Test Procedure
Before starting work the 'Responsible Electrical Person' and engineer MUST:-
Confirm all appropriate Work Permits are in place
Confirm the Drive is de-energised, isolated, earthed down and dead
Confirm Surface panel (ZSP) is powered down and isolated
Confirm the system is isolated and safe before any work commences
Disconnect Surface choke and ZSP during any Drive and/or cable megger testing
Physical Examination
Carry out physical examination and confirm system is appropriately wired
Confirm Choke fuses are each (independantly) wired to the 3 down hole cable terminals
Confirm Choke fuses are not linked and/or wired to a single phase or to transformer Y Point
Confirm all connections clean dry and secure - Confirm wiring continuity
Confirm high integrity earth path between Surface choke and well head (confirm continuity)
Ensure Screen is earthed at one end only (choke or ZSP)
Choke Wiring Choke Fuses Signal cable Wiring Choke Earth to WH Screen connection
3 - Phase to Line Phase A to Line Phase B to Line Phase C to Line Expected Value
Resistance (ohm) 2900ohm
4 - Phase to Earth Phase A to Gnd Phase B to Gnd Phase C to Gnd Expected Value
Resistance (ohm) OL
5 - LINE to Earth - Diode Signal terminal LINE connection to Earth Stud Expected Value
Voltage Test (Volt) ~0.6V
Comments
NOTE: -
Ph/ph (5700ohm) and ph/ln(2900ohm) resistances apply to Choke part no - 14460052000 - Serial number BEFORE
SC4651 and AFTER SC4921