Government Procurement Law SCOPE AND APPLICATION

An act providing for the modernization,  This IRR shall apply to all
standardization and regulation of the procurement of any branch, agency,
procurement activities of the government and for department, bureau, office, or
other purposes. (government procurement reform instrumentality of the GoP, including
act) government-owned and/or –
controlled corporations (GOCCs),
government financial institutions
GENERAL PRINCIPLES (GFIs), state universities and
SEC. 2. Declaration of Policy. - It is the declared colleges (SUCs), and local
government units (LGUs).
policy of the State to promote the ideals of good
 Any Treaty or International or
governance and its effort to adhere to the
Executive Agreement to which the
principles of transparency, accountability, equity, GoP is a signatory affecting the
efficiency, and economy in its procurement subject matter of the Act and this IRR
process in all its branches, departments, agencies, shall be observed. In case of conflict
subdivisions, and instrumentalities, including between the terms of the Treaty or
government-owned and/or controlled International or Executive Agreement
corporations, and local government units. and this IRR, the former shall prevail.
 Unless the Treaty or International or
SEC. 3. Governing Principles on Government Executive Agreement expressly
Procurement. - All procurement of the national provides another or different
government, its departments, bureaus, offices and procurement procedures and
agencies, including state universities and colleges, guidelines, R.A. 9184 and this IRR
government-owned and/or controlled shall apply to Foreign-funded
corporations, government financial institutions Procurement of Goods, Infrastructure
and local government units, shall, in all cases, be Projects, and Consulting Services by
the GoP.
governed by these principles:
 The GoP negotiating panels shall, as
a) Transparency in the procurement
its default position, adhere to R.A.
process and in the implementation of
9184 and this IRR, or at the very
procurement contracts.
least, selection through competitive
b) Competitiveness by extending equal
bidding, in all Foreign-funded
opportunity to enable private
Procurement. If the Treaty or
contracting parties who are eligible
International or Executive Agreement
and qualified to participate in public
states otherwise, then the negotiating
bidding.
panel shall ensure that the reasons
c) Streamlined procurement process
for the adoption of a different rule or
that will uniformly apply to all
method of procurement are clearly
government procurement. The
reflected in the records of discussion.
procurement process shall be simple
This IRR shall not apply to the following activities:
and made adaptable to advances in
modern technology in order to ensure a) Procurement of Goods, Infrastructure
an effective and efficient method. Projects and Consulting Services
d) System of accountability where both funded from Foreign Grants covered
the public officials directly or indirectly by R.A. 8182, as amended by R.A.
involved in the procurement process 8555, entitled “An Act Excluding
as well as in the implementation of Official Development Assistance
procurement contracts and the (ODA) from the Foreign Debt Limit in
private parties that deal with order to Facilitate the Absorption and
government are, when warranted by Optimize the Utilization of ODA
circumstances, investigated and held Resources, Amending for the
liable for their actions relative thereto. Purpose Paragraph 1, Section 2 of
e) Public monitoring of the procurement R.A. 4860, As Amended,” unless the
process and the implementation of GoP and the foreign grantor/foreign
awarded contracts with the end in or international financing institution
view of guaranteeing that these agree otherwise;
contracts are awarded pursuant to b) Acquisition of real property which
the provisions of this Act and its shall be governed by R.A. 107523,
implementing rules and regulations, entitled “An Act Facilitating the
and that all these contracts are Acquisition of Right-Of-Way Site or
performed strictly according to Location for National Government
specifications. Infrastructure Projects,” and other
applicable laws, rules and
regulations; and approved by the Sanggunian through
c) Public-Private sector infrastructure or an appropriations ordinance in the
development projects and other case of LGUs. For multi-year
procurement covered by R.A. 6957, contracts, for which a Multi-Year
as amended by R.A. 7718, entitled Obligational Authority (MYOA) or an
“An Act Authorizing the Financing, equivalent document is required, the
Construction, Operation and ABC shall be that incorporated in the
Maintenance of Infrastructure project cost reflected in the MYOA or
Projects by the Private Sector, and equivalent document.
for Other Purposes,” as amended: For Foreign-funded
Provided, however, That for the Procurement, the ABC refers to the
portions financed by the GoP, in cost estimate prepared by the
whole or in part, the provisions of the Procuring Entity and approved by the
Act and this IRR shall apply.(a) foreign government/foreign or
The following are not procurement activities international financing institution as
under R.A. 9184 and this IRR: specified in the Treaty or International
a) Direct financial or material assistance or Executive Agreement.
given to beneficiaries in accordance  BAC - refers to the Bids and Awards
with the existing laws, rules and Committee established in
regulations, and subject to the accordance with Article V of this Act.
guidelines of the concerned agency;  Bidder. Refers to a contractor,
b) b) Participation in local or foreign manufacturer, supplier, distributor
scholarships, trainings, continuing and/or consultant who submits a bid
education, conferences, seminars or in response to the requirements of
similar activities that shall be the Bidding Documents.
governed by applicable COA, CSC,  Bidding Documents - refer to
and DBM rules; documents issued by the Procuring
c) Lease of government-owned Entity as the basis for Bids, furnishing
property as lessor for private use; all information necessary for a
d) Hiring of Job Order Workers; prospective bidder to prepare a bid
e) Joint Venture under the revised for the Goods, Infrastructure
NEDA Guidelines (GOCC and Projects, and Consulting Services to
Private Entities), and Joint Venture be provided.
Agreements by LGU with Private  Bid - refers to a signed offer or
entities; and proposal submitted by a supplier,
f) Disposal of Property and Other manufacturer, distributor, contractor
Assets of the Government.(n) or consultant in response to the
DEFINITION OF TERMS Bidding Documents.
 Common-Use Supplies and
For purposes of this IRR, the following
Equipment (CSE). Refer to those
terms or words and phrases shall mean or be
goods, materials and equipment that
understood as follows: are used in the day-to-day operations
 Act. Refers to R.A. 9184, entitled “An of Procuring Entities in the
Act Providing for the Modernization, performance of their functions. For
Standardization and Regulation of the purpose of this IRR, CSE shall be
the Procurement Activities of the those included in the Electronic
Government and for other Purposes,” Catalogue of the PhilGEPS.
otherwise known as the Government  Competitive Bidding - refers to a
Procurement Reform Act. method of procurement which is open
 Approved Budget for the Contract to participation by any interested
(ABC). Refers to the budget for the party and which consists of the
contract duly approved by the HoPE, following processes: advertisement,
as provided for in the General pre-bid conference, eligibility
Appropriations Act (GAA), screening of prospective bidders,
continuing, and automatic receipt and opening of bids,
appropriations, in the case of national evaluation of bids, post-qualification,
government agencies (NGAs); the and award of contract, the specific
corporate budget for the contract requirements and mechanics of
approved by the governing board, which shall be defined in the IRR to
pursuant to Executive Order (E.O). be promulgated under this Act.
No. 518, s. 1979, in the case of  Consulting Services - refer to
GOCCs and GFIs, and R.A. 8292 in services for Infrastructure Projects
the case of SUCs; the budget and other types of projects or
activities of the Government requiring of the Philippines.
adequate external technical and  Foreign-funded Procurement.
professional expertise that are Refers to the acquisition of goods,
beyond the capability and/or capacity consulting services, and the
of the government to undertake such contracting for infrastructure projects
as, but not limited to: (i) advisory and by the GoP which are wholly or partly
review services; (ii) pre-investment or funded by Foreign Loans or Grants
feasibility studies; (iii) design; (iv) pursuant to a Treaty or International
construction supervision; (v) or Executive Agreement. For
management and related services; purposes of, and throughout this IRR,
and (vi) other technical services or the term “foreign-funded
special studies. procurement” shall have the same
 Domestic Bidder. Refers to any meaning as and shall be used
person or entity offering interchangeably with “foreign-funded
unmanufactured articles, materials or projects” or “foreign-assisted
supplies of the growth or production projects.”
of the Philippines, or manufactured  Foreign Grants. Refer to grants with
articles, materials, or supplies no repayment obligations and are
manufactured or to be manufactured provided in monetary form, goods,
in the Philippines substantially from works, and consultancy services,
articles, materials, or supplies of the among others.
growth, production, or manufacture,  Foreign Loans. Refer to loans,
as the case may be, of the credits, and indebtedness with
Philippines. private foreign banks or with foreign
 Domestic Entity. Refers to an governments, agencies, or
individual or a sole proprietor who is instrumentalities of such foreign
a citizen of the Philippines or a governments, foreign financial
partnership, corporation, institutions, or other international
cooperative, or association duly organizations with whom, or
organized under the laws of the belonging to countries with which, the
Philippines and of which at least Philippines has diplomatic relations,
seventy five percent (75%) of the as may be necessary and upon such
interest or outstanding capital stock terms and conditions as may be
belongs to citizens of the Philippines, agreed upon, to enable the GoP to
habitually established in business finance, either directly or through any
and habitually engaged in the government office, agency or
manufacture or sale of the instrumentality or any government-
merchandise covered by his bid, and owned and controlled corporation,
the business has been in existence industrial, agricultural or other
for a least five (5) consecutive years economic development purposes or
prior to the advertisement and/or projects authorized by law.
posting of the Invitation to Bid.4  PhilGEPS - refers to the Government
 Executive Agreements. Refer to Electronic Procurement System as
International Agreements except that provided in Section 8 of this Act.
they do not require legislative  Goods - refer to all items, supplies,
ratification. Expendable Supplies. materials and general support
Refer to articles which are normally services, except consulting services
consumed in use within one (1) year and infrastructure projects, which
or converted in the process of may be needed in the transaction of
manufacture or construction, or those public businesses or in the pursuit of
having a life expectancy of more than any government undertaking, project
one (1) year but which shall have or activity, whether in the nature of
decreased substantially in value after equipment, furniture, stationery,
being put to use for only one (1) year materials for construction, or
(e.g., medicines, stationery, fuel, and personal property of any kind,
spare parts). including non-personal or contractual
 Foreign Bid. Refers to any offer of services such as the repair and
articles, materials or supplies not maintenance of equipment and
manufactured or not to be furniture, as well as trucking, hauling,
manufactured in the Philippines, janitorial, security, and related or
substantially from articles, materials, analogous services, as well as
or supplies of the growth, production, procurement of materials and
or manufacture, as the case may be, supplies provided by the procuring
entity for such services. written form and governed by
 GPPB - refers to the Government international law, whether embodied
Procurement Policy Board in a single instrument or in two (2) or
established in accordance with more related instruments.
Article XX of this Act. (j) Head of the  Non-expendable Supplies. Refer to
Procuring Entity - refers to: (i ) the articles which are not consumed in
head of the agency or his duly use and ordinarily retain their original
authorized official, for national identity during the period of use,
government agencies; (ii) the whose serviceable life is more than
governing board or its duly authorized one (1) year and which add to the
official, for government owned assets of the GoP (e.g., furniture,
and/or controlled corporations; or (iii) fixtures, transport and other
the local chief executive, for local equipment). For this IRR, the term
government units. Provided, That in a non-expendable supplies shall
department, office or agency where include semi-expendable property.
the procurement is decentralized, the  IRR - refer to the implementing rules
Head of each decentralized unit shall and regulations to be promulgated in
be considered as the Head of the accordance with Section 75 this Act.
Procuring Entity subject to the  Philippine National. Refers to an
limitations and authority delegated by individual or a sole proprietor who is
the head of the department, office or a citizen of the Philippines or a
agency. partnership, corporation, or
 Head of the Procuring Entity association organized under the laws
(HoPE). Refers to: (i) the head of the of the Philippines of which at least
agency or body, or his duly sixty percent (60%) of the capital or
authorized official, for NGAs and the interest is owned by citizens of the
constitutional commissions or offices, Philippines, or cooperatives
and other branches of government; registered with the Cooperative
(ii) the governing board or its duly Development Authority.
authorized official, for GOCCs, GFIs  Portal - refers to a website that
and SUCs; or (iii) the local chief aggregates a wide variety of content
executive, for LGUs: Provided, for the purpose of attracting a large
however, That in an agency, number of users.
department, or office where the  Procurement - refers to the
procurement is decentralized, the acquisition of Goods, Consulting
head of each decentralized unit shall Services, and the contracting for
be considered as the HoPE, subject Infrastructure Projects by the
to the limitations and authority Procuring Entity. Procurement shall
delegated by the head of the agency, also include the lease of goods and
department, or office. real estate. With respect to real
 Infrastructure Projects - include the property, its procurement shall be
construction, improvement, governed by the provisions of
rehabilitation, demolition, repair, Republic Act No. 8974, entitled "An
restoration or maintenance of roads Act to Facilitate the Acquisition of
and bridges, railways, airports, Right- -Way Site or Location for
seaports, communication facilities, National of Government
civil works components of information Infrastructure Projects and for Other
technology projects, irrigation, flood Purposes", and other applicable
control and drainage, water supply, laws, rules and regulations.
sanitation, sewerage and solid waste  Procuring Entity - refers to any
management systems, shore branch, department, office, agency,
protection, energy/power and or instrumentality of the government,
electrification facilities, national including state universities and
buildings, school buildings, hospital colleges, government-owned and/or -
buildings and other related controlled corporations, government
construction projects of the financial institutions, and local
government. government units procuring Goods,
 International Agreement. Refers to Consulting Services and
a contract or understanding, Infrastructure Projects.
regardless of nomenclature, entered  Treaties. Refer to international
into between the GoP and another agreements entered into by the GoP
government or foreign or which require legislative ratification
international financing institution in after executive concurrence.
 Universal or Commercial Banks. in the IRR, in which case, the holding of the same is
Refer to universal or commercial optional.
banks duly authorized under R.A.
8791, otherwise known as “The The pre-procurement conference shall assess the
General Banking Act of 2000.”\ readiness of the procurement in terms of
confirming the certification of availability of funds,
PROCUREMENT PROCEDURES as well as reviewing all relevant documents in
1. PREPARATION OF BIDDING DOCUMENTS relation to their adherence to law. This shall be
SEC. 17. Form and Contents of Bidding attended by the BAC, the unit or officials who
Documents. - The Bidding Documents shall be prepared the bidding documents and the draft
prepared by the Procuring Entity following the Invitation to Bid, as well as consultants hired by the
standard forms and manuals prescribed by the agency concerned and the representative of the
GPPB. The Bidding Documents shall include the end-user.
following:
SEC. 21. Advertising and Contents of the Invitation
a) Approved Budget for the Contract; to Bid. - In line with the principle of transparency
b) Instructions to Bidders, including and competitiveness, all Invitations to Bid for
criteria for eligibility, bid evaluation contracts under competitive bidding shall be
and post-qualification, as well as the advertised by the Procuring Entity in such manner
date, time and place of the pre-bid and for such length of time as may be necessary
Conference (where applicable), under the circumstances, in order to ensure the
submission of bids and opening of widest possible dissemination thereof, such as, but
bids; not limited to, posting in the Procuring Entity's
c) Terms of Reference; premises, in newspapers of general circulation, the
d) Eligibility Requirements; G-EPS and the website of the Procuring Entity, if
e) Plans and Technical Specifications; available. The details and mechanics of
f) Form of Bid, Price Form, and List of
implementation shall be provided in the IRR to be
Goods or Bill of Quantities;
promulgated under this Act.
g) Delivery Time or Completion
Schedule; The Invitation to Bid shall contain, among others:
h) Form and Amount of Bid Security;
i) Form and Amount of Performance a) A brief description of the subject matter
Security and Warranty; and, of the Procurement;
j) Form of Contract, and General and b) A general statement on the criteria to be
Special Conditions of Contract. used by the Procuring Entity for the
The Procuring Entity may require additional eligibility check, the short listing of
document requirements or specifications prospective bidders, in the case of the
necessary to complete the information required Procurement of Consulting Services, the
for the bidders to prepare and submit their examination and evaluation of Bids, and
respective bids. post-qualification;
SEC. 18. Reference to Brand Names. - c) The date, time and place of the deadline
Specifications for the Procurement of Goods shall for the submission and receipt of the
be based on relevant characteristics and/or eligibility requirements, the pre-bid
performance requirements. Reference to brand conference if any, the submission and
names shall not be allowed. receipt of bids, and the opening of bids;
d) The Approved Budget for the Contract to
SEC. 19. Access to Information. - In all stages of the be bid;
preparation of the Bidding Documents, the e) The source of funds;
Procuring Entity shall ensure equal access to f) The period of availability of the Bidding
information. Prior to their official release, no Documents, and the place where these
aspect of the Bidding Documents shall be divulged may be secured;
or released to any prospective bidder or person g) The contract duration; and,
having direct or indirect interest in the project to h) Such other necessary information
be procured. deemed relevant by the Procuring Entity.
SEC. 22. Pre-bid Conference. - At least one pre-bid
2. INVITATION TO BID conference shall be conducted for each
SEC. 20. Pre-Procurement Conference. - Prior to the procurement, unless otherwise provided in the IRR.
issuance of the Invitation to Bid, the BAC is Subject to the approval of the BAC, a pre-bid
mandated to hold a pre-procurement conference conference may also be conducted upon the
on each and every procurement, except those written request of any prospective bidder.
contracts below a certain level or amount specified
The pre-bid conference(s) shall be held within a submit another Bid for the same contract either
reasonable period before the deadline for receipt directly or indirectly.
of bids to allow prospective bidders to adequately
prepare their bids, which shall be specified in the SEC. 27. Bid Security. - All Bids shall be
IRR. accompanied by a Bid security, which shall serve as
a guarantee that, after receipt of the Notice of
3. RECEIPT AND OPENING OF BIDS Award, the winning bidder shall enter into contract
SEC. 23. Eligibility Requirements for the with the Procuring Entity within the stipulated
Procurement of Goods and Infrastructure time and furnish the required performance
Projects. - The BAC or, under special circumstances security. The specific amounts and allowable
specified in the IRR, its duly designated organic forms of the Bid security shall be prescribed in the
office shall determine the eligibility of prospective IRR.
bidders for the procurement of Goods and
Infrastructure Projects, based on the bidders' SEC. 28. Bid Validity. - Bids and Bid securities shall
compliance with the eligibility requirements be valid for such reasonable period of time
within the period set forth in the Invitation to Bid. indicated in the Bidding Documents. The duration
for each undertaking shall take into account the
The eligibility requirements shall provide for fair time involved in the process of Bid evaluation and
and equal access to all prospective bidders. The award of contract.
documents submitted in satisfaction of the
eligibility requirements shall be made under oath SEC. 29. Bid Opening. - The BAC shall publicly open
by the prospective bidder or by his duly authorized all bids at the time, date, and place specified in the
representative certifying to the correctness of the bidding documents. The minutes of the bid
statements made and the completeness and opening shall be made available to the public upon
authenticity of the documents submitted. written request and payment of a specified fee.

A prospective bidder may be allowed to submit his 4. BID EVALUATION


eligibility requirements electronically. However, SEC. 30. Preliminary Examination of Bids. - Prior
said bidder shall later on certify under oath as to to Bid evaluation, the BAC shall examine first the
correctness of the statements made and the technical components of the bids using "pass/fail"
completeness and authenticity of the documents criteria to determine whether all required
submitted. documents are present. Only bids that are
determined to contain all the bid requirements of
SEC. 25. Submission and Receipt of Bids. - A bid the technical component shall be considered for
shall have two (2) components, namely the opening and evaluation of their financial
technical and financial components which should component.
be in separate sealed envelopes, and which shall
be submitted simultaneously. The bids shall be SEC. 32. Bid for the Procurement of Goods and
received by the BAC on such date, time and place Infrastructure Projects. - For the procurement of
specified in the invitation to bid. The deadline for Goods and Infrastructure Projects, the BAC shall
the receipt of bids shall be fixed by the BAC, giving evaluate the financial component of the bids. The
it sufficient time to complete the bidding process bids that passed the preliminary examination shall
and giving the prospective bidders sufficient time be ranked from lowest to highest in terms of their
to study and prepare their bids. The deadline shall corresponding calculated prices. The bid with the
also consider the urgency of the procurement lowest calculated price shall be referred to as the
involved. "Lowest Calculated Bid."

Bids submitted after the deadline shall not be SEC. 33. Bid Evaluation of Short Listed Bidders for
accepted. Consulting Services. - For the Procurement of
Consulting Services, the Bids of the short listed
SEC. 26 Modification and Withdrawal of Bids. - A bidders shall be evaluated and ranked using
bidder may modify his bid, provided that this is numerical ratings in accordance with the
done before the deadline for the receipt of bids. evaluation criteria stated in the Bidding
The modification shall be submitted in a sealed Documents, which shall include factors such as,
envelope duly identified as a modification of the but not limited to, experience, performance,
original bid and stamped received by the BAC. quality of personnel, price and methodology. The
Bids shall be ranked from highest to lowest in
A bidder may, through a letter, withdraw his bid terms of their corresponding calculated ratings.
or express his intention not to participate in the The Bid with the highest calculated rating shall be
bidding before the deadline for the receipt of bids. the "Highest Rated Bid."
In such case, he shall no longer be allowed to
After approval by the Head of the Procuring Entity c) Whenever the bidder with the highest
of the Highest Rated Bid, the BAC shall invite the rated/lowest calculated responsive
bidder concerned for negotiation and/or bid refuses, without justifiable cause
clarification on the following items: financial to accept the award of contract, as
proposal submitted by the bidder, terms of the case may be.
reference, scope of services, methodology and Under any of the above instances, the contract
work program, personnel to be assigned to the job, shall be re-advertised and re-bid. The BAC shall
services/facilities/data to be provided by the observe the same process and set the new periods
Procuring Entity concerned, and provisions of the according to the same rules followed during the
contract. first bidding.

When negotiations with the first- -rank bidder fails After the second failed bidding, however, the BAC
in , the financial proposal of the second rank may resort to negotiated procurement as provided
bidder shall be opened for negotiations: for in Section 53 of this Act.

Provided, That the amount indicated in the SEC. 36. Single Calculated/Rated and Responsive
financial envelope shall be made as the basis for Bid Submission. - A single calculated/rated and
negotiations and the total contract amount shall responsive bid shall be considered for award if it
not exceed the amount indicated in the envelope falls under any of the following circumstances:
and the ABC. Whenever necessary, the same
a) If after advertisement, only one
process shall be repeated until the bid is awarded prospective bidder submits a Letter of
to the winning bidder. Intent and/or applies for eligibility
check, and meets the eligibility
5. POST-QUALIFICATION
requirements or criteria, after which it
SEC. 34. Objective and Process of Post-
submits a bid, which is found to be
qualification. - Post-qualification is the stage responsive to the bidding
where the bidder with the Lowest Calculated Bid, requirements;
in the case of Goods and Infrastructure Projects, or b) If after the advertisement, more than
the Highest Rated Bid, in the case of Consulting one prospective bidder applies for
Services, undergoes verification and validation eligibility check, but only one bidder
whether he has passed all the requirements and meets the eligibility requirements or
conditions as specified in the Bidding Documents. criteria, after which it submits a bid
which is found to be responsive to the
If the bidder with the Lowest Calculated Bid or bidding requirements; or
Highest Rated Bid passes all the criteria for post c) If after the eligibility check, more than
qualification, his Bid shall be considered the one bidder meets the eligibility
"Lowest Calculated Responsive Bid," in the case of requirements, but only one bidder
Goods and Infrastructure or the "Highest Rated submits a bid, and its bid is found to
Responsive Bid," in the case of Consulting Services. be responsive to the bidding
requirements.
However, if a bidder fails to meet any of the In all instances, the Procuring Entity shall ensure
requirements or conditions, he shall be "post- that the ABC reflects the most advantageous
disqualified" and the BAC shall conduct the post- prevailing price for the Government.
qualification on the bidder with the second Lowest
Calculated Bid or Highest Rated Bid. If the bidder 6. AWARD, IMPLEMENTATION AND
with the second Lowest Calculated Bid or Highest TERMINATION OF THE CONTRACT
Rated Bid is post-disqualified, the same procedure SEC. 37. Notice and Execution of Award. - Within
shall be repeated until the Lowest Calculated a period not exceeding fifteen (15) calendar days
Responsive Bid or Highest Rated Responsive Bid is from the determination and declaration by the
finally determined. BAC of the Lowest Calculated Responsive Bid or
Highest Rated Responsive Bid, and the
In all cases, the contract shall be awarded only to recommendation of the award, the Head of the
the bidder with the Lowest Calculated Responsive Procuring Entity or his duly authorized
Bid or Highest Rated Responsive Bid. representative shall approve or disapprove the
said recommendation.
SEC. 35. Failure of Bidding. - There shall be a
failure of bidding if: In case of approval, the Head of the Procuring
Entity or his duly authorized representative shall
a) No bids are received; immediately issue the Notice of Award to the
b) No bid qualifies as the Lowest
bidder with the Lowest Calculated Responsive Bid
Calculated Responsive Bid or
or Highest Rated Responsive Bid.
Highest Rated Responsive Bid; or,
Within ten (10) calendar days from receipt of the made. However, if no award is possible, the
Notice of Award, the winning bidder shall formally contract shall be subjected to a new bidding.
enter into contract with the Procuring Entity.
When further approval of higher authority is In the case of a failure to post the required
required, the approving authority for the contract performance security, the bid security shall be
shall be given a maximum of twenty (20) calendar forfeited without prejudice to the imposition of
days to approve or disapprove it. sanctions prescribed under Article XXIII.

In the case of government owned and/or SEC. 41. Reservation Clause. - The Head of the
controlled corporations, the concerned board shall Agency reserves the right to reject any and all Bids,
take action on the said recommendation within declare a failure of bidding, or not award the
thirty (30) calendar days from receipt thereof. contract in the following situations:

The Procuring Entity shall issue the Notice to a) If there is prima facie evidence of
Proceed to the winning bidder not later than seven collusion between appropriate public
(7) calendar days from the date of approval of the officers or employees of the
Procuring Entity, or between the BAC
contract by the appropriate authority. All notices
and any of the bidders, or if the
called for by the terms of the contract shall be
collusion is between or among the
effective only at the time of receipt thereof by the bidders themselves, or between a
contractor. bidder and a third party, including any
act which restricts, suppresses or
SEC. 38. Period of Action on Procurement
nullifies or tends to restrict, suppress
Activities. - The procurement process from the or nullify competition;
opening of bids up to the award of contract shall b) If the BAC is found to have failed in
not exceed three (3) months, or a shorter period following the prescribed bidding
to be determined by the procuring entity procedures; or
concerned. Without prejudice to the provisions of c) For any justifiable and reasonable
the preceding section, the different procurement ground where the award of the
activities shall be completed within reasonable contract will not redound to the
periods to be specified in the IRR. benefit of the government as defined
in the IRR.
If no action on the contract is taken by the head of
the procuring entity, or by his duly authorized DISCLOSURE OF RELATIONS
representative, or by the concerned board, in the
case of government owned and/or controlled
corporations, within the periods specified in the SEC. 47. Disclosure of Relations. - In addition to
preceding paragraph, the contract concerned shall the proposed contents of the Invitation to Bid as
be deemed approved. mentioned under Section 21 of this Act, all bidding
documents shall be accompanied by a sworn
SEC. 39. Performance Security. - Prior to the affidavit of the bidder that he or she or any officer
signing of the contract, the winning bidder shall, as of their corporation is not related to the Head of
a measure of guarantee for the faithful the Procuring Entity by consanguinity or affinity up
performance of and compliance with his to the third civil degree. Failure to comply with the
obligations under the contract prepared in aforementioned provision shall be a ground for the
accordance with the Bidding Documents, be automatic disqualification of the bid in
required to post a performance security in such consonance with Section 30 of this Act.
form and amount as specified in the Bidding
Documents. ALTERNATIVE METHODS OF
SEC. 40. Failure to Enter into Contract and Post
PROCUREMENT
Performance Security. - If, for justifiable causes,
the bidder with the Lowest Calculated Responsive SEC. 48. Alternative Methods. - Subject to the
Bid or Highest Rated Responsive Bid fails, refuses prior approval of the Head of the Procuring Entity
or is otherwise unable to enter into contract with or his duly authorized representative, and
the Procuring Entity, or if the bidder fails to post whenever justified by the conditions provided in
the required performance security within the this Act, the Procuring Entity may, in order to
period stipulated in the Bidding Documents, the promote economy and efficiency, resort to any of
BAC shall disqualify the said bidder and shall the following alternative methods of
undertake post-qualification for the next-ranked Procurement:
Lowest Calculated Bid or Highest Rated Bid. This a) Limited Source Bidding, otherwise
procedure shall be repeated until an award is known as Selective Bidding - a
method of Procurement that involves the plant as a whole.
direct invitation to bid by the SEC. 50. Direct Contracting. - Direct Contracting
Procuring Entity from a set of pre- may be resorted to only in any of the following
selected suppliers or consultants with conditions:
known experience and proven
capability relative to the requirements a) Procurement of Goods of proprietary
of a particular contract; nature, which can be obtained only
b) Direct Contracting, otherwise known from the proprietary source, i.e. when
as Single Source Procurement - a patents, trade secrets and copyrights
method of Procurement that does not prohibit others from manufacturing
require elaborate Bidding Documents the same item;
because the supplier is simply asked b) When the Procurement of critical
to submit a price quotation or a pro- components from a specific
forma invoice together with the manufacturer, supplier or distributor
conditions of sale, which offer may be is a condition precedent to hold a
accepted immediately or after some contractor to guarantee its project
negotiations; performance, in accordance with the
c) Repeat Order - a method of provisions of his contract; or,
Procurement that involves a direct c) Those sold by an exclusive dealer or
Procurement of Goods from the manufacturer, which does not have
previous winning bidder, whenever sub-dealers selling at lower prices
there is a need to replenish Goods and for which no suitable substitute
procured under a contract previously can be obtained at more
awarded through Competitive advantageous terms to the
Bidding; Government.
d) Shopping - a method of Procurement SEC. 51. Repeat Order. - When provided for in the
whereby the Procuring Entity simply Annual Procurement Plan, Repeat Order may be
requests for the submission of price allowed wherein the Procuring Entity directly
quotations for readily available off- - procures Goods from the previous winning bidder
shelf Goods or ordinary/regular equi whenever there arises a need to replenish goods
the pment to be procured directly procured under a contract previously awarded
from suppliers of known qualification; through Competitive Bidding, subject to post-
or qualification process prescribed in the Bidding
e) Negotiated Procurement - a method
Documents and provided all the following
of Procurement that may be resorted
conditions are present:
under the extraordinary
circumstances provided for in Section a) The unit price must be equal to or
53 of this Act and other instances that lower than that provided in the
shall be specified in the IRR, whereby original contract;
the Procuring Entity directly b) The repeat order does not result in
negotiates a contract with a splitting of requisitions or purchase
technically, legally and financially orders;
capable supplier, contractor or c) Except in special circumstances
consultant. defined in the IRR, the repeat order
In all instances, the Procuring Entity shall ensure shall be availed of only within six (6)
that the most advantageous price for the months from the date of the Notice to
Government is obtained. Proceed arising from the original
contract; and,
SEC. 49. Limited Source Bidding. - Limited Source d) The repeat order shall not exceed
Bidding may be resorted to only in any of the twenty-five percent (25%) of the
following conditions: quantity of each item of the original
contract.
a) Procurement of highly specialized
SEC. 52. Shopping. - Shopping may be resorted to
types of Goods and Consulting
under any of the following instances:
Services which are known to be
obtainable only from a limited number a) When there is an unforeseen
of sources; or contingency requiring immediate
b) Procurement of major plant purchase: Provided, however, That
components where it is deemed the amount shall not exceed Fifty
advantageous to limit the bidding to Thousand Pesos (P50,000); or
known eligible bidders in order to b) Procurement of ordinary or regular
maintain an optimum and uniform office supplies and equipment not
level of quality and performance of available in the Procurement Service
involving an amount not exceeding service; or,
Two Hundred Fifty Thousand Pesos e) Subject to the guidelines specified in
(P250,000): Provided, however, That the IRR, purchases of Goods from
the Procurement does not result in another agency of the Government,
Splitting of Contracts: Provided, such as the Procurement Service of
further,That at least three (3) price the DBM, which is tasked with a
quotations from bona fide suppliers centralized procurement of
shall be obtained. commonly used Goods for the
The above amounts shall be subject to a periodic government in accordance with
review by the GPPB. For this purpose, the GPPB Letters of Instruction No. 755 and
shall be authorized to increase or decrease the said Executive Order No. 359, series of
amount in order to reflect changes in economic 1989.
conditions and for other justifiable reasons.

SEC. 53. Negotiated Procurement. - Negotiated


Procurement shall be allowed only in the following
instances:

a) In cases of two failed biddings, as


provided in Section 35 hereof;
b) In case of imminent danger to life or
property during a state of calamity, or
when time is of the essence arising
from natural or man-made calamities
or other causes where immediate
action is necessary to prevent
damage to or loss of life or property,
or to restore vital public services,
infrastructure facilities and other
public utilities;
c) Take-over of contracts, which have
been rescinded or terminated for
causes provided for in the contract
and existing laws, where immediate
action is necessary to prevent
damage to or loss of life or property,
or to restore vital public services,
infrastructure facilities and other
public utilities;
d) Where the subject contract is
adjacent or contiguous to an on-going
infrastructure project, as defined in
the IRR: Provided, however, That the
original contract is the result of a
Competitive Bidding; the subject
contract to be negotiated has similar
or related scopes of work; it is within
the contracting capacity of the
contractor; the contractor uses the
same prices or lower unit prices as in
the original contract less mobilization
cost; the amount involved does not
exceed the amount of the ongoing
project; and, the contractor has no
negative slippage: Provided, further,
That negotiations for the
procurement are commenced before
the expiry of the original contract.
Whenever applicable, this principle
shall also govern consultancy
contracts, where the consultants
have unique experience and
expertise to deliver the required