Professional Documents
Culture Documents
NEC IDENTIFICATION CODE TCM IDENTIFICATION CODE TITLE OWNER DOCUMENT Nr.
This document has been produced by Contractor for LORESTAN. It is confidential and cannot be disclosed to or used by any third party for any purpose without prior written consent.
Bakhtar Petrochemical Company
Lorestan Petrochemical Company (LPC)
Lorestan Petrochemical Company
NEC IDENTIFICATION CODE TCM IDENTIFICATION CODE TITLE OWNER DOCUMENT Nr.
LIST OF CONTENTS
This document has been produced by Contractor for LORESTAN. It is confidential and cannot be disclosed to or used by any third party for any purpose without prior written consent.
Bakhtar Petrochemical Company
Lorestan Petrochemical Company (LPC)
Lorestan Petrochemical Company
NEC IDENTIFICATION CODE TCM IDENTIFICATION CODE TITLE OWNER DOCUMENT Nr.
1.1 INTRODUCTION
This document covers all units falling under Plant Unit 40 i.e. Utilities and Offsites. For
convenience the units are sub-divided into various plant area codes listed as under.
This document has been produced by Contractor for LORESTAN. It is confidential and cannot be disclosed to or used by any third party for any purpose without prior written consent.
Bakhtar Petrochemical Company
Lorestan Petrochemical Company (LPC)
Lorestan Petrochemical Company
NEC IDENTIFICATION CODE TCM IDENTIFICATION CODE TITLE OWNER DOCUMENT Nr.
The objective of the Safety Integrity Level (SIL) classification study was to assess the SIL
of the Safety Instrumented Functions (SIF), based on an assessment of the risk of injury to
people (operators or public) and damage to the environment. This involves evaluating the:
Elements forming the SIF;
SIF Design Intent;
SIF demand scenarios and frequency of demand;
Potential consequences if the SIF is not implemented; and
Effectiveness of Impendent Protective Layers (IPL).
The SIL defines the level of the safety integrity (or reliability) required to be implemented
for each specific SIF application, such that the residual risk due to each hazardous event in
the plant is broadly acceptable. The SIL could range from SIL 4 (SIL 3 being the highest level
of safety integrity expected in the process industry). SIL ‘-‘ does not call for any safety
integrity requirements. For SIL 4 a requirement to redesign the system to achieve an
inherently safer design is recommended.
The SIL Classification was performed for the SIFs as identified from Cause and Effects
Diagrams/ Tables (CED) and the Piping and Instrument Diagrams (P&IDs).
The SIL study was conducted in accordance with:
IEC 61511 Part 3, which incorporates the requirements from ISA S84.01-1996.
This document has been produced by Contractor for LORESTAN. It is confidential and cannot be disclosed to or used by any third party for any purpose without prior written consent.
Bakhtar Petrochemical Company
Lorestan Petrochemical Company (LPC)
Lorestan Petrochemical Company
NEC IDENTIFICATION CODE TCM IDENTIFICATION CODE TITLE OWNER DOCUMENT Nr.
The SIF is required to be operated on demand. It will act upon detection of a process upset
leading to a hazardous situation and take corrective action by shutting down the unit/ plant to
bring to a safe status. The SIL defining a minimum level of reliability in terms of Probability of
Failure on Demand (PFD), as shown in Table 2.1 is applied for this project.
SIL 4 is considered extremely rare in the process industry. If a classification leads to SIL 4,
further study should be performed including a review of the design.
The safety functionality that calls for integrity level below SIL 1 shall be retained in the ESD
system as provided now.
The safety functionality that calls for integrity levels SIL 1, 2 and 3 will be implemented in
the ESD system.
Safety instrumented functions (SIF), such as high level trip, high temperature trip, high
pressure trip etc are widely used in the process industry to protect against hazards of
overfilling, design temperature being exceeded or overpressure respectively. These are
safeguards implemented using instrumentation, and comprise one or more sensors, a logic
solver and one or more final elements. However, they do not provided absolute protection as
they may fail to perform its desired function when required due to various reasons including
failure of the various components that make up the system which is designed to implement
the function.
The probability of failure of a SIF depends on the configuration of the system, i.e. the level
of redundancy, testing/ maintenance frequency etc. for example, a system with two
independent level sensors (1oo2 configuration) is less likely to fail as compared to a system
with only one sensor. Similarly, a system with two shut down valves in series (1oo2
configuration) is less likely to fail to perform as compared to a system with only one shutdown
valve. Redundant systems for all applications are however, not cost effective and may not
This document has been produced by Contractor for LORESTAN. It is confidential and cannot be disclosed to or used by any third party for any purpose without prior written consent.
Bakhtar Petrochemical Company
Lorestan Petrochemical Company (LPC)
Lorestan Petrochemical Company
NEC IDENTIFICATION CODE TCM IDENTIFICATION CODE TITLE OWNER DOCUMENT Nr.
provide any significant additional safety benefit for all cases. Hence, a risk based approach is
adopted to determine the level of reliability required for the particular SIF.
Risk is a function of likelihood and consequence, as follows:
Risk (inherent or unmitigated risk)= Likelihood of a unwanted event x consequence (in
terms of fatality or environmental damages)
A SIF reduces the risk, as follows:
Risk (mitigated risk)= Likelihood of an unwanted event x consequence x probability of
failure of SIF on demand (expressed as SIL)
This study assesses the risk posed by each hazardous event in the plant which is resulted
from SIF failure and determines the level of reliability of the SIF to meet a target risk level or
broadly acceptable risk level. A qualitative (or a semi-quantitative approach) is adopted to
determine the risk using the Risk Graphs.
Probability of failure on demand of SIF (PFD), i.e. the reliability of the SIF is thus derived
as follows
For Example, using safety classification as illustration, and assuming that the target risk
level is 10-4 per year, the likelihood of an unwanted event is 10-1 per year and consequence
is 1 fatality, then.
The required SIL based on safety classification is therefore 3 for this SIF.
If the likelihood of an unwanted event is 10-1 per year and the Consequence is 0.1 fatality
(i.e. injury), then.
PFD= 10-4/(10-1x0.1)=10-2
This document has been produced by Contractor for LORESTAN. It is confidential and cannot be disclosed to or used by any third party for any purpose without prior written consent.
Bakhtar Petrochemical Company
Lorestan Petrochemical Company (LPC)
Lorestan Petrochemical Company
NEC IDENTIFICATION CODE TCM IDENTIFICATION CODE TITLE OWNER DOCUMENT Nr.
The above approach ensures that a consistent basis (i.e. a risk based approach) is
adopted in determining the configuration of the instrumented system, while avoiding over
engineering, where not necessary.
The assessment is however, qualitative and is base on guidelines, experience and
judgment. A more detailed quantitative approach may be adopted put is time consuming. The
above approach is therefore considered reasonable and fit for purpose.
A conservative approach to system design may still be adopted for various reasons, such
as licensors’ past experience or other factors which may not be quantifiable easily. In such
cases, although the SIL derived from above may be lower (say SIL a or SIL) a more
conservative SIL may be assigned, say SIL 1 or SIL 2 respectively. This study seeks to set
the minimum requirements, which however, may be exceeded if required.
3 SIL METHODOLOGY
3.1 OVERVIEW
The CEDs were first reviewed to identify the SIFs that required SIL classification. These
were also confirmed by reviewing the P&IDs and the HAZOP sheets. Only those functions
within the ESD system and initiated by the process to prevent a specific hazardous situation
This document has been produced by Contractor for LORESTAN. It is confidential and cannot be disclosed to or used by any third party for any purpose without prior written consent.
Bakhtar Petrochemical Company
Lorestan Petrochemical Company (LPC)
Lorestan Petrochemical Company
NEC IDENTIFICATION CODE TCM IDENTIFICATION CODE TITLE OWNER DOCUMENT Nr.
were selected for classification, thus, the following types of functions listed in the CED were
not classified:
Hand-switch operated functions (operator activated). A default value of SIL 1 may be
assumed;
Control function (FIC, TIC reset etc);
Functions related to normal process control (e.g. auto-start /stop of pumps as a
means of normal level control);
Proposed or indicative machine related protection functions such as those relating to
lube oil systems;
Emergency equipment isolation functions. A default value of SIL 1 may be assumed;
and
Fire & gas systems which are not part of the process/ utility system, such as fire &
gas detectors, deluge systems etc.
DCS interlocks were generally not assessed, except in a few cased they were assessed to
see whether the interlocks need to be upgraded. In all of those cases DCS interlocks were
found to be adequate.
The SIFs were defined with a function description, design intent, one or more initiator(s)
(i.e. instrument(s) to detect a hazardous situation) and one or more final element(s) (i.e.
elements that act to mitigate the hazardous situation).
The final element(s) of the SIF were chosen as those which directly meet their design
intent. Thus, only one or two final elements were usually defined for any function, and where
more than one was selected, a success criterion was defined for these final elements. The
other elements acted upon by the initiators were left unclassified (they may however, by
retained for implementation in the ESD system). Some of these unclassified elements may
act as primary final element for another SIF and assigned appropriate SIL classification.
Those final elements not covered under any other SIF as primary final element were
checked, where required, to ensure no separate classification was required.
The study team then described the demand scenario and consequence(s) of failure on
demand (CoFoD) and the numerical frequency and consequence ratings were then assigned
according to Risk Diagrams as shown in Annex C.
This document has been produced by Contractor for LORESTAN. It is confidential and cannot be disclosed to or used by any third party for any purpose without prior written consent.
Bakhtar Petrochemical Company
Lorestan Petrochemical Company (LPC)
Lorestan Petrochemical Company
NEC IDENTIFICATION CODE TCM IDENTIFICATION CODE TITLE OWNER DOCUMENT Nr.
This document has been produced by Contractor for LORESTAN. It is confidential and cannot be disclosed to or used by any third party for any purpose without prior written consent.
Bakhtar Petrochemical Company
Lorestan Petrochemical Company (LPC)
Lorestan Petrochemical Company
NEC IDENTIFICATION CODE TCM IDENTIFICATION CODE TITLE OWNER DOCUMENT Nr.
Where multiple sensors are provided, success criterion is defined if they detect the same
hazard. This approach for defining the sensor success criteria was taken for all SIF with
multiple sensors.
For some SIFs several final elements are acted upon simultaneously to put the system to a
safe state. Where more than one action is require4d to be successful in order to put the
system of a safer state, success criteria (eg 1oo2 or 2oo2 etc.) may be selected for the final
elements. Not all of the actions in one particular SIF, however, may be required or important
enough to protect against the particular hazard, some may be secondary in nature, i.e. to
prevent collateral hazards or may be for operator assistance in restarting the unit quickly.
Where a SIF is provided in addition to a PSV, PSV will in most cases operate to mitigate
an overpressure hazard. External conditions (send, dust, corrosion), internal vessel
conditions (dirty service, clogging), manufacturing defects, potential inadequate preventive
maintenance, or induced vibrations or ice formation during a release (which may lead to
blockage of line and subsequent line rupture/ leakage) could potentially lead to the PSV
being ineffective. For this study, most PSVs has been considered as an IPL with a risk
reduction factor of 100, except for selected cases where a lower credit (i.e. 10 instead of 100)
has been given as a conservative measure to meet the requirements of risk graph.
Credit was given to an independent protective layer (IPL). Only if it could be demonstrated
that the IPL could be independent from the SIF studied and independent from the cause of
the hazard studied. However, before taking credit for IPLs, due consideration was made to
the effectiveness of the IPLs, the time required for successful intervention and the level of
independence with the SIF classified and the event causing a demand on the SIF.
This document has been produced by Contractor for LORESTAN. It is confidential and cannot be disclosed to or used by any third party for any purpose without prior written consent.
Bakhtar Petrochemical Company
Lorestan Petrochemical Company (LPC)
Lorestan Petrochemical Company
NEC IDENTIFICATION CODE TCM IDENTIFICATION CODE TITLE OWNER DOCUMENT Nr.
In order to ensure consistency in the assessment, rule sets for assessing independent
protection layer, frequency of demand, presence in danger area and possibility to avert
hazard in Table 3.1 to Table 3.4, these rule sets serve as an aid for assigning the levels for
the various parameters shown in the Risk Graphs in Annex C.
Table 3.1 Rule Set for Independent Protective Layer
Independent Protection Layer Risk Reduction Factor
Pressure Relief Device (mechanical safety trip) 100
SIS- SIL 1 10
SIS – SIL 2 100
BPCS, when independent of initiating event 10
Internal mechanical safety trips that are independent of 10 to 1000 (Base on actual operating
the SIS or BPCS experience with similar device)
Operator response under high stress, average training 0
Operator response to Alarms with procedures, low stress,
10
recognized event and least 5 minutes to respond
Double check valves designed for the hazardous scenario 10
Single check valve 0
Dikes when capable of mitigating the initiating event. This
100
is an IPL only for environmental events
Notes: where more than one protective measure exists, the highest IPL value assumed, without taking credit for all, as a conservative
measure.
Table 3.2 Rule Set for Frequency of Demand
Initiating Event
Frequency of Demand
Scenario Frequency (per
(W)
year)
Control loop failure >1.E-01 W2
Analyzer failure >1.E-00 W3
Pump Failure loss of flow (conservatively W3) 7.9E-01 W3
Positive Displacement pump trip 1.1E-00 W3
Reciprocating compressor trip 2.1E-00 W3
Single mechanical pump seal leak 1.0E-01 W2
Double mechanical pump seal leak with announcement 1.0E-02 W1
Canned/ magnetic drive pump leak 1.0E-02 W1
Loss of electrical power 1.0E-01 W2
General utility failure 1.0E-01 W2
Heat exch. Tube leak 1.0E-02 W1(<100 TUBES)
W2 (>100 TUBES)
Operator failure (if considered in the analysis):
W1
This document has been produced by Contractor for LORESTAN. It is confidential and cannot be disclosed to or used by any third party for any purpose without prior written consent.
Bakhtar Petrochemical Company
Lorestan Petrochemical Company (LPC)
Lorestan Petrochemical Company
NEC IDENTIFICATION CODE TCM IDENTIFICATION CODE TITLE OWNER DOCUMENT Nr.
3.4 WORKSHEETS
The session proceedings were recorded using PHA-Pro 7. The records were projected on
a screen for comment and agreement by the team members during the sessions.
Preparation for the study was conducted prior to the commencement of the classification
sessions. This comprised input of the study SIF into the PHA software, based on the
information in CED.
3.5 ASSUMPTIONS
Several assumptions were made regarding the basis of the design during the course of the
SIL study. The main items are:
In case of multiple equipments (with duty a standby/ spare equipment) inside a unit, the study
was conducted for one set of equipment. The recommendations from this study will therefore
apply for such similar systems as well. The study has however, considered the impact of
simultaneous operation of systems in parallel or series including the control requirements
This document has been produced by Contractor for LORESTAN. It is confidential and cannot be disclosed to or used by any third party for any purpose without prior written consent.
Bakhtar Petrochemical Company
Lorestan Petrochemical Company (LPC)
Lorestan Petrochemical Company
NEC IDENTIFICATION CODE TCM IDENTIFICATION CODE TITLE OWNER DOCUMENT Nr.
and the effect of trip of one system on the other. In spite of this, the mentioned functions
report has been presented in the worksheet.
The CEDs were reviewed to identify the SIFs that required SIL classification. Only those
functions within the ESD system and initiated by the process to prevent a specific hazardous
situation were chosen for classification, thus, the following types of functions listed in the
CED were not classified:
Hand-switch operated functions (operator activated). A default value of SIL 1 may be
assumed;
Control function (FIC, TIC reset etc);
Functions related to normal process control (e.g. auto start/stop of pumps as a means of
normal level control); and Proposed or indicative machine related protection functions.
The final element(s) of the SIF were chosen as those which directly meet their design intent.
Thus, only one or two final elements were usually defined for any function. The other
elements acted upon by the initiators were left unclassified (they may however, be retained
for implementation). However, these unclassified elements may act as a primary final
element for another SIF and assigned appropriate SIL classification. Those final elements
not covered under any other SIF as primary final element were checked, where required, to
ensure no separate classification was required.
This document has been produced by Contractor for LORESTAN. It is confidential and cannot be disclosed to or used by any third party for any purpose without prior written consent.
Annex A
Attendance List
Team Members
First Name Last Name Title Company Department
ALi Mirfakhraie Senior Engineer Nargan HSE
Farian Daiepour Engineering Nargan HSE
Kianoosh Karimpour Engineering Nargan HSE
Annex B
START ANALYSIS
INITIATOR AND
FINAL ELEMENT
IDENTIFICATION
SCENARIO
FREQUENCY OF EVALUATION OF
-Personnel Safety
-Environmental Damage
NEXT SIF
YES
STOP ANALYSIS
Annex C
Risk Diagrams
1 PERSONAL SAFETY
W1= Low (A very slight probability that the unwanted occurrence will occur and
only a few unwanted occurrences are likely (>once per 10 years))
W2= Moderate (A slight probability that the unwanted occurrence will occur and a
few unwanted occurrences are likely (>once per 1 year & > once per 10 years))
W3= High (A relatively high probability that he unwanted occurrence sill come to
pass and frequent unwanted occurrences are likely (>once per 1 year))
(S) Potential extent of human injury per demand if ESD system fails on
demand
S0= No injury
S1= Slight injury, non-permanent
S2= Severe injury, death of 1 person
S3= Death of several persons
S4= Catastrophe, many casualties
W1= Low (Avery slight probability that the unwanted occurrences will occur and
only a few unwanted occurrences are likely (>once per 10 years))
W2= Moderate (A slight probability that he unwanted occurrence will occur and a
few unwanted occurrences are likely (<once per 1 year & > once per 10 years))
W3= High (A relatively high probability that the unwanted occurrence will come to
pass and frequent unwanted occurrences are likely (>once per 1 year))
E1= Release with minor damage to the environment that should be reported (e.g.,
moderate leak from a flange or a valve, small scale liquid spill)
E2= Release within fence with significant damage to the environment (e.g., a
could of obnoxious vapor travelling beyond the unit following flange gasket blow-
out or compressor seal failure)
E3= Release outside fence with temporary major damage to the environment
(e.g., a vapor or aerosol release with or without liquid fallout that cases
temporary damage to plants or fauna)
E4= Release outside fence with permanent major damage to the environment
(e.g., liquid spill into a river or sea, a vapor or aerosol release with or without
liquid fallout that causes lasting damage to plants or fauna, solids fallout, liquid
release that could affect groundwater)
22. on 40LT-2002, high high level in 40TK- 40LT-2002 40HV-2002 None Off-Site 40ESD-2001 1) 3454-XZ-DM-40-020
2004, hexene tank, to protect overfilling by 40P-2008A/B
closing 40HV-2002 and stopping 40P-2008
A/B.
23. On low low level in 40LT-2002 and not 40LT-2002, 40HV- 40P-2007 None Off-Site 40ESD-2002 1) 3454-XZ-DM-40-020
activation of 40HZSH-2001 in hexene tank to 2001
protect feeding pumps by stopping them
24. On hexene feeding pumps to start stand by 40P-2007A/B, 40P-2007A/B None Off-Site 40ESD-2003 1) 3454-XZ-DM-40-020
pump in case of stop of the duty pump 40YLH-2001A/B 40HSH-2001A/B
Other Final
Function Name Initiators Final Element Unit Interlock ID P&ID
Element
25. On truck connection on hexene loading bay 40XS-1903, 40XS- 40UAE-2101 None Off-Site 40ESD-2101 1) 3454-XZ-DM-40-020
to check 40XS-1903, truck earthing operation, 1902, 40XS-1901, 40XL-2101 1) 3454-XZ-DM-40-021
40ZE-2101, 40ZE-
on and 40SX-1902, truck front barrier, 40XS- 2102, 40LSHH-
1901, truck parking position, 40ZE-2101, vapor 2101, 40HV-2102,
loading arm, connected, 40ZE-2102, liquid 40HV-2101
loading arm, connected, 40LSHH-2101, truck
overfilling system detection, connected, 40HV-
2102, emergency valve on nitrogen connection
line, closed, 40HV-2101, emergency valve on
liquid line closed, to board signaling 40VAE-
2101 and local boarding "ready to align truck1"
40XL-2101 be activated
26. On truck unloading valve to align all the 40ESD-2101, 40HV-2102 None Off-Site 40ESD-2102 1) 3454-XZ-DM-40-21
valves before running the pumps and start 40HS-2111 40HV-2101
unloading session by checking the activation of 40HV-2002
40ESD-2101 and local push button truck 40HL-2111
unloading, 40HS-2111 pressed to open 40HV-
2102, emergency valve on Nitrogen, 40HV-
2002 emergency valve on hexene tank, 40HV-
2101, emergency valve on liquid line and
activation of 40HL-2111, local boarding
"alignment for truck unloading OK"
27. To trip the truck unloading due to gas 40ESD-2101, 40P-2008A/B None Off-Site 40ESD-2103 1) 3454-XZ-DM-40-020
detector intervention, any emergency condition 40ESD-2102, 40HV-2101
40AAHH-
and permissive no more verified. These items 2101,2102,2103,21 40HV-2102
will be checked by disturbance in 40ESD-2101, 04,2105, 40HS-
permissive not verified, not activation of 2110, 40LSHH-
40ESD-2102, truck loading valve not aligned, 2110, 40YA-2101,
40FQAH-2101,
activation of 40AAHH-2101, or 2102 or 2103 or 40PT-2155
2104 or 2105, emergency local push button
40HS-2110, truck overfilling signal, 40LSHH-
2110, fault pumps 40P-2008A/B, rest valve
reached in 40FQAH-2101 and low pressure on
N2 connection to truck 40PT-2155 to trip
hexene truck unloading pump 40P-2008A/B,
close emergency valve on liquid line 40HV-
2101 and emergency valve on Nitrogen line.
28. On hexane storage high high level in 40LT- 40LT-1802 40HV-1802 None Off-Site 40ESD-1801 1) 3454-XZ-DM-40-018
1802 to close 40HV-1802, and stopping 40P- 40P-2006A/B
2006A/B
29. On low low level of hexane tank in 40LT- 40LT-1802, 40HV- 40P-2005A/B None Off-Site 40ESD-1802 1) 3454-XZ-DM-40-018
1802 and not activation of 40HZLH-1801, to 1801
stop 40P-2005A/B hexane feeding pumps.
30. On hexane feeding pumps 40P-2005A/B to 40-P-2005A/B 40P-2005A/B None Off-Site 40ESD-1803 1) 3454-XZ-DM-40-018
start the standby pump in case of stop of the
duty pump
Other Final
Function Name Initiators Final Element Unit Interlock ID P&ID
Element
31. On hexane truck unloading to give the 40XS-1903, 40XS- 40UAE-1901 None Off-Site 40ESD-1901 1) 3454-XZ-DM-40-018
permission to the operator to align the valves 1902, 40XS-1901, 40XL-1904
40ZE-1901, 40ZE-
for truck, these items will be checked by 40XS- 1902, 40LT-1901,
1903, truck earthing connection on, 40XS-1902 40HV-1901, 40HV-
truck front barrier, 40XS-1901, truck parking 1902
position, 40ZE-1901, vapor loading arm
connection, 40ZE-1902 liquid loading arm
connection, 40LSHH-1901, truck overfilling
system detection connection, 40HV-1901,
emergency valve on liquid line to be closed,
40HV-1902, emergency valve on vapor
connection to be closed to activate 40UAE-
1901 and 40XL-1904
32. On hexane truck unloading valve to check 40ESD-1901, 40HV-1902 None Off-Site 40ESD-1902 1) 3454-XZ-DM-40-018
valve alignment before starting operation by 40HS-1911 40HV-1901 1) 3454-XZ-DM-40-019
checking 40ESD-1901 activation, and local 40HV-1802
push button truck unloading press to open 40HL-1911
40HV-1902, emergency valve on vapor return
line, 40HV-1901, emergency valve on liquid
line, 40HV-1802, emergency valve on hexane
tank and local loading 40HL-1911.
33. To trip the truck unloading due to gas 40ESD-1901, 40P-2006A/B None Off-Site 40ESD-1903 1) 3454-XZ-DM-40-019
detector intervention, any emergency condition 40ESD-1902, 40HV-1901
40AAHH-
and permissive no more verified. These items 1911,1912,1913,19 40HV-1902
will be checked by disturbance in 40ESD-1901, 14,1915, 40HS-
permission not verified not activation of 1910, 40LSHH-
40ESD-1902, truck loading valve not aligned, 1901, 40P-
2006A/B, 40FQAH-
activation of 40AAHH- 1901
1911/1912/1913/1914/1915, emergency local
push button, 40HS-1910, 40LSHH-1901, truck
overfilling signal, fault pumps 40P-2006A/B,
reset valve reached in 40FQAH-1901 to trip
Hexane truck unloading pump, 40P-2006A/B,
close emergency valve on liquid line 40HV-
1901, emergency valve on nitrogen line 40HV-
1902.
34. On safety shower water pump 40P- 40P-7001A/B 40P-7001A/B None Off-Site 40FCS-1001 1) 3454-XZ-DM-40-010
7001A/B to start the standby pump in case of
stop of the duty pump.
35. On low low level of 40LT-1001 in 40D- 40LT-1001 40P-7001A/B None Off-Site 40FCS-1002 1) 3454-XZ-DM-40-010
7001, safety shower buffer drum, to stop safety
shower water pumps, 40P-7001A/B.
36. On high high level of 40LT-2302 in C6+ 40LT-2302 40HV-2302 None Off-Site 40ESD-2301 1) 3454-XZ-DM-40-023
storage tank (40TK-2005) to close 40HV-2302
and board signaling
Other Final
Function Name Initiators Final Element Unit Interlock ID P&ID
Element
37. On low low level of 40LT-2302 in 40TK- 40LT-2302, 40HV- 40P-2009A/B None Off-Site 40ESD-2302 1) 3454-XZ-DM-40-023
2005 or not opening of 40HV-2301, valve on 2301 1) 3454-XZ-DM-40-024
hexane tank, to stop 40P-2009A/B, C6+
loading pumps
38. On C6+ truck unloading to give permission 40XS-2303, 40XS- 40UAE-2401 None Off-Site 40ESD-2401 1) 3454-XZ-DM-40-024
to the operator to start loading operation by 2402, 40XS-2401, 40XL-2404
40ZE-2401, 40ZE-
checking procedure. This procedure includes, 2402, 40LSHH-
40XS-2303, truck earthing connection on, 2401
40XS-2402 truck front barrier, 40XS-2401, 40HV-2401, 40HV-
truck parking position, 40ZE-2401, vapor 2402
loading arm connection, 40ZE-2402, liquid
loading arm connection, 40LSHH-2401 truck
overfilling system detection connection, 40HV-
2401, emergency valve on liquid line to be
closed, 40HV-2402, emergency valve on N2
connection line to be closed to board signaling
at FCS and local boarding 40XL-2404
39. On C6+ truck loading valve to check 40ESD-2401, 40HV-2402 None Off-Site 40ESD-2402 1) 3454-XZ-DM-40-024
permissive verifications, 40ESD-2401, and 40HS-2411 40HV-2401
press 40HS-2411 local push button to open 40HV-2302
40HV-2402, emergeny valve on vapor return
line, 40HV-2401 emergency valve on liquid
line, 40HV-2302, emergency valve on C6+ tank
40. on C6+ truck loading to trip the operation 40ESD-2401, 40P-2006A/B None Off-Site 40ESD-2403 1) 3454-XZ-DM-40-024
due to gas detection, emergency contingencies 40ESD-2402, 40HV-2401
40AAHH-
and no verification in permissive procedure to 2411,2412,2413,24 40HV-2402
trip C6+ truck unloading pump 40P-2006A/B 14,2415, 40HS-
closing 40HV-2401 emergency valve on liquid 2410, 40LSHH-
line and 40HV-2402, emergency valve on 2401, 40P-
2006A/B, 40FQAH-
nitrogen due to not activation of 40ESD-2401, 2402
40ESD-2402, truck loading valve not aligned,
gas detection by 40AAHH-2411,
2412,2413,2414,2415, press emergency local
push button (40HS-2410), truck overfilling
signal by 40LSHH-2401, fault pumps 40P-
2006A/B and rest value reached 40FQAH-2402
41. On waste water collection basin, to control 40LSLL-0801, 40P-1002 A/B None Off-Site 40FCS-0801 1) 3454-XZ-DM-40-008
level high/low by start/stop pumps 40P- 40LSHL-0804
1002A/B.
On low low level of 40LSLL-0801, selected
main pump 40P-1002A/B will be stopped.
On high high level in 40LSHL-0804 or not
running of 40P-1002A/B to start stand by pump
40P-1002A/B.
Other Final
Function Name Initiators Final Element Unit Interlock ID P&ID
Element
42. On low level alarm in 40LSHL-0803 to stop 40LSHL-0803, 40P-1003 A/B None Off-Site 40FCS-0802 1) 3454-XZ-DM-40-008
selected main pump 40P-1003A/B. 40P-1003A/B
On 40P-1003A/B to automatic start of stand by
pump when duty pumps is stopped.
On high level alarm in 40LSHL-0803 to start
duty pump 40P-1003.
43. On low level alarm in 40LSHL-0802 to stop 40LSHL-0802, 40P-1004 A/B None Off-Site 40FCS-0803 1) 3454-XZ-DM-40-008
selected main pump 40P-1004A/B. 40P-1004
On 40P-1004 A/B to automatic start of stand by
pump when duty pump is stopped.
On high level alarm in 40LSHL-0802 to start
duty pump 40P-1004.
3. SIL STUDY - RISK GRAPH
Node: 1.
Area: Off-Site
Initiators: 40LT-1601
Final Element: 40HV-1601; 40P-2002 A/B; 40UAE-1601
SIL determination
and liquid carry over to BDM line by 40FV-1703 malfunction or any explosion and ball fire.
closing raw propane bullet valve other circumstances.
(40HV-1601) and stopping 40P-
2002A/B.
Node: 2.
Area: Off-Site
SIL determination
level in sphere or inlet line blockage by not open or any other case jet fire
stopping pumps. which may lead to input cut off.
It is recommended to study on providing pressure alarm in inlet line pressure indicators 40PL-1604, 40PI-1605, 40PI-1607
Node: 3.
Area: Off-Site
Drawings: 3454-XZ-DM-40_016-ISO4
SIL determination
Node: 4.
Area: Off-Site
Drawings: 3454-XZ-DM-40_017-ISO4
SIL determination
Area: Off-Site
Drawings: 3454-XZ-DM-40_017-ISO4
SIL determination
Node: 6.
Area: Off-Site
Drawings: 3454-XZ-DM-40_017-ISO4
SIL determination
Area: Off-Site
Initiators: 40LT-1401
Final Element: 40HV-1401; 40P-2004 A/B; 40UAE-1401
SIL determination
and liquid carryover to BDM line by 40FV-1501, 1502 malfunction or leakage, explosion and ball
closing butene-1 inlet valve (40HV- any other circumstances. fire
1401) and stopping 40P-2004 A/B.
Node: 8.
Area: Off-Site
SIL determination
Area: Off-Site
Drawings: 3454-XZ-DM-40_014-ISO4
SIL determination
Node: 10.
Area: Off-Site
Drawings: 3454-XZ-DM-40_014-ISO4
Initiators: 40PT-1413
Final Element: 40PV-1413
SIL determination
Area: Off-Site
Drawings: 3454-XZ-DM-40_014-ISO4
Initiators: 40PT-1411
Final Element: 40P-2009 A/B
SIL determination
1 storage sphere. leakage and jet fire. to trip pump due to low low level in
tank, operator intervention
considered to be possible.
Node: 12.
Area: Off-Site
Drawings: 3454-XZ-DM-40_015-ISO4
SIL determination
Area: Off-Site
Drawings: 3454-XZ-DM-40_015-ISO4
SIL determination
Node: 14.
Area: Off-Site
Drawings: 3454-XZ-DM-40-015
SIL determination
Area: Off-Site
Drawings: 3454-XZ-DM-40_015-ISO4
SIL determination
Node: 16.
Area: Off-Site
Drawings: 3454-XZ-DM-40_015-ISO4
SIL determination
Area: Off-Site
Drawings: 3454-XZ-DM-40_015-ISO4
SIL determination
Node: 18.
Area:
Drawings: 3454-XZ-DM-40_015-ISO4
SIL determination
Area: Off-Site
Drawings: 3454-XZ-DM-40_015-ISO4
SIL determination
Node: 20.
Area: Off-Site
Drawings: 3454-XZ-DM-40_015-ISO4
SIL determination
Area: Off-Site
Drawings: 3454-XZ-DM-40_015-ISO4
SIL determination
Node: 22.
Area: Off-Site
Initiators: 40LT-2002
Final Element: 40HV-1502; 40HV-1504; 40HV-1401; 40HL-1516
SIL determination
Area: Off-Site
SIL determination
Node: 24.
Area: Off-Site
Drawings: 3454-XZ-DM-40_020-ISO4
SIL determination
Area: Off-Site
Drawings: 3454-XZ-DM-40_020-ISO4
SIL determination
Node: 26.
Area: Off-Site
Drawings: 3454-XZ-DM-40_020-ISO4
SIL determination
Area: Off-Site
SIL determination
Node: 28.
Area: Off-Site
Drawings: 3454-XZ-DM-40_021-ISO4
Initiators: 40LT-1802
Final Element: 40HV-2102; 40HV-2101; 40HV-2002; 40HL-2111
SIL determination
Area: Off-Site
Drawings: 3454-XZ-DM-40_020-ISO4
SIL determination
Node: 30.
Area: Off-Site
Drawings: 3454-XZ-DM-40_018-ISO4
Initiators: 40-P-2005A/B
Final Element: 40HV-1802; 40P-2006 A/B
SIL determination
Area: Off-Site
Drawings: 3454-XZ-DM-40_018-ISO4
SIL determination
verifications and give permission to formation and pool fire. intervention considered to be
start truck loading/unloading operation. possible
Node: 32.
Area: Off-Site
Drawings: 3454-XZ-DM-40_018-ISO4
SIL determination
Area: Off-Site
Drawings: 3454-XZ-DM-40_018-ISO4
SIL determination
Node: 34.
Area: Off-Site
Initiators: 40P-7001A/B
Final Element: 40HV-1902; 40HV-1901; 40HV-1802; 40HL-1911
SIL determination
Area: Off-Site
Drawings: 3454-XZ-DM-40_019-ISO4
Initiators: 40LT-1001
Final Element: 40P-2006 A OR B; 40HV-1901; 40HV-1902
SIL determination
Node: 36.
Area: Off-Site
Drawings: 3454-XZ-DM-40_010-ISO4
Initiators: 40LT-2302
Final Element: 40P-7001 A OR B
SIL determination
Area: Off-Site
Drawings: 3454-XZ-DM-40_010-ISO4
SIL determination
considered to be possible.
Node: 38.
Area: Off-Site
Drawings: 3454-XZ-DM-40_023-ISO3
SIL determination
Area: Off-Site
SIL determination
Node: 40.
Area: Off-Site
Drawings: 3454-XZ-DM-40_024-ISO3
SIL determination
Area: Off-Site
Drawings: 3454-XZ-DM-40_024-ISO3
SIL determination
loss of in duty pump (control of level in formation, no safety issues. considered to be possible.
waste water basin)
Node: 42.
Area: Off-Site
Drawings: 3454-XZ-DM-40_024-ISO3
SIL determination
Area: Off-Site
Drawings: 3454-XZ-DM-40_008-ISO4
SIL determination