Professional Documents
Culture Documents
Civil Engineering
All AE JE Exams Covered
8-10-14
2 6
8
6-8-11 4-10-12
1 4 5
4-7-10
9 10
3
7
Compute The Earliest Expected Times and The
Latest Allowable Occurence Times of Various
Events.
ABOUT ME
❖ Teaching Experience: 5+ Years
❖ Qualification: B.Tech in Civil Engg, Postgraduate in Urban
Planning & Development
❖ Achievements:
▪ SSC JE , NBCC , NPCC
▪ GATE
▪ Mentored More Than 50,000+ Students
After removing
A Redundant Dummy
C
B
| Construction Planning &Management | CPM PERT |
After removing
Redundant Dummy
B
A
C
| Construction Planning &Management | CPM PERT |
A C
B D
| Construction Planning &Management | CPM PERT |
➢ Rules Of A Network
1. There can be only one initial & one final event.
➢ Rules Of A Network
Example:
4 8 9
1 2 3 6 7 10
5
| Construction Planning &Management | CPM PERT |
Example 2:
2 4
1 6
3 5
| Construction Planning &Management | CPM PERT |
➢ Errors In A Network
2
1. Looping Error A B
Loops Should not be Formed.
1 3
C
2 Right
A B
1 3
C
Wrong
| Construction Planning &Management | CPM PERT |
➢ Errors In A Network
2. Dangling Error
Project is complete only when all its activities are complete
but the duration of activity 'R' has no effect on the project time.
3
Q T
P S U
1 2 4 5
R More than one Final Event
6
| Construction Planning &Management | CPM PERT |
➢ Errors In A Network
3. Redundancy Error
Redundant Dummies are those which are in
excess in any network. Such Dummies makes the
Network Lengthy and Calculations Difficult.
Activity B Activity E
3
| Construction Planning &Management | CPM PERT |
A Errors In A Network
t=0 3. Redundancy Error
B Redundant Dummies are those
which are in excess in any network.
C
Such Dummies makes the Network
Lengthy and Calculations Difficult.
After removing
A Redundant Dummy
C
B
| Construction Planning &Management | CPM PERT |
➢ PERT
• Based on Probabilistic Approach
• It is event oriented.
• Three types of times are estimated for every
activity.
• Cost is directly proportional to time.
➢ CPM
• Based on Deterministic Approach.
• It is Activity Oriented.
• Only One Time is calculated for every Activity.
• It is suitable for repititive types of work.
➢ PERT
(Project Evaluation and Review Technique)
• It Involves Uncertinity into the project completion
time.
• It is a Numerical Technique used in the Projects in
which time can not be estimated accurately such as
research work and development works.
• It is Event Oriented Network.
| Construction Planning &Management | CPM PERT |
➢ PERT
Three Times Estimates are Made in PERT:
σ = tp - to
6
It can be seen σ is affected by relative distance
from to to tp
Hence, Wide Range in time estimate represents
greater Uncertainity.
| Construction Planning &Management | CPM PERT |
➢ β-Distribution Curve
It is a curve between Probability of completion of Activity and its
Time.