OFFICE OF THE SUB DIVISIONAL OFFICER

TELE: 055-4287151 CHAND-DA-QILA SUB DIVISION GEPCO


www.gepco.com.pk 132 KV LAHORE ROAD GRID STATION NEAR WAPDA TOWN GRW
(READING SECTION)

MEMO NO.________________/CD-09 DATED._________________

To,

The Executive Engineer


Division No.3 GEPCO
Gujranwala

SUB: SEGREGATION OF UNITS AGAINST A/C NO. 11-12136-1268501.


It is submitted that the consumer against above subjected account number approached
to this office with written application regarding wrong billing. The meter inspector of this office checked
the record / site and reported that the meter of the consumer was installed as new connection on dated
31/05/2022 and appeared in 07/2022. The meter reader could not find the meter so he did not charged
any units to the consumer in 07/2022. In 08/2022 he accumulatively charged 775 units. Thereafter the
sub batches were shuffled and the new meter reader of the area also could not found the meter so he
did not charged any unit to the consumer from 09/2022 to 12/2022. Thereafter he charged 415 units in
01/2023, which is not one month consumption.

It is therefore requested please aggregate the units charged to the consumer in 08/2022
and 01/2023 i.e. 1193 units and segregate from date of connection to 01/20232 as well as issue revised
bill to the consumer to settle the complaint.

SUB DIVISIONAL OFFICER


CHAND-DA-QILA SUB DIVISION
GEPCO GUJRANWALA