Professional Documents
Culture Documents
Risk Assessment
Risk Rating
Probability
Severity
No Activity Hazards/Risk Hazard Effect low 1-4,
1-5
1-5
. Mid 5-14
High 15-
25
Underground facilities ,
cave in ,rest restricted
Electrocution Damage
access , Lack of Lighting ,
2 Excavation to pipeline , water 3 3 9 M
oxygen deficiency , Water
flooding .
flooding , poor
communication.
Hit to Person.
Vehicle Misleading of Vehicle
3 Movement Overturning Physical Injury 3 3 9 M
At site Toppling of vehicle
Vehicle accidents
Vehicle Misleading of Vehicle
3 Movement Overturning Physical Injury 3 3 9 M
At site Toppling of vehicle
Vehicle accidents
Lack of Earthing
Poor PPE's to work
Spark & Flash
Fire
Electrical shock *PH = Physical
7 Welding 4 5 20 H
Hazard
Burn Injury
Poor cables connections
Absence of ELCB
Observations / Comments:
Reviewed By Prepared By
TIFICATION AND RISK ASSESSMENT HIRA
Risk Rating
Probability
Severity
CONTROL MEASURES low 1-4, Responsibility
1-5
1-5
Mid 5-12
High 15-
25
Do the keep
the excavated
soil near the
excavation
area , vehicle
movmovement
should nonot
be allowed
near the
Check for any existing underground facilities , shoring must excavation ,
be provided to avoid sliding of soil , person should enter in warning signs
exavaexcavation with adequate PPE'S , If water floodin 1 2 2 L Site Supervisor,Engg should be
occurs must be drained out prior to enter in to displayed,sta
exavaexcavation. standard man
should be
available , use
adequate ppe
1 2 2 L Site Supervisor,Engg
Continuous Supervision should be there.
Managing traffic by providing safety & traffic signboards,
signalman etc.
Ensure the signal man & banks man near work area.
1 2 2 L Site Supervisor,Engg
Continuous Supervision should be there.
Managing traffic by providing safety & traffic signboards,
signalman etc.
Ensure the signal man & banks man near work area.
Scaffolding
tubes should
not have any
bends ,
Material Should be transferred from lower level to higher scaffolding
level through buckets , experienced person should erect the 1 2 2 L Site Supervisor,Engg erection should
scaffolding. be monitored
by supervisor
plumb checks.
Prepared By Approved By