08 ELECTRICALS

08.01 Power requirement

The estimated power requirement of the proposed


steel melt shop project is as follows.

Connected load: 35 MVA

Maximum demand: 28 MVA

Annual energy consumption: 125 MkWh

08.02 Source of power supply

The electrical power supply for steel plant will be


made available at 33/66 kV 3-phase, 50 Hz from
the UAE electrical Authority from the nearby located
Substation. 33 kV lines will be received at an
outdoor substation at the plant site and will be
connected to the SVC and suitable distribution
centers or stepped down to 11 kV / 6.6 kV, 440V by
suitably rated power transformers. Further
distribution to plant load centers will be through 11
kV / 6.6 kV, 440V indoor type switchgear.