Booking Confirmation and shipment status details

s.no. Inv no.: inv details No.of containers type of container


1 FEIPL/22-23/03 1st lot Boiler- 3 3x40OT
2 FEIPL/22-23/04 Cooling Tower 2 2X40HC
3 FEIPL/22-23/05 2nd Lot Boiler-1 3 3x40OT
4 FEIPL/22-23/06 ESP 8 7x40OT and 1x40HC
5 FEIPL/22-23/07 2nd Lot Boiler -2 2 2x40OT
6 FEIPL/22-23/08 2nd Lot Boiler -3 2 2x40OT
7 FEIPL/22-23/10 3rd Lot Boiler-1 1 1x40OT
8 FEIPL/22-23/11 CHS-1 1 1x40OT
9 JSPL inv-1 EOT Crane 1 1x40OT
10 JSPL inv-3,4,5 Barbil Auxillary items 2 2x40OT
11 JSPL inv-5 Condenser 2 1x40 FR & 1x40 HC
12 FEIPL/22-23/12 Chimney -1 4 2x40FR and 2x40OT
13 FEIPL/22-23/13 3rd Lot Boiler-2 2 2x40OT
14 FEIPL/22-23/15 3rd Lot Boiler-3 1 1x40OT
15 FEIPL/22-23/17 3rd Lot Boiler-4 2 2x40OT
16 FEIPL/22-23/16 Crush motors 2 1x20FR and 1x40HC
17 FEIPL/22-23/18 Crusher-18 included in item no.17
18 FEIPL/22-23/20 TG Bolts-20 included in item no.17
19 FEIPL/22-23/19 Boiler-19 1 1 OT
20 FEIPL/22-23/21 Boiler-21 3 1x40HC and 2x40OT
21 FEIPL/22-23/22 Boiler-22 included in item no.20
22 FEIPL/22-23/23 CHS-2 included in item no.20
23 FEIPL/22-23/24 CHS-2 included in item no.20
24 JSPL inv - 7 Turbine 1 1x40 FLAT RACK
25 JSPL inv- 8 Generator 2 1x40FR and 1x40HC
26 JSPL inv -9 Panels 1 1x40HC
27 FEIPL/22-23/25 Compressors 1 1x40HC
28 FEIPL/22-23/26 DG Set included in above
29 FEIPL/22-23/27 Boiler-AIr Boxes 2 2x40HC
30 boiler-balance heaters 1
FEIPL/22-23/28 etc 1x40HC
31 FEIPL/22-23/29 ASH Silo 1 1x FR
32 FEIPL/22-23/30 CHS bal Structure 1 1 x HC
33 FEIPL/22-23/31 Transformers 3 2 FR + 1 HC
34 FEIPL/22-23/34 WTP 2 material ready
35 AHS bal equip 1 not ready
36 LHS silo 1 not ready
37 CHS BC4 Gallery 1 not ready
38 CHS Motor frames 1 not ready
39 CHS Transfer tower etc. 1 not ready
40 LHS andd AHS Bal 1 not ready
41 HT Panels 1 not ready
42 PCC and MCC 2 not ready
43 Boiler balance 6 not ready
44 PLC 1 not ready
45 PRDS & BUS Ducts 1 not ready
46 CE & CW Pumps 1 not ready
47 ETP & FFS 1 not ready
48 Cables, trays etc. 1 not ready
49 Piping and instruments 1 not ready
50 CEMS etc. 1 not ready
51 Valves etc. 1 not ready
FEIPL/22-23/32 Dearator 1 1XFR
Total containers 80 already sailed 48
Delivery in Moza reaching site Packiging list
Received 23.09.2022 https://drive.google.com/file/d/1xWoH6QaGjNwFFnbo6TEirRYiFxNRfB3j/view?usp=share_link
Received 02.10.2022 https://drive.google.com/file/d/1KFVsPZTcDN0G7u5bubyuhDuQDMRAS76E/view?usp=share_link
Received 18.10.2022 https://drive.google.com/file/d/1M4FI7rMkLhMQY5hQX75urqRK4f3uY4sU/view?usp=share_link
Received 20.10.2022 https://drive.google.com/file/d/1Lz97C1ul_ISnKOSbJmu800nYdQZFLoIw/view?usp=share_link
Received 19.10.2022 https://drive.google.com/file/d/1LyJQ2wzWnSt8yPIIwLvOGOFUw5NQIBZt/view?usp=share_link
Received 17.11.2022 https://drive.google.com/file/d/1LyJQ2wzWnSt8yPIIwLvOGOFUw5NQIBZt/view?usp=share_link
Received 05.12.2022 https://drive.google.com/file/d/1LpsW_jZ4Q2U9-I7AddR4x_qBdsPG51_Y/view?usp=share_link
Received 05.12.2022 https://drive.google.com/file/d/1LmSmP9loAw034O5vi8XAmy0A0XTkDCED/view?usp=share_link
Received 29.10.2022 https://drive.google.com/file/d/1qnJClQ3MIkDR5HF2k3WD90WHMUq10E9W/view?usp=share_link
Received 07.11.2022
Received 10.01.2023 https://drive.google.com/file/d/1qnJClQ3MIkDR5HF2k3WD90WHMUq10E9W/view?usp=share_link
Received 27.12.2022 https://drive.google.com/file/d/1LiIKpm4Y1V12YA4jYwQti1SwmuzFMu8R/view?usp=share_link
Received 27.12.2022 https://drive.google.com/file/d/1LY0020gcyseWVGbb9sAJjbQv9JlT22U9/view?usp=share_link
Received 23.01.2023 https://drive.google.com/file/d/1LW3IYlfoRxxkqxCtmFGweFqieKGiMyh6/view?usp=share_link
Received 23.01.2023 https://drive.google.com/file/d/1LHP-RHZ-NOFQtCpSXSi3oSdH0WZhzzzn/view?usp=share_link
Received 28.01.2023 https://drive.google.com/file/d/1LQYfcx3Efdk-P1QIDjyr6yFzJRTM7bhk/view?usp=share_link
Received 04.02.2023 https://drive.google.com/file/d/1LCILwpgbE_6XpoW1W1N37zCkgPxOI59v/view?usp=share_link
28.01.2023
Received 23.01.2023 https://drive.google.com/file/d/1OPNtI25NLWdidX8o-6pRzH-1KY5_fegd/view?usp=share_link
Received 28.01.2023 https://drive.google.com/file/d/1LAGtMk-oWCHv4uPCX7r9HxFl7a3nNI6B/view?usp=share_link
Received https://drive.google.com/file/d/1L8KgAjX3_uQWg7KkV_BfuDB_UBYFWmvx/view?usp=share_link
Received 05.02.2023 https://drive.google.com/file/d/1LAGtMk-oWCHv4uPCX7r9HxFl7a3nNI6B/view?usp=share_link
Received 05.02.2023 https://drive.google.com/file/d/1LAGtMk-oWCHv4uPCX7r9HxFl7a3nNI6B/view?usp=share_link
Received 09.02.2023 https://drive.google.com/file/d/1pJHHaKnr-UdvI-5WvE4Suhoj4X34YYyW/view?usp=share_link
Received 02.02.2023 https://drive.google.com/file/d/1JAO09cesQivf-z-ptdtuepFI9-m9meq7/view?usp=share_link
At Beira https://drive.google.com/file/d/1puOKa4OlDdlv5SWcbjEVlp-nNjmEg-jn/view?usp=share_link
Received 02.02.2023 https://drive.google.com/file/d/1L6hPb8Hye0mIY0DVTd5rilF2HrafKO_7/view?usp=share_link
Received 02.02.2023 https://drive.google.com/file/d/1L6hPb8Hye0mIY0DVTd5rilF2HrafKO_7/view?usp=share_link
At Beira https://drive.google.com/file/d/1L34b1yWnnWPZFN--Hix6WFi2pa9JmbHm/view?usp=share_link

At Beira https://drive.google.com/file/d/1KxW1yZol4MhKg7ZOb0s6d_XpMmaqg12t/view?usp=share_link
At Beira https://drive.google.com/file/d/1KvoeEYVF1yMZq3hFEBxk1foz0lO14RxX/view?usp=share_link
At Beira https://drive.google.com/file/d/1KguHEP8eF6KLlgZQZh7XlhP_TjAHvhQP/view?usp=share_link
Received 02.02.2023 https://drive.google.com/file/d/1Kf-JTDEejTFivaWtlEKivo3hNISLAIJV/view?usp=share_link
https://drive.google.com/file/d/1KH1CMoEscDF1XKYXbAqHTt6uB1seX3_s/view?usp=share_link

At Beira https://drive.google.com/file/d/1KbyAH0OHxugf5l0W7X2NGowaGQMjorkC/view?usp=share_link
49
Major Challenges in OCean Shipment
1 Containers availability
2 beira route (less vessels, weekly once)if we skip 12 th date, then 19th vessel only we can catch
3 Space availability
4 liners delay without information liner will inform only postponement of schedule, in the bo
, then 19th vessel only we can catch

postponement of schedule, in the booking copy itself they are mentioning