Professional Documents
Culture Documents
However, they are generally used only for wind energy first stage of the Zhangbei national demonstration project is
storage or solar energy storage respectively. Although the shown in Fig. 1. As can be seen, the wind/PV/BESS hybrid
MW power level of BESS is generally high, the MWh power generation system consists of a 100 MW wind farm,
capacity level is relatively low. For example, the BESS of a 40 MW PV power station, a 14 MW/63 MWh lithium-
Japan Hokkaido wind farm incorporates a vanadium redox ion BESS, a 2 MW/8 MWh redox flow BESS, and a power
flow BESS with the power capacity 4 MW/6 MWh and is grid. The wind farm, PV power station and BESS are
mainly for smoothing the wind power output fluctuations connected to the power grid through transformers. Specif-
[18–20]. The Japan Aomori Six Village energy storage ically, the 14 MW/63 MWh lithium-ion BESS includes
power station utilizes a sodium sulfur BESS with the power nine units (C001 to C009) in parallel (as shown in Table 1),
capacity 34 MW, mainly for smoothing the wind power each connected to a 35 kV AC bus by means of a 380 V/
fluctuations [18, 21]. The Texas wind farm storage power 35 kV transformer unit. The topology of each lithium-ion
station uses an advanced lead-acid battery (36 MW/ BESS connected to the power grid is shown in Fig. 2. As
9 MWh), principally for frequency regulation, energy indicated, each BESS contains multiple lithium-ion battery
transfer and peak load shaving [18, 22]. The West Virginia energy storage units in parallel, each unit consisting of a
Elkins wind farm energy storage power station incorporates 500 kW power converter system (PCS) and multiple
a lithium-ion battery (32 MW/8 MWh) which is for fre- lithium-ion battery packs. Currently the large lithium-ion
quency regulation and output climbing control [18, 23]. electrochemical energy storage station contains 46 sets of
In China, there are a number of large-scale BESS demon- PCS and around 275000 lithium battery single cells. The
stration projects currently underway. For example, in Zhang- lithium-ion battery energy storage unit can be controlled by
bei, a large-scale BESS, which includes a 14 MW/63 MWh using the PCS for management of start/stop and charging/
lithium-ion BESS and a 2 MW/8 MWh vanadium redox flow discharging functions, etc.
BESS, has been put into operation (flow BESS is still in the site The redox flow BESS, meanwhile, includes two sets of
commissioning stage). It is part of a national wind, PV, storage 1 MW/4 MWh redox flow sub-BESS (C010 to C011) in
and transmission demonstration project. The purpose of this parallel, each connected to a 35 kV AC bus by means of a
project is to smooth the wind and PV power fluctuations and 380 V/35 kV transformer unit.
trace the scheduled power outputs to grid. Further, Guodian
Longyuan Woniushi wind farm energy storage power station,
using total vanadium flow batteries (5 MW/10 MWh), is 3 Key technologies for large battery energy
adopted mainly to resolve wind-curtailment and brownout storage systems
issues arising at the Woniushi wind farm. The BESS of
Southern Power Grid Shenzhen Baoqing adopted the lithium- The key BESS technologies includes system integration
ion battery (planned capacity is 10 MW and completed and access, monitoring and control, energy management
capacity is 4 MW/16 MWh) to achieve peak load shaving, and application, and other aspects.
frequency regulation, and voltage regulation, etc.
In this paper, the system configuration of a national 3.1 Structure and function of supervisory control &
renewable generation demonstration project, combining a data acquisition system for BESS
large-scale BESS with wind farm and PV power station all
coupled to a power transmission system, is introduced, and The supervisory control and data acquisition (SCADA)
the key technologies and operational status of this BESS system is the core component of battery energy storage
are presented. Additionally, the technical benefits of such a power station, by which centralized access, real-time con-
large-scale BESS in dealing with power fluctuation and trol and operation scheduling are achieved. More specifi-
intermittence issues resulting from grid connection of cally, it is utilized to send information to and accept
large-scale renewable generation, and for improvement of information from BESS equipment such as local control
operation characteristics of transmission grid, are discussed monitoring system and PCS, as well as to conduct real-time
with relevant case studies. monitoring and carry out control management functions.
The SCADA structure proposed in this paper is illus-
trated in Fig. 3. As can be seen, a hierarchical distributed
2 Large battery energy storage station control scheme for BESS mainly includes three layers,
in Zhangbei namely, the master station layer, the local control and
monitoring system (CMS) layer, and the device layer. The
The Zhangbei energy storage power station is the largest master station layer includes servers, workstations, and
multi-type electrochemical energy storage station in China coordinated controllers. In the local CMS layer, there are
so far. The topology of the 16 MW/71 MWh BESS in the eleven local controllers, and each is used to manage four or
Optimal control and management of a large-scale battery energy storage system to mitigate… 595
Transformer 35 kV AC bus
Wind farm
Transformer
PV power station
Transformer
35 kV AC bus
380 V AC
2 MW 2 MW 2 MW 2 MW 2 MW 1 MW 1 MW 1 MW 1 MW 1 MW 1 MW
li-ion li-ion li-ion li-ion li-ion li-ion li-ion li-ion li-ion flow flow
BESS BESS BESS BESS BESS BESS BESS BESS BESS BESS BESS
01 02 03 04 05 06 07 08 09 010 011
six PCS devices. In the device layer, there are PCS, battery and is realized by means of a dual network communication
devices, and power distribution cabinets. system combining a monitoring network with a control
Between these layers, information transmission is network, as shown in Table 2. The functions of each layer
implemented via 100 Mbit/1000 Mbit fiber ring networks, are shown as follows.
596 Xiangjun LI et al.
Coordinated controller
...
PCS PCS
... PCS PCS PCS
... PCS
...
...
Supplier Supplier
local local
monitoring monitoring
system system
#1 #2 #L #1 #2
unit of ... unit of ... unit#Lof
...
CAN bus
CAN bus
The local controllers monitors the BESS in real-time by BMU #3 Battery pack #3 BMU #3 Battery pack #3
using the VxWorks embedded operating system. Addi-
tionally, at the local CMS layer, the PCS, battery and BMU #4 Battery pack #4 BMU #4 Battery pack #4
Firstly, the work specification of the energy manage- Fig. 5 EMS structure for BESS
ment system (EMS) for large-scale BESS has been
designed as shown in Fig. 5. In the charge status, power is The main-EMS, according to current collection status
less than zero; and in the discharge status, power is greater information of each transformer unit, calculates the power
than zero. The PCS is used to achieve the power and commands in real-time based on BESSs’ total power
energy balance. The principles of the energy management demand, so as to prevent excess charge or excess discharge
supervision, in this paper, have been proposed according to of the batteries. In accordance with the total power allo-
the following objectives and constraints. cation strategy for a transformer unit, the sub-EMS allo-
1) Objectives: To meet the real-time power requirement; cates the transformer unit demand power to each PCS unit
To ensure the energy balance and availability. according to the status of PCS unit. The status parameters
2) Constraints: The limit of allowable maximum charge/ include the allowable maximum charge/discharge power of
discharge power; The limit of the charge/discharge the PCS unit, and the state of charge (SOC), etc. And then
capacity. real-time demand power is guaranteed to prevent over-
In this paper, a two level EMS has been proposed. One charge/discharge of the battery, ensuring the safety and
is main-EMS layer for transformer units in the station reliability of the transformer unit. The flow chart of the
control layer. The other is sub-EMS layer for PCS units in proposed EMS algorithm is shown in Fig. 6 and that is
the local CMS layer. described in detail in the following sections respectively.
598 Xiangjun LI et al.
Start
Main-EMS layer:
Obtain total active power demand of BESS, Pall − BESS Power allocation based on Pall − BESS
Y Y
Calculate target power of each transformer unit i Calculate target power of each transformer unit i
uTUi SOCTUi uTUi SODTUi
PTUi = S Pall − BESS PTUi = S Pall − BESS
Σ (u TUi SOCTUi )
where i=1,…,S
Σ (u TUi SODTUi )
i =1 i =1 where i=1,…,S
i =1 i =1
N N
i ≤ S? i ≤ S?
i = i +1 Y Y i = i +1
Y Y
Determine active power demand of each transformer unit, PTUi where i=1,…,S
Y Y
Calculate target power of each PCS unit k Calculate target power of each PCS unit k
based on power of each transformer unit i based on power of each transformer unit i
SOCk SODk
Pk = L PTUi Pk = L PTUi
Σk =1 SOCk where k=1,…,L Σk =1
SODk where k=1,…,L
i=1,…,S i=1,…,S
k =1 k =1
N N
k ≤ L? k ≤ L?
k = k +1 Y Y k = k +1
N N
Pk > Pˆkdisch ? Pk > Pˆkch ?
Y Y
Recalculate target power of each PCS unit k Recalculate target power of each PCS unit k
based on power of each transformer unit i based on power of each transformer unit i
u Pˆ disch u Pˆ ch
Pk = L k k PTUi Pk = L k k PTUi
Σ
k =1
(
uk Pˆkdisch )
where k=1, …,L Σ (
uk Pˆkch )
where k=1,…,L
i=1,…,S k =1 i=1,…,S
End
Fig. 6 Flow chart of the proposed EMS algorithm for active power control
Optimal control and management of a large-scale battery energy storage system to mitigate… 599
power is absorbed and wind power curtailment is reduced, 4.2 Reactive power compensation
by implementing the ‘‘tracking power schedule output’’
mode at the specified time. Figure 10 shows the test result for tracking reactive
Figure 7 shows the operation status for tracking power power plan by using BESS. The blue curve is target and the
generation plan of 80 MW. By implementing the ‘‘tracking red curve is actual reactive power.
power schedule output’’ mode in the EMS, the deviation Based on the reactive power demand instructions sent
between the actual wind/PV power and the plan is effec- by the master station, the total reactive power of the
tively reduced, and the wind/PV/BESS hybrid system BESS can effectively follow the dispatched reactive
output power is restricted within the planned power range, power and its response speed meets the application
thus meeting the ‘‘tracking power schedule output’’ mode’s requirements for voltage regulation. This reactive power
requirements. Figure 8 shows power profiles of each compensatory utility has been applied in practice to the
transformer unit and total BESS. As shown in Fig. 8, olive 16 MW BESS.
curve is power of total BESS. Larger version of each
transformer unit power is shown in Fig. 9.
By implementing EMS, the power of each transformer 5 Technical benefits of system
unit is effectively determined according to the allowable
charging and discharging power ability and SOC. In the The technical benefits of the BESS are reflected in many
demonstration project, the allowable range of the battery aspects.
SOC is usually set between 20% and 80%. Under this 1) Improvement of friendliness of renewable energy
mode, the depth of discharge of the energy storage system generation connected to the grid: The power fluctuations of
is generally within 60%. renewable generation (such as wind and PV generations)
1000
Power (MW)
60
20 -1000
BESS power
0 -2000
-20 -3000
12:00:00 12:57:36 13:55:12 14:52:48 15:50:24 16:48:00 12:00:00 12:57:36 13:55:12 14:52:48 15:50:24 16:48:00
12:28:48 13:26:24 14:24:00 15:21:36 16:19:12 12:28:48 13:26:24 14:24:00 15:21:36 16:19:12
Time Time
C007; C008; C009
Fig. 7 Power generation tracking plan C005; C006; C001
C002; C003
10000
Power (kW)
5000
5000
Reactive power (kvar)
0 4000
3000
-5000 2000
1000
-10000 0
-15000 -1000
12:00:00 12:57:36 13:55:12 14:52:48 15:50:24 16:48:00 -2000
12:28:48 13:26:24 14:24:00 15:21:36 16:19:12 -3000
Time -4000
-5000
C007; C008; C009 16:16:19 16:30:43 16:45:07 16:59:31 17:13:55 17:28:19 17:42:43
C005; C006; C001 Time
C002; C003; Total Target reactive power; Actual reactive power
Fig. 8 Power profiles of each transformer unit and total BESS Fig. 10 Control effect of tracking reactive power command
602 Xiangjun LI et al.
[2] Toge M, Kurita Y, Iwamoto S (2013) Supplementary load fre- power/battery energy storage system. In: Proceedings of the 2006
quency control with storage battery operation considering SOC IEEE PES power systems conference and exposition (PSCE’06),
under large-scale wind power penetration. In: Proceedings of the Atlanta, GA, USA, 29 Oct-1 Nov 2006, pp 1244–1251
2013 IEEE Power and Energy Society general meeting, Van- [21] Viswanathan V, Kintner-Meyer M, Balducci P et al (2013)
couver, Canada, 21–25 Jul 2013, 5 pp National assessment of energy storage for grid balancing and
[3] Kawakami N, Iijima Y, Fukuhara M et al (2010) Development arbitrage, phase II volume 2: cost and performance. PNNL-
and field experiences of stabilization system using 34 MW NAS 21388 PHASE II/Vol 2. Pacific Northwest National Laboratory,
batteries for a 51 MW wind farm. In: Proceedings of the 2010 Richland, WA, USA
IEEE international symposium on industrial electronics [22] Supra JD (2012) Washington energy update: August-September
(ISIE’10), Bari, Italy, 4–7 Jul 2010, pp 2371–2376 2012. White & Case LLP, New York, NY, USA
[4] Khatamianfar A, Khalid M, Savkin AV et al (2013) Improving [23] Kumagai J (2012) A battery as big as the grid. IEEE Spectrum
wind farm dispatch in the Australian electricity market with 49(1):45–46
battery energy storage using model predictive control. IEEE
Trans Sustain Energy 4(3):745–755
[5] Teleke S, Baran ME, Huang AQ et al (2009) Control strategies Xiangjun LI received the B.E. degree in electrical engineering from
for battery energy storage for wind farm dispatching. IEEE Shenyang University of Technology, China, in July 2001, and the
Trans Energy Convers 24(3):725–732 M.E. and Ph.D. degrees in electrical and electronic engineering from
[6] Baccino F, Grillo S, Marinelli M et al (2011) Power and energy Kitami Institute of Technology (KIT), Japan, in March 2004 and
control strategies for a vanadium redox flow battery and wind March 2006, respectively. From May 2006 to March 2010, he worked
farm combined system. In: Proceedings of the 2nd IEEE PES as post-doctoral research fellow at Korea Institute of Energy Research
international conference and exhibition on innovative smart grid (KIER), Daejeon, Korea, and Tsinghua University, Beijing, China,
technologies (ISGT Europe’11), Manchester, UK, 5–7 Dec respectively. In March 2010, he joined Electrical Engineering and
2011, 8 pp New Material Department, China Electric Power Research Institute
[7] Li WY (2015) Framework of probabilistic power system plan- (CEPRI), Beijing, China, where he has been engaged in the topic of
ning. CSEE J Power Energy Syst 1(1):1–8 integration/control/SCADA/application technologies for large-scale
[8] Nguyen CL, Lee HH (2016) Effective power dispatch capability multi-type battery energy storage system/station, wind/PV/battery
decision method for a wind-battery hybrid power system. IET hybrid distributed generation systems, and micro-grids. His research
Gener Transm Distrib 10(3):661–668 interests include renewable energy power generation, electric energy
[9] Haaren RV, Morjaria M, Fthenakis V et al (2015) An energy saving/storage technology, and power system engineering. Dr. Li is a
storage algorithm for ramp rate control of utility scale PV chartered engineer, and the senior members of IEEE, CSEE, CAS,
(photovoltaics) plants. Energy 91:894–902 and CES, etc. He has been the Editor-in-Chief for a Springer book
[10] Wang GS, Ciobotaru M, Agelidis VG (2014) Power smoothing series entitled ‘‘Renewable Energy Sources & Energy Storage’’ since
of large solar PV plant using hybrid energy storage. IEEE Trans 2016. He has served as the Chair of the IEEE CIS Task Force on
Sustain Energ 5(3):834–842 ‘‘ADP and RL in Power and Energy Internets’’ since 2016. He also
[11] Yuan Y, Sun CC, Li MT et al (2015) Determination of optimal serves as several members, such as the IEC TC120 WG3, the IEEE
supercapacitor-lead-acid battery energy storage capacity for CIS Adaptive Dynamic Programming and Reinforcement Learning
smoothing wind power using empirical mode decomposition and Technical Committee, and the IEEE CIS Intelligent Systems Appli-
neural network. Electr Power Syst Res 127:323–331 cations Technical Committee, respectively.
[12] Trung TT, Ahn SJ, Choi JH et al (2014) Real-time wavelet-
based coordinated control of hybrid energy storage systems for Liangzhong YAO received the M.Sc. and Ph.D. degrees in electrical
denoising and flattening wind power output. Energies power engineering from Tsinghua University, Beijing, China, in 1989
7(10):6620–6644 and 1993, respectively. He is currently the Vice President and the
[13] Abbey C, Strunz K, Joós G (2009) A knowledge-based approach Doctoral Supervisor of the China Electric Power Research Institute
for control of two-level energy storage for wind energy systems. (CEPRI). Prior to CEPRI, he was the Senior Power System Analyst at
IEEE Trans Energy Convers 24(2):539–547 ABB UK Ltd from 1999 to 2004, and was the Department Manager
[14] Shigematsu T (2011) Redox flow battery for energy storage. SEI for network solution and renewable energy at Alstom Grid Research
Tech Rev 73:4–13 & Technology Centre in the UK from 2004 to 2011. Dr. Yao is a
[15] Senjyu T, Kikunaga Y, Yona A et al (2008) Coordinate control Fellow of IET, a chartered engineer, and a member of CIGRE. He is
of wind turbine and battery in wind power generator system. In: also the visiting professor at the University of Bath in the UK, and the
Proceedings of the 2008 IEEE Power and Energy Society gen- guest professor at both Shanghai Jiao Tong University and Sichuan
eral meeting—conversion and delivery of electrical energy in University, China.
the 21st century, Pittsburgh, PA, USA, 20–24 Jul 2008, 7 pp
[16] Ferreira SR, Rose DM, Schoenwald DA et al (2012) Protocol for Dong HUI received his B.S. and M.S. degrees in semiconductor
uniformly measuring and expressing the performance of energy physics and devices from Huazhong University of Science and
storage systems. PNNL-22010. Pacific Northwest National Technology, China in 1990 and 1995, and Ph.D. degree in applied
Laboratory, Richland, WA, USA superconductivity, from Institute of Electrical Engineering, Chinese
[17] US utility-scale battery storage market surges forward. Academy of Sciences, in 1998, respectively. He worked as visiting
2011NARP 825-110928. IHS Emerging Energy Research LLC, scientist at Deutsches Elektronen Synchrotron (DESY), Hamburg,
Cambridge, MA, USA Germany, from May 1999 to May 2002. After then, he worked as
[18] DOE global energy storage database. http://www. associate professor, at the Institute of Electrical Engineering, Chinese
energystorageexchange.org/projects Academy of Sciences, from May 2002 to May 2007. He has been a
[19] Skyllas-Kazacos M, Kazacos G, Poon G et al (2010) Recent professor at China Electric Power Research Institute since June 2007
advances with UNSW vanadium-based redox flow batteries. Int and now the chief engineer of electrical engineering and new material
J Energy Res 34(2):182–189 department of CEPRI. His research interests include large scale
[20] Yoshimoto K, Nanahara T, Koshimizu G (2006) New control battery energy storage and power electronics.
method for regulating state-of-charge of a battery in hybrid wind
(Editor Xiaorong GU)