Hereunder are the findings, observations and recommendations of the joint ocular inspection conducted by the
undersigned Field Engineers held on (Date of Inspection).
PUNCHLIST REPORT
(Upon 95% Accomplishment)
Pay Item No. Pay Item Description Location Quantity to be completed Remarks
III. Recommendations
Require the Contractor, at his own expense to effect immediately the necessary corrective measures on all noted
defects/deficiencies and to complete the remaining works in accordance with the plans and specifications prior to the
contract expiry date. Furthermore, provide the corresponding documentation on the corrective works taken before,
during and after the rectification process.
Noted:
PIF-14-PCA-01A Rev 00
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
<IMPLEMENTING OFFICE>
<Office Address>
Date
Contract ID:
Contract Name:
Location:
Contractor:
Hereunder are the findings, observations and recommendations of the joint ocular inspection conducted by the undersigned
Field Engineers held on the (Date of Inspection).
II. Recommendations
Require the Contractor at his own expense to effect immediately the necessary corrective measures on all noted
defects/deficiencies in accordance with the plans and specifications within ninety (90) days upon this issuance. Furthermore,
provide the corresponding documentation on the corrective works taken before, during and after the rectification process.