Procedure
Contents
1.0 PROCEDURE 3
2.0 RESPONSIBILITIES 4
3.0 DEFINITIONS 4
1.0 PROCEDURE
NOTES:
(1) When a technical question, deviation, or concession is generated the originator must provide a definitive
statement in sufficient detail to enable those not directly involved with the onsite problem to understand the
query and its implications. Sketches and/or diagrams are to be included where appropriate.
2.0 RESPONSIBILITIES
2.1 CIR Initiator
Ensuring that all queries are prepared in accordance with this procedure.
Ensure CIR raised accurately and all boxes filled in.
Proposing suitable solutions to queries
2.2 CIR Coordinator
Allocation the correct sequential numbers.
Issue registered CIR to Operation management for review and respond
Ensure data base updated accordingly CIR Status
Distribute CIR Status report weekly in according with distribution matrix
Ensuring all affected documentation and drawings are revised and all approved CIR are
incorporated.
2.3 Operations Management
Assess change, ranking CIR.
Approval or reject for further action.
Assign a CIR action person.
Answering the CIR within the time limit required with a positive reply.
3.0 DEFINITIONS
Flowchart Symbols
Safety
Environmental
Maintenance
Construction
Other
Attachment:
Item # Document Description Document Number Rev