Cost Breakup for toilet works of PIFD

overheads
/profit/ris
Description Quantity Unit Rate Amount k cost tax 13%
Demolition of 4 x toilets including
floor and cavtiy walls to lay the pipe 4 Nos 4000 16000 18400 20792
Removal of debris 4 3500 14000 16100 18193
floor tile 4x toilets 168 SFT 560 94080 108192 122257
concrete in toiletsupto 1.5 feet 84 CFT 620 52080 59892 67677.96
supplying and fixing of seats 4 5800 23200 26680 30148.4
sewer line pipes and accessories8 x
p traps, 8 elbows, 4x t's and 4 inch
pipe popular lengths 3x, vent covel 1 45920 45920 52808 59673.04
laying of PPRC pipes in cluding
accessories 1 17250 17250 19837.5 22416.38
sealing of existing P traps to prevent
the seapage 8 x with epoxy 1 16000 16000 18400 20792
lifting up the doors including
alteration of doors ony, repairing
and paint exlusive of accessories as
per requirements 1 19000 19000 21850 24690.5
297530 342159.5 386640.2