You are on page 1of 1

Firstly my journey started for civil engineering from 2015 firstly I passed Diploma in 2015 from

Board of Technical Education, Uttar Pradesh after completion of Diploma in 2015 I started my
first Job with the Leonine construction as a Site Engineer and I was deployed at IIT Delhi campus
for renovation project that project included all the renovation activities in the houses like execution
in foundation, brick work, sunken portion waterproofing, flooring, carpentry works, replacing of
doors and windows, flooring, tiling , painting, GI and CI pipes, sanitary fittings etc. and my journey
was ended with leonine constructions on Aug 2017, also In 2016 I gave entrance test of Delhi
Technological University for B.Tech admission and after clearing the exam I took admission in
B.Tech where my classes held 6 PM to 9 PM (Monday- Saturday) and full day during Sunday and
Public Holiday (if Required), In Aug 2017 I joined a new Firm i.e, Modern Concept Construction
where I deployed in the office of Asst. Executive Engineer (Civil) now Executive Engineer (Civil)
at IIT Delhi where my work was the preparation of preliminary and detailed estimates, preparation
of tenders, Technical evaluation after opening the technical bids, comparative statement after
opening the financial bids, preparation of justifications of tenders, preparation bills in CMB
formats, preparation of extra or substitute items, preparation deviations statement of the work. In
Feb 2019 I resigned for better opportunity and I again joined Leonine Construction as a Junior
Engineer (Civil), I deployed at various sites of CPWD and IIT for rehabilitation, renovation and
retrofitting of old buildings and there I learnt about constructions chemicals, how can we use it
and these chemicals can increase the ages of old structures and During all these things I also
completed my Engineering in 2020, In 2021 I joined Garg Builder where my duties are preparation
of bills in CMB format, submission of bills to client, Taking actual measurement on site,
preparation extra items if required, preparation deviation statements etc.