Darcliffe Homes
17 Albury Close
Reading
RG30 1BD
01189 508366
[Link]
Written by: Ben Longworth
Date: 21st March 2023
Method Statement
Abandonment of Existing and Installation of New Foul Drainage Diversion
Project: Parkside Road
Site address: 18 Parkside Road, Reading, RG30 2DB. Date of works: 6th May 23–17th May23
Brief Description of activity
Divert existing, live foul drain run.
Construct temporary diversion whilst permanent adoptable standard manholes and pipe runs are being
installed, then make final connection to achieve uninterrupted service.
Involves:
● Clay and plastic drainage installation
● Concrete Chambers
● Excavator
● Pipe Lazer
● Pipe Grease and Collars
Page 1 of 4
Plant/materials/tools to be used:
8T Excavator
6T Dumper
Concrete
Pipe Shingle
Clay Pipe 150 dia
Concrete Chambers to suit Design
.
Personal Protective Equipment
Safety Helmet At all times
High Visibility Jacket At all times
Gloves (hand protection) As necessary / working with concrete/abrasives
Safety Boots At all times
Safety Glasses As necessary / working with concrete
Dust Masks Working with cement / cutting concrete
Supervision and personnel
(Direct Personnel)
● Site Manager – Chris Cousins 07794 500159
● Groundworker – John Sheehan
(Sub-contractors)
● MOS Construction – x3
Training
All operatives are adequately trained to carry out required tasks and have attended a site induction.
Specific skilled operatives such as plant operators hold current certification and have the following training:
● CPCS certification
Page 2 of 4
Access and Egress
Deliveries will be offloaded from the front of site via 8m JCB telehandler
Materials placed into position at rear of site
Stacked in line with manufacturer’s instructions
A stone ramp approx..4m wide at 1:10 Gradient is present from roadside to working surface
The working surface consists of a piling mat of 375mm compacted and rolled 6f2 stone
The surface is to be checked regularly for suitability of the tower scaffold
Site Induction
Upon arrival and prior to work commencing, all personnel will report to the site office to be inducted by the
site manager.
Plant operative tickets will be checked and a full review of the Risk Assessment and Method statement will
be carried out.
Signed records of the induction will be stored in the site office file
Detailed Method of Work
In advance of work commencing, the survey of the drainage to be abandoned will be assessed and a visual
inspection of the flow rate in the pipe viewed.
CAT Scan all excavation areas for live services
Check invert levels and outfall levels of existing manholes to ensure temporary diversion will be
suitable for existing chambers
Construct temporary chambers and pipe bed in shingle to correct falls
Make connection to final manhole
Use stopper to temporarily block first manhole flow
Make connection to first manhole from temp run and close connection to drainage section to be
abandoned
Release the stopper
Check flow of foul drainage runs correctly through the diversion
Remove existing drainage to be abandoned
Install new adoptable standard drainage run
Make connection to final manhole
Use stopper to temporarily block incoming flow to first manhole
Make new connection to first manhole
Remove all stoppers
Check and confirm that adoptable drainage run flows correctly and no visible defects
Abandon temporary run
Page 3 of 4
Legislation
● Health and Safety Work Act 1974
● The Management of Health and Safety at Work Regulations 2006
● Workplace (Health, Safety and Welfare) Regulations 1992
● Provision and Use of Work Equipment Regulations (PUWER) 1998
● Control of Substances Hazardous to Health Regulations 2002
● The Work at Height Regulations 2005
● The Personal Protective Equipment at Work Regulations 2002
● The Manual Handling Operations Regulations 1992
● The Construction (Design and Management) Regulations 2015
Working at height
When working at height, site operatives must ensure that the working area is cleared on a periodical basis
to ensure that there is continually a clear and safe working area to prevent slips trips and falls.
First aid
Refer to the onsite safety notice board for all first aid information.
A first aid box with enough equipment to cope with 20 workers on site should is provided within the site
office.
Emergency procedures
The client or principal contractor will ensure that the existing site emergency procedures are followed and
that relevant information is given to operatives at time of induction or when changes are made to
procedures.
The closest hospital with A&E is: Royal Berkshire Hospital, London Rd, Reading RG1 5AN
Page 4 of 4