7 DAYS NOTICE FOR WORKS AS A WHOLE/ IN PARTS

(DETALS OF PART OF WORK TO BE MENTIONED)


(Without Prejudice)

Letter No. ER/HWH/Civil/2022/0134/RD-0005 Dated 27/02/2023

To
M/s DEBIPRASANNA SAHA-NADIA
84/1 KUMOR PARA GHAT LANE P0-GHURNI, NADIA, West Bengal-741103 India

ontract Agreement No. ER/HWH/Civi/2022/0134


In connection
Provision of 2 nos. passenger lifts at Pakur station..
with

Dear Sir,
In spite of repeated instructions to you by the subordinate officesas well as by this office through
various letters ofeven no. ER/HWH/Civi/2022/0134/RD-0003, dated 20/01/2023. You have failed to start
work/show adcquate progress and/or submit detailed programme for completing the work/ part of work
(details of part of work to be mentioned).

2.Your attention is invited to this office/Chief Engineer's office letter no. null, dated null in reference to your
representation, dated null.

3. As you have failed to abide by the instructions issued to commence the work /to show adequate progress of
work you are hereby given 7 days' notice in accordance with Clause 62 of Standard General Conditions of
Contract to commence works/ to make good the progress, failing which further action as provided in Clause
62 of the Standard General Conditions of Contract viz. to terminate your Contract and complete the balance
work without your participation will be taken.

Kindly acknowledge receipt.

Yours Faithfully
Signature Not Verified
Digitaly sigrid by RAJEEV
RANJAN
Date: 20232 wH
Reason: Cot¥espqnesHe

For and on behalfofthePAPSIAETAt of India

SSE/W/RPH
Copy To:AEN/RPH ,