Date
RISK ASSESSMENT FOR
MS Ref. No.
XXXXXX Rev. No.
Probability
Probability
Sl. No.
Severity
Severity
Activity Risk Owner
PXS
PXS
Risks identified
1 Shifting of Manual Handling - 3 4 12 Approved method statement must be in place 1 4 4 Project Manager/
Equipment and Injury to Personnel prior to start the work activity Construction Manager,
Materials 3 4 12 Ensure Job safety analysis (JSA) is completed. 1 4 4 Plant Manager,
Collision/Collapse - Hazard identification and Specific Risk Project Engineer,
Injury to Personnel / Assessment must be carried out prior to heavy Foremen
Damage to work commencing.
equipment Project Lead HSE
Mechanical methods to be used where
Engineer for monitoring
possible, or multiple person lifting.
2 Mobile/ Manual Handling – 3 4 12 Approved method statement must be in place 1 4 4 Project Manager/
Tower Back injury/ Strain/ prior to start the work activity Construction Manager,
Scaffolds Sprain Ensure Job safety analysis (JSA) is completed. Plant Manager,
3 5 15 Ensure that scaffold is erected to 1 5 5 Project Engineer,
Collapse/Collision - manufacturer’s instructions. Foreman and
Injury to persons 4 5 20 Certified erectors only to erect scaffold as per 1 5 5 Scaffolding Foreman
training guidance and Instructions.
Falls from Height - 3 5 15 Erect Scaffold on firm level surface. 1 5 5 Project Lead HSE
Injury to Operative Min 3.5:1 Height to Base Ratio (Internal) Engineer for monitoring
Min 3:1 Height to Base Ratio (External)
Falling of Materials - Double handrail with the top hand rail erected
Injury to other to no less then 910mm with the gap between
persons the toe board and mid guard rail and the mid
and top guard rail to not exceed 470mm.
Toe boards should be no less then 150mm,
Access must be achieved from inside by way
of secured ladder.
Page 1 of 11
PROJECT NAME: PROJECT NO.
Date
RISK ASSESSMENT FOR
MS Ref. No.
XXXXXX Rev. No.
Probability
Probability
Sl. No.
Severity
Severity
Activity Risk Owner
PXS
PXS
Risks identified
Page 2 of 11
PROJECT NAME: PROJECT NO.
Date
RISK ASSESSMENT FOR
MS Ref. No.
XXXXXX Rev. No.
Probability
Probability
Sl. No.
Severity
Severity
Activity Risk Owner
PXS
PXS
Risks identified
Page 3 of 11
PROJECT NAME: PROJECT NO.
Date
RISK ASSESSMENT FOR
MS Ref. No.
XXXXXX Rev. No.
Probability
Probability
Sl. No.
Severity
Severity
Activity Risk Owner
PXS
PXS
Risks identified
Page 4 of 11
PROJECT NAME: PROJECT NO.
Date
RISK ASSESSMENT FOR
MS Ref. No.
XXXXXX Rev. No.
Probability
Probability
Sl. No.
Severity
Severity
Activity Risk Owner
PXS
PXS
Risks identified
7 Working at Falls from Height - 4 5 20 Approved method statement must be in place 1 5 5 Project Manager/
Height Back Injury, prior to start the work activity Construction Manager
Fractures, Cuts, Ensure Job safety analysis (JSA) is completed Project Engineer,
Bruises, Death 4 5 20 Planned work to ensure safe access, working 1 5 5 Foremen
platform and system of work.
Fall of Materials – Suitable signs and barriers below work to Project Lead HSE
Head Injury, Death, inform others of work above. Engineer for monitoring
Fractures, Cuts, Edge protection above 2m with double
Bruises handrail and toe boards, or brick guards/fans
to prevent materials falling.
Harnesses worn where protection is not
possible secured to fixed structure capable of
weight.
PPE including hard hats with chin straps must
be worn by all.
Working Platforms to be erected and used by
Competent Persons.
Roofs should be surveyed in plans prior to
work commencing, with routes for safe
walking.
Tools should be suitably secured to prevent
the fall of tools
8 Use of PPE Poor operation - 3 4 12 Employers must provide PPE, RPE, safety 1 4 4 Project Manager/
(Personal Injury to person equipment at all times when necessary. Construction Manager
protective 3 5 15 Ensure that all PPE, RPE is assessed for 1 5 5 Project Engineer,
Equipment), Poor seal - Death, or suitability for job, limitations, capability, Foremen
Page 5 of 11
PROJECT NAME: PROJECT NO.
Date
RISK ASSESSMENT FOR
MS Ref. No.
XXXXXX Rev. No.
Probability
Probability
Sl. No.
Severity
Severity
Activity Risk Owner
PXS
PXS
Risks identified
Page 6 of 11
PROJECT NAME: PROJECT NO.
Date
RISK ASSESSMENT FOR
MS Ref. No.
XXXXXX Rev. No.
Probability
Probability
Sl. No.
Severity
Severity
Activity Risk Owner
PXS
PXS
Risks identified
Page 7 of 11
PROJECT NAME: PROJECT NO.
Date
RISK ASSESSMENT FOR
MS Ref. No.
XXXXXX Rev. No.
Probability
Probability
Sl. No.
Severity
Severity
Activity Risk Owner
PXS
PXS
Risks identified
Page 8 of 11
PROJECT NAME: PROJECT NO.
Date
RISK ASSESSMENT FOR
MS Ref. No.
XXXXXX Rev. No.
Probability
Probability
Sl. No.
Severity
Severity
Activity Risk Owner
PXS
PXS
Risks identified
Page 9 of 11
PROJECT NAME: PROJECT NO.
Date
RISK ASSESSMENT FOR
MS Ref. No.
XXXXXX Rev. No.
Probability
Probability
Sl. No.
Severity
Severity
Activity Risk Owner
PXS
PXS
Risks identified
Page 10 of 11
PROJECT NAME: PROJECT NO.
Date
RISK ASSESSMENT FOR
MS Ref. No.
XXXXXX Rev. No.
Probability
Probability
Sl. No.
Severity
Severity
Activity Risk Owner
PXS
PXS
Risks identified
Approved
Reviewed By:
By:
Signature: Signature
Date: Date:
Page 11 of 11