50208
CONFIDENTIAL
by
CONFIDENTIAL
This document is made available subject to the condition that the recipient will neither use nor disclose the contents except as agreed in
writing with the copyright owner. Copyright is vested in Shell Global Solutions International B.V., The Hague.
Neither the whole nor any part of this document may be reproduced or distributed in any form or by any means (electronic, mechanical,
reprographic, recording or otherwise) without the prior written consent of the copyright owner.
Shell Global Solutions is a trading style used by a network of technology companies of the Shell Group.
CONFIDENTIAL 1 GS.08.50208
Document History
Summary
The SMDS JV intends to implement a fast track project to expand their wax plant production
at their premises in Bintulu.
* Design is 300 t/d to take into account losses, off-specs and downtime
The decision at the end of scouting is to build the new wax plant with new granulation
technology and to re-use the moulder for the slabbing line. It is also decided that the new
warehouse will be located off-site, and is thus removed from the scope of this wax plant
project. Basic Design Package (BDP) Rev0 was finalised and issued on this basis.
After Value Engineering Review, Decision Executive (DE) of SMDS Decision Review Board
(DRB) made decision to build the new wax plant with new granulation technology and to
expand slabbing capacity with new moulder. BDP Rev0 was revised to Rev1.
The project will start with a Scouting phase, followed by a Basic Design Package (BDP) to be
prepared during a combined FED1/FED2 phase and will further developed into a Basic
Design & Engineering Package (BDEP) in the FEED phase. Final Investment Decision (FID)
is to be requested prior to completing FEED phase, following the work-up of the +/-15%
estimate to a more accurate cost by including the vendor +/-10% estimates. The project
execution will follow. The project will be closed out with a Post Implementation Review (PIR).
The EPC phase will be fast-tracked to aim for the unit to be on stream as early as possible.
In order to meet a tight schedule, the project will take advantage of the con-current projects
underway at SMDS under the X-VM title, by utilising the synergy with regards to contracting
strategy and resources (both contractors and Shell Global Solutions).
Table of Contents
Document History .....................................................................................................................................1
Summary ..................................................................................................................................................2
1. Project Premises ......................................................................................................................4
1.1 Outline of Investment Proposal – Scope ..................................................................................4
1.2 Objectives .................................................................................................................................7
1.2.1 Main Objectives ..................................................................................................................7
1.2.2 Schedule/Capex Objectives ................................................................................................7
1.2.3 Opportunity Statement ........................................................................................................7
1.2.4 Value Drivers and Critical Success Factors........................................................................7
1.2.5 Business expectations ........................................................................................................8
1.3 Priorities ...................................................................................................................................8
1.4 Customer / Operator ................................................................................................................8
1.4.1 Stakeholder identification and mapping ..............................................................................8
1.4.2 Operating and maintenance practices ................................................................................9
2. Key Issues, Risks .................................................................................................................. 10
2.1 Main Issues, Investment Origin ............................................................................................. 10
2.1.1 Boundaries and Givens.................................................................................................... 10
2.1.2 Synergy opportunities: ..................................................................................................... 10
2.2 Risk Identification .................................................................................................................. 10
2.2.1 Key Risk and Opportunities ............................................................................................. 10
2.2.2 Risk framework ................................................................................................................ 10
2.2.3 Show stoppers ................................................................................................................. 11
2.3 Authority Engineering ............................................................................................................ 11
2.4 Main Changes From Previous Revisions .............................................................................. 13
3. Strategic Fit And Business Case........................................................................................... 14
3.1 Feedstock, Product And Utilities ........................................................................................... 14
3.2 Economics ............................................................................................................................. 14
4. Project Management – Organisation .................................................................................... 15
4.1 Responsibilities ..................................................................................................................... 15
4.1.1 SMDS ............................................................................................................................... 15
4.1.2 Shell Global Solutions ...................................................................................................... 16
4.2 Project Site Considerations ................................................................................................... 17
4.2.1 Synergy effects with adjacent and/or existing facilities .................................................... 17
4.2.2 General facilities requirements ........................................................................................ 17
4.3 Project Overall Schedule ....................................................................................................... 17
4.4 Project Phases ...................................................................................................................... 18
4.4.1 Project Design .................................................................................................................. 18
4.4.2 Project Construction ......................................................................................................... 18
4.4.3 Project Commissioning and Start-Up ............................................................................... 19
5. Technology ............................................................................................................................ 20
5.1 Technologies ......................................................................................................................... 20
5.1.1 Technology selection ....................................................................................................... 20
5.2 Capacities, Yields, Feed And Product Quality ...................................................................... 22
5.2.1 Nameplate capacity ......................................................................................................... 22
5.2.2 Proposed availability ........................................................................................................ 22
5.2.3 Run length ........................................................................................................................ 22
5.2.4 Turndown requirements ................................................................................................... 22
5.2.5 Feedslate and indication min and max quality ................................................................. 22
5.2.6 Product slate and quality.................................................................................................. 23
6. HSE and Sustainable Development ...................................................................................... 24
6.1 Identification of Key HSE And SD Issues ............................................................................. 24
Bibliographic Information ....................................................................................................................... 25
Report distribution.................................................................................................................................. 26
CONFIDENTIAL 4 GS.08.50208
1. Project Premises
1.1 Outline of Investment Proposal – Scope
The Wax Plant Expansion & Rejuvenation project aims to:
* Design is 300 t/d to take into account losses, off-specs and downtime
The plant consists of 2 main processing lines: hard-wax (SX100 and SX105 solidified to wax
granules) and soft-wax (SX55R, SX60M, SX70 solidified to wax slabs), including the solids
and materials handling for each line.
The decision at the end of scouting is to build the new wax plant with new granulation
technology and to re-use the moulder for the slabbing line. It is also decided that the new
warehouse will be located off-site, and is thus removed from the scope of this wax plant
project. Basic Design Package (BDP) Rev0 was finalised and issued on this basis.
After Value Engineering Review, Decision Executive (DE) of SMDS Decision Review Board
(DRB) made decision to build the new wax plant with new granulation technology and to
expand slabbing capacity with new moulder. BDP Rev0 was revised to Rev1.
The project scope also includes debottlenecking of upstream U-5600 to realise 270t/day to
the new wax plant. This detailed scope is defined during FED1/FED2 process modelling and
a plant test run confirmed that there are no kinetic constraints, only hydraulic. Thus the scope
includes changing of pumps and increase line-size.
New feed tanks will also be required to enable intermediate storage (and product sampling
prior to solidification) for the hard wax (currently the plant in operating in pump and run
mode). It is decided to use existing T-8412 (2,000-tonne) and to swap existing hot slops tank
T-7502 as T-8418 (2,000-tonne). Therefore another slops tank is required, and it is proposed
to build a bigger slops tank equivalent to T-8413 (5,500-tonne).
See simplified process flow scheme below, which illustrates new and existing units.
The warehouse review and other supply-chain improvements are out of the scope of the
project; subject of separate reviews that will progress in parallel. These reviews need to
integrate the outcome of the wax plant scope definition and plot plan considerations.
CONFIDENTIAL 6 GS.08.50208
SX 30
SX 50
U-8500 (NEW)
C-5401
PALLETISING
& FILM
GRANULATION/ WRAPPING
WFE STAGE II 4
WFE STAGE III
(5-6)
U-5400 (7) PASTILLATION LINE
U-5400
BL BL 3
T-8412
SX 100
U-5600 Note 2
Note 1
P-841X
BL
BL BL
P-841X
P-750X STREAM 1 2 3 4
PHASE L S L S
TOTAL FLOW t/sd 81 81 180 180
Notes TOTAL FLOW kg/s 0.94 0.94 2.1 2.1
MW(V) or d15/4 (L) 0.812 - 0.824 -
1. Unit 5600 capacity to be increased from 225 t/d to 270 t/ d (BULK)DENSITY act kg/m3 762 884 765 (572)
TEMPERATURE 0C 90 35 125 35
2. It is proposed to utilize the existing tanks T-8412 and T-7502 as batching tanks PRESSURE bara 3.0 1.0 3.0 1.0
for the U8500 granulation / pastillation unit.
A new slop tank, T-841X with capacity equal to the existing tank T-8413, to be included in the scope
LEGEND
EXISITNG
NEW
S Page 1
1.2 Objectives
At the same time, it is also clear that several work processes, for example automation and
contingency processes, as well as HSE and asset integrity aspects such as reducing /
eliminating confined space work, can be substantially improved.
Fast track schedule - Project Execution strategy to look for ways to bring
project online as early as possible
- Determining long lead time equipment and approaching
vendors and contractors early
- Ensuring sufficient resources (internally and external
consultants, e.g. Shell Global Solutions, contractors)
Granulation capacity - Although feed is 270 t/d on average, the capacity of the
reaches a sustainable granulators and packaging etc. should exceed 270 t/d to
output of 270 t/d compensate for any temporary downtime (design is 300
t/d)
- Designing manual contingency procedures in case of
equipment failure / malfunction
- Debottlenecking of U-5600
Slabbing capacity reaches - Again, to ensure that production can reach target
140 t/d values, contingency procedures should be designed in,
and bottlenecks eliminated by having some spare
capacity
Improvement / Reduction - The wax plant fire fighting and ammonia systems need
in HSE / AI-PS risk to major upgrades to meet current Group / Industry
ALARP requirements
- Remove of manual operations as far as
possible/feasible
1.3 Priorities
Although both slabbing and granulation capacities require additional capacity as soon as
possible, if it is feasible, the capacities may be added in phases so as to meet demand for a
few years.
It has been identified that the existing upstream unit (U-5600) needs to be de-bottlenecked to
supply the required feed capacity to meet the desired granulation capacity of the project. It is
to be further explored/defined during Define (FEED) how to implement the necessary unit
upgrades and tie-ins etc (e.g. via unit shutdowns or hot-tappings).
It is confirmed that the existing SMDS utilities are sufficient to cope with the new project.
Shell 72%
Mitsubishi 14%
Petronas 7%
Sarawak Government 7%
Refer the project risk and opportunity register (kept live and updated):
CONFIDENTIAL 11 GS.08.50208
https://sww-knowledge.shell.com/knowhow/livelink.exe?func=ll&objId=73614721&objAction=browse
DOSH (Kuching/KL) Safety - Certificate of First engagement to explain the Perunding Timur Q2 2009 SMDS, SGS(M),
fitness project, how many equipment items, (Kuching/KL) EPCm Contractor
etc (if required) and Consultant
Notification for construction - Update Perunding Timur Q2 2009 SMDS, SGS(M),
(send in Form E) (Kuching/KL) EPCm Contractor
and Consultant
Certified Machinery Design Approval for pressure vessels TBD Q3 2009 EPCm Contractor
and Consultant
Commissioning & Certificate of fitness for certified Perunding Timur Q3 2010 SMDS, SGS(M),
Operation of Certified machinery (Kuching/KL) EPCm Contractor
Machinery and Consultant
CIMAH report TBD TBD TBD SMDS, SGS(M),
EPCm Contractor
and Consultant
BDA (Bintulu) Local authority - building, Approval for early commencement Perunding Timur Q2 2009 SMDS, SGS(M),
sewers, overall of works EPCm Contrator and
construction - certificate Consultant
of fitness (based on
Approval for building plans (Wax Perunding Timur Q2 2009 EPCm Contractor
DOSH, DOE)
Plant) and Consultant
Certificate of Fitness for building Perunding Timur Q3 2010 EPCm Contractor
and Consultant
BOMBA (Kuching/KL) Fire - certificate of fitness Approval for modification/additional Multipline Q2 2009 EPCm Contractor
fire fighting equipment (if any) Associates and Consultant
DOE Environment - Approval Internal environmental impact and N/A Q2 2009 SMDS
for Operation aspect assessment to be carried out
by SGS(M). If no impact, submission
to DOE is not required
Customs Dept Warehouse License Approval for project N/A Q2 2009 SMDS
MIDA Tax exemption Approval for tax exemption on N/A Q2 2009 SMDS, SGS(M)
imported equipment
CIDB Levy 0.125% Construction contractor to pay levy N/A Award of Construction
Construction Contractor
Contract
SESCO Electrical Construction of new electrical N/A TBD SMDS, SGS(M) and
substation (possibly to be done by EPCm Contractor
Wax Plant Project)
CONFIDENTIAL 13 GS.08.50208
BDP Rev0 is revised to BDP Rev1 to include following findings from Value Engineering
Review and decision by SMDS DRB:
Slabbing capacity expanded from 81t/d to 140t/d for all grades of products
Air Compressor
Use Standard Industry package for non-hazardous areas instead of DEP standards for
hydrocarbon environment.
Electrical and Power supply
The electrical power supply system designed to fit for purpose, but without impacting
functionality.
Instrumentation and DCS
Leverage on the vendor packages control systems, reducing the number of I/Os and the DCS
size.
Others
Process simplification of the systems resulting in;
Elimination of the Lump crusher, the rebagging system, top and bottom sheets for the pallets
and the common spare pumps for the feed preparation unit (Slabber).
Reuse the existing remelter, but use MP Steam as the heat medium.
See Value Engineering Review TOR, Value Engineering Options Matrix and Wax Project
Results, below
https://sww-knowledge.shell.com/knowhow/livelink.exe/Open/96694848
The schedule is updated to accelerate the project by taking FID in early FEED phase.
Utilities Power
Cooling / refrigerant (R134a)
LP Steam
Instrument Air
Plant air
Inhibited service water - BFW (jacket and tempered water)
Potable water
Firewater
Flushing oil
Nitrogen
Effluent treatment (COCS)
3.2 Economics
Economic data are considered confidential to the SMDS(M) JV and are thus not included in
this PPD.
CONFIDENTIAL 15 GS.08.50208
4.1 Responsibilities
The current responsibilities (scouting and FED1/FED2 phases) are listed below.
Refer to the project execution plan for a more detailed breakdown of roles and
responsibilities between SMDS, SGS(M) and engineering contract (JGC Singapore).
4.1.1 SMDS
SMDS govern the project through DRBs (decision review boards) and decide on whether the
project is to proceed to the next phase. The SMDS project manager coordinates the project
development between SMDS and Shell Global Solutions.
CONFIDENTIAL 16 GS.08.50208
DRB Members:
From Define (FEED) phase SGS(M) will take on role as PMC and engineering contractor,
JGC Singapore, will deliver the phase and BDEP documentation.
https://sww-knowledge.shell.com/knowhow/livelink.exe/Open/101917575
See also the BDEP Cost Estimation Schedule submitted by engineering contractor.
https://sww-knowledge.shell.com/knowhow/livelink.exe/Open/101975901
The project will start with a scouting phase, followed by a Basic Design Package (BDP) to be
prepared during a combined FED1/FED2 phase and will further developed into a Basic
Design & Engineering Package (BDEP) in the FEED phase. Final Investment Decision (FID)
is to be requested early in FEED phase to allow the detailed engineering of long lead items to
be carried out as these would constitute the critical path, following the work-up of the +/-15%
estimate to a more accurate cost by including the vendor +/-10% estimates. The project
execution will follow. The project will be closed out with a Post Implementation Review (PIR).
Shell Global Solutions will carry out the initial scouting phase work in-house whilst engaging
with vendors, and follow-on with Front End development FED1/FED2 phases jointly with
vendor and FEED with contractor.
Shell Global Solutions will act as Project Management Consultant (PMC) and technical
advisor from FEED until RFSU.
5. Technology
5.1 Technologies
For a full description of the technology selection refer to Key Investigation report (Scouting
phase) GS.08.50210:
https://sww-
knowledge.shell.com/knowhow/livelink.exe?func=ll&objId=73609600&objAction=browse
The summary of the vendor packages for the granulation line is illustrated below:
CONFIDENTIAL 21 GS.08.50208
Granulation Granulation
unit vendor
package
conveying
Screening
Solids Note:
handling
vendor
2 lines - for
package bagging and also
conveying re-bagging
Silos
FIBC
conveying bagging
FFS
bagging
Materials handling
vendor package
(consortium with
Palletising FFS vendor)
conveying
Stretch
Hood
For the slabbing line, the moulder will be new will capacity of 140t/d, and the materials
handling will be under the same vendor as for the granulation line. The lesson’s learnt from
another operating plant (Nippon Seiro) in Japan) will be taken during a scheduled visit to their
operations.
Additionally there are vendor packages for a chiller unit, the slabbing cartoniser.
The stretch hood will be shared between granulation and slabbing lines.
CONFIDENTIAL 22 GS.08.50208
https://sww-knowledge.shell.com/knowhow/livelink.exe/Open/96700653
With SMDS decision to expand Slabbing capacity from 81 t/d to 140t/d for all grades of
product and other output from Value Engineering Review will require further modelling in
Define Phase.
However, only some systems in the wax plant require DOSH inspection. If utilities are
available and there is stock in the tanks, then the plant can granulate and slab during parts of
the SMDS turnaround.
However, for certain scenarios i.e. start-up when the tanks are empty, the granulation units
can run to 50% capacity, i.e. 150 t/day.
0
Melting Point, C 48.8 TBD TBD 71.3 108 TBD
Density – Liquid D 15/4 0.75 0.812 0.824
3 0 TBD TBD TBD
-Solid Kg/m (25 C) 881 884 948
Liquid Dyn.Viscosity 1.8 4.9 <20
-3 2 0 TBD TBD TBD
‘ 10 Ns/m ( C) 90 90 120
0
Specific Heat, KJ/Kg C
-Liquid 2.3 TBD TBD 2.40 2.55 TBD
-Solid 2.2 2.25 2.30
0
Thermal Conductivity, W/m C
0.145 TBD TBD 0.14 0.14 TBD
(for liquid and solid)
Heat of Fusion, KJ/Kg 242.4 TBD TBD 264 264 TBD
The project also aims to improve HSE aspects of the existing operation and processes,
particularly any manual contingency processes and workspace issues.
The other key issue is the ammonia inventory and the associated refrigeration systems full of
pressurised ammonia. The latest Fire Safety Review1 highlighted improvements to the
existing arrangement would be required in order to reduce the risk of personnel exposure to
ammonia to ALARP. The current dependency for personnel intervention needs be improved.
For the new build plant, the new refrigeration should be designed as per DEPs, and the
preference is to eliminate ammonia and any toxic or flammable refrigerants. The HSE risks of
the refrigeration system will be assessed as part of the Hazard and Effect Management
Process (HEMP).
HSE/SD risk identification was made during the HAZID in FED1/FED2 phase and captured in
the HSE register:
https://sww-knowledge.shell.com/knowhow/livelink.exe?func=ll&objId=73609621&objAction=browse
1
Refer to SMDS Bintulu Fire Safety Review report (GS.07.51298)
CONFIDENTIAL 25 GS.08.50208
Bibliographic Information
This report has been classified as Confidential and is not subject to US Export
Control regulations.
Report distribution
This report can be freely shared with all Shell Global Solutions employees.