#Actionable points on TBM Commissioning and Excavation Dated: 05.05.

2023
A1 TBM-1 (SHAKTI) Progress Beyond RTB Chainage 48180
Shield Chainage 48795.95 Total excavtion by TBM-1 (in RM) 617.10
Face Chainage 48797.10 in terms of Rings 363.00 Inverts installed- 296
A2 TBM-2 (SHIV) Progress Beyond RTB Chainage 878
Shield Chainage 1210.05 Total excavtion by TBM-2 (in RM) 333.20
Face Chainage 1211.20 in terms of Rings 196.00 Inverts installed- 128

B Supply of Conveyor belts: Remarks


CB -1 Target: Nov-22 2 KM for Upline & 2 KM Downline is available for initial setup , remaining will be dispatched for
CB -2 Target: Nov-22 site as per consumption on a regular basis every 3 months.
Target Status Remarks
1st, 8th and 9th Lot: 20.01.2023 reached site Conveyor for TBM-1 is functional since 24.04.2023 and
2nd, 3rd, 4th & 7th Lot: 10.02.2023 reached site for TBM-2 by May'23-Week-4 , till then for TBM-2,
Structural units contractor has planned alternative muck handling
5th Lot and 12th Lot : 12.02.2023 reached site
10th and 11th Lot: Feb'23 - W3 reached site system with TBM main conveyor extended with a
chute to collect & transport muck through tippers to
Partial 6th Lot: Mar'23 - W3 reached site
the Dumping Yard. Temporary extension has been
13th Lot: Mar'23 - W4 reached site
completed and is being used at the moment.
14th Lot Mar'23 - W4 reached site
Electrical Units reached site
16th Lot for TBM 2: May'23 - W1
17th Lot for TBM 2: May'23 - W1 reached site

Supply of MSV – 1,2,3,4 (separately)


S.No. Item Target in (Status in %/ Target Date)
MSV-1 MSV-2 MSV-3 MSV-4 Remarks
1 Procurement Completed Completed Completed Completed
2 Factory Assembly Completed Completed Completed Completed
C 3 FAT Completed Completed Completed Completed
4 Transport to Site Dec-22 (W-2) Jan-23 (W-2) Completed Completed
5 Assembly Jan-23 (W-2) Jan-23 (W-3) Completed Completed
MSV's - 1 to 4 comissioned and
6 Commissioning Jan-23 (W3) Jan-23 (W-3) Completed Completed
functional at site.

# Sensitivity: LNT Construction Internal Use Page 1 of 2


#Actionable points on TBM Commissioning and Excavation Dated: 05.05.2023

Casting of Ring segments/Invert segment (Availability of parts for initial start-up of casting activities)
S.No. Item Scope Available Target Remarks
In % Date
Availability of Mould Sets 12 12 100% 100% i.e. 12 sets recived
1
INVERT 12 12 100%
Supplying of gaskets, Total Available
12,224 Rings 2436 Gasket for 2436 ring along with 8.6
D 2
ton adhesive is available at site.

Segment rings casted FTW FTM Available 1679 Ring casted & 1216 Invert
Cumulative
Casted.
3 Factory-1 38 20 1371 Tentative target- 2080 rings by
Factory-2 20 11 435 1806 May 2023
Invert 60 30 1348 (305 Rings for May 2023)

E Availability of spares - Target


Remarks
S.No. % Date
1 As per desired list of items 100% Jan-23-W-4
2 Disc Cutters (Total No. reqd:) TBM 1 1 set These are through SLA with HK.
Received at Site
3 Disc Cutters (Total No. reqd:) TBM 2

F Stacking of aggregates/raw materials vis-à-vis Total required


S.No. Material Required Available (Tons) Remarks
1 Aggregates 21920
2 Grout- 1 component (BENTONITE) 145.00
3 Grout- 2 component 111
4 Microfine cement 9.75
5 Collidal Silica 3.60
6 PU grout 1

G Planning for Ventilation/Dust gathering. Remarks


Reqd. Length: 03 Km Available: 2.7 Km Target date= Dec-22 For Initial Set up.

H Availability of TBM consumable as per OEM List. Target Date = Dec-22 (Available for initial drive), remaining will be delivered at site as per consumption.