You are on page 1of 9

Engineering Structures 74 (2014) 233–241

Contents lists available at ScienceDirect

Engineering Structures
journal homepage: www.elsevier.com/locate/engstruct

Review article

Recent development of design and construction of medium and long


span high-speed railway bridges in China
Nan Hu a, Gong-Lian Dai b, Bin Yan b,⇑, Ke Liu b
a
Department of Civil and Environmental Engineering, Michigan State University, East Lansing, MI 48824, USA
b
School of Civil Engineering, Central South University, Changsha, Hunan 410075, China

a r t i c l e i n f o a b s t r a c t

Article history: Medium- and long-span bridges of the high-speed rail (HSR) projects play a significant role when crossing
Received 18 September 2013 certain obstacles, such as rivers, existing highways, etc. This paper provides a state-of-the-art review on
Revised 26 May 2014 the design practice of these special spans in the HSR projects of China. Given standard spans are usually
Accepted 30 May 2014
smaller than 100 m, special spans can be divided into two categories by the length of main span: medium
Available online 20 June 2014
length (100–200 m) and large length (200–500 m). For medium length, three structural forms are dis-
cussed as feasible design options, including steel arch, rigid frame and hybrid arch-girder. In addition,
Keywords:
recently completed long-span bridges are reviewed to feature several innovative structural forms on
High-speed rail
Bridges
the HSR of China, including steel truss arches and cable-stayed bridges with truss girder. Finally, the
Design key technical features of long-span HSR bridges are summarized, and a discussion of the feasibility of
Construction longer spans is also included.
Medium-span Ó 2014 Elsevier Ltd. All rights reserved.
Long-span

Contents

1. Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 233
2. Deflection control. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 234
3. Medium length (100–200 m). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 235
3.1. Tied steel arch . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 235
3.2. Rigid frame . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 236
3.3. Arch-rigid frame hybrid . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 237
4. Long length (200–500 m). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 237
4.1. Steel truss arch . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 237
4.2. Cable-stayed bridge with truss girder . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 239
5. Discussion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 239
6. Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 240
Acknowledgements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 240
References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 240

1. Introduction speed travel, also known as Shinkansen. The first Shinkansen


opened Tokyo-Osaka segment for the Tokyo Olympics in 1964.
High-speed rail (HSR) offers a fast and robust travel option that HSR in Europe first developed in several countries and now
enhances the quality of life and supports economic growth. Japan expanded into a regional service network. Over the past few dec-
was the first country to build a passenger dedicated line for high ades, a total of 13 countries have developed the HSR network,
mainly in Europe and East Asia. International examples from those
⇑ Corresponding author. Tel.: +86 13787799105. countries have proved that high speed trains are capable of reach-
E-mail addresses: daigong@vip.sina.com (G.-L. Dai), binyan@csu.edu.cn (B. Yan),
ing speeds over 250 km/h on high speed passenger dedicated line
liuke1009@gmail.com (K. Liu). which significantly reduce the travel hours. Detailed historical

http://dx.doi.org/10.1016/j.engstruct.2014.05.052
0141-0296/Ó 2014 Elsevier Ltd. All rights reserved.
234 N. Hu et al. / Engineering Structures 74 (2014) 233–241

reviews of the development of HSR in those countries can be found girder and tracks such that it is not easy to meet the service limits
in papers by Taniguchi [1], Bouley [2], the European Commission of HSR. Further studies on the use of HSR suspension bridge in
[3], Gourvish [4], Zuber [5], and Harrison et al. [6]. China is still in progress.
HSR in China is composed of upgraded existing lines with an The objective of this paper is to present an up-to-date review of
average design speed of 250 km/h and new lines with an average the emerging design and construction techniques on medium and
design speed of 350 km/h, including 9356 km of new built lines long spans on the HSR of China, including the key design
and 3209 km of upgraded lines. By 2020, the total length in China philosophies, the main structural dimensions and the construction
will reach more than 20,000 km with a complete grid network that methods. For medium length bridges, three forms are discussed,
will connect all provincial capital cities as well as large cities with including steel arch, rigid frame and hybrid arch-girder. For large
population more than five million. For a typical HSR line in China, length bridges, the discussion focuses on steel truss arches and
most spans are composed of standardized simply-supported beam truss cable-stayed bridges. This paper summarizes the structural
(with span of 24 m, 32 m and 40 m) when spanning lower than options for special spans for future HSR constructions.
40 m and a few standardized continuous beam bridges (main span
from 48 m to 100 m). For example, 95% bridges in the Beijing–
Shanghai segment are standard span (90% simply-supported beam 2. Deflection control
along with 5% continuous beam) and only 5% are special spans.
Even though medium and long span bridges only cover a small por- HSR requires high deflection limits to ensure track smoothness.
tion of a HSR line, it plays a key role in the completion of the entire No matter what structural forms selected for the special spans, the
line, crossing over physical barrier such as existing highway, HSR control of the deflection on the main girder is still a key design
lines and rivers, etc. issue because the average design speed of trains on those spans
The selection of a rational and cost-effective structural form is is more than 250 km/h [10]. The threshold limits on bridges with
the main assignment in bridge design. Structural forms for long- a ballastless track bed are higher than bridges with ballast track
span railway bridges have evolved during the past two centuries, bed, because it is difficult to adjust the smoothness on the ballast-
primarily featuring with longer span and more diverse forms. On less deck. Thus, all the long-span HSR bridges in China used ballast
the heel of the birth of the steam railways, iron truss bridges track. However, no detailed requirements are applied to long-span
were widely constructed to support these earliest railway trains. bridges, since the design and analysis of those bridges are usually
In the late 19th century, three milestone railway bridges were carried out case by case, which at least should satisfy those mini-
successively built to support the larger live load of trains, includ- mum limits of small span HSR bridges. Four key aspects on the
ing the Eads Bridge (1874, 158 m), the Brooklyn Bridge (1883, deflection control on small span are as follows: (1) Vertical deflec-
486.3 m), and the Firth of Forth Rail Bridge (1889, 521 m). These tion of the beam, smaller than 2.0 mm; (2) the rotation at the beam
bridges represented the advanced building techniques used on an end, smaller than 0.4%; (3) long-term deflections (for example,
arch bridge, a suspension bridge and a cantilever truss. The devel- creep effects), smaller than L/1000 (L in m and result in mm); (4)
opment of those well-recognized spans relied on the use of steel longitudinal deflection of the substructure. All those requirements
rather than iron which reduced the dead load weight. As railroads must be met in order to ensure the smoothness of the track and the
expanded throughout the world in the early 20th century, engi- safety of the trains.
neers raced to design bridges that were stronger and longer, Track stability and smoothness of the HSR is highly dependent
without adding too much weight. A number of longer spans were on the control of the vertical and lateral deflection of the main
developed, such as the Hell Gate Bridge in New York (1916), and girder. Design specifications by the former Ministry of Railways
the Sydney Harbor Bridge (1932). In the 1970s, Japan began the (MOR) of China have certain requirements on short-term and
construction of the Honshu  -Shikoku Bridge Project, connecting long-term deflection on short length continuous beams [11]:
Honshu  and Shikoku islands. The link between Okayama and the vertical deflection must be smaller than 1.1 L/1000 (L is the
Kagawa is the only one with railroad connections. A total of six main span); lateral deflection must be smaller than L/4000; and
long-span bridges were built to support both the highway and beam end rotation must be smaller than 0.2% in a ballast track
the railway, including a continuous truss bridge, two cable stayed bed and 0.1% in a ballastless track bed. However, no such
bridges, and three suspension bridges. Currently, China is the requirements in the design specifications have been proposed
leading country in the large number of regular rail upgrades for special spans, including the medium length continuous beam,
and new HSR constructions. the arch bridge and the cable-stayed bridge. Deflection limits on
The development of railway bridges in China began with the similar bridges from international examples were studied and
completion of the Qiantang River Bridge in 1937. Two milestone compared to develop a recommended range for the long-span
steel truss bridges were built subsequently across the Yangtze designs [12].
River in Wuhan (1957) and in Nanjing (1968). Since then, the steel Due to higher serviceability limits compared to conventional
truss bridge was used as the main structural form for the railway railway bridge design, other technical issues associated with
bridges in China until the first cable-stayed bridge with a main dynamic response of HSR bridges have been studied by many pre-
span of 312 m was completed in Wuhu over the Yangtze River in vious studies, such as seismic performance [13–17], track–struc-
2000. Then, a series of cable-stayed bridges were planned and con- ture interaction [18–20], creep effect [21,22], thermal effect [23],
structed [7]. Similar to the design of standard spans for HSR, the etc. In the development of HSR bridge in China, those special issues
design of special spans also require a strict service limit due to (such as thermal expansion, seismic design, wind effect and creep
the need for smoothness of the track and the stability of the high effect) have been considered and additional analysis may be
speed train. For a certain span range and site condition, several required for multiple loading cases that may cause large deflection.
options of structural form are available [8,9]. Special spans in (1) A single span over 100 m long requires measures to control the
HSR of China can be divided into two categories by the length of thermal expansion and contraction of the rail, because the contin-
the main span: medium length (100–200 m) and large length uous welded tracks could become distorted in hot weather and
(200–500 m). Several cable-stayed bridges with a longer main span cause the derailment of a train. Clips and anchors were widely used
more than 500 m are also included in the long spans. No in the HSR on multiple span bridges [24]. Zhu [25] compared the
suspension bridges are currently used in the HSR of China. The sus- multiple combinations of expansion devices on a cable-stayed
pension bridge is too flexible to maintain low deflection on main bridge. It were found that the optimal way to control the thermal
N. Hu et al. / Engineering Structures 74 (2014) 233–241 235

effect on the track is through the use of the small clips in certain 3. Medium length (100–200 m)
spots along the main girder and large expansion devices at both
end of the girder. Yan [26] carried out a numerical analysis on a Medium length spans are usually adopted to cross over the
single-tower 112 m long cable-stayed bridge and proved that existing highways or railroads. Most of the standard spans have a
longitudinal movement and the stress level of the rail can be signif- main span smaller than 100 m and the maximum span is only
icantly reduced through using expansion device at the joint seg- 128 m. Even though the prestressed concrete continuous beam is
ment of the tower and the girder. Performance-based still one of the options, alternative forms can be chosen for HSR
requirements on seismic hazards are mentioned on the HSR design special spans. Table 1 lists a total of 19 medium length spans that
code of China, but those general requirements are only applied to have been completed in the past five years. It can be seen that the
small span bridges (i.e. main span smaller than 48 m). (2) Seismic tied steel arch bridge and the rigid frame bridge are two commonly
design and analysis is required for long-span HSR bridges in China used structural forms. The hybrid system of these two forms also
yet varied case by case. For example, Yue [27] showed that most of offered new solutions for the design of special spans. The detailed
the long-span HSR bridges did install dampers along the description on each form will be discussed in this section using
longitudinal direction to reduce the large dynamic response under design examples.
earthquake or emergency braking of the trains. (3) Similar to the
seismic design issue, the aerodynamic effect of long-span bridges 3.1. Tied steel arch
is also considered case by case, but the design process of most
long-span bridges in China have went through dynamic analysis Commonly used steel arch bridges can be divided into tubular
along with multi-scale wind tunnel tests. Li et al. [28] and Wang arch and box arch by the cross-section of the arch rib.
et al. [29] found that the deflection of the main girder can be The tubular arch, also known as the concrete filled steel tube
affected by train speed and wind speed. Li [30] carried out a wind (CFST) arch, has been used in the Wuhan-Guangzhou segment of
tunnel test on a twin girder linked by a cross-beam to identify the the Beijing–Guangzhou line [31]. Tian et al. [32] proved that this
optimal pattern of depth-width ratio for a better aerodynamic arch type with inclined hangers has better dynamic characteristics
performance. (4) Excessive long-term deflection (creep effect) including greater vertical and lateral stiffness than other arch
may result in an uneven track surface, which could threaten the types. It is noted that the 112 m long tubular arch with inclined
operation of HSR trains. For the medium and large-span of HSR hangers was standardized as shown in Fig. 1a such that this design
bridges, all the long span HSR bridges currently used ballast track, can be used in similar conditions for spanning existing lines. The
which the creep effect was easier to adjust than ballastless track. rise to span ratio of the main arch is 1/5 with a rise of 22.4 m from
From structural design point of view, the creep effect is controlled the top of deck [33]. The uniform-depth arch ribs have a twin
by increasing the depth of beam and lowering the difference of circular tube connected by cross links filled with low shrinkage
stress between beam top and beam bottom under long-term concrete. Each tube has a diameter of 1.28 m with a wall thickness
loading combination. In addition, the train speed has been of 18 mm. Two main arch ribs are inclined inward about 9°, which
restricted to lower than 250 km/h to reduce the induced vibration. has better dynamic characteristics including greater vertical and
It should be noted that the design philosophy of considering creep larger lateral stiffness. The spacing of the hangers is 8 m. The arch
effect in the Chinese design code is very conservative and was designed without horizontal thrust due to the use of prestress-
improvement on the requirement of the long-term effect is ing tendons as tied bars in the main girder. The main girder is a sin-
undergoing. gle box prestressed concrete structure with a depth of 2.5 m and a
Overall, three most important limits for designing HSR bridges width of 17.8 m. The estimated structural responses under the
in the future is to ensure the vertical stiffness, beam end rotation dead load are a vertical deflection of 19.4 mm and a beam end rota-
and longitudinal stiffness of piers. It is note that no large structural tion of 0.0705%. Estimated material costs per unit length (one
health monitoring system has been reported to record the deflec- meter) are 37.2 m3 of concrete, 8.9 tons of steel and 2.1 tons of
tion history on the HSR bridges in China, but there are undergoing the prestressing tendons. Small clips on the main girder and large
studies on the optimal arrangement of sensors, the use of different expansion devices at both ends of the girder are used to meet the
monitoring system and the fast diagnose of damage, etc. smoothness requirements. The construction of this bridge started

Table 1
Recent completed medium length special span in the HSR of China.

Structural type Bridge name Main span (m) HSR segment Built
Tied steel arch East Lake 112 Wuhan-Guangzhou 2008
Hujiawan 112 Wuhan-Guangzhou 2008
Liangjiawan 112 Wuhan-Guangzhou 2008
Tingsihe 140 Wuhan-Guangzhou 2008
Yandangshan 2  90 Ningbo-Wenzhou 2009
Mulanxi 128 Fuzhou-Xiamen 2009
Xinkaihe 138 Harbin-Dalian 2012
Rigid frame Tianluo 160 Wenzhou-Fuzhou 2008
Baimahe 3  145 Wenzhou-Fuzhou 2008
Liuxihe 168 Wuhan-Guangzhou 2009
Zinihe 2  168 Guangzhou-Shenzhen 2010
Hybrid steel arch with concrete girder Kunyang 136 Wenzhou-Fuzhou 2007
Yichang Yangzte 2  275 Yichang-Wanzhou 2008
Shawan Channel 160 Guangzhou- Shenzhen 2009
Liugangyong 160 Guangzhou- Hong Kong 2010
Xiaolan Channel 220 Guangzhou-Zhuhai 2010
Zhenjiang Channel 180 Beijing-Shanghai 2010
Xianyang West 136 Xi’an-Baoji 2012
Songhuajiang Channel 3  156.8 Harbin-Qiqihar 2013
236 N. Hu et al. / Engineering Structures 74 (2014) 233–241

(a) Hujiawan Bridge (b) Tingsihe Bridge

(c) Yandangshan Bridge (d) Xinkaihe Bridge


Fig. 1. Steel arch bridges in the HSR of China.

with the fabrication of the arch ribs along with concrete cast as a uneven settlement of the substructure, which leads to the
tied beam. Then, the ribs are vertically rotated to the positions at reduction of track smoothness. Completed examples on the HSR
the temporary hinges that are installed at four spring lines [34]. line include the Tianluo Bridge (88 + 160 + 88) m (Fig. 2a) and
Additional analysis during the rotation of the ribs was carried the Liuxihe Bridge (84 + 168 + 84) m [39] (Fig. 2b). These two
out to ensure the stress concentrations at the spring line meet bridges have a similar structural configuration. Thus, only the Tian-
specification [35]. luo Bridge was selected for the discussion of the structural design.
The Tingsihe Bridge built in 2008 is a classic example of tied box The Tianluo Bridge is planned to span a shallow strait with a
arch bridge for supporting a double track HSR line, as shown in design wind speed reaching 56 m/s. This prestressed concrete
Fig. 1b. This 140 m-long arch bridge has a rise-span ratio of 1/5. structure was selected to satisfy the required clearance of
The 2.0 m uniform width arch ribs have a thin-wall rectangular 120  24 m. The cross-section of the superstructure is a varied-
cross-section with a depth varying from 3.0 m at the crown to depth box with a top width of 13 m and bottom width of 8.2 m.
4.5 m at the spring line. The spacing between ribs is 16 m, con- At the rigid connection to the pier, the box girder has a depth of
nected with five lateral bracings. Underneath each rib, a single
box steel girder with a depth of 3.5 m and an inner width of
1.94 m is adopted as a tie to the arch rib. The hangers are designed
as rigid components with equally spaced holes to improve the
aerodynamic characteristics. The construction of this bridge con-
sumed more than 3800 tons of steel. The cantilever method was
used to erect the arch rib by segments to avoid interruption of
the highway operation and reduce costs. The segments of the rib
are hoisted by heavy duty truck cranes through temporary blocked
half lanes on the highway without using falsework during the rib
installation [36]. The estimated structural responses under dead
load include a vertical deflection of 48.7 mm and a beam end (a) Tianluo Bridge
rotation of 0.186% [24]. Due to the high rotation at the end of tied
girder, a short length beam is adopted as a transition element
between the arch and the neighboring 32 m simply supported
beam. Tied box arch bridges among the completed bridges, include
other forms [37], as shown in Fig. 1c and d.

3.2. Rigid frame

Due to the rigid connection between the beam and pier, rigid
frame bridges can span a greater length and provide better vertical (b) Liuxihe Bridge
stiffness when compared to continuous beams [38]. This form is
preferable at good site conditions; otherwise it may suffer from Fig. 2. Rigid frame bridges in the HSR of China.
N. Hu et al. / Engineering Structures 74 (2014) 233–241 237

9.8 m, a top wall thickness of 55 cm, a bottom wall thickness of of the train and the structure. It was also found that the stability
100 cm and a web wall thickness of 150 cm. At the two support of a running train can be improved by increasing the depth of
columns, the bottom wall thickened to 200 cm. At the mid-span the noise barrier.
and the end of side span, the box girder has a depth of 5.0 m, a
top wall thickness of 45 cm, a bottom wall thickness of 50 cm
3.3. Arch-rigid frame hybrid
and a web wall thickness of 100 cm. Three additional thin walls
are added in the lateral direction of the girder to main its stability,
As discussed previously, both the tied steel arch and the rigid
including two 160 cm thick walls at the end of each side span and
frame bridge offer certain advantages on the HSR line. The hybrid
one 80 cm thick wall at the mid-span. Two-way drainage is used on
system of these two forms is also an alternative choice when the
the bridge deck with a slope of 2%. The prestressing tendons are
use of a steel arch or a rigid frame cannot satisfy the clearance
used in all three directions of the girder to ensure the main struc-
requirement. Examples in the HSR line of China include the
ture is in a complete compressive stress state. The pulling pres-
Kunyang Bridge in Fig. 3a and the Yichang Yangtze River Bridge
sures in prestressing jacks are usually between 1230 and
in Fig. 3b. The key structural features of this hybrid system are dis-
1300 MPa. Due to high corrosion potential at the bridge site, high
cussed below as related to the Kunyang Bridge.
performance C60 Grade concrete was used. The consumption of
The Kunyang Bridge supports a double-track joint passenger-
materials per meter for the beam is 26.1 m3 of concrete, 3.3 t of
freight HSR line with a main span of (64 + 136 + 64) m. The
steel and 1.5 t of prestressing tendons.
11.5 m wide main girder of the Kunyang Bridge has a double-box
The supports of a rigid frame are commonly two thin wall legs.
cross section with a varied depth from 3.5 m in the mid-span to
In this case, two vertical legs with a spacing of 8 m are used with a
7.0 m at the support. High performance C60 Grade concrete was
leg height to main span ratio of 0.2, which maintain an optimal
used to improve the durability of structural performance under
stress distribution on the legs and beams. The leg has a lateral
the environmental impact. These dimensions are smaller than a
width of 10 m and a longitudinal width of 2.2 m. The use of two
solely rigid frame structure because the live load is partially sup-
legs improves the longitudinal stiffness of the beam and provides
ported by the steel arch. The rise to span ratio of the main arch
a relatively flexible constraint for the mid-span as compared to sin-
is 1/5 with a 27.2 m rise from the top of deck. The uniform-depth
gle leg. The two legs are supported by a cubic concrete pile cap
arch ribs have a twin circular tube filled with low shrinkage C50
(14.5 m  19.7 m  5 m) and 12 drilled piles with a diameter of
Grade concrete. Each tube has a diameter of 2.8 m with wall thick-
2.5 m. C45 Grade concrete is used for the legs and C30 Grade
ness of 16 mm. Two arch ribs are connected by nine lateral truss
concrete is used for the pile cap.
bracings [41]. A total of 14 pair of hangers are used with a spacing
Commonly, the cantilever method is adopted in the construc-
of 8 m. High stress concentration at the joint region between on
tion of a rigid frame. The erection of the girder starts from the sup-
steel rib and concrete girder was reduced by using a special con-
ports and the closure is in the mid-span and the end of each side
nection [42]. The construction of such bridge per meter consumed
span. The key issue for the cantilever method is that real-time
more than 23.6 m3 concrete and 8.8 tons of steel. The common
monitoring is required to measure the position of each segment
sequence of construction started from casting the girder segment
and maintain a theoretical line shape at the top of the girder
by the cantilever method followed by the erection of arch ribs
[38]. For the Tianluo Bridge, additional analysis was needed to
[43]. Huang et al. [44] estimated that the structural responses
measure and control the dynamic response of the girder during
under dead load are a vertical deflection of 35 mm, and a beam
the construction phases. Gong [40] carried out the dynamic
end rotation of 0.1%.
analysis for this bridge and found that the actual response of the
structure was better than the estimate from an integrated model
4. Long length (200–500 m)

There are only a few completed long-span HSR bridges in China,


as shown Table 2. The reason is that the main girder of a long-span
bridge is known to be flexible compared to the medium spans. It
can be seen from Table 2 that two existing structural forms are
the steel truss arch and the cable-stayed bridge with truss girder.

4.1. Steel truss arch

A cost-effective steel truss arch should have a main span


between 300 m and 400 m. The structural efficiency of the steel
(a) Kunyang Bridge truss arch relies on the strength of each truss member. This form
was first used at the Wuhan-Guangzhou segment in 2009 to span
over the Dongping channel as shown in Fig. 4a. The Dongping
Bridge supported a four-track railway with a span arrangement
of (99 + 242 + 99) m. This truss arch features three main trusses
in the longitudinal direction with a spacing of 14 m, integrated
joints for connecting truss members, the use of high performance
Q370qD (yield strength is 370 MPa) Grade steel and the applica-
tion of an orthogonal steel deck system. Detailed information can
be found in a paper by Liu and Dai [45]. Later, a similar truss arch
was built at the Beijing–Shanghai segment in 2011 with a longer
(b) Yichang Yangtze Bridge span, i.e. the Dashengguan Bridge shown in Fig. 4b. The hybrid
form of truss and arch has also be used, such as the Minjiang Bridge
Fig. 3. Hybrid arch-rigid frame bridges in the HSR of China. in Fig. 4c with a span arrangement of (99 + 198 + 99) m. The key
238 N. Hu et al. / Engineering Structures 74 (2014) 233–241

Table 2
Recent completed and ongoing long-span bridges in the HSR of China.

Structural type Bridge name Main span (m) HSR segment Built
Truss arch Dongping 242 Beijing-Guangzhou 2009
Dashengguan 2  336 Beijing-Shanghai 2011
Minjiang 198 Fuzhou-Xiamen 2011
Cable-stayed with truss girder Tianxingzhou 504 Beijing-Guangzhou 2008
Zhengzhou Yellow River 5  168 Beijing-Guangzhou 2010
Yujiang 228 Nanjing-Guangzhou 2011
Tongling Yangtze 630 Hefei-Fuzhou 2013
Anqing Yangtze 580 Nanjing-Anqing 2014 (expected)
Huanggang Yangtze 567 Wuhan-Huanggang 2014 (expected)
Concrete arch Beipanjiang 445 Shanghai-Kunming 2015 (expected)

(a) Dongping Bridge

(a) Tianxingzhou Bridge

(b) Dashengguan Bridge

(b) Yujiang Bridge

(c) Minjiang Bridge


Fig. 4. Steel truss arch bridges in the HSR of China.

structural features of steel truss arch bridge are introduced with


the Dashengguan Bridge.
The Dashengguan Bridge supports a six-line railway, including
two regular rails, two HSR and two subway lines. A six-span steel
truss with (108 + 192 + 336 + 336 + 192 + 108) m was selected to
provide the large stiffness for such heavy live loads. Similar to (c) Zhengzhou Bridge
the Dongping Bridge, the three truss planes in the longitudinal
Fig. 5. Steel truss cable-stayed bridge in the HSR lines of China.
direction was used with a spacing of 15 m. The depth of the truss
arch rib varied from 12 m at the crown to 96 m at the spring line.
Sixteen meter depth uniform truss sections are used at both side
spans. This bridge consumed more than 20.12 tons of Q420qE this structure can be found in a paper by Xia and Zhong [46]. More
Grade steel (yield strength is 420 MPa). The use of a steel box as detailed structural dimensions can be found in the paper by Gao
the deck system is another feature in the design of this steel truss et al. [47]. The greatest difficulty encountered during the construc-
arch. This 16 mm thick steel orthogonal plate is adopted as the bot- tion of the superstructure was the installation of the prefabricated
tom chord of the entire truss segment to reduce uneven deflection truss segments. The lifting of the main truss started from the sup-
on the deck. A final design feature presented here is that the hang- ports to the mid-span and side span, which is synchronized at
ers of the main span have an octagonal thin-wall cross-section to three supports. Four closures for this truss arch includes two at
improve the aerodynamic characteristics. A seismic analysis for the end of each side span and two at the crown of the two main
N. Hu et al. / Engineering Structures 74 (2014) 233–241 239

spans. The truss segments at the two main spans were lifted by a Zhengzhou Yellow River Bridge is an eight-span extradosed bridge
cable hoisting system on temporary towers and installed by with six short pylons, supporting six-lanes of motor traffic on the
70 tons capacity heavy cranes. upper deck and a double-track HSR on the lower deck, as shown
in Fig. 5c. A total of 1684.35 m is divided into eight spans with
4.2. Cable-stayed bridge with truss girder (120 + 5  168 + 120) m length to satisfy the required clearance
of the channel. This 14 m depth cross-section has an inverted trap-
Cable-stayed bridges with truss girders have been widely used ezoid shape with a top width of 24 m and a bottom width of 17 m.
as long-span HSR bridges in China. It can be seen in Table 2, the The truss girder is supported by a total of 60 cables. Six 37 m tall
main span of the Anqing Bridge and the Tongling Bridge each steel pylons stand on the top of the middle truss plane and are rig-
exceeded more than 500 m. idly connected to the main truss girder at each support. Each pylon
The milestone project for the HSR cable-stayed bridge in China is fabricated in three segments and connected on the bridge site.
is the Tianxingzhou Bridge (Fig. 5a) that supported four-track traf- The consumption of material includes 26,970 t of steel and
fic and a six-lane highway over the Yangtze River with a span 14,109 m3 of concrete. More details on the design and construction
arrangement of (98 + 196 + 504 + 196 + 98) m. Similar to the (incremental launching method) can be found in a paper by Gao
long-span steel truss arch, three 15.2 m uniform-depth truss [53].
planes in the longitudinal direction were used, with a spacing of
15 m in order to improve the torsional stiffness of the cross-section 5. Discussion
and the average tensile stress in each truss member. The truss gir-
der has a total length of 1092 m, 14 m per segment for fabrication As discussed above, a large number of long-span bridges for HSR
and erection. This truss girder consumed more than 43,600 tons of have been built in China during the past decade. Based on those
steel. At the lower level for the HSR lines, the ballast track bed was examples, it can be seen that the development of medium- and
adopted. The top chord of the truss segment served as the deck sys- long-span bridges in China relied on the use of high performance
tem for the motor traffic by using 158 m long concrete plates from materials, efficient structural systems and new construction
each end of the side span and a 756 m long orthogonal steel plate methods [49,53,54].
for the rest of the main span. The purpose of using a composite sys- High strength steel and high performance concrete have been
tem is to reduce the unbalanced effect on the piers at the side span widely used in the long-span HSR bridges in China. As discussed
under the live load. Each truss plane on the girder is supported by a in the medium span section of this paper, high performance con-
pair of 16 cables for each of the three truss planes (a total of 192 crete is commonly used to provide higher strength and durability.
cables) with a total consumption of 4500 tons of steel. The For long span HSR bridges, a steel truss girder is widely used.
reinforced concrete tower is 188.5 m tall from the top of pile cap, Heavy live loads lead to a larger internal force in truss members.
consuming 11,240 tons of steel and 44,088 m3 of concrete. A For example, the maximum member force on the Dashengguan
detailed description can be found in papers by Liu [48], Qin [49], Bridge exceeds 10,000 tons. Thus, two types of steel were devel-
Zheng and Dai [50]. oped to meet this need, including the Q370qE (yield strength is
Since the completion of the Tianxingzhou Bridge, similar spans 370 MPa) for relatively lower force members (<5500 t) and the
have been designed. The Yujiang Bridge in Fig. 5b has a span Q420qE (yield strength is 420 MPa) for higher force members
arrangement of (36 + 96 + 228 + 96 + 36) m for supporting dou- (>5500 t).
ble-track HSR line with a design speed of 300 km/h. The 14 m Two major improvements on the structural system of HSR
depth main girder has two truss planes with a spacing of 15 m. long-span bridges in China are the use of a three truss planes main
Fabrication of girder was conducted using 12 m segment. The rein- girder and the use of the orthogonal steel bridge deck. Fig. 6 shows
forced concrete tower has a height of 105 m. Another example with two typical cross-sections of two long-span bridges with three
a longer span is the Anqing Bridge over the Yangtze River that has truss planes. This form has been widely used because these long-
six-spans (101.5 + 188.5 + 580 + 217.5 + 159.5 + 116) m, using span bridges need to support multiple lines with a heavy live load.
three 15 m depth truss planes with a spacing of 14 m. Fabrication Truss members in these forms can be designed with a smaller size
of girder was conducted using 14.5 m segment. The reinforced con- such that the internal force in each member is lower and the trans-
crete tower has a height of 210 m. The material consumption on port of such members is easier. The orthogonal steel deck is also
this bridge is 66,293 t of steel and 53,120 m3 of concrete [51,52]. widely used as a part of the truss system in order to maintain
Some long span bridge designs use a variation from the tradi- smoothness on the tracks so that high speed trains can run more
tional cable-stayed bridge with truss girder. For example, the than 200 km/h on the bridges.

6 highway lanes
15.2

HSR Inter-city railway


HSR City railway

15 15 14 14

(a) Tianxingzhou Bridge (b) Dongping Bridge


Fig. 6. Three truss planes from HSR bridges.
240 N. Hu et al. / Engineering Structures 74 (2014) 233–241

The construction of these long-span bridges mainly used the to acknowledge Dr. William C. Taylor, a civil engineering emeritus
cantilever method, hoisting prefabricated members into position. professor from Michigan State University for checking the
The main truss girder is generally divided into segments (typically language.
14–16 m per segment). Other construction method was also avail-
able for special circumstances, such as the incremental launching
method used in the Zhengzhou Yellow River Bridge. Auxiliary facil- References
ities that ensured the safety of the bridge, as well as the high speed
trains include: (1) small clips along the main girder and large [1] Taniguchi M. High-Speed Rail in Japan: a review and evaluation of the
expansion devices at the end of main girder to reduce the rotation Shinkansen train. Working Paper no. 103, University of California
Transportation Center; 1992.
of the girder and thus maintain the smoothness of the track; (2)
[2] Bouley J. Short history of ‘‘high-speed’’ railway in France before the TGV. Japan
High strength ball bearings with freedom of movement in all direc- Rail Trans Rev 1994;3:49–51.
tions to support large live loads and control the rotation of the gir- [3] European Commission. High-speed Europe, a sustainable link between
citizens. Luxembourg: Publications Office of the European Union; 2010: 22.
der; (3) a number of magnetorheological (MR) dampers were
[4] Gourvish T. The high speed rail revolution: history and prospects. London: HS2
installed along the longitudinal direction to reduce the large Ltd.; 2010.
dynamic response under earthquake or emergency braking of the [5] Zuber W. High speed rail in Europe – a three decade success story. Network
trains [55]; (4) Anti-collision devices and warning lights are 2011;73:8–11 (in Chinese).
[6] Harrison J, Dezarn S, Dobbins A, Issac L. Short history of HSR in the USA.
attached to the bridge to avoid collisions. Network 2011;73:17–9.
It is noted that the main span of these HSR bridges are shorter [7] Dai GL, Song XM. Man Hua Qiao Liang. China Railway Publishing House,
than some highway bridges. For example, the main span of the Beijing; 2009 (in Chinese).
[8] Qin SQ. Large span bridges on high speed railway lines. J Rail Eng Soc
recently completed highway bridge over the Yangtze River in 2008;10:53–61.
China exceeded 1000 m. HSR bridges required higher serviceability [9] Dai GL, Hu N, Liu W. The recent improvement of high-speed railway bridges in
limits to ensure an average train speed of 200–300 km/h with China. In: IABSE symposium report. International association for bridge and
structural engineering; 2010. p. 8–15.
much heavier live load than highway bridges. Nevertheless, the [10] Chen LJ, Qiao J. Development and practice of large-span bridges on China HSR.
development of new special spans in the future will depend on Rail Econ Res 2010;98:46–50 (in Chinese).
the social need, the design competition, new concepts and experi- [11] Ministry of Railways of China. Code for Design of High Speed Railway, TB
10621–2009. China Railway Press; 2009 (in Chinese).
ence [56]. Based on the new techniques discussed above, longer [12] Yi LX. Engineering characteristic and key technique of Dashenguan Changjiang
spans have been planned in China with careful feasibility studies. river bridge. Steel Constr 2007;22:78–80 (in Chinese).
For example, a cable-stayed bridge with a main span of 1092 m [13] Kwark JW, Choi ES, Kim YJ, Kim BS, Kim SI. Dynamic behavior of two-span
continuous concrete bridges under moving high-speed train. Comput Struct
has been studied for span over the Yangtze River as part of Nan-
2004;82:463–74.
tong-Shanghai line that supports both highway and HSR [57]. In [14] Frýba L. A rough assessment of railway bridges for high speed trains. Eng
addition, feasibility studies of HSR suspension bridges are being Struct 2001;23:548–56.
carried out, such as a bridge at Yangzhou over the Yangtze River [15] Xia H, Zhang N, De Roeck G. Dynamic analysis of high speed railway bridge
under articulated trains. Comput Struct 2003;81:2467–78.
with a main span of 1120 m and a bridge over the Qiongzhou Strait [16] Raghunathan RS, Kim HD, Setoguchi T. Aerodynamics of high-speed railway
with a main span of 1408 m. train. Prog Aerospace Sci 2002;38:469–514.
[17] Dias R, Goicolea Ruigómez JM, Gabaldón Castillo F, Cuadrado Sanguino M,
Nasarre J, González Requejo P. A study of the lateral dynamic behaviour of high
6. Summary speed railway viaducts and its effect on vehicle ride comfort and stability;
2008.
HSR offers safe, affordable, green transportation that relieves [18] Calcada R, Delgado R, Campos e Matos A, Goicolea JM, Gabaldon F. Track-
bridge interaction on high-speed railways. Portugal 2007:15–6.
congestion on highways and traditional railways in China. This
[19] Fitzwilliam D. Track structure interactions for the Taiwan high speed rail
paper presented a brief history of the special spans that support project IABSE Symposium Report. Int Assoc Bridge Struct Eng 2003;87:10.
HSR over rivers and existing lines with a single span more than [20] Dutoit D. New evolutions for high speed rail line bridge design criteria and
corresponding design procedures IABSE Symposium Report. Int Assoc Bridge
100 m. The construction of medium- and long-span HSR bridges
Struct Eng 2003;87:12.
during the past decade is driven by the ongoing development of [21] Kristek V, Vrablik L. Optimisation of tendon layout to avoid excessive
the national HSR network. Compared to the design and construc- deflections of long-span prestressed concrete bridges. Concr Eng
tion of standard spans, special spans still require high serviceabil- 2007;11(1):30–3.
[22] Fiore A, Foti D, Monaco P, Raffaele D, Uva G. An approximate solution for the
ity limits so the trains can maintain high speed on these spans. A rheological behavior of non-homogeneous structures changing the structural
variety of structural forms have been used to meet the deflection system during the construction process. Eng Struct 2013;46:631–42.
requirements. For medium length, the tied steel arch and the rigid [23] Kumar Rakesh, Upadhyay Akhil. Effect of temperature gradient on track–
bridge interaction. Interact Multiscale Mech 2012;5(1):1–12.
frame are two commonly used forms. The hybrid system of these [24] Xu Y, Jin FH, Yang FT, Cai SM. Bridge overall design by siyuan survey on
two forms also offers an alternative choice. For large lengths, the Wuhan-Guangzhou high-speed railway. Rail Stand Des 2010;1:94–9 (in
steel truss arch and cable-stayed bridge with truss girder are Chinese).
[25] Zhu B. Design of continuous welded rail upon long span cable-stayed bridge
widely used. Such progress on the design and construction of spe- with steel–concrete composite box beam. Rail Stand Des 2012;2:4–15 (in
cial spans in the HSR of China depended on the use of advanced Chinese).
material and construction technologies. Further investigations are [26] Yan B. Longitudinal forces of continuously welded rail on high-speed railway
cable-stayed bridge considering impact of adjacent bridges. J Central South
ongoing to establish more comprehensive design specifications
Univ 2012;19:2348–53.
for long-span HSR bridges. The fast development of the HSR [27] Yue CD. Research on seismic response reduction of cable-stayed bridge on
long-span bridges in China are based on learning from experience based on viscous damper long-span railway. J Lanzhou Jiaotong Univ
2013;32:10–4.
of developed countries accumulated in the 20th century. Now, in
[28] Li Y, Qiang S, Liao H, Xu YL. Dynamics of wind–rail vehicle–bridge systems. J
turn, China has provided new experience and will continually lead Wind Eng Ind Aerodyn 2005;93:483–507.
the construction of HSR long-span bridges in the next decade. [29] Wang SQ, Xia H, Guo WW, Du XT. Nonlinear coupling vibration analysis of
wind load-train-long-span bridge system. J Beijing Jiaotong Univ
2012;36:36–46 (in Chinese).
Acknowledgements [30] Li Y. Study on variation rules of longitudinal force of continuous welded rails
on long-span cable-stayed bridge. J Rail Eng Soc 2012;169:42–6 (in Chinese).
The authors gratefully acknowledge the financial support and [31] Hu N, Dai GL. The introduction of high-speed railway bridges in Wuhan-
Guangzhou passenger dedicated line, China. In: IABSE symposium report.
first-hand design information provided by China Railway Siyuan International association for bridge and structural engineering; 2009. p. 45–
Survey and Design Group CO., LTD. The authors also would like 54.
N. Hu et al. / Engineering Structures 74 (2014) 233–241 241

[32] Tian XM, Li Q, Zhang QH. Study on static stiffness and model test of long-span [46] Xia C, Zhong T. Numerical analysis of the Nanjing Dashengguan Yangtze River
X-style tied arch bridge in high-speed railway. Bridge Constr 2002;4:12–5 (in Bridge subjected to non-uniform seismic excitations. J Mech Sci Technol
Chinese). 2011;25:1297–306.
[33] Feng CQ. Design of 112 m a-shaped tied arch bridge of nielsen system in high [47] Gao ZY, Yi L, Xiao HZ. Dashengguan bridge, largest span steel arch bridge for
speed railway with Ballastless track. J Rail Eng Soc 2007;12:232–9 (in high-speed railway. Struct Eng Int 2010;20:299–302.
Chinese). [48] Liu XG. Key technics of engineering consultation in Wuhan Tian Xingzhou
[34] Zhang XH, Chai XZ. Lying construction technology of Donghu bridge. Rail Eng highway and railway bridge over Yangtze river. In: Proceedings of 8th Pacific
2010;1:75–7 (in Chinese). structural steel conference – steel structures in natural hazards, PSSC 2007;
[35] Jin WC, Huai CZ, Zhang YC, Cheng ZQ. Analysis of simulation on the 2007. p. 195–7.
construction process of Donghu basket arch bridge. J Huazhong Univ Sci [49] Qin SQ. Wuhan Tianxingzhou bridge over the Yangtze river: a great salute to
Technol 2009;26:15–9 (in Chinese). the first crossing of the yangtze river in fifty years. In: IABSE symposium
[36] Li XB. Construction of Tingsihe bridge of 140 m steel box girder with tied arch. report. International association for bridge and structural engineering; 2009.
Rail Constr Technol 2009:1–4 (in Chinese). p. 212–20.
[37] Zhang Y, Luo R. Patch loading and improved measures of incremental [50] Zheng PF, Dai GL. Comparative study on static properties of three-main-truss
launching of steel box girder. J Constr Steel Res 2012;68:11–9. and three-cable-plane cable-stayed bridge. J Eng Des Technol 2013;11:7.
[38] Kou YC. Design of Tianluo bridge on Wenzhou-Fuzhou. Rail Stand Des [51] Xiao HZ, Xu W, Gao ZY. Design of Anqing Changjiang river railway bridge.
2005;11:25–8 (in Chinese). Bridge Constr 2009;5:6–8 (in Chinese).
[39] Luo JF, Ma WT, Wang WF. Construction monitoring and control of Liuxihe [52] Wang SQ, Liu AL. Key techniques for construction of superstructure of main
bridge. Sci Technol Eng 2011;15:057 (in Chinese). bridge of Anqing Changjiang river railway bridge. Bridge Constr 2013;43:33–9
[40] Gong QY. Wind loads response of large span continuous rigid frame bridge. (in Chinese).
M.S. Dissertation, Changsha: Central South University; 2009 (in Chinese). [53] Gao ZY. Zhengzhou yellow river road-cum-railway bridge, China. Stahlbau
[41] Zhou D. The study on structural system and mechanical behaviors of through 2012;81:151–5.
steel tied-arch composite bridge on high-speed railway. Ph.D. Dissertation, [54] Gao ZY. High-speed railway bridges across the Yangtze and Yellow river. Eng
Central South University; 2011 (in Chinese). Sci 2009;11:17–21 (in Chinese).
[42] Dong HX. Force Analysis of Large Continuous Beam Bridge with Arch. M.S. [55] Li J, Su M, Fan L. Vibration control of railway bridges under high-speed trains
Dissertation, Changsha: Central South University; 2009. using multiple tuned mass dampers. J Bridge Eng 2005;10:312–20.
[43] Wang DH. Swivel construction design of Yichang Yangtze bridge. Rail Stand [56] Hu N, Dai GL. Four significant factors in evolution of bridge engineering. In:
Des 2009;6:31–5 (in Chinese). Proceeding of 1st international conference on structures & architecture (ICSA
[44] Huang NX, Yan AG, Luo SY. Construction of Kunyang special continuous beam 2010), Portugal; 2010. p. 329–30.
with arch on Wenzhou-Fuzhou HSR. Rail Stand Des 2005;11:31–3 (in [57] Zi HM. Feasibility study on 1092 m cable-stayed bridge on Shanghai-Nantong
Chinese). HSR. Rail Eng 2011;6:1–4 (in Chinese).
[45] Liu WS, Dai GL. Dongping channel bridge: long-span steel arch bridge in high-
speed railway China. Struct Eng Int 2011;21:492–6.

You might also like