Risk Assessment Risk level A Risk Level B Risk Level C Risk Level D Risk Level E
Standard 16 – 25 10- 15 5- 9 3-4 1-2
Likelihood x Severity Unacceptable Severe Risk Through review required Acceptable Level Acceptable Level
Subcon Permit Signature Subcon Dept Signature Subcont Site Signature Subcon HSE Signature
Reciver Head manager Manager
Name Name Name Name
Doosan Permit Signature Doosan Dept Signature Doosan Gen. Signature Doosan Gen. HSE Signature
Issuer Manager Manager Manager
Changyeol Song
Name Name Name Name
No. Work Activity Hazard Factor & E Type of Damage & RISK Control Measure & Detailed RISK Correcti
TUWAIQ CASTING & FORGING FACILTY PROJECT
TUWAIQ C&F Continuous (Baseline) Risk Assessment Register
GRADE
GRADE
H
information Environmental impact S Env. Impact L S T management Plan L S T In Charge on Date
S
5 Painting work on Fall of men and materials S Project Violation 4 4 16 A Make sure the scaffold is inspected and 3 4 12 B Work
elevated platform having GREEN TAG prior commencing Crew
Untrained workers activity.
Operator
Defective ladder Application of full body harness with double
lanyard while working in an elevated area in
Inadequate supervision excess of 1.8 mtr and above. Ensure
proper anchor to safe anchorage point
Pinch point Ensure proper anchor to safe anchorage
point.
Tripping hazard
Follow 100% tie off policy.
Obstructed access
Leaning, twisting, stooping shall be avoided
Un secured tools while working on elevated area.
Failure of operation. Keep the body part away from the line of
fire
Cut and crush injury
Identify all possible pinch point hazard. Use
Fall injury adequate hand gloves to eliminate pinch
point hazard
Entrapment
Avoid keeping of excessive materials on
Falling of unsecured tools the platform for evade tripping hazard.
caused bodily
Injury Provide adequate access and make sure
the access is clear from any obstruction
Injury to self and others.
Personal injury Tool belt and lanyard shall be used and
ensure tools are properly secured to
prevent from fall.
6 Spray painting by Uninspected/ defective S Project Violation 4 4 16 A Air compressor shall be inspected and 3 4 12 B Work
using air equipment approved by DOOSAN prior mobilization at Crew
compressor site
Noise Operator
Air compressor shall process a valid 3rd
Electric hazard party certification.
Contact with machine All cables are to be hung off the ground
rotating parts (2.10 meters) & kept dry.