Risk Hazard Risk/Impact Risk Assessment Control Measures Risk Assessment Responsible
No (Pre Controls) (Post Controls) Person
Risk Rating
Risk Rating
Probability
Probability
Categories
Categories
Severity
Severity
Poor Ergonomics Musculoskeletal 2 B P 2BP All workers involved in handling and lifting of 1 A P 1AP Engineer
01 injuries (MSI) or blocks must be trained on manual lifting.
repetitive strain
injuries (RSI) Manual lifting shall be avoided and it should be
replaced by trolleys.
Risk Hazard Risk/Impact Risk Assessment Control Measures Risk Assessment Responsible
No (Pre Controls) (Post Controls) Person
Risk Rating
Risk Rating
Probability
Probability
Categories
Categories
Severity
Severity
06 Short-Circuiting 3 C P 3C Electrician and operator shall ensure that all 2 B P 2BP Engineer
Electrocution, P
2 B A machine electrical connections are being 1 A A 1AA
Burns, Injuries,
2BA properly secured and insulated through cable
Property damage
trays.
Proper earthling has been provided.
The inlet and outlet power supply has been
provided as per manufacturer recommendations.
All electrical connections have been connected
to distribution boards having ELCB installed in it.
Water mixing hose shall be routed in such a way
that it should not be mixed with any electrical
connection.
07 Contact with 3 C P 3C Operator shall be wearing only recommended 2 B P 2BP Engineer
Amputation P
rotating blade PPEs including stainless steel mess hand
gloves, no loose clothes shall be allowed to wear
which has the potential to have contact with
moving blade.
One additional concrete block shall be
placed ,rear to the concrete block being cut
which will be serving as a cut off barrier for
revolving blade.
Engineer shall provide a cut off limit by providing
any mean on the moving shaft (Engineering
control)
Operator shall hold the concrete block at the
rear side of the block while pushing the concrete
block against the moving blade.
ABU DHABI GAS DEVELOPMENT COMPANY LIMITED
SHAH GAS DEVELOPMENT (SGD) PROGRAM
RISK ASSESSMENT and WORK INSTRUCTIONS
Risk Hazard Risk/Impact Risk Assessment Control Measures Risk Assessment Responsible
No (Pre Controls) (Post Controls) Person
Risk Rating
Risk Rating
Probability
Probability
Categories
Categories
Severity
Severity
Operator shall collect the cut blocks only after
machine is switched off and the blade is
retracted away from the blocks
Risk Hazard Risk/Impact Risk Assessment Control Measures Risk Assessment Responsible
No (Pre Controls) (Post Controls) Person
Risk Rating
Risk Rating
Probability
Probability
Categories
Categories
Severity
Severity
Work Instructions:
1. All hazard control measures prescribed in this Risk Assessment is issued as a work instruction to be implemented by site supervision.
2. All persons and vehicles must comply with Site HSE Rules and Requirements.
3. Under no circumstance shall any person will work under suspended load / bucket while manually handling/ loading / offloading from equipment.
4. Hand brake to be applied when workers are working near equipment for lifting/ transferring load to and from the equipment
5. Do a tool box talk with all site supervision, operators and operatives. Explain these control measures to all relevant operatives.
6. Housekeeping to be done and workplace to be made safe prior to leaving the workplace.
7. All persons shall sign their understanding and confirmation in the Tool Box Talk attendance sheet.
8. All construction waste will be removed daily from the work area.
9. All Near Misses and Accidents will be reported immediately to the on-duty Medic and site safety officers
10. Copy of this RA will be discussed in pre- start TBT. Copy will be available on site.
Prepared by Name Date and Signature Approved by Name Date and Signature
Sr, Project Engineer Sivaraman HSE Manager Larry Alzaga
Project Engineer Prabhakar Issued by Name Date and Signature
HSE Engineer Mohd. Salauddin Construction Manager Abdul Nasar
HSE Engineer Hassan Abbas Cc: HSE Files, Worksite