You are on page 1of 7

Version 1.

0
Enter Date Here

ADD LOGO HERE

Lessons Learned Report


Project id – <Client Name> Implementation

COMPANY NAME
COMPANY ADDRESS
Project id – <Client Name> Implementation Lessons Learned Report

Document Control
Date Author Version Change Reference

Document Owner

Name Department Email Contact #

V1.0 01-Aug-2013 Page i


Project id – <Client Name> Implementation Lessons Learned Report

Table of Contents
1 PURPOSE OF THE LESSONS LEARNED REPORT...............................................................................1
2 PROJECT BACKGROUND...............................................................................................................1
3 EXECUTIVE SUMMARY.................................................................................................................1
3.1 SUCCESS FACTORS ............................................................................................................................... 2
3.2 PRIMARY CHALLENGES ......................................................................................................................... 2
3.3 RECOMMENDATIONS ........................................................................................................................... 2
4 LESSONS LEARNED ......................................................................................................................3

V1.0 01-Aug-2013 Page ii


Project id – <Client Name> Implementation Lessons Learned Report

1 PURPOSE OF THE LESSONS LEARNED REPORT


Throughout each project life cycle, lessons are learned and opportunities for improvement are
discovered. As part of a continuous improvement process, documenting lessons learned helps project
teams discover the root causes of problems that occurred and avoid those problems in later project
stages or future projects. Data for this report was gathered by surveying the project team and
stakeholders.

The objective of this report is to gather all relevant information for better planning of later project
stages and future projects, improving implementation of new projects, and preventing or minimizing
risks for future projects.

Project lessons learned reports are saved on the project’s SharePoint site so that they can be easily
referenced by project managers, project team members, sponsors, and stakeholders.

Ultimately, the goals of the lessons learned exercise are:

 List successes to document what went right


 Document what can be improved upon
 Streamline processes based on this information
 Communicate this information to project management and user community

2 PROJECT BACKGROUND
<Client Name> (<CLIENT NAME>), with the assistance of Oracle Consulting, reviewed and analyzed the
current Human Resource (HR) Recruiting and Onboarding processes along with best practices to
implement a future state of the Recruiting and Onboarding process to support <CLIENT NAME>’s current
and growing needs. Oracle <Client Name> was implemented to support this process and integrations
were developed to support and automate data sharing between Oracle <Client Name> and ORACLE HR.

3 EXECUTIVE SUMMARY
Effectively communicating across various cultures, time zones, and processes/tools is a challenge and
<Client Name> absolutely critical to the success of the project implementation.

 The project manager should connect stakeholders across the extended team to demonstrate a
clear commitment to building strong relationships and a common goal for project success.
 Project documents and key deliverables should be created, distributed, reviewed, updated and
approved in different project phases accordingly.
 The project manager has full responsibility to verify that the project moves in the right direction
by building a team that supports local talent working jointly with the corporate team.
 Key users must be involved and committed throughout the project lifecycle.

Page 1
Project id – <Client Name> Implementation Lessons Learned Report

3.1 SUCCESS FACTORS


 Strong support during the transition phase helped educate and prepare users for post go-live
activities.
 Scope changes from the Chinese government were effectively managed.
 Local communication and collaboration was strong and thorough.
 A SharePoint site was created to centrally manage and store data.
 Team resources were knowledgeable and skilled.
 User testing was well planned and executed.
 High quality deliverables were distributed.
 Time spent with local and corporate resources were essential to the design and ultimate success
of this project. Very few issues (relative to the size of the project) were encountered.

3.2 PRIMARY CHALLENGES


 Effective communication with Corporate
 Project documentation management
 Resource commitment
 Project management

3.3 RECOMMENDATIONS
 Encourage strong communication between team members who are globally dispersed.
 User participation should be consistent throughout the project lifecycle.
 Manage scope creep, risk and other issues timely and effectively.

Page 2
Project id – <Client Name> Implementation Lessons Learned Report

4 LESSONS LEARNED
The Categories below were considered during the Lessons Learned Session.

 Integration Management  Procurement Management  Change Control/Change Requests


 Scope Management  Roles and Responsibilities  Knowledge Transition
 Time Management  Project Methodology  Project Reporting
 Cost Management  Architecture/Technical Solution  Deployment
 Quality Management  Training
 Human Resource Management  Testing / QA
 Communication Management
 Risk Management

Lessons Learned Log


Impact on
ID Category Situation Description Analysis or Cause Improvement Recommendations
Project
LL-001 Communication/Risk Mgmt Feedback from Security team Security impact on The analysis that was Ensure that the Security department is
needed at project start. project delayed. provided by Security was included in project initiation and design to
delayed because they were resolve any security related issues that must
not involved in the project be addressed from the beginning. This
from the start. participation can reduce risk to the project
and prevent significant changes to the
project after it has started.
LL-002 Communication/Risk Mgmt Resources from Career Potential risk to the Delay in project timeline Additional resources impacted for this
Site/Marketing and Web project and possible and risk to project’s timely project should be identified early and
Design should be engaged effect on project success. included throughout the project. Their
from project start. scope and plan with deliverables should be included in the
late involvement. project plan and timeline to ensure effective
project delivery.
LL-003 Communications Mgmt Communication plans and These plans were Miscommunication Develop communications and training plans
training plans were created not assigned in a occurred and delivery of and assign ownership for development and
late in the project. timely fashion. documents was untimely. execution.

Page 3
Project id – <Client Name> Implementation Lessons Learned Report

Lessons Learned Log


Impact on
ID Category Situation Description Analysis or Cause Improvement Recommendations
Project
LL-004 Time Mgmt Interface testing/completion Delay in project Users did not have enough Determine the correct amount of time for
was not given adequate time. schedule. time to thoroughly test and interface testing/ completion – ensure time
complete UAT. is accounted for in project timeline.
LL-005 Time Mgmt Project timeline dates were Delay in Strict dates were not set or Set project update milestones and pre-set
missed implementation adhered to accommodate dates / time for updates.
changes in scope or
changes is deliverable due
dates.
LL-007 Time Mgmt Users were not aware of time User’s schedules Impact to resource Better prepare for the required time needed
required for on-going and go- were impacted scheduling. for ongoing support (HR / IT) for post go live
live support. negatively. support.
LL-008 Procurement Mgmt Experienced consultants were Errors and issues Consultants were not part Hire a consultant in the future to provide
needed during the were not resolved in of the project team. guidance and expertise for rollouts.
implementation. a timely manner.
LL-009 Quality Mgmt/Knowledge Product features were Setup could have The impact of the OLF Fully explain the impact of all features that
Transition implemented without in been designed and (organization, location, are to be implemented so users have a
depth knowledge of their implemented more function) was not clearly strong knowledge of their effects.
consequences. effectively. explained and may have led
to inadequate setup and in
addition contributed to
confusion on the project.
LL-010 Communication Key resources should be Lack of knowledge Key resource participation Ensure that all appropriate team members
Mgmt/Knowledge Transition informed and engaged in transferred to key was needed during parts of are involved with process mapping sessions
activities that affect significant individuals. the project which may have so that they can fully understand their
parts of the project. let to miscommunication impact.
and confusion for users.
LL-011 Roles and The appropriate resources did Knowledge transfer Resources did not have Train applicable users on all functionality as
Responsibilities/Knowledge not have access to key was not adequately access to the correct it pertains to their roles and responsibilities
Transition functionality during testing. completed. permissions/responsibilities prior to go-live.
which reduced the
effectiveness of the team.
LL-012 Roles and <Client Name> Consultant was Users are not Users know little about Users should have been knowledgeable and
Responsibilities/Knowledge the only one fully informed knowledgeable creating or changing had the ability to perform all setups in
Transition about setup and performed about setups and processes in transitions. production as applicable.
them in test and production. how they impact
functionality.

Page 4

You might also like