A scaffold that is suspended by scaffold tube and load
bearing couplers to an overhead structure It has a working platform that cannot be raised or lowered
Criteria for underhang scaffold
All underhung scaffolds shall be hung from structures capable of supporting at least 4 times the load imposed on them by scaffold A guardrail system shall be provided UNDERHUNG SCAFFOLDS SUSPENDED BY TUBE AND COUPLERS
• Suspension points of hanger tubes shall be
securely fixed • Hanger tubes are coupled to two horizontal tubes • The first horizontal tube placed across the top of a supporting beam and second horizontal tube shall be attached underneath of supporting beam with a pair of girder coupler • Both horizontal tubes shall be attached to the hanger tube with right angle coupler • Check couplers shall be installed at tops and bottoms of all hanger tubes. UNDERHUNG SCAFFOLDS SUSPENDED BY TUBE AND COUPLERS
• Check coupler shall be
installed directly beneath all trapeze tube • Trapeze tube is a horizontal tube have length between 300&450 shall be installed approximately 600 mm (2 feet) below the runners to assist erection, modification and dismantling. And also to serve as a secondary support if the runner slip UNDERHUNG SCAFFOLDS SUSPENDED BY TUBE AND COUPLERS
Runners(ledger) and bearer(transom) shall be coupled to
hanger tube using right angle coupler Hanger tube spacing shall be given based on load rating At least one board bearer (intermediate transom) shall be installed when hanger tube spacing more than 1.5 meter apart in longitudinal direction Only drop forged girder couplers shall be used for the support of hanging scaffold pressed girder coupler shall not be used for the support of hanging tube