Transformer Yard 1 ST1 Completed 2 UAT1 Completed 3 UAT2 Completed Transformer piping Deluge valve balance- 4 GT1 Available completedCompleted 28.03.23 Transformer piping Deluge valve balance- 5 GT2 Available U/p completedCompleted 02.04.23 6 GT3 Available U/p 3/30/2024 7 UT1 Available 4/1/2024 4/10/2024 8 UT2 Available 4/11/2024 4/20/2024 9 ST2 Available 4/20/2024 5/5/2024 Conveyer priority path 10 WT1 Available 3/28/2024 4/6/2024 11 WT2 Available 3/28/2024 4/6/2024 12 BCN-1AB Available 3/15/2024 3/25/2024 Available ( water 13 JT1 logging) 3/23/2024 3/30/2024 Partially available (JT1 14 BCN-2AB to PH1) 3/28/2024 4/9/2024 16 CH 1 floor available 17 BCN-3AB Not Available 18 JT2 Available UP 4/5/2024 75% completed 19 BCN-4AB Available UP 3/20/2024 95% completed 20 JT3 Available UP 4/10/2024 Assembly ready at floor 21 JT4 Available 4/1/2024 4/15/2024 22 BCN-5AB Available 3/28/2024 4/10/2024 90% complete 23 JT5 Not Available 24 BCN-6AB Not Available 25 ST1 Not Available 26 JT6 Not Available 27 JT7 Not Available 28 TBC-2AB Not Available Remarks