Professional Documents
Culture Documents
Module 2 Dicussion Board
Module 2 Dicussion Board
I ran through the simulations 4 times. Each time I ran through the simulation I tried to focus on
adjusting one aspect of the simulation more than the others. For example in one of my run-
throughs, I focused on the number of people on my team more than I did any of the other
aspects. I obviously adjusted other aspects as needed but I wanted to see if focusing on a specific
aspect would help keep the simulation within the management targets. One of the biggest
challenges was trying to keep the team’s mood in a relatively good place. There were times when
I would adjust something small and as simple as the number of one-on-one meetings that the
team would have and it would have such a negative effect on the team's attitude. For the next
scenario, I want to try making different-level printers. I didn’t mess with that aspect of the
project and looking back at my run-throughs that seems like something that could have a big
impact on the overall project. Also when starting off a run-through, trying to stay under budget
or within the budget is so important because once you go over budget it is very hard to come
It took me a little over an hour to complete all my attempts. There were a few approaches that I
took to gain some information on how to best go about running through the scenarios. The first
approach I took was advancing a couple of weeks at a time without adjusting much. I wanted to
see if there were certain things that the team could stick out and complete the project with even if
it meant they were stressed one week then perfectly fine the next. One of the other approaches
that I took was drastically adjusting things and letting myself go over budget or get behind
schedule. This approach showed me that I was better off making small changes here and there.
As I stated earlier anything that put me over budget was really hard to come up back from.
If I ever fell behind schedule I would try to outsource help and I would adjust the number of
meetings that the teams would have. While this did help the team to get back on schedule, these
When the teams became stressed, bored, or not as productive I would manage this by increasing
the number of meetings that were had. These meetings seemed to keep the teams more in the
loop and up to date about what needed to be done. I would also add a team member or two if the
teams were consistently stressed by the amount of work that needed to be done.
For the next scenario, I want to focus on things such as the use of overtime and the level of
product that is being made. I didn’t adjust those things in my first run-throughs and looking back
I want to see if those elements could impact the success of the project. I also want to be smarter
with my budget next time. Allowing myself to go a little over budget one week and then maybe
going under budget another week when there has been some good consistency in the team's
attitude.
Management Strategy
One of the strategies that I attempted when managing my project was keeping the team size
small but their skill levels high. At the beginning of the run-throughs, this seemed to work but as
the project progressed and it became more demanding it seemed as though the team members
couldn't keep up with the amount of work, and then when I would outsource help it only made
them feel as if they were doing the same tasks over and over again. A strategy that I think
worked well was making sure that there were lots of meetings being held. If the team’s attitude
ever became one where they felt as though they needed more direction I would add more one-on-
one meetings to the agenda! The meetings help to keep the team members up to date and they
Every adjustment or decision that was made had an impact on one thing or another. For example,
when it came to decreasing the number of team members, this would cut cost but it would put the
team behind schedule. Therefore more outsourcing needed to be done in order to keep up with
the schedule. Also, the fewer team members that there were usually resulted in more problems
discovered then team morale would be very low and stress levels would increase. Any parameter
that was adjusted would usually affect more than one of the project outcomes, which then leads
to the team attributes shifting. This just goes to show how much attention to detail there needs to
People Factors
Stress levels and team morale are heavily impacted by deadlines. When the team felt as though
they were falling behind on the schedule or they felt as though they didn’t have enough hands to
complete the project on time the team would become very stressed which lead to a decrease in
The stress levels and morale of the team can make or break how productive a team can be. If a
team feels as though they are more than capable of completing a project with the correct tools
and the right amount of hands the team can be incredibly productive. On the other hand, if a team
feels like they aren’t being supported, they don’t have the skill level to complete the project, or
they simply don’t have enough people to get it done, a team won’t be as motivated to get the job
done.
Changing team members can have a big influence on team productivity. The more people there
are on a team generally the more tasks can be accomplished per day which can lead to the project
being completed on schedule. The only issue there is that with this simulation it was hard to keep
a high amount of people on a team because the budget wouldn’t always allow for it. That would
lead to people being removed from the team which can sometimes lead to a decrease in team
morale.
Communicating with outsourcing vendors was quite tricky for me throughout the simulation.
There were times when communication with the outsourcing vendors was necessary to stay on
schedule but it would create confusion and frustration within the team. That confusion and
frustration would then lead to holding more meetings to make sure team members were kept up
to date with what was happening with the project. So while it helped with productivity to did