Week Start: 27-Aug

Dates
Level

27-Aug-22

28-Aug-22

29-Aug-22

30-Aug-22

31-Aug-22

1-Sep-22

2-Sep-22

3-Sep-22

4-Sep-22

5-Sep-22

6-Sep-22

7-Sep-22

8-Sep-22

9-Sep-22
Activity Name Work Location Original Duration Start Finish Remarks

1 MOD Construction
2 Subcontractor : "Alfarouq"
3 "Warehouse Building"
A Foundation Internal Side Treatment & Ground Beam Warehouse 3 25/Aug/2022 27/Aug/2022 x o o o o o o o o o o o o o
A Foundation & Ground Beam Painting Warehouse 1 28/Aug/2022 28/Aug/2022 o x o o o o o o o o o o o o
A Protection Board Installation Warehouse 1 29/Aug/2022 29/Aug/2022 o o x o o o o o o o o o o o
A Backfilling Warehouse 3 30/Aug/2022 01/Sep/2022 o o o x x x o o o o o o o o
3 "Maintainance Building"
A Ground Beam & Pedestal Concrete Pouring Maintainance 1 28/Aug/2022 28/Aug/2022 o x o o o o o o o o o o o o
A Deshuttering & Concrete Curing Maintainance 1 29/Aug/2022 29/Aug/2022 o o x o o o o o o o o o o o
A Concrete Curing Maintainance 7 28/Aug/2022 03/Sep/2022 o x x x x x x x o o o o o o
A Pitumin Painting & Final Inspection Maintainance 4 31/Aug/2022 03/Sep/2022 o o o o x x x x o o o o o o
A Protection Board Installation Maintainance 2 04/Sep/2022 05/Sep/2022 o o o o o o o o x x o o o o
3 "Chemical Building"
A Ground Beam & Pedestal Allocation & Reinforcement Chemical 3 28/Aug/2022 30/Aug/2022
A Anchor Bolt Installation Chemical 3 29/Aug/2022 31/Aug/2022
A Foundation Concrete Pouring Chemical 1 01/Sep/2022 01/Sep/2022
A Foundation Concrete Curing Chemical 2 02/Sep/2022 03/Sep/2022
A Deshuttering & Pedastal Reinforcement & Formwork Installation Chemical 2 04/Sep/2022 05/Sep/2022
A Pedastal Concrete Pouring Chemical 1 06/Sep/2022 06/Sep/2022
A Pedastal Concrete Curing Chemical 5 07/Sep/2022 11/Sep/2022
A Pedastal Deshuttering & Grond Beam Formwork & Reinforcement Chemical 1 09/Sep/2022 09/Sep/2022
A Pedastal & Ground Beam Treatment Chemical 1 12/Sep/2022 12/Sep/2022
A Foundation Paiting Works Chemical 3 12/Sep/2022 14/Sep/2022
A Ground Beam & Pedastal Paiting & Protection Board Installation Chemical 2 15/Sep/2022 16/Sep/2022
3 " Security Building"
Parapit Reinforcement Security 2 26/Aug/2022 27/Aug/2022
Parapit Formwork Installation Security 4 28/Aug/2022 31/Aug/2022
Parapit Concrete Pouring Security 1 01/Sep/2022 01/Sep/2022
Level

Activity Name

1 MOD Construction
2 Subcontractor : "Alfarouq"
3 "Warehouse Building"
A Foundation Internal Side Treatment & Ground Beam
A Foundation & Ground Beam Painting
A Protection Board Installation
A Backfilling

3 "Maintainance Building"
A Ground Beam & Pedestal Concrete Pouring
A Deshuttering & Concrete Curing
A Concrete Curing
A Pitumin Painting & Final Inspection
Week Start: 27-Aug

27-Aug-22

28-Aug-22

29-Aug-22

30-Aug-22

31-Aug-22

1-Sep-22

2-Sep-22

3-Sep-22

4-Sep-22

5-Sep-22

6-Sep-22

7-Sep-22

8-Sep-22
Dates
Work Location

12 24 14 16 10 0 0 0 0 0 0 0 0

Warehouse 12 12 6 8
Warehouse 12 8 8 10
Warehouse
Warehouse

Maintainance
Maintainance
Maintainance
Maintainance
0
9-Sep-22