This document summarizes the risks associated with a coffee shop construction project. It outlines the project details, including having one basement and 3 floors to host up to 60 customers. It identifies potential risks such as weather delays, contractor inexperience, and design flaws. It provides a risk breakdown structure with 4 levels that categorizes risks as construction, project, business, and organizational risks. Some high-impact risks identified are contractor, design, and funding risks. The document recommends ways to address these high-impact risks such as selecting an experienced contractor, using specialized construction methods, and having a backup fund. It also discusses general approaches to reacting to risks by avoiding, removing, reducing, or accepting them.
This document summarizes the risks associated with a coffee shop construction project. It outlines the project details, including having one basement and 3 floors to host up to 60 customers. It identifies potential risks such as weather delays, contractor inexperience, and design flaws. It provides a risk breakdown structure with 4 levels that categorizes risks as construction, project, business, and organizational risks. Some high-impact risks identified are contractor, design, and funding risks. The document recommends ways to address these high-impact risks such as selecting an experienced contractor, using specialized construction methods, and having a backup fund. It also discusses general approaches to reacting to risks by avoiding, removing, reducing, or accepting them.
This document summarizes the risks associated with a coffee shop construction project. It outlines the project details, including having one basement and 3 floors to host up to 60 customers. It identifies potential risks such as weather delays, contractor inexperience, and design flaws. It provides a risk breakdown structure with 4 levels that categorizes risks as construction, project, business, and organizational risks. Some high-impact risks identified are contractor, design, and funding risks. The document recommends ways to address these high-impact risks such as selecting an experienced contractor, using specialized construction methods, and having a backup fund. It also discusses general approaches to reacting to risks by avoiding, removing, reducing, or accepting them.
Pusan National University Midterm Exam Spring Semester, 2021 Student: NGUYEN THI HOA PHUONG - 202199119
COFFEE SHOP CONSTRUCTION PROJECT
1. The process of coffee shop construction project
The coffee shop will suit customers who want to experience a special taste of coffee and wonderful space. The coffee shop will construct with one basement and 3 floors with fitted sitting areas and tables and can host up to 60 customers. The basement will be a parking area, the first floor will be the counter to order coffee and payment, and prepare area, kitchen, storage. The second floor is the area for those who want their own space. And the third floor is an area for groups of friends. The coffee shop will also provide customers with free Wi-Fi, books, and entertaining games.
2. The need of risk management in this project
Projects always have a multitude of potential risks, so the fact that some incidents happen without a contingency plan will lead to the project goal being affected. That can delay construction, not enough budgets to build and maintain a project, reduce product quality, disrupt within the organization, and possibly close the coffee shop. 3. The risk breakdown structure (RBS) in this project
4. Checklist based on the risk breakdown structure (RBS) in this
project RBS Level RBS Level 1 RBS Level 2 Example risks 0 The location is not favorable for the Site/ Location construction Construction Weather maybe unseasonable Weather Risk (better or worse than expected) Contractor Lack of experience in construction Design It may have design flaws Competitors Increase in competition Project Risk Resourcing It may be possible to recruit existing subcontract staff permanently Business Risk Strategy becomes less effective Strategic over time
Quality of product Available materials may be of
insufficient quality Organizational Team support Lack of number of staff Poor attendance Poor team communication Customer issues Change in demand Risk Lack of project funding Funding Fund availability does not meet cashflow forecast
Reputation Improved reputation may increase
availability of funds and resources Program/ Other projects may divert key Project portfolio management resources Management Operation Risk management Design may expose weaknesses in existing products or processes The client 's requirement may be Communication misunderstood 5. The high-impact risk factors in this project The high – impact risk factors of this project are contractor risk, design risk and funding risk. 6. My response to these risk My response to the high – impact risk factors: - With the contractor risk: avoid risk by the way selection of a contractor with many years of experiences. - With the design risk: avoid risk by the way design special construction methods suitable for the project requirements. - With the funding risk: reduce risk by the way prepared a backup fund. The way to react to the risk impact - Avoid the risk by completely eliminating a process or activity. - Remove the risk by removing the source of the risk. - Reduce the level of the risk through controls. - Accept the risk.