COST ESTIMATE
I SURVEY QTY UNIT UNIT COST LABOR COST TOTAL COST
BOUNDARY RELOCATION AND
1 MONUMENTING 1.00 KM. 15,000.00 15,000.00
TOTAL SURVEY: 15,000.00
II TEMPORARY FACILITY
1 FIELD OFFICE 1 LOT 50,000.00 50,000.00
2 WAREHOUSE 1 LOT 30,000.00 30,000.00
3 BARRACKS 1 LOT 75,000.00 75,000.00
4 ELECTRICAL AND WATER 1 LOT 20,000.00 20,000.00
TOTAL TEMFACIL: 175,000.00
III EARTHWORKS
1 LEVELLING/SCRAPPING 3,000.00 M3 600.00 1,800,000.00
2 COMPACTION 10,000.00 SQ.M 300.00 3,000,000.00
3 GRAVEL BEDDING 1,500.00 M3 1,500.00 2,250,000.00
TOTAL EARTHWORKS: 7,050,000.00
IV FORMWORKS