
DG Sets Number 3 nos.
Capacity 250 kVA : 1 No.
750 kVA : 2 No.
Fuel Used HSD (sulphur content: 0.01%)
Fuel Consumption 88 lt/hr & 125.6 lt/hr respectively

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

2.7 Any other natural resources Yes Solar hot water generators will be used.
(use appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could


be harmful to human health or the environment or raise concerns about actual or
perceived risks to human health.

S. Information/Checklist Yes/ Details thereof (with approximate quantities/


No confirmation No rates, wherever possible) with source of
information data
3.1 Use of substances or materials, No There will be DG sets installed at the project site.
which are hazardous (as per There will be storage of Low Sulphur Diesel
MSIHC rules) to human health (HSD) for the project.
or the environment (flora, The significant hazard due to the same will be
fauna, and water supplies) negligible as the exposure level will be confined
within a small area in the consequence of
unforeseen hazard.
3.2 Changes in occurrence of No There will be no release of any hazardous
disease or affect disease vectors substance in the construction as well as post-
(e.g. insect or water borne construction phase.
diseases) The waste water generated to the tune of 245 KLD
will be treated in STP of capacity 300 KLD based
on MBBR technology.
Further, storm water network will be well designed
to leave no stagnant water pockets.
The biodegradable as well as non- biodegradable
waste will be collected at earmarked places and
will be sent to the Jaipur Municipal Corporation
disposal sites. Proper sanitization will be done to
prevent any disease vector.
3.3 Affect the welfare of people No There will be proper treatment of the solid as well

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

e.g. by changing living as liquid waste generated and the waste will not be
conditions? dumped in the nearby localities thereby, causing
change in the living conditions. The solid waste
will be suitably treated, while the liquid effluent
will be treated in the sewage treatment plant.
3.4 Vulnerable groups of people No There are many schools and health care centers
who could be affected by the within the 3 km. radius from the project site.
project e.g. hospital patients, The project planning has been done to avoid any
children, the elderly etc., adverse impact by means of proper waste
management during construction as well as
operation phase.
3.5 Any other causes No No other causes are significant.

4. Production of solid wastes during construction or operation or decommissioning


(MT/month)

S. Information/Checklist Yes/ Details thereof (with approximate quantities/


No confirmation No rates, wherever possible) with source of
information data
4.1 Spoil, overburden or mine No Not Applicable
wastes
4.2 Municipal waste (domestic and Yes Municipal solid waste to the tune of 475 Kg/day
or commercial wastes) will be generated and the details of the various
activities generating solid waste, its classification,
collection facilities, treatment and disposal is given
in CP & EMP.
4.3 Hazardous wastes (as per No Construction Phase:
Hazardous Waste Management No hazardous waste as per HWMR will be
Rules) generated.

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

Post Construction/ Operational Phase:


Spent oil will be generated which will be carefully
stored in High Density Polythene (HDPE) drums in
isolated covered facility and will be disposed off to
the registered actual users. Suitable care will be
taken so that spills/leaks of spent oil from storage
could be avoided.
4.4 Other industrial process wastes. No There are no industrial process waste
4.5 Surplus product. No No surplus product is anticipated
4.6 Sewage sludge or other sludge Yes About 25 KLD sludge will be generated from STP,
from effluent treatment. which will be sent to MC disposal sites.
4.7 Construction or demolition Yes Construction waste : 2268 MT
wastes. Management of the same is explained in CP &
EMP.
4.8 Redundant machinery or No There will not be any redundant machinery or
equipment. equipment at site.
4.9 Contaminated soils or other No Proper care will be taken to avoid contaminated
materials. soil and if oil spilled soil will be found; the same
will be scrapped off and stored at earmarked places
and sent to disposal sites.
4.10 Agricultural wastes. No There will be no agriculture waste.
4.11 Other solid wastes. No There will be no other solid waste.

5. Release of pollutants or any hazardous, toxic or noxious substances to air (kg/hr)

S. Information/Checklist Yes/ Details thereof (with approximate quantities/ rates,


No confirmation No wherever possible) with source of information data
5.1 Emissions from combustion Yes There will be emissions from DG sets (used in the
of fossil fuels from stationary case of power cuts or failure only). The maximum
or mobile sources. predicted concentrations from the proposed project
considering line (vehicular exhausts) as well as

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

point source emissions will be under:

Mitigation measures:
 Effective stack height of 39 m will be provided
(as per the norms of CPCB) to contain the
emissions within the permissible norms.
 Around 2234 sq. m (21.25 %) is under
landscape which will help to contain the
emissions within the permissible range.
 Effective traffic management plan including
guided traffic ways and separate entry/ exits
will help to avoid congestions during peak
traffic hours.
5.2 Emissions form production No There is no production process in the project.
process.
5.3 Emissions from materials Yes The emission expected from construction phase will
handling including storage or be dust arising from material handling and vehicular
transport emission from transport vehicles. These include the
emissions due to idling of the vehicles during
loading and unloading activities.
Management:
The same is explained at point no. 1.5 above
5.4 Emissions from construction Yes The dust emission sources are:
activities including plant and  Construction
equipment  Material Handling
 Finishing

Impacts:
Increased levels of PM10, PM2.5, NOx, HC, VOC etc.
from the above activities.
Mitigation:
 Enclosures,

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

 Covered transport,
 Plantation,
 Avoiding idling of vehicles etc.
5.5 Dust or odours from handling Yes The dust etc. emanating from various construction
of materials including activities are described along with the impact &
construction materials, mitigation measures are given in CP & EMP.
sewage and waste.
5.6 Emissions from incineration No There will be no incineration of waste.
of waste
5.7 Emissions from burning of No No open burning of waste will be allowed. The civil
waste in open air (e.g. slash contractor along with site manager will be
materials, construction debris) responsible for the same.
5.8 Emissions from any other No None
sources

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

S. Information/Checklist Yes/ Details thereof (with approximate quantities/ rates,


No confirmation No wherever possible) with source of information data
6.1 From operation of equipment Yes Noise may be generated from the construction
e.g. engines, ventilation equipment’s.
plant, crushers The following measures will be taken:
 No heavy machinery/ noise generating activity will
be carried out during night.
 Noise barriers will be provided around the
construction area(s).
 All construction equipment and machineries will
be maintained in good conditions.
 An area of about 2234 sq. m (21.25 %) will be

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

under landscape during post construction phase


which will help to contain the noise.
6.2 From industrial or similar No Not Applicable
processes
6.3 From construction or Yes During construction work D.G. Sets, Pumps, Trucks,
demolition vibrators, etc will be the tentative sources of noise.
The same will be mitigated by effective EMP such as
use of Ready mix concrete to reduce the noise &
vibrations due to the operation of concrete mixer
truck, etc.
6.4 From blasting or piling No No blasting or piling operations are anticipated for the
proposed project
6.5 From construction or Yes There may be marginal increase in the noise levels
operational traffic due to constructional /operational traffic arising due to
the proposed project, which will be minimized by:
 Effective traffic management including sufficient
width of driveways to avoid traffic congestions
especially during the peak hours.
 Provisions of internalized designated parking
facilities to ensure smooth traffic movement.
 Effective green belt 2234 sq. m (21.25 %) will help
in reducing the noise propagation.
6.6 From lighting or cooling No Not Applicable
systems
6.7 From any other sources No None

7. Risks of contamination of land or water from releases of pollutants into the ground or
into sewers, surface waters, groundwater, coastal waters or the sea:

S. Information/Checklist Yes/ Details thereof (with approximate quantities/


No confirmation No rates, wherever possible) with source of

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

information data

7.1 From handling, storage, use No The project will not involve any handling and storage
or spillage of hazardous of hazardous material.
materials
7.2 From discharge of sewage or No No untreated sewage will be discharged into the open
other effluents to water or the surfaces causing the contamination of ground water.
land (expected mode and The wastewater generated will be treated in STP
place of discharge) based on MBBR technology of capacity 300 KLD.
7.3 By deposition of pollutants No During construction, there will be emissions
emitted to air into the land or generated from material transfer, construction
into water operations, finishing operations, exhaust from
vehicles, and stationary sources, etc.
The management of the same has been described at
relevant sections.
7.4 From any other sources No There will not be any other sources, which will
contaminate land & water resources.
7.5 Is there a risk of long term No No significant contribution of long-term built-up of
build-up of pollutants in the pollutants is envisaged from this project.
environment from these
sources?

8. Risk of accidents during construction or operation of the project, which could affect
human health or the environment

S. Information/Checklist Yes/ Details thereof (with approximate quantities/rates,


No confirmation No wherever possible) with source of information data
8.1 From explosions, spillages, Yes Spent oil will be generated which will be stored in the
fires etc from storage, spent oil tank prior to disposal to actual users at
handling, use or production earmarked places.
of hazardous substances The fuel will be stored in the storage tanks which will

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

be designed to meet out all safety norms.


Proper fire-fighting arrangements will be provided all
around the project site (as per the norms of the NBC-
2016)
8.2 From any other causes Yes All safety measures will be in place prior to
commencement of operations so as to avoid any risk
to human life and as per the prevailing local by laws.
Sources of Construction & Post Construction Risks
along with Impact & Mitigation of the same is given
in CP & EMP.
8.3 Could the project be Yes As under:
affected by natural disasters Natural Occurrence Management
causing environmental Disasters Probability

damage (e.g. floods, Floods As per the  For effective


secondary data functioning, pre-
earthquakes, landslides,
available no such monsoon and post-
cloudburst etc)? precedents has monsoon checks of
been reported. the drainage
However the structures will be
possibility of undertaken
such incidents  The project has
cannot be ruled planned storm water
out. layout in regards to
the peak intensity of
the rainfall so far
received as recorded
by IMD.
Earth- The site is located  The building design
quakes in the Seismic will be made with
Zone II, as per earthquake resistant
the seismic design structure.
zoning of  Structure with ductile
map
India given in detailing is
BIS code IS: considered as per IS:

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

1893 (Part1)- 13920-1993.


2002, which is
Low Damage
Risk Zone.
Landslides No such -
precedent has
been reported.
Cloudburst No such --
precedent has
been reported.

9. Factors which should be considered (such as consequential development) which could


lead to environmental effects or the potential for cumulative impacts with other existing
or planned activities in the locality.

S. Information/Checklist Yes/ Details thereof (with approximate quantities/


No. confirmation No rates, wherever possible) with source of
information data.
9.1 Lead to development of No The project is coming up in the land with well
supporting cities, ancillary developed infrastructure around.
development or development
stimulated by the project which
could have impact on the
environment e.g.
 Supporting infrastructure
(roads, power supply, waste or
waste water treatment, etc.)
 housing development
 extractive industries
 supply industries
 other

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

9.2 Lead to after use of the site, No No lead to after use of the site, which could have
which could have an impact on an impact on environment
environment
9.3 Set a precedent for later No There are no precedents as similar developments
developments are proposed around.
9.4 Have cumulative effects due to Yes There are no similar projects planned as of now.
proximity to other existing or
planned projects with similar
effects.

III. Environmental Sensitivity

S. Areas Name/ Aerial distance (within 15 km.)


No Identity Proposed project location boundary
1 Areas protected under
international conventions, As per Archaeological Survey
national or local legislation Badgaon Sub Post Office : 2.2 km towards ENE
for their ecological, Police Chowki Fatehpura : 2.4 km towards ESE
landscape, cultural or other City Palace : 5.0 km towards SSE
related value.
2 Areas which are important
Forest
or sensitive for ecological
Magra R.F. 11.5 km towards NNW
reasons -Wetlands,
Jhindoli R.F. 9.7 km towards NNW
watercourses or other water
Rama P.F. 8.1 km towards NNE
bodies, coastal zone, Bikharni R.F. 13.3 km towards NE
biospheres, mountains, Nauva R.F. 11.7 km towards NE
forests. Amberi P.F. 8.3 km towards NE
Kheradi R.F. 14.8 km towards ENE
Dhenkli R.F. 9.7 km towards ENE
Bhainsra R.F. 11.0 km towards ENE
Kanti R.F. 14.0 km towards E
Bara Magra R.F. 12.6 km towards E

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

Segria R. F. 10.3 km towards ESE


Kamlodia R.F. 13.3 km towards ESE
Bordi R.F. 10.9 km towards ESE
Umra R.F. 14.3 km towards SE
Raniji ka Bir R.F. 14.4 km towards SE
Chittoria R.F. 13.9 km towards WSW
Hora R.F. 9.5 km towards SE
Eklinggarh R.F. 5.5 km towards SSE
Suklia P.F. 9.8 km towards SSW
Nai Nadra P.F. 7.0 km towards SW
Paga R.F. 6.9 km towards WSW
Sajjangarh R.F. 2.6 km towards SSW
Thora Magra P.F. 0.7 km towards SSE
Tiklia P.F. 0.3 km towards E
Pandwa P.F. 0.3 km towards WSW
Kaler R.F. 4.6 km towards WSW
Makreda P.F. 4.1 km towards WNW
R.F.(Khejara ki pati) 12.7 km towards SSE
Arnia Magra R.F. 9.8 km towards SSW
Arnia (Magra) R.F. 9.7 km towards SSW
Chhota Ghata R.F. 8.2 km towards SW
Rama R.F. 7.4 km towards N
Mathara & Mota Ghara R.F. 10.0 km towards WSW
Dodawali R.F. 11.8 km towards WSW
Kunda R.F. 11.3 km towards W
Manbhang R.F. 12.7 km towards W
Majawad R.F. 11.0 km towards WNW
Bagrunda R.F. 11.8 km towards NW
Bhadwi Gurhar R.F. 12.8 km towards NW
Water Bodies
Amanishah Nala 4.6 km towards W
Dhund River 11.5 km towards E
Jal Mahal 11.3 km towards NNE

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

3 Areas used by protected, Sajjangarh Wild life sanctuary : 2.68 km


important or sensitive
species of flora or fauna for
breeding, nesting, foraging,
resting, over wintering,
migration
4 Inland, coastal, marine or None --
underground waters
5 State, National boundaries None --
6 Routes or facilities used by As under:-
the public for access to Nearest Name Distance (aerial) &
recreation or other tourist, Direction

pilgrim areas. Railway Udaipur City Railway 6.6 KM SE


Station Ranapratap Nagar 7.7 KM ESE
Railway Station
Airport Maharana Pratap 22.5 KM E
Airport Udaipur

7 Defence installations None -


8 Densely populated or built- Malviya Nagar
up area

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

9 Areas occupied by sensitive As under:-


man-made land uses Name Distance with Direction
(hospitals, schools, places Educational Facilities

of worship, community Wisdom School 2.7 km towards ENE

facilities) Central Public School 2.2 km towards SE


Medical Facilities
Star Hospital And Cosmetic Centre 2.2 km towards ESE
Apna Hospital 2.4 km towards ENE
Lake City Hospital 2.5 km towards ESE
Places of Worship
Neemach Mata Mandir 1.2 km towards ESE
Harinath Temple 1.5 km towards ENE
Mahadev Temple 1.7 km towards ENE

10 Areas containing important, Girwa The entire block is categorized as non-


high quality or scarce notified critical level for ground water
resources (ground water use.
resources, surface
resources, forestry,
agriculture, fisheries,
tourism, minerals)
11 Areas already subjected to None Not Applicable
pollution or
environmental damage.
(those where existing legal
environmental standards
are exceeded)
12 Areas susceptible to natural Earthquake Zone II The area is classified as Zone II (Least to
hazard which could cause moderate) as per the BIS classification.
the project to present Suitable seismic coefficients in horizontal
environmental problems and vertical directions respectively will
(earthquakes, subsidence, be adopted while designing the structures.
landslides, erosion,

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
Project : Proposed Hotel Project “JW. Marriott Udaipur”
Form 1
Promoter : Shri Madhav Hotels Pvt. Ltd.

flooding or extreme or
adverse climatic conditions)
*(As per secondary source available)

"I hereby give an undertaking that the data and information given in the application and enclosure
are true to the best of my knowledge and belief and I am aware that if any part of the data and
information submitted is found to be false or misleading at any stage, the project will be rejected and
clearance given, if any, to the project will be revoked at our risk and cost.”
Date:
Place:
Aarif Khan
Authorized Signatory
Shri Madhav Hotels Pvt. Ltd.

Gaurang Environmental Solutions Pvt. Ltd


Report No: GESPL_437/2021/EC/187 Rev No. 01
N Forest
1. Magra R.F. 11.5 km NNW
NW NE 2. Jhindoli R.F. 9.7 km NNW
3. Rama P.F. 8.1 km NNE
W E 4. Bikharni R.F. 13.3 km NE
5. Nauva R.F. 11.7 km NE
SW SE 6. Amberi P.F. 8.3 km NE
S 7. Kheradi R.F. 14.8 km ENE
8. Dhenkli R.F. 9.7 km ENE
1 Legend 9. Bhainsra R.F. 11.0 km ENE
40 10. Kanti R.F. 14.0 km E
2 4
Project site 11. Bara Magra R.F. 12.6 km E
12. Segria R. F. 10.3 km ESE
13. Kamlodia R.F. 13.3 km ESE
14. Bordi R.F. 10.9 km ESE
3 15. Umra R.F. 14.3 km SE
E 32 16. Raniji ka Bir R.F. 14.4 km SE
5 7
17. Chittoria R.F. 13.9 WSW
39
18. Hora R.F. 9.5 km SE
19. Eklinggarh R.F. 5.5 km SSE
6 20. Suklia P.F. 9.8 km SSW
21. Nai Nadra P.F. 7.0 km SW
22. Paga R.F. 6.9 km WSW
38 23. Sajjangarh R.F. 2.6 km SSW
24. Thora Magra P.F. 0.7 km SSE
28 9 25. Tiklia P.F. 0.3 km E
8
26. Pandwa P.F. 0.3 km WSW
Sajjangarh wildlife 27. Kaler R.F. 4.6 km WSW
Project 11 sanctuary ESZ 100 m SW 28. Makreda P.F. 4.1 km WNW
10 29. R.F.(Khejara ki pati) 12.7 km SSE
26 Site
D 5.0 km 10.0 km 15.0 km Sajjangarh wildlife 30. Arnia Magra R.F. 9.8 km SSW
25
31. Arnia (Magra) R.F. 9.7 km SSW
F sanctuary 2.4 km SW 32. Chhota Ghata R.F. 8.2 km SW
37 36 24 12
B 33. Rama R.F. 7.4 km N
27 Source - Final Notification 34. Mathara & Mota Ghara R.F.10.0 km WSW
S.O. 107(E) New Delhi, the 6th 35. Dodawali R.F. 11.8 km WSW
23
17 35 January, 2020 36. Kunda R.F. 11.3 km W
34 22 37. Manbhang R.F. 12.7 km W
14 C 38. Majawad R.F. 11.0 km WNW
33 13 39. Bagrunda R.F. 11.8 km NW
A 40. Bhadwi Gurhar R.F. 12.8 km NW
31 G 19
Water Bodies
21 H A. Pichola 4.3 km SSE
B. Fathe Sagar 1.0 km SE
C. Udaisagar 14.3 km ESE
18
D. Ahar Nadi 2.6 km E
E. Madar ka Talav 8.8 km NW
20 15 F. Bari Ka Talav 40 km WSW
30 G. Amarjok Nadi 5.4 km SSW
H. Kotra Nadi 6.4 km SSW

16
TOPOGRAPHICAL MAP
29 OF 15 KM RADIUS
Project Name : Proposed Hotel Project
Scale “JW. Marriott”
Site address : Khasra no. 1360,
0 2 4 6 8 Km SOURCE: SOI TOPOSHEET NO. Village Hawala Khurd, Girwa Udaipur Rajasthan
45 H/10, 45 H/14, 45 H/11 & 45 H/9 Promoter : Shri Madhav Hotels Pvt. Ltd.
Project Site
Project : Proposed Hotel Project “JW. Marriott”
Project Summary
Promoter : Shri Madhav Hotels Pvt. Ltd.

PROJECT SUMMARY
Project Name : Proposed Hotel Project “JW. Marriott”
Site address : Khasra no. 1360, Village Hawala Khurd, Girwa Udaipur Rajasthan
Promoter : Shri Madhav Hotels Pvt. Ltd.
Registered Address : G-4, B-6B, Steerling Apartment Prithviraj Road C-Scheme Jaipur

1. Project Description
The project involves the proposed hotel project at Udaipur promoted by Shri Madhav Hotels
Pvt. Ltd. Details are as under:-

Details as under:-

Table No. 1: Salient features of the Project


S. No. Particulars Details
1. Authorized Signatory Hari Maohan Dangayach (Director)
2. Category and S. No. in Schedule as per Item 8 (a)- Building & Large Construction Projects
EIA Notification, 2006 Cat. B-2
3. Project cost Rs.250 crores
5. Project Details
4. Total plot area 10508 sq.m
5. Built up area 37,790.80 sq.m
6. Standard BAR 2
7. Achieved BAR 2.18 (22942.80 sq.m)
8. Permissible Ground Coverage 40 % (4203.2 sq.m)
9. Achieved Ground Coverage 39.9 % (4192.69 sq.m )
10. No. of Blocks 1No.
11. No. of Floors LB+UB+ GF+ Seventh Floor
12. Height of project Upto Terrace level : 30 m
13. Landscape area 2234 sq. m (21.25 %)
14. Project details and facilities  Guest Rooms : 230nos.
 Restaurant : 1 no. ( 253 Pax)
 Banquet hall : 1 no. ( 1226pax)
Gaurang Environmental Solutions Pvt. Ltd

Report No: GESPL_437/2021/EC/187 Rev No. 01


Project : Proposed Hotel Project “JW. Marriott”
Project Summary
Promoter : Shri Madhav Hotels Pvt. Ltd.

 Ball room : 468 sq.m (361 Pax)


 Retail : 89 sq.m
15. Power requirement  Connected load : 3800 KW
 Max demand : 1100 KW
16. Power back up DG set : 2x750KVA+1x250KVA

2. BREAK UP OF BAR AREA & BUILT UP AREA


Floors wise details Builtup area (sq.m ) BAR
Lower Ground floor 7350 00
Upper Ground Floor 7350 710
Ground Floor 4196 4128
First Floor 3560 3492
Mezzanine Floor 1174.80 1106.80
Second to Fifth 2360 2292
Third 2360 2292
Fourth 2360 2292
Fifth 2360 2292
Sixth Floor 2360 2046
Seventh 2360 2292
Total 37790.80 22942.8

3. FLOORWISE DETAILS
Floors wise details Details
Lower Ground floor Parking, STP, MEP area: 2 nos. & store and services
Upper Ground Floor Parking, Fire room, BOH : 430 sq.m
 Parking, Gym Swimming pool
 SPA & sauna : 373 sq.m
 Office : 120 sq.m
Ground Floor  Banquet kitchen : 761 sq.m
 Banquet hall : 1031 sq.m (1226 pax)
 Pre function area : 306 sq.m +132 sq.m
 Electric substation

Gaurang Environmental Solutions Pvt. Ltd

Report No: GESPL_437/2021/EC/187 Rev No. 01


Project : Proposed Hotel Project “JW. Marriott”
Project Summary
Promoter : Shri Madhav Hotels Pvt. Ltd.

 Banquet Lawn : 800 sq.m


First Floor  Coffee shop/Restaurant :345 sq.m (253 Pax)
 BAR : 250 sq.m
 Ball room :468 sq.m (361 Pax)
 Sit out :230 sq.m
 Reception
 Front office : 31 sq.m
 Retail : 89 sq.m
 Kitchen and utilities :374 sq.m
 All day dining :468 sq.m
Mezzanine Floor West Wing : 230 sq.m
East Wing : 450 sq.m
Second to Fifth & Seventh Guest rooms : 39 *5 :195 nos.
Sixth Floor Guest rooms : 35 nos.
Refuge area : 2 nos. (101 sq.m & 145 sq.m )

4. Parking Requirements:
Particulars Details Basis Required ECU
BAR Area 22942.80 sq. m. @ 1 ECU/75 sq. m. of BAR area 306
Visitors @25% of the total parking 76
Required ECU 382

Required Parking : 382 ECU


Proposed Parking : 392 ECU

********

Gaurang Environmental Solutions Pvt. Ltd

Report No: GESPL_437/2021/EC/187 Rev No. 01


List of Directors
S. No Name of Directors DIN
1. Kamlesh Dangayach 00112010
2. Hari Mohan Dangayach 00111764
Project : Proposed Hotel Project “Marriott Udaipur”
Promoter : Shri Madhav Hotels Pvt. Ltd.

DECLARATION BY CONSULTANT

Declaration by Experts contributing to the EIA for the construction of Hotel Project “Marriott
Udaipur” coming up at Khasra no. 1360, Village Hawala Khurd, Girwa Udaipur Rajasthan
promoted by Shri Madhav Hotels Pvt. Ltd.

I hereby certify that I was part of the EIA team in the following capacity that developed the
above project for grant of Environmental Clearance.
Particulars Signature & Date
EIA Coordinator

Ms. Pooja Bunker

Period of Involvement
Contact Information Gaurang Environmental Solutions Pvt. Ltd.
#102, SNG, Shri Ratna Apartment, Peetal Factory,
Bani Park, Jhotwara Road, Jaipur-302016
Phone No.:- 0141- 4029115

Functional area experts:


S. Functional Name of the expert/s Involvement (period and task**) Signature and date
No. Areas
1 AP*  Ginni Barotia  Identify the significant sources of
air emissions during Pre-
construction, construction and
Post-construction phases.
 The sources of project emissions
and the surrounding emissions
sources were identified and suggest
the mitigation measures.
2 WP*  Pooja Bunker  Calculate the water demand during
the post construction phase as per
the NBC norms and prepare the

Gaurang Environmental Solutions Pvt. Ltd

Report No: : GESPL_437/2021/EC/187


Project : Proposed Hotel Project “Marriott Udaipur”
Promoter : Shri Madhav Hotels Pvt. Ltd.

water balance accordingly.


 The waste water generated has
been quantified with appropriate
treatment technology proposed.
 Identify the impact on water
environment and suggest the
mitigation measures.
3 SHW*  Ginni Barotia  Identification of nature of waste,
 Ms. Pooja Bunker categorization and quantification
(BMW ) of waste generated.
 Suggest the management of
generated waste as per MoEF &
CC and applicable rules.
4 SE* Gajendra Singh Rathore.  Prepare the baseline socio –
economic based on secondary data
Census of India – 2011.
 Identify the socio-economic
observation and identify the
impact and suggest mitigation
measures.
 Preparing socio economic plan
5 EB* Dr. Yati Kacchawa Prepare greenbelt plan and suggest
the native tree species as per the
MoEF requirement.

6 HG* Vidya Bhushan Trivedi  Hydrogeological assessment of


aquifer distribution of the area and
suggest the Rain Water Harvesting
structure design & capacity as per
the rainfall data.
7. GEO* Vidya Bhushan Trivedi  No geological structure has been
observed during the primary
survey.

Gaurang Environmental Solutions Pvt. Ltd

Report No: : GESPL_437/2021/EC/187


Project : Proposed Hotel Project “Marriott Udaipur”
Promoter : Shri Madhav Hotels Pvt. Ltd.

8 SC* Pradyumna Arvind  Assessment of soil sample


Deshpande analysis.
 Proposed measures of top soil
conservation and re-use for
plantation.
9 AQ*  Mallikarjuna Murthy  Study of Secondary Micro-
Guttula. Meteorological data.
 Air quality modelling and its
interpretation.
 Predict the incremental GLC’s
AERMOD Version 8.9 model
used to predict changes in air
quality.
 Air quality contours superimpose
on toposheet, indicating the
location of site, sensitive
receptors, habitation and pre-
dominant wind direction.
10 NV* Mallikarjuna Murthy  The sources of noise emission
Guttula. have been identified and proposed
mitigation measures.
 The monitored data at project site
have been verified for any
additional contribution by the
project.
11 LU* Vinod Kumar Verma  Identify the impact and suggest
mitigation measures.

12 RH* Ginni Barotia  Identification of hazards and


proposed mitigation measures.
 Occupational Health and safety
measures.
*One TM against each FAE may be shown
**Please attach additional sheet if required
Gaurang Environmental Solutions Pvt. Ltd

Report No: : GESPL_437/2021/EC/187


Project : Proposed Hotel Project “Marriott Udaipur”
Promoter : Shri Madhav Hotels Pvt. Ltd.

# Team Member

Declaration by the Head of the accredited consultant organization/authorized person


I, Vipul Khandelwal hereby confirm that the above mentioned experts prepared the report of
construction of Hotel Project “Marriott Udaipur” coming up at Khasra no. 1360, Village
Hawala Khurd, Girwa Udaipur Rajasthan promoted by Shri Madhav Hotels Pvt. Ltd., I also
confirm that the consultant organization shall be fully accountable for any misleading
information mentioned in this statement.

Signature

Name Vipul Khandelwal


Designation Director
Name of the EIA Consultant Gaurang Environmental Solutions Pvt. Ltd.
Organization
NABET Certificate No. & Issue Date NABET/EIA/2023/RA 0192 (Rev.01) dated
16.07.2021 valid up to 19.01.2023.

*********

Gaurang Environmental Solutions Pvt. Ltd

Report No: : GESPL_437/2021/EC/187


T R, aT uTke afavi 7 161, 0294-2800009
Email ID -defwludz@gmail.com
HT7 U5 9( Td/3aw/ qut /2021-22/ U3Y fH 99/292

TRHT 31TYcT 7 pHT5 AA 05.01.2021 ya HETT5 T7


77 Hu YA15 H. 1 f 28.02.2022 4 HI

yRaT fàUT UTHr7 y7 4 TU I f Shri Madhav Hotels Pvt.

ETHET77 F R , quuia TTT ETRT fic 28.02.2022it

DHTCT 9( d/3ai/7u/2021-22/
1. FTET775 77 TRA5, aYTta HTT

Survey-9/Letter 2019-21/Doc-WLClearance letter 198


Annexure G

Format for Building projects

Name of the Project : Proposed Hotel Project “Marriott Udaipur”


Address : Khasra no. 1360, Village Hawala Khurd, Girwa Udaipur Rajasthan
Project Proponent : Shri Madhav Hotels Pvt. Ltd.
Address : G-4, B-6B, Steerling Apartment Prithviraj Road C-Scheme Jaipur
Email : arifkhan73@gmail.com
udaipurmarriott@gmail.com
Name of the Consultant: : Gaurang Environmental Solutions Pvt. Ltd.
Address : #102, SNG, Shri Ratna Apartment Peetal factory, Jhotwara road, Jaipur-
302016
Email : gaurangenviro@gmail.com

1. Category /
Item no.(in Cat.B2, item 8(a) (Building and Construction Projects.
Schedule):
2. Location of Khasra no. 1360, Village Hawala Khurd, Girwa Udaipur Rajasthan
Project
3. Project Area as under:
Details Total Plot area 10508 sq.m (113066 sq. ft)

Built up area 37,790.80 sq.m

Green Area 2234 sq. m (21.25 %)

Ground Coverage Permissible : 40 % (4203.2 sq.m)

Achieved : 39.9 % (4192.69 sq.m )

BAR Standard :2

Achieved : 2.18 (22942.80 sq.m)

Maximum height & Details are as under:-


number of floors
No of 1 no.
blocks
No of LB+UB+ GF+ Seventh Floor
Floors
Height Up to Terrace level : 30
m

Project facilities  Guest Rooms : 230nos.


 Restaurant : 1 no. ( 253 Pax)
 Banquet hall : 1 no. ( 1226pax)
 Ball room : 468 sq.m (361 Pax)
 Retail : 89 sq.m
Parking facilities Required Parking : 382 ECU

Proposed Parking : 392 ECU

Power requirement & Connected load : 3800 KW


source
Maximum demand : 1100 KW

Source : AVVNL Supply

Power backup D.G sets of cumulative capacity 1750 kVA

 2x750KVA
 1x250KVA
Renewable Energy Grid tied Solar : 120 KW

Utilities Boiler : Steam Boiler

Chillers : 3 Nos.

Capacity : 2x160TR+1x130TR

Water requirement & Total Water requirement : 433 KLD


source
Fresh Water : 241 KLD

Recycled Water : 192 KLD

Source : PHED water supply

Sewage treatment & Sewage treatment facility : STP of 300 KLD capacity
disposal
Waste water Generation : 245 KLD

STP Technology : MBBR Technology

RWH Structures 4 no.s

Project cost Rs. 250 crores

4. Details of Proposed Project


construction
taken place
at site
5. Parking Required Parking : 382 ECU
facility Provided Parking : 392 ECU

6. Project cost Rs. 250 crores.


7. Water Total Water requirement : 433 KLD
Requirement Fresh Water : 241 KLD
per day Recycled Water : 192 KLD
& Source Source : Municipal Water Supply
8. Fuel & As under:
Energy:- Source of supply 33 kV AVVNL GSS
Electrical Load Connected load : 3800 KW
Demand Load : 1100 KW
Transformer Number : 1 No.
Capacity : 1500 KVA
DG Sets
 Number 3 Nos.
 Capacity 250 kVA : 1 no.
750 kVA : 2 no.
Fuel Used HSD (sulphur content: 0.01%)
Fuel consumption 88 lt/hr & 125.6 lt/hr respectively

9. Application Application Submission date


No. & Date Online : 10.01.2022
&
documents
submitted :-
10 Environment Capital cost : Rs.149 lacs
Management Recurring cost : Rs.11.50 lacs
Plan with As under:
budgetary S. Particulars Capital Annual recurring cost
provision. No. Cost (in lacs)

(in lacs)

1. Acoustic enclosures & stack 10 2


attached to DG sets

2 STP 75 0.50

3 Rain water harvesting 6 0.30

4 Solid waste management 3 5

5 Pollution monitoring - 1

6 Fire fighting & emergency 50 0.70


handling

7 Green Belt 5 2

TOTAL 149 11.50

11 CER An amount of Rs.2.5 Cr will be spent on social EMP under EMP.


Activities
12 STP Sewage treatment facility : 300 KLD
Waste water generated : 245 KLD
Technology : MBBR Technology
13 Green Belt/ 2234 sq. m (21.25 %) will be under the landscape.
Plantation
area and %
of total area
in sq. mts.
14 Budgetary Capital Cost : Rs.6,15,000/-
Breakup for Recurring cost per Annum : Rs. 3,70,000/-
Labour As under:-
S. No Facilities to be Capital Cost Recurring cost
provided for per Annum
Labourers
1. Temporary housing 30 nos. of temporary --
facilities for houses@ Rs.10,000/-
construction workers Total- Rs.3,00,000/-
2. Sanitation facility Rs.70,000/- --
 Separate toilets 6 nos.@ Rs.10,000/-each
 Other charges other charges
(Rs.10,000/-)
3. Safe Drinking water Water Tank Rs.25,000/- Rs.1,50,000/-
4. Utensils Rs.30,000/- -
5. Fuel for cooking Rs.20,000/- Rs.5000/-
6. First Aid Facility First aid room with Rs. 20,000/-
equipped first-aid boxes
and cupboards
Rs.1,30,000/-
7. Medical Examination -- Twice in a
year@Rs.300/-
for 100 nos. of
worker Total -Rs.
60,000/-
8. Crèche & recreation Rs.40,000/- Rs.75,000/-
facility
9. Education for their - Rs. 60,000/-
children
Total Rs.6,15,000/- Rs. 3,70,000/-
15 Present Proposed Project
status
*******
3/8/22, 11:23 AM Gmail - Request for water assurance

marriott udaipur <udaipurmarriott@gmail.com>

Request for water assurance

1 message

marriott udaipur <udaipurmarriott@gmail.com> Mon, Mar 7, 2022 at 5:40 PM


To: uitudaipur@rediffmail.com
Bcc: "pooja.gespl@gmail.com" <pooja.gespl@gmail.com>

Sir,
In regards to the above, we would like to bring
in your kind notice we are coming up with the Hotel Project “JW
Marriott
Udaipur” promoted by Shri Madhav Hotels Pvt. Ltd. at Khasra no. 1360,
Village Hawala Khurd, Girwa,
Udaipur Rajasthan. During the operational phase the
fresh water requirement will be 241 KLD. We request your good
self to kindly let us
know the availability of the water supply in the area and the formalities which
have to be
undertaken to obtain water sanction from your department.      

Thanking you

For
Shri Madhav Hotels Pvt. Ltd