Professional Documents
Culture Documents
AN INTERNSHIP REPORT
Master of Technology
in
Construction Technology
Submitted by
Mr. RAKESH S
1BM16CCT10
At
CERTIFICATE
External Viva
The satisfaction and euphoria that accompany the successful completion of any task
would be incomplete without the mention of people who made it possible, whose constant
guidance and encouragement crowned out effort with success.
I extend my thanks to Mr. Ahmedulla Baig, Assistant General Manager for guiding me
throughout the course of training.
I would also like to express my gratitude to Mr. Muheeb Ahmed , Mr. Nelson,
Mr.Prashanth SP , Mr.Nithin Gowda, Mr.Sachin, Mr.vivek T, Mr.Patrick Jones,
Mr.Sumit patil, Mr.Manjesh for helping me out with some difficulties during the
course.
Thanks to Prestige Estates Project Ltd for giving me an opportunity for doing internship
at Prestige Falcon city site.
I would like to thank my internal guide Dr. Mangala Keshava for her guidance and
helpful suggestions beginning from industrial training, I thank her for thoughtful
suggestions and advices.
I would like to thank Dr. Maya Naik, HOD, Department of civil Engineering, BMSCE
who supported me in carrying out the internship in 3rd semester
I would like to thank all my lecturers and non-teaching staff of civil Engineering,
BMSCE,Bengaluru,for their support to carrying out the internship in 3rd semester
My deepest recognition goes to my beloved parents, who are helping me in all possible
ways to achieve my objectives and fulfill my dreams.
RAKESH S
DECLARATION
RAKESH S
1BM16CCT10
EXECUTIVE SUMMARY
The internship report in broad-spectrum contains four chapters in which I try to explain
my four months experience working with Prestige Estates Projects Ltd. The content of all
chapters is broadly explained and it is constructed from the practical basis of knowledge
acquired in four months.
In the opening chapter I gave details about the company background including its
Landmark projects, vision, mission, quality policy, Awards & Recognitions.
The second chapter is the most important chapter which explains about the project where
I got allotted to do internship in the last successive months. It includes Project details,
departments Organization structure at site and specifications.
The third chapter solely includes about the task performed includes site supervision,
components & sequence of works in aluminium formwork & concreting
This chapter also gives brief explanation about the activities where I observed and learnt.
Fourth chapter explains the main benefits of the internship in terms of different aspects
and areas. It is obvious that the internship has a plus in terms of improving skills,
technical and non technical outcomes and different abilities as a whole.
CONTENTS
CHAPTER 1 ABOUT THE COMPANY
1.1 Introduction ................................................................................................................ 1
1.2 Company’s vision ....................................................................................................... 1
1.3 Company’s mission .................................................................................................... 1
1.4 Accomplishments ....................................................................................................... 2
1.5 Landmark projects ...................................................................................................... 3
1.6 Awards & recognitions............................................................................................... 5
1.7 Quality policy ............................................................................................................. 6
CHAPTER 2 ABOUT THE PROJECT AND DEPARTMENTS
2.1 Project overview ......................................................................................................... 7
2.2 Specifications ........................................................................................................... 10
2.3 Organisation structure .............................................................................................. 12
2.4 Emergency evacuation route & logistic plan ........................................................... 12
2.5 Departments at project site PFLN ............................................................................ 13
2.5.1 Plant and Machinery (P & M) Department ............................................................... 13
2.5.2 Safety Department .................................................................................................... 18
2.5.3 Quality Department ................................................................................................... 21
CHAPTER 3 TASK PERFORMED
3.1 Building 1 Details..................................................................................................... 28
3.2 Kumkang Aluminium formwork.............................................................................. 30
3.3 Components in Kumkang Aluminium formwork .................................................... 31
3.4 Sequence of works in Aluminium formwork ........................................................... 34
3.4.1 Structural line (grid line) marking on the slab by surveyor for wall panels erections
as per the farming layout (form plan). ............................................................................... 34
3.4.2 External Working platform ....................................................................................... 35
3.4.3 Reinforcement of walls and beams (Floor & Link beam) ........................................ 35
3.4.4. Placing of sleeves for plumbing and fire fighting. ................................................... 37
3.4.5 Electrical Conduting & placing of wall panels. ........................................................ 37
3.4.6 Installation of Slab corner (SC) & Slab level (SL) panels…………………………38
LIST OF TABLES
Table no Name of table Page no
2.1 Project Prestige Falcon city details 8
2.2 Builder Hoist Technical Specifications 14
2.3 Batching plant details 16
2.4 Testing frequency of construction materials 24
2.5 Rolling margin test results 27
2.6 Rolling margin tolerance as per IS 1786 27
3.1 Building 1 details 28
3.2 Chairs, Spacer bars & cover blocks 36
3.3 Concreting 44
3.4 Concrete grades for structural components 44
3.5 Materials used in SDC & normal concrete at project site 45
3.6 Mix proportions 45
INTERNSHIP AT PRESTIGE GROUP
Over the last decade, the Prestige Group has firmly established itself as one of the leading
and most successful developers of real estate in India by imprinting its indelible mark
across all asset classes. Founded in 1986, the group's turnover is today in excess of Rs.
3518 Cr (for FY 15). A leap that has been inspired by CMD Irfan Razack and marshalled
by his brothers Rezwan Razack and Noaman Razack. Having completed more than 210
projects covering over 80 million sqft, currently the company has 53 ongoing projects
covering 54 million sqft and 35 upcoming projects aggregating to 48 million sqft of
world-class real estate space across asset classes. In October 2010, the Prestige Group
also successfully entered the Capital Market with an Initial Public Offering of Rs 1200cr.
Now with over 205 landmark developments across the city, the company has extended its
expertise to major cities across South India including Chennai, Hyderabad, Kochi,
Mysore, Mangalore and Goa. Giving each city an unparalleled experience with landmark
malls on the lines of 'The Forum', large townships, tech parks, hotels, luxury villas, and
SEZs. The company already has several successful completed and ongoing projects in
Chennai to its credit, spanning the commercial and retail segments. Prestige Cyber
Towers, Prestige Polygon and Prestige Palladium are three completed commercial
developments, which have received an overwhelming response. The Forum Vijaya Mall,
Chennai's largest mall was unveiled in 2013. The Prestige Group launched Chennai's first
township project - a Rs. 1,000 crore development in partnership with the Rattha Group in
2012. They also launched Prestige Silver Springs the first-of-its-kind luxury villas in the
city in 2013.
1.4 ACCOMPLISHMENTS
The Prestige Group today has become a name that is synonymous with innovation. The
company has pioneered many landmark developments and introduced many firsts to
South India:
On the hospitality front, the Prestige Group has been credited with introducing some of
the most reputed international brands in the world to South India, such as the Hilton
Group and Marriott International for hotels; the Banyan Tree for resorts and Oakwood
for service apartments. In association with Starwood Hotels & Resorts Worldwide, the
company launched their hotel, 'The Aloft', in Cessna Business Park in 2014 and will be
launching the Sheraton Hotel in Prestige Shantiniketan in the near future.
The Scope of their Quality System is Planning, development, marketing and management
of residential, commercial and Institutional layouts.
Prestige follows a Quality Management System hierarchy that is strictly abided by in all
its residential and commercial properties in Bangalore and elsewhere. This system
includes departmental guidelines and work instructions as well as essential directions for
the quality management system from the top management, covering all requirements of
ISO 9001:2000.
The group ensures that wastage during construction is as low as 5%, thus providing
optimum value for the client's money whether it is a commercial property investment or
an individual who wants to buy an apartment or villa. They adopt latest technologies for
safer, timely and reliable construction across all our properties in Bangalore and in other
cities, giving you the best bet when you buy an apartment.
The group encourages customer feedback and reviews so that corrective actions can
immediately be put in place. Their quality standards and procedures are periodically
reviewed so as to maintain continuous improvement in all areas of activities based on
customer inputs to enhance customer satisfaction.
The group’s aim is not restricted to being among the best Bangalore builders or in the
country alone but also to be as environment friendly as possible. They address
environmental safeguards and improvements in all our developments for the conservation
and development of a greener and safer environment.
Each of the 5 buildings in Phase I consists of 32 floors (G+31). Building 6 and 7 of Phase
II consists of 26 floors (G+25) and 31 floors (G+30) respectively. Each building has a
helipad on top it. Each building also consists of lower basement and upper basement
completely dedicated for vehicular parking and staff office and quarters.
Apartment unit varies from 2, 2.5, 3 & 4 BHK. Area of the unit’s varying from a
minimum of 1204 sqft to a maximum of 2710 sqft. All this exactly translates into a total
of 2520 number of apartment units. Fig 2.1 gives the aerial view and table 2.1 gives the
details of the project. The location of map and master plan are presented in Fig 2.2 and
2.3 respectively.
2.2 SPECIFICATIONS
1. Structure
3. Lifts
4. Apartment Flooring
Vitrified/Ceramic tiles in the foyer, living area, dining area, corridors and all
bedrooms.
Anti-skid ceramic tiles in balconies
5. Kitchen
6. Maid’s Room
Vitrified/Ceramic tile flooring and dado in the maid's room and toilet.
7. Toilets
Anti-skid ceramic tiles for flooring with ceramic tile on walls upto false ceiling.
Granite counter with ceramic wash basin in the master toilet.
Pedestal wash basins in the other toilets.
EWCs and chrome plated fittings.
Chrome plated tap with shower mixer.
8. Painting
10. Electrical
All electrical wiring is concealed and uses PVC isolated copper wires with modular
switches.
Sufficient power outlets and light points provided for.
4 KW power will be provided for 2 & 2.5 Bed units.
6.4 KW power will be provided for 3 Bed units.
8 KW power will be provided for 4 Bed units.
TV and telephone points provided in the living area and all bedrooms.
Provision to install split AC in living area and in all bedrooms.
ELCB and individual meters will be provided for all apartments.
12. DG Power
Generator will be provided for all common services. 100% backup power will be
provided for all apartments at extra cost.
Fig 2.4 Organization Chart for Prestige Falcon City at site level
As a trainee, I was exposed to four departments within the firm for 16 weeks. The
departments are Plant & machinery, Safety, quality & Execution.
Rollers
Hydraulic Excavators cum Loaders- Back Hoe
Stationary Concrete Pumps- 3 numbers
Passenger cum material hoist
Weighing Bridge
Transit mixers (6 m³ capacity)-8 numbers.
Needle vibrators.
Batching plant -2 numbers.
S205 Bobcat loader.
Tower Crane.
Bar Bending machine.
Recycling wash water / aggregate recovery plant.
Tough rider- for transporting concrete (0.4m³).
Fig 2.8 Passenger cum material hoist Fig 2.9 Builder hoist permissible load chart
(Builder hoist)
Delivery Distance,
600 m
Horizontal
150 m
Vertical
Fig 2.10 Putzmeister Concrete Pump
2500mm x
Dimensions
700mm x 1100
Power 3.6 KW
This left over concrete is washed in Aggregate Recovery plant to recovery the
aggregates.
Transit mixer washout concrete discharges into the charging hopper and flows in to
the washing drum.
The drum rotates to separate the aggregates and slurry water by reverse flow
method.
The slurry water gets collected into the slurry tank.
The aggregates get collected through vibrating sieve.
The agitator stirs the slurry tank in regular intervals to avoid deposition.
The mechanism that enables the jumping of the tower crane is hydraulic jack and a pair of
interim supports (steel brackets, steel beams).
Safety at construction site means absence of accidents and hazardous events. Safety
department in which coordination of labours is very important as their tendency of
negligence can pose threat to their life as well as others.
Safety practices followed at the site prestige falcon city are as per the Indian standards &
OSHA guidelines
All persons should wear approved helmet, safety shoe and all required PPE.
Child labour at site is strictly prohibited.
Smoking is prohibited at work place, except in smoking zones.
Gambling, Alcohol, drugs and unruly behavior are strictly prohibited.
Follow all safety signs, site traffic rules and obey all instructions given by
authorized persons.
Always maintain good housekeeping and the work area clean and tidy.
Safety posters/placards must be displayed and followed
Emergency escape procedures.
Display Safety park board at entrance.
Fig 2.18 Open edges –installation of safety nets & proper barricading
Specific gravity
Sieve analysis
Silt content (wet sieve through 75µ)
Flakiness index
Elongation index.
Aggregate impact value
Aggregate crushing value
Water absorption
Moisture content
Test on Steel
Test on Concrete
Fineness of Flyash
Chemical & Physical analysis
Test on steel
Every 50 m³
received-CA &
1.2 Sieve analysis Of aggregate
Site lab 100 m³ received-
(CA/FA) FA.
Selection of
Test for organic
1.5 Third party source/change of
impurities(FA)
source.
2. Cement
Every 6 months
3 Water Third party IS 456
once
4 Reinforcement steel
3 sample for
4.1 Rolling margin Site lab
each lot
Manufacturer test
Tensile test, Elongation, Bend Certificate or test Third party test IS 1786
4.2
& Rebend test report from third for every 50MT :2008
party
Chemical Third
4.3 While change of source
analysis party
5 Concrete
IS
Outside Third party for all grades (initially).
Mix design 10262
5.1 lab/Site lab In site lab- change in brand of cement
:2009
1-5 m³ =3, 6-15 m³ = 6, 16-30 m³ = 9, 31-50 m³ = 12 & 51 & above = 12 + 6 sample for
each 50m³ concrete
Fig 2.21 Construction materials (Aggregate, Cement) tests conducted at QA/QC lab
Lot/heat number.
Dia of Bar mm, Quantity in MT.
Chemical composition- Carbon, Sulphur,
phosphorous content.
Mechanical properties- weight (Kg/m),
Proof/yield stress N/mm², Tensile strength,
Elongation, Bend & Rebend Test, Grade of steel.
Steel falling below or beyond the following tolerances should be rejected from the site.
Fig 3.1 Level 1 Floor Plan (Ground Floor) Fig 3.2 Level 2 Floor plan (1st Floor)
The level 1 & 2 consist of total 12 flats & 2 Lobbies (Double height space)
Ground level RL = 105.45m, Terrace finished floor level = 203.05m & Parapet
height=1.5m. Therefore total height of Building 1 is (203.05-105.45) + 1.5 = 99.1 m.
All Windows present in Building 1 is of height 1200mm. Sill height for windows, Duct
Door is of 900/1200mm and Lintel Height is of 2100/2400 mm.
Advantages
Limitations
SC Slab corner
Slab Panel
Prop Head
1. Structural line
(grid line) marking
on the slab by 6.Installation of slab
Surveyor for wall corner (sc) and slab 7. Placing of stair
panels erections as level (sl) case panels
per the farming
layout (form plan).
3.4.1 Structural line (grid line) marking on the slab by surveyor for wall panels
erections as per the farming layout (form plan).
Procedure:-
Entire platform is covered with safety net with aid of 20mm steel bar.
Description Photo
Splicing
The process of joining two bars to transfer the force from one bar to another bar in an
RCC element is called as Splicing.
M 20 57D
M25 50D
M30 46D
M35 40D
Groove
Sleeves are opening in the concrete that allows passage of pipes i.e. water supply pipes,
fire fighting pipes in building once finished.
1. Wall panels
3. Beam Bottom SC
5. Beam Panel
Note:-If installation order is not trained properly to workers, it will damage the
panels and delay the construction period.
3.4.6. Installation of Slab corner (Sc) & Slab level (SL) panels.
Slab level
Slab Corner
Fig 3.12 Installation of Slab corner (SC) & Slab level (SL) panels
Installation of beams (span), props & slab panels as per the formwork layout
Beams are assembled using the middle beam or End Beam & prop head with joint bars &
long pin. Assemble the Beams on the floor before installing them on the slab level.
Fig 3.14 Assembled view of beams (span), props & slab panels
3.4.7 Staircase
Fig 3.15 Assembly of stair case slab panels Fig 3.16. Placing of reinforcement
& side panels.
Fig 3.17 Assembly of staircase wall panels Fig 3.18 Assembly of gun panels
Fig 3.19 Assembly of tread & riser panels Fig 3.20 Completed view of aluminium
formwork Stair case.
3.4.8 Applying form oil on the slab panels
Sunken Arrangements
Bar dia, shape of bars, dimension of bar, number of bar, cleanliness of bars.
Check for correct placing and spacing of bars as per drawings.
Provision of chairs, cover blocks & spacer bars.
Lap length and location of laps.
Check for satisfactory tying of reinforcement with binding wire.
3.5.2 Shuttering
Horizontal alignment of wall panels (Line dory & grid line by surveyor) & inner
dimensions of rooms, doors & windows.
Vertical alignment of internal wall panels (Plumb check).
Vertical alignment of external wall panels (Plumb check) for straightness and
verticality of the wall.
Whether wedge pin and flat ties have been installed correctly.
Whether the props have been installed as per the formwork layout.
Whether all panels have been installed.
Check for cleanliness of the panels.
Whether form oil has been applied on the slab panels.
Check for the sealing of gaps, joints & holes.
Check for completion of other preceding activities such as fixing of sleeves, electrical
conduits and other services before fixing of wall panels.
A alignment of kicker panels
3.6 CONCRETING
The process of mixing, transporting and placing of concrete is called concreting.
mineral admixture Fly ash from Ash Tech Fly ash from Ash Tech
Table 3.5 Materials used in SDC & normal concrete at project site
Testing readings are sent to Batching plant (Concrete production plant) for moisture
content corrections.
SDC is used for concreting the units (i.e. flats from G + 31st floor).
Normal concrete is using for concreting the raft foundation, isolated footings, column,
beams, flat slab.
Bonding agent used at site is FOSROC product -Nitobond EP Base & Nitobond EP
hardener.
Methodology
Fig 3.31 Arrangement of concrete Fig 3.32 stair case concreting upto
Pump & pipes midlanding
End
Start
2. Tendency of the workers to keep the needle vibrators dropped at a single point for
more duration, instead of lifting and dropping at different points of concreting.
3. Concrete pipeline burst due to wear of pipes (reduce the gauge of pipeline).This can be
minimized by frequent checking of gauge and changing of the pipes which are having less
gauge.
Dismantling process is a very important process. Therefore engineers should train the
workers to know the Dismantling method of walls, Beam & Slab panels.
Note:-
While de shuttering the slab panels, the steel props & prop head will not be dismantled &
disturbed.
Steel props & prop head will be dismantled only after the next level casting this is known
as BACK PROPING.
The formwork is designed to safely support the combined loads (dead and live loads)
during concreting, without bulging or deflecting.
A) Staging- Cup -lock system, is a supporting system required to keep the form work in
position. It carries loads and transmits it to the firm surface/base.
1. Base jack
2. Verticals/standards of different height
3. Horizontals/ledgers of different lengths
4. Adjustable screw jack (U head)
5. Primary Waller - (ISLC – 75mm x 40mm)
6. Secondary Waller – Hollow square tube of size 50mm x 50 mm x 2.9 mm
B) Ply wood dimensions – 2.44 m x 1.22m thickness – 6mm
C) Wooden Runner size -75 mm x 50mm, Runners are used to strengthen the plywood
and to prevent the plywood from bending, warping & Bulging. Spacing & size of runners
depends on loads that will be imposed on the formwork.
Fig 3.37 Excavation of soil as per markings Fig 3.38 Checking the depth, length,
given by the surveyor. breadth and level of excavation using
measuring tapes & auto level, as per the
drawing.
3. Pouring & finishing the top level of PCC
with aluminum straight edges.
Fig 3.40 Placing of Footing reinforcement Fig 3.41 Column reinforcement &
with reference to markings shuttering for the footing
Fig 3.42 Pouring, vibrating & Finishing Fig 3.43 Placing of wooden runner
the top level of footing concrete piece at column location.(Shear Key)
Fig 3.46 Beam staging in process Wooden runner is placed on steel tube
to nail the Beam Bottom plywood.
Fig 3.47 Placing of centering sheets Fig 3.48 Application of form oil &
placing of reinforcement.
Fig 3.49 Stair case Reinforcement Fig 3.50 Stair case Shuttering
Fig 3.54 Compacting Concrete by needle vibrators (Beams & Beam Column Junction)
OBSERVATIONS
Fig 3.58 Earth filling Fig 3.59 compacting the soil in layers by
using vibratory rollers
3.14.1 Determination of the dry density of compacted soil by core cutter method
(IS2720- part 29)
3.15.1 Methodology
Fig 3.64 Water ponding test Fig 3.65 Pressure grouting machine
(To arrest the leakages) to arrest leakages
Fig 3.66 Applying Fosroc Brush Bond Fig 3.67 Fix geo fabric over the coated
surface
3.16.1 Methodology
Cement- 275 kg/m3, Flyash -45 Kg/m3, M sand-803 Kg/m3, 12.5 coarse aggregate -1156
Kg/m3, Water-160 Kg/m3, Admixture-2.24
Admixture Kg/m3.
Fig 3.70 Pouring concrete & finishing the surface using troweling machine
Bondit 151
High performance bonding agent for gypsum on RCC surface. Do not need to hack the
RCC surface when we use Bondit for the application of gypsum.
Application Procedure
Fig 3.71 Mixing of gypsum Fig 3.72 Fixing up of Bull marks on walls &
& water in correct Ceiling at every 1.5 m -2m spacing (this facilitates
proportions the accurate thickness of the gypsum plaster.)
After undergoing my internship, I came across the various departments that prevail at
the construction site like safety, plant and machinery, QA/QC & Execution etc.
I came to know about various materials that were used at the site.
I came to know about the process and specification of different activities starting
from reading of drawings till execution.
I understood media of communication between client and contractor.
Study and understanding of architectural and structural drawings.
Reinforcement details and Bar bending schedules.
Different waterproofing methods and techniques.
Mass concreting process, methods & techniques
Quality check for various materials.
Complete understanding of aluminium formwork system
I came to know finishing works that is gypsum plastering, tiling and door & window
fixings.