Professional Documents
Culture Documents
Assurance Volume III
Assurance Volume III
VOLUME- III
1.3 Contractor shall nominate project quality Lead and Quality coordinator
who will be single nodal personnel for all communication and
coordination.
1.4 The Contractor shall ensure the vendors are proposed during the pre-bid
discussion. The credentials of such vendors shall be approved by SPGVL.
It is the contractor’s responsibility to ensure that the vendors are finalized
before signing of the contract.
1.5 In case of any additional vendor approval derived after awarding the
contract, the following minimum requirement shall be met by the vendor.
Also contractor should justify the reasons for additional vendor proposal
with clear documentary evidences and audit report performed by
contractor.
** Any Item not covered in the list shall be discussed and finalized
during Kick Off Meeting.
MQP:
a. For category I & II items, contractor should submit MQP for
SPGVL review and approval.
b. For category III items, contractor will approve the MQP and
submit to SPGVL for information.
c. Final “Factory Acceptance Test” for Category I & II items as per
agreed categorization plan – Witness Point
d. Type test: If valid type test report is not available (or) combination
of the new manufacturer products - Witness Point
FQP:
1.7 The procedure for purchase of materials, parts components and selection
of sub-Contractor’s services including vendor analysis, source inspection,
incoming raw material inspection, verification of material purchases etc.
shall be submitted for Owner approval
1.8 Valid Type test reports for combination of materials as applicable shall be
submitted to Owner for review. If any combination of materials differs,
type test shall be carried out before taking mass production.
1.9 The contractor shall be responsible for all supply materials inspection
irrespective of category and the inspection and certification of supply
materials should be from any of the following inspection agencies.
a. Bureau Veritas
b. Tata Project Limited
c. DNV
d. TUV Nord
1.10 The contractor shall appoint one FQA in-charge with 15 years’ TL
experience at project site, one field quality graduate engineer with
minimum of 10 years of TL experience with 3 technicians of 5 to 8 years’
experience shall be deployed for every 75 KM of stretch to ensure all the
activities performed at site are as per the specification and FQP.
1.11 The cube compression testing machine shall be installed at every 100 KM
for cube testing. The same shall be calibrated and records shall be
maintained for Owner verification.
2.3 The Contractor shall keep the Owner informed in advance about the time
of starting and of the progress of manufacture and fabrication of various
tower parts / equipments at various stages, so that arrangements could be
made for inspection.
2.4 The acceptance of any part of items shall in no way relieve the Contractor
of any part of his responsibility for meeting all the requirements of the
Tender Specification.
2.5 The norms and procedure of sampling for lot testing shall be as per the
ISO 2500. The Level of acceptance shall be discussed with the Owners
and agreed upon.
2.9 The Contractor shall dispose any non-conformity observed in the products
or services only with due approval from the Owner.
2.10 Material release note will be issued by the representative of the Owner
after satisfactory compliance of inspection and testing requirements. For
further issuing of dispatch instruction will be issued by the SCM or
Project Management. This will be agreed during the KOM with the
contractor.
2.11 In case of any dispute in acceptance criteria, the Tender specification and
Technical specification will be the binding references.
2.13 The manufacturer shall ensure only calibrated testing equipment’s are
used for conformity test.
2.14 Type Tests shall mean those tests which are to be carried out to prove the
process of manufacture and general conformity of the material to this
Specification. These tests shall be carried out on samples prior to
commencement of commercial production against the order. The Supplier
/ contractor shall indicate his schedule for carrying out these tests.
3.1 All field quality activity shall be carried out in accordance with Owner
approved field quality plan. All field check details shall be recorded /
documented in approved field quality check list at site and duly approved
by SPGVL field quality engineer at site.
3.2 The Contractor shall provide relevant technical inputs and documents to
the Owner for activities related to Field Quality at project site in line with
the recommendations, standards and practices of the original equipment
manufacturers.
3.3 Construction raw material source approval shall be taken before starting
the construction work at site.
3.4 The contractor shall provide the store management system and Store
layout plan for SPGVL approval before starting of the construction.
3.6 The Civil foundation requirements shall be as per IS 456 latest edition.
The minimum and maximum temperature requirement of concrete during
pouring is to be as per code. The procedure shall be submitted for
approval before starting of the concrete.
3.7 The contractor shall be responsible and accountable for the following.
3.8 The cubes for casting shall be drawn as per IS 456 considering the volume
of concrete on day basis as detained in code.
3.9 Curing of concreting shall be as per IS 456 and only OPC shall be used
for concreting.
3.11 All construction & supply bills of contractor will be certified by Owner
Field Quality Engineer.
3.12 The Owner or his duly authorized representatives reserves the right to
carry out Quality Audit and quality surveillance of the systems and
procedures of the Contractor's / his vendor's Quality Management and
Control Activities.
3.13 The contractor shall carry out technical audit during construction through
in-house or through external agencies every three months. The report shall
be submitted to Owner for review. The audit shall cover all the aspects of
construction including foundation, tower erection, stringing activities,
contractual obligations, applicable process & procedures, FQP &
procedures implementation, material handling, material storage and
technical competent manpower availability etc…
3.14 Owner will conduct Technical audit of manufacturing facilities and site
function of the contractor. If any non-conformity or observation is noted
the same shall be implemented or resolved within 2 days of notification.
In case of any critical non conformity the work shall not proceed without
taking corrective and preventive action.
3.15 If any NCR observed, the contractor shall propose corrective & preventive
action, analysis the root cause and submit the detailed report.
3.17 The contractor shall generate monthly quality report detailing all the
activity performed at site & submit the same to SPGVL Quality Head on
or before 5th of every month.
3.18 The contractor shall submit the Project quality assurance documentations
after project completion including Mechanical completion report, as built
drawing, pre commissioning and commissioning reports. The format and
detailed content of the report shall be discussed with the owner during
KOM.
4 Final Documentation
4.0 The contractor shall submit the Project Quality Assurance document
dossier after project completion. The format and detailed content of the
report shall be discussed with owner during KOM. The Project Quality
Assurance document dossier should contain the following documents.
S Components Type of Quantum of Reference Acceptance Type of Manufacturer Supplier Client/ Remarks
N / Operation & check check / document Criteria record TPI
o. Description sampling
of test with basis
Title Sheet: