Professional Documents
Culture Documents
2023
A1 TBM-1 (SHAKTI) Progress Beyond RTB Chainage 48180
Shield Chainage 48795.95 Total excavtion by TBM-1 (in RM) 617.10
Face Chainage 48797.10 in terms of Rings 363.00 Inverts installed- 296
A2 TBM-2 (SHIV) Progress Beyond RTB Chainage 878
Shield Chainage 1210.05 Total excavtion by TBM-2 (in RM) 333.20
Face Chainage 1211.20 in terms of Rings 196.00 Inverts installed- 128
Casting of Ring segments/Invert segment (Availability of parts for initial start-up of casting activities)
S.No. Item Scope Available Target Remarks
In % Date
Availability of Mould Sets 12 12 100% 100% i.e. 12 sets recived
1
INVERT 12 12 100%
Supplying of gaskets, Total Available
12,224 Rings 2436 Gasket for 2436 ring along with 8.6
D 2
ton adhesive is available at site.
Segment rings casted FTW FTM Available 1679 Ring casted & 1216 Invert
Cumulative
Casted.
3 Factory-1 38 20 1371 Tentative target- 2080 rings by
Factory-2 20 11 435 1806 May 2023
Invert 60 30 1348 (305 Rings for May 2023)
H Availability of TBM consumable as per OEM List. Target Date = Dec-22 (Available for initial drive), remaining will be delivered at site as per consumption.