1/23/23, 12:46 AM Internal Assessment - 3: Attempt review

Dashboard → My courses → School of Online Education (SOE) → JULY 2021 Batch → SOE-PUNE → MBA (Online) → 2nd Year

→ Semester III → MBA SEM III - PR02 Microsoft Project 2010 → Quadrant IV : Assessment → Internal Assessment - 3

Started on Saturday, 21 January 2023, 5:12 PM

State Finished

Completed on Monday, 23 January 2023, 12:45 AM

Time taken 1 day 7 hours

Grade 18.00 out of 20.00 (90%)

Question 1
Correct

Mark 1.00 out of 1.00

You can use Project’s ….. to change the appearance and behavior of various Project elements.

a. data area
b. timeline
c. auto schedule
d. status bar 

The correct answer is: status bar

Question 2
Correct

Mark 1.00 out of 1.00

You can display the Organizer by clicking the Organizer button in the ….... view.

a. Display
b. Organiser
c. Backstage 
d. Windows

The correct answer is: Backstage

https://cdoe.bharatividyapeeth.integratededucation.pwc.in/lms/mod/quiz/review.php?attempt=177683&cmid=37787 1/7
1/23/23, 12:46 AM Internal Assessment - 3: Attempt review

Question 3
Correct

Mark 1.00 out of 1.00

Project allows you to undo actions you take while working in a Project file, and you can set the number of times you
can click Undo to any number between 1 and 99. By default, Project lets you undo your last …. actions

a. 10
b. 20 
c. 30
d. 40

The correct answer is: 20

Question 4
Correct

Mark 1.00 out of 1.00

The Macro Recording indicator appears between the …...... indicator and the …... indicator.

a. Cell Mode & New Tasks 


b. Read Mode & Page layout
c. Gantt chart &Task usage
d. Team planner & Resource Sheet

The correct answer is: Cell Mode & New Tasks

Question 5
Incorrect

Mark 0.00 out of 1.00

You can decide to show number of recent projects accessed in project options …

a. Advance - Display
b. Advance - Edit
c. Advance - Display options for this project
d. Customise Ribbons 

The correct answer is: Advance - Display

https://cdoe.bharatividyapeeth.integratededucation.pwc.in/lms/mod/quiz/review.php?attempt=177683&cmid=37787 2/7
1/23/23, 12:46 AM Internal Assessment - 3: Attempt review

Question 6
Correct

Mark 1.00 out of 1.00

You can switch among Project files by using the …... button in Project or the Windows taskbar.

a. Network Diagrams
b. Other Views
c. Switch Windows 
d. Find & Select

The correct answer is: Switch Windows

Question 7
Correct

Mark 1.00 out of 1.00

Project uses the …......... to help you share views, tables, forms, reports, and more among projects.

a. Display
b. Organiser 
c. Windows
d. None of the given responses

The correct answer is: Organiser

Question 8
Correct

Mark 1.00 out of 1.00

When you copy an element to the …........., that element becomes available to all files created with your copy of
Project.

a. Open Project
b. Hidden Project
c. Linked Project
d. Global template 

The correct answer is: Global template

https://cdoe.bharatividyapeeth.integratededucation.pwc.in/lms/mod/quiz/review.php?attempt=177683&cmid=37787 3/7
1/23/23, 12:46 AM Internal Assessment - 3: Attempt review

Question 9
Correct

Mark 1.00 out of 1.00

You can quickly add any button that appears on the ….... to the QAT if you right-click the button and choose

a. Ribbon 
b. Status Bar
c. Options
d. None of the given responses

The correct answer is: Ribbon

Question 10
Correct

Mark 1.00 out of 1.00

You can place the same button on two different tabs; if you do, Project assigns ….. keyboard shortcuts to that button
on each tab.

a. same
b. aligned
c. different 
d. None of the given responses

The correct answer is: different

Question 11
Correct

Mark 1.00 out of 1.00

When you analyze the progress of your project, you also measure the progress based on the costs you incur by
measuring the ….......... of your project

a. earned value 
b. earned cost
c. losses
d. liabilities

The correct answer is: earned value

https://cdoe.bharatividyapeeth.integratededucation.pwc.in/lms/mod/quiz/review.php?attempt=177683&cmid=37787 4/7
1/23/23, 12:46 AM Internal Assessment - 3: Attempt review

Question 12
Correct

Mark 1.00 out of 1.00

Where the scheduled or actual project performance differs from the baseline plan, you have variance. Variance is
usually measured as …

a. Duration
b. Time 
c. Spaces
d. None of the given responses

The correct answer is: Time

Question 13
Correct

Mark 1.00 out of 1.00

Budgeted Cost of Work Scheduled is also known as …

a. FV
b. PV 
c. EV
d. SV

The correct answer is: PV

Question 14
Correct

Mark 1.00 out of 1.00

Acronym EAC stands for

a. Estimate above Completion


b. Earned at Completion
c. Estimate at Completion 
d. None of the given responses

The correct answer is: Estimate at Completion

https://cdoe.bharatividyapeeth.integratededucation.pwc.in/lms/mod/quiz/review.php?attempt=177683&cmid=37787 5/7
1/23/23, 12:46 AM Internal Assessment - 3: Attempt review

Question 15
Incorrect

Mark 0.00 out of 1.00

These fields are really at the heart of earned value analysis ….

a. PV, AV and AC
b. SC, PV and FV
c. BAC, VAC and EAC
d. None of the given responses 

The correct answer is: PV, AV and AC

Question 16
Correct

Mark 1.00 out of 1.00

This field represents your estimate of the progress of a task, regardless of actual work or time, and is not a time
phased field.

a. % Complete
b. % Progress
c. % on Track
d. Physical % Complete 

The correct answer is: Physical % Complete

Question 17
Correct

Mark 1.00 out of 1.00

Project calculates Cost Performance Index(CPI) by dividing.

a. FV by PV
b. FV by EV
c. EV by AC 
d. EV by PV

The correct answer is: EV by AC

https://cdoe.bharatividyapeeth.integratededucation.pwc.in/lms/mod/quiz/review.php?attempt=177683&cmid=37787 6/7
1/23/23, 12:46 AM Internal Assessment - 3: Attempt review

Question 18
Correct

Mark 1.00 out of 1.00

Project calculates % Complete by dividing …

a. actual task duration by total duration 


b. task duration by total duration
c. total duration by task duration
d. total duration by actual task duration

The correct answer is: actual task duration by total duration

Question 19
Correct

Mark 1.00 out of 1.00

Project stores …. Baselines to for earned value

a. 11 
b. 10
c. 9
d. 7

The correct answer is: 11

Question 20
Correct

Mark 1.00 out of 1.00

You can turn off Project’s ability to reschedule incomplete work on tasks for which any actual work has been
recorded. By selecting “….....” check box in shedule Tab

a. Update manually
b. New task
c. Default task type
d. Split in-progress tasks 

The correct answer is: Split in-progress tasks