UPDATE REPORT
Feb 9th 2023
BUILDING & AREA UPDATE A. 3BR Villa 1.1
B. 2BR Villa 2.1
C. 2BR Villa 3.2
G D D. 2BR Villa 3.4
12 E. Duplex Villa 4.1
F
H
E C F. Duplex Villa 5.1
B G. Duplex Villa 5.2
A
9 7 5
H. Kidz Club
8 6 4 3 2
10
11
Update of each building & area include with target completion at next page
SB 6
SB 4
SB 2
SB 7
SB 5
SB 3 SB 1
WORKS ON GOING
MAIN BUILDING HAND OVER TARGET :
- Demix for interior
- 1st Floor : 20 Feb
- Exterior Wall with MU 210
- 2nd Floor : 25 Feb
- Galam wood & Sumba Stone final coating
- Public Area : 25 Feb
- Polished Concrete repair & finalization
- Floor Deck final coating - Canopy (Tali Ijuk ) - Paving Block
- Woodwork final finishing - Wood frame Main Canopy - MEP Instalation
- Finishing detail (repair) - Canopy Glass Instalation (4 Canopy) - Audio
- Landscape (additional & revision) - Office Glass Partition
STD BUNGALOW HAND OVER TARGET :
STANDARD BUNGALOW - STB 1-4 : 28 Feb
- Public Area : 28 Feb
POND
YOGA
WORKS ON GOING
- Polished Concrete repair & finalization - Changing Room wall clading
- Floor Deck final coating - Glass Partition at GYM
- Paving Block - Audio
- Woodwork final finishing - Soffit chamfer at all building
- MEP Instalation - Pool lamp & system
- Landscape (additional & revision)
WORKS ON GOING