Professional Documents
Culture Documents
V Sangha’s
BASAVESHWAR ENGINEERING COLLEGE
BAGALKOT – 587102
(Government Aided Institution and permanently affiliated to Visveshvaraya
Technological University,
Belagavi accredited by NAAC with ‘A’ grade from 2019-2023)
Submitted By
RAKSHITA SARANGMATH 2BA19CV059
Shri B.V.V Sangha’s
BASAVESHWAR ENGINEERING COLLEGE
BAGALKOT – 587102
(Government Aided Institution and permanently affiliated to Visvesvaraya Technological
University,
Belagavi accredited by NAAC with ‘A’ grade from 2019-2023)
CERTIFICATE
This is to certify that RAKSHITA
SARANGMATH(2BA19CV059) has satisfactorily completed the
INTERNSHIP on “RESIDENTIAL BUIDLING AND
QUARTERS” for partial fulfillment of course in Civil Engineering
Prescribed by Basaveshwar Engineering College, Bagalkot during
the year 2022-2023.
Under the Guidance of Internship Coordinator Head Of Department
Mr.Vijay Patagunde Prof. G. H. Bandihal Dr. P. G. Rakaraddi
1.___________________ 1.___________________
2.___________________
2.___________________
3.___________________
3.___________________
DECLARATION
PHASE-2:
STUDY AREA
2.1 TECHNICAL REASONS FOR SELECTION OF PARTICULAR
AREA
2.2 STUDY AREA DISCRIPTION AND LOCATION (MAP)
2.3 BRIEF DISCRIPTION OF WORK
2.4 OUTCOMES
PHASE-3:
RESIDENTIAL BUILDING CONSTRUCTION
3.1 EARTHWORK EXCAVATION
3.2 PCC (PLAIN CEMENT CONCRETE)
3.3 FOOTING
3.4 CLOUMN
3.4.1 CALCULATION OF STEEL QUANTITY
3.4.2 CALCULATION OF CONCRETE QUANTITY UPTO PLINTH LEVEL
PHASE-4:
PLINTH
4.1 LINE MARKING FOR PLINTH BEAM
4.2 CONSTRUCTION OF STONE MANSORY UPTO PLINTH LEVEL
PHASE-5:
5.1 SITE VISIT PHOTOGRAPHS
5.2 CONCLUSION
INTRODUCTION:
MISSION:
Provide professional design and project management consultancy services.
Emerge as a preferred technology partner for small, medium and large
enterprises.
Consistently deliver quality and value.
Build talented and skilled professionals in all relevant fields.
Eliminate all forms of discriminations and, promote tolerance and mutual
respect for each other.
Create value for all stakeholders.
about;
OUTCOMES:
1. An understanding of professional and ethical responsibility.
7. Learn from the others experience to avoid the pitfalls and minimizing the
repetition of erosion work.
10. An ability to use the techniques, skills, and modern engineering tools
necessary for engineering practice.
EARTH WORK EXCAVATION:
Excavation is the process of moving earth, rock or other materials with tools,
equipment or explosives. It also includes trenching, wall shafts, tunneling
and underground. It is the preliminary activity of the construction project.
FOOTING:
A structure essentially consists of two parts, namely the superstructure which
is above the plinth level and the substructure which is below the plinth level.
Substructure is otherwise known as the foundation and this forms the base
for any structure. Generally, about 30% of the total construction cost is spent
on the foundation.
The soil on which the foundation rests is called the “Foundation Soil”.
OBJECTIVES OF FOOTING:
ISOLATED FOOTING:
Isolated footings (also known as Pad or Spread footings) are commonly used
for shallow foundations in order to carry and spread concentrated loads,
caused for example by columns or pillars. Isolated footing can consist either
of reinforced or non-reinforced material.
The isolated footing should only be used when it is absolutely certain, that
no varying settlements will occur under entire building.
Types of Isolated Footing:
Pad Footing
Stepped Footing
Sloped Spread Footing
COMBINED FOOTING:
Combined footing is used while construction of two or more columns when
they are close to each other and their foundations overlap. The main purpose
of using combined footing is to distribute uniform pressure under the footing
Hence, this is done so that the center of the gravity of the footing area should
be equal to center of gravity of the two columns.
It is useful when the soil bearing capacity is slow when causes overlapping
of adjacent isolated footings. It is also useful when the proximity of a
building line or existing building or sewer is adjacent to a building column.
TYPES OF COMBINED FOOTING:
• Slab type combined footing
• Slab -Beam type combined footing
• Strap -Beam type combined footing
COLUMN:
RCC column is a vertical structural member which transfers loads from
beam and slab directly to the underneath soil. That means an entire building
stands on columns. Most of the building failure occurs not only for design
fault but also for poor construction practices.
Therefore, it is essential to know the construction procedure of RCC column
appropriately.
RCC Column Construction Process:
RCC columns are mainly constructed in four different stages, which are
Column Layout Work
Column Reinforcement Work
Column Framework and
Pouring Concrete
PLINTH:
Plinth is the part of the superstructure between the top of the tie beam at the
finished ground level
(The top level of the soil surrounding the structure that has been prepared
and levelled prior to
Construction) and the floor level of the building (the ground floor level
inside the building).
It is also called ground floor level. It is the level where you actually starts
columns rising from the floor. As well as its first level the of beams from
where superstructure starts. Plinth is used to describe column bases. Beam
which braces the plinth level is called plinth beam. The Plinth is technically
from where the superstructure starts after the foundation.
PLINTH HEIGHT:
APPLICATIONS OF PLINTH: