Professional Documents
Culture Documents
Civil Engineering
All AE JE Exams Covered
Daily 9:00 PM on Youtube
Class Link : https://youtu.be/l4P3dkih7Fg
8-10-14
2 6
8
6-8-11 4-10-12
1 4 5
4-7-10
9 10
3
7
Compute The Earliest Expected Times and The
Latest Allowable Occurence Times of Various
Events.
ABOUT ME
❖ Teaching Experience: 5+ Years
❖ Qualification: B.Tech in Civil Engg, Postgraduate in Urban
Planning & Development
❖ Achievements:
▪ SSC JE , NBCC , NPCC
▪ GATE
▪ Mentored More Than 50,000+ Students
b
BASICS OF PROJECT MANAGEMENT
Objective:
1. It should be completed in minnimum time with minnimum
capital Investment.
2. It should use available Manpower & other Resources
Optimally.
b
Phases Of Project Management
1. Planning
2. Scheduling
3. Controlling
➢ Planning Involves:
1. Define objective of the project.
2. Listing Jobs that have to be performed.
3. Determining the gross requirements for materials,
equipments and man power and preparing estimates of costs
and duration for various jobs.
4. The satisfactory completion of Project.
Assigning starting and completion dates to each activity to proceed in a logical sequence
and in a systematic manner.
➢ Methods of Scheduling
a. Charts
1. Bar Charts
b
2. MileStone
3. Linked Barcharts
b. Network Analysis Methods
➢ PERT
➢ CPM
➢ UNETICS
➢ LESS
➢ TOPS
➢ SCANS
➢ Controlling
This Phase is the execution of Planning and Scheduling.
Project Objective
The Process of Breaking the whole project into Objective -1
easily identificable smaller units.
Objective -2
It is usually the 1st Process Adopted In Project
Management. Objective -3
➢ Elements of a NETWORK
Network
It is the flow of Daigram consisting of
• Activities
• Events
Connected logically and Sequentially.
Event
• An Event is either Start or Completion of an Activity.
• Events are Significant points in a project which act as
control points of the Project.
• An Event is an Instant of time and does not Require
time or Resources.
• It is Represented by NODE usually CIRCLE.
Activity
• It is actual performance of a task required for
completion of the project.
• Activity Consumes time and resources.
• It is usually represented by
• → (Arrow) in Activity on Arrow Network(AOA).
• (Node) in Activity on Node Network(AON).
Activity
• It is usually represented by
• → (Arrow) in Activity on Arrow Network(AOA).
• (Node) in Activity on Node Network(AON).
1
A 2
B 3 AOA is Generally Used
A B AON
Event
Example:
• Budget Prepared
• Construction Completed
Activity
Example
• Preparing Budget
• Mixing Concrete
Types of Event:
Activity B
4
Types of Event:
3. Dual Event
All Event except the 1st and Last Event of a Project
are Dual Role Events.
Example:
Activity B Activity E
3
Types of Event:
1 3 4 5
Tail Event Dual Event Head Event
2
Dual Event
Types of Event:
Successor Event:
The Event that follow another Event are called
Successor Events to that Event.
Example: Successor Event to Event 1 are Event 2 &
Event 3.
1 3 4 5
2
Types of Event:
Predeccessor Event:
The Event that occur before another Event are
called Predecessor Events to that Event.
Example: Successor Event to Event 1 are Event 2 &
Event 3.
1 3 4 5
2
2 Types of Activities:
A C
B D 1. Parallel Activities:
1 3 5 The Activities which can be
E performed simultaneously and are
4 F independent of each other .
F is a Successor Activity to
Activity E.
2 Types of Activities:
A C
B D 3. Predeccessor Activities:
1 3 5 Activities that are performed before
E any other activity can begin.
4 F
A is a Predeccessor Activity of
Activity C.
A C ➢ Logical Relationship
1. To Show Realtionship with other
t=0 activities.
2. Here dummy is required to show
B that Activity D can start after
D
completion of A & B Both.
Unnecessary Dummies
Should be Avoided
➢ Grammatical Relationship
1. To Prevent two arrows having
common beginning and common
end.