BUDGETARY QUOTATION

NO 255-QO-2022 PT.HITEK INSPIRA INDONESIA


Sales Engineer : Hary Harimurti Bambu Kuning B2 No.16
DATE : 23-11-22 Batu Aji - Kota
Batam Phone : 0778-
4099869
To Email : sales@hitekinspira.co.id
PT.PINITEC www.hitekinspira.co.id

MALAISYA

Attn Mr THOMAS
NO WORK DESCRIPTION QTY VOLUME PRICE TOTAL
1 PAINTING LINE RELOCATION WORKS
DEINSTALLATION WORK
I Preparation
1 Equipment tagging 1 Ls 2,500,000 2,500,000
2 Worktool/Equipment preparation 1 Ls
3 Temporary partition installation 60 m3 27,500 1,650,000

II Partition and roof work


1 Equipment/ room partition deinstallation and clearing 350 M3 75,000 26,250,000

III Electrical Power Distribution


De installation work and relocation 1 Ls 22,500,000 22,500,000
1 Oven Conveyor
2 Spray booth
3 Filtration
4 Air Shower
5 Batch oven
6 Paint/ Mixing room
7 External and Internal Air blower

IV Piping and ducting


De installation and relocation 1 Ls 20,000,000 20,000,000
1 Gas line piping
2 Air pressure piping
3 Water piping
4 Blower ducting

V Equipment/Mechanical
All equipment de installation 1 Ls 62,500,000 62,500,000
1 Conveyor Line Oven
2 Spray Booth
3 Filtration unit
4 Air shower Unit
5 Batch oven
6 Mixing room.

VI Finishing
2 Roof repair /installation with SAKURA Plafon 250 M3 250,000 62,500,000
1 Partition re installation, repair 200 m3 220,000 44,000,000
3 Wall & room finishing 1 Ls 10,000,000 10,000,000
4 Electrical Installation Finishing 1 Ls 10,000,000 10,000,000
6 Clearing works 1 Ls 7,500,000 7,500,000

VII Transportation 1 Ls 15,000,000 15,000,000


1 All equipment transportation
TOTAL 284,400,000
NO WORK DESCRIPTION QTY VOLUME PRICE TOTAL
1 PAINTING LINE RELOCATION WORKS
INSRALATION WORK
PLACEMENT, INSTALL, TEST AND COMISSIONING
I Preparation
2 Worktool/Equipment preparation 1 Ls
3 Temporary partition installation 60 m3 27,500 1,650,000

II Electrical Power Distribution


Electrical power distribution installation (new Install) 1 Ls 48,500,000 48,500,000
All distribution box / protection, used existing unit
1 Oven Conveyor
2 Spray booth
3 Filtration
4 Air Shower
5 Batch oven
6 Paint/ Mixing room
7 External and Internal Air blower

III Partition and roof work


All door using existing material
1 Partition work 400 M3 220,000 9,000,000
2 Roof repair /installation with SAKURA Plafon 250 M3 250,000 67,500,000

IV Piping and ducting


re installation used old material and add new material 1 Ls 62.500,000 62.500,000
1 Gas line piping
2 Air pressure piping
3 Water piping
4 Blower ducting

V Equipment/Mechanical
All equipment placing, leveling, Installation and testing 1 Ls 105,000,000 110,000,000
And troubleshooting
1 Conveyor Line Oven
2 Spray Booth
3 Filtration unit
4 Air shower Unit
5 Batch oven
6 Mixing room.

TOTAL 362,400,000
NO ITEM DESCRIPTION PRICE QTY TOTAL

1 PAINTING LINE RELOCATION WORKS 362,400,000 1 Ls 362,400,000


INSRALATION WORK
PLACEMENT, INSTALL, TEST AND COMISSIONING
TOTAL 362,400,000

Term and Condition


1 Delivery time :1 Month
2 Quotation validity : 30 days
3 Payment terms :
Down Payment : 30% 70% termin per
progress
4 Warranty : 1 Month

Yours faithfully, HARYONO HARIMURTI


Email : harimurti@hitekinspira.co.id
CC. EKO WAHYONO [ 0819 90802074 ]
This is a computer-generated document. No signature is required