Professional Documents
Culture Documents
Liyfgniorfgiprw Piugpierph
Liyfgniorfgiprw Piugpierph
8 NDT
1 Oil leak test
m
media solar,, method sp
pray, tempe
erature amb
bient, holdin
ng period 4 hours.
4 Penetrant test
Ø Liquid penetrant examination shall be performed in accordance to ASME Section
V, Article 6.
Ø Magnetic particle examiner shall meet the requirements on API Standard 650 par.
6.4.3.
Ø The acceptance criteria and repair of defects shall be per ASME Section VIII,
Division 1, Appendix 8, Par. 8-3, 8-4, and 8-5.
5 Ultrasonic test
Ø Ultrasonic examination method shall be in accordance with ASME Section V,
article 5.
Ø Ultrasonic examiner shall be qualified in accordance with as specified on API
Standard 650 par. 6.3.3.
Ø The acceptance criteria and repair of defects shall be per ASME Section VIII,
Division 1, Appendix 12, Par. 12-3 and 12-4
API 650 Tank Joint Welding & Inspection for Field
Erected ASTs
Butt welded steel tanks have been a main stay in the field of constructing above ground
storage tanks for decades. Around 1936, welded steel tanks overtook riveted tanks as the
preferred method in new above ground storage tank construction. In step with this change,
API standards were published to guide construction of such tanks for adequate safety and
reasonable economy. Now in its twelfth edition, API 650 is the current standard to which
welded steel tanks are built. This standard covers the minimum requirements for materials,
design, fabrication, erection, welding, and inspection for constructing a new above ground
storage tank.
In building welded steel above ground storage tanks, different welding processes can be
used. Shield Metal Arc Welding (SMAW) or better known as stick (arc) welding was the
leading welding process and still very common today for construction of above ground
storage tanks. The SMAW process is versatile and very well suited to the environment of
field erected work.
Submerged Arc Welding (SAW) became popular in the tank industry in the early 1980s.
This process was used on lap welded bottoms and roofs and butt welded shell joints. The
first use of this process took many years of education to develop a method of welding that
would be clean of porosity under the surface of the weld. Many tank builders abandoned
this method of welding on bottoms due to the inability to control moisture from the bottom
side of the lap plates. However, the use of preheat in the winter time has made this a very
successful way of the welding the girth (round) seams connecting one shell course to the
next. This method of welding, known as Three O’Clock welding (3-O’Clock), delivers good
clean and smooth penetration and provides a more uniform weld. The submerged arc weld
blends and merges well with the two plates being joined and also provides X-ray quality
welds.
API 650 section 9 requires all welding on above ground storage tanks to be done in
accordance with the manufactures Weld Procedure Specifications (WPS) and the
supporting Procedure Qualification Record (PQR). Welding operators are tested and
certified in accordance with the tank builders welding procedures. Welds on newly
constructed above ground storage tanks are subjected to various types of inspection.
Radiographic (x-ray) testing is performed to prove that the welding operators are in
compliance with the welding procedure. The radiographic method is used on the shell butt
weld joints, annular plate butt joints, and flush type connections with butt joints. This method
is not used on the bottom and roof lap joints, top angle joints, man-way necks, shell to
bottom joints, structural joints, and appurtenances. Welds examined by radiography are
judged as acceptable or unacceptable by the standards of ASME section VIII. Section 8 of
API 650 provides criteria for determining the number of shots to be taken for each welding
operator based upon the thickness, number of shell courses, number of T joints, and the
linear feet of vertical and horizontal welds completed. The storage tank owner/operator has
the right to select the locations of the x-rays based on the Section 8.1.2 criteria.
All tank shell welds should also be cleaned and visually checked from both sides of the joint
making sure weld joints are free of defects such as craters, pinholes, undercut, and under
fill. Excessive weld reinforcement or overlay should be ground smooth along with the
removal of all arc strikes, weld spatter, fit up, and scaffold strap burrs to include replacing
any parent metal that might have been lost in the process of removing the bracket straps,
nuts, and fit up equipment.
Vacuum box testing is the most common way of testing the tank floor weld seams for leaks.
Care should be taken in ensuring all floor welds are visually checked to be complete and
free of any slag, weld burrs, and other defects such as pinholes, undercut, and under fill
before the vacuum testing is performed.
The shell to floor/bottom joint is visually inspected in the same manner. When one side of
the welded joint is complete, the most common weld test is to apply a high flash point
penetrating fluid such as diesel fuel to the opposite side. The welded side is then checked
for any visible signs of wicking. If any repairs are required, the penetrating fluid test is
performed again before the other side is welded.
Appurtenances, including inlet and outlet nozzles, should also have a good visual check
making sure welds are free of defects. Air pressure is then applied through a quarter-inch
pipe threaded tell-tale hole in the re-pad. Soap suds are then brushed or sprayed onto all
sides of the re-pad and both sides of the penetration where the weld attaches the pipe
nozzle to the shell. The welds are visually checked for small air bubbles penetrating the
soap solution.
Once the welds on a new above ground storage tank pass all of these weld inspection
processes, the tank is ready for service. If repairs are needed on a tank during its lifetime,
similar weld inspection methods are used for the particular type of weld repair performed.
Dome Roof with Internal Floating Roof
October 23, 2009 by ferrysibarani
Pictures below are sequential procedure of tank erection in one of my project. This project titled
Installation and Erection of Knock Down Tank in Brunei Methanol Project, Negara Brunei
Darussalam. Project owner is Brunei Methanol Company Sdn. Bhd., with Mitsubishi Heavy
Industries Ltd. as Main Contractor and PT. Rekayasa Industri is the Sub-Contractor. Consortium
of PT. Bangun Bejana Baja and Adinin Works and Engineering is the manufacturer of 15 units
Knock Down in this project.
One of the biggest tank that built in the project is Product Methanol Tank with type Dome Roof
with Internal Floating Roof, shell size 63 metres inside diameter and 18 metres height, dome roof
radius is 50.4 metres, and internal floating roof diameter is 62.6 metres. Tank construction was
done from September 2008 to October 2009.
Bottom plate consist of annular, rectangular, and sketches plate. The annular plate is the outer
plate which on top of it the shell plate will be installed. Butt joint type welding connection used
for annular to annular plate, and shall be 50% radiographic test. Rectangular and sketches plate
was welded using fillet weld and all joint shall be 100% vacuum box tested.
Fit-up of bottom plate usually using temporary welding to plate using nut and u-bar, then bullpen
used to make the overlap plate flat to each other.
After plate fit-up finished, the work continue with fillet welding. Welder classification for this
welding is welder 1G.
The first installation of shell plate. Rigging using 2 automatic clamps (vertical clamp) with
spreader bar.
Nozzle connection installation to shell plate. After welding completed, the welding shall be Post
Weld Heat Treatment (PWHT).
Finished installation shell course #1 and #2 completed with vertical weld butt-joint.
Horizontal weld between shell course #1 and #2 and so on will be done by Automatic Girth
Welding (AGW) Machine.
Dome roof ground assembly. Install the rafter and continue with roof plate welding. There are 24
block of roof will be assembly, 12 of them will be ground assembly and block in between section
will install inside tank.
Some part of shell plate #1 and #2 was removed as entry access for crane and material, it is call
door sheet.
Centre column support installation. This part will support the centre rafter of the dome roof
which is the part that all roof block will be connected into.
Finish assembly of centre support and installation centre rafter on the top.
First installation of dome roof block. Roof block lifted by 300 Ton Crane.
Adjusted lower part of the roof block into the outer support.
Adjusted upper part of the roof block into the centre rafter.
Finished installation of the first 4 numbers of roof block (beautiful, isn’t it). It is important to
keep the balance between installations section by section.
Overtime work for catch-up schedule, but only welding work without any rigging or fit-up.
In between roof block assembly. Manlift basket used to install and weld rafter. Rafters erected by
crane from outside tank.
Roof plate installation in between roof block. The first 3 section roof plate were install from
inside tank before finished rafter in between block. The 4th and 5th roof plate installed from
outside tank.
Last shell course (#8) installation with tension bar. Last shell course and tension bars were
assembled on workshop to decrease welding work on height.
Installation of roof plate in between block was remaining in the door sheet area. This part welded
the last due to entry access for crane only available through door sheet.
Finished dome roof assembly viewed from inside tank. Dome roof now ready to be lifted up to
the tension bar by air raising method. The roof will float due to air pressure inside tank increased
by blower through shell nozzle.
This picture showing the completion of air raising process of dome roof, and dome roof
completely fixed to the tension bar.
Single deck internal floating roof assembly on process. This floating roof consists of general part
and pontoon compartment. Floating roof supported by permanent pipe support with height
approximately 2 metres. During construction the floating roof temporary supported then will be
raised up by water to the correct elevation.
Pontoon compartments work as the buoy of the floating roof. These compartments shall be fully
tested by oil leak test to ensure 100% leak proof.
Floating roof assembly finished and ready to be raised up. Next preparation will be closing all
the shell manhole and nozzles and fill up the tank with water.
Water raising finished and the floating roof already setup on the permanent pipe support, locked
with stud bolt.
Accessories of tank such as roof periphery platform, spiral and roof stairway, piping for fire
fighting, etc. continue assembled prior to hydrostatic test.
Hydrostatic test was to fill the tank with water to the design pressure to ensure there is no leaking
in the tank as well as to check the stability of the tank foundation. After all inspection finished,
the water inside tank discharged.
Touch-up primer coat for welding area to be finished prior to applying final coat.
The tank installation finished. Awesome, isn’t it?