TUWAIQ CASTING & FORGING FACILTY PROJECT

TUWAIQ C&F Continuous (Baseline) Risk Assessment Register

Contractor / Specific Date of Risk


Al Fanar
Subcontractor Location Assessment
Duration of
Work Discipline Civil No. of Works 15
Work
Activity Anchor Bolt Installation

Risk Assessment Risk level A Risk Level B Risk Level C Risk Level D Risk Level E
Standard 16 – 25 10- 15 5- 9 3-4 1-2
Likelihood x Severity Unacceptable Severe Risk Through review required Acceptable Level Acceptable Level

Review and Approval

Subcon Permit Signature Subcon Dept Signature Subcont Site Signature Subcon HSE Signature
Reciver Head manager Manager
Name Name Name Name

Doosan Permit Signature Doosan Dept Signature Doosan Gen. Signature Doosan Gen. HSE Signature
Issuer Manager Manager Manager
Changyeol Song
Name Name Name Name

No. Work Activity Hazard Factor & E Type of Damage & RISK Control Measure & Detailed RISK Correcti
TUWAIQ CASTING & FORGING FACILTY PROJECT
TUWAIQ C&F Continuous (Baseline) Risk Assessment Register

GRADE

GRADE
H
information Environmental impact S Env. Impact L S T management Plan L S T In Charge on Date
S

All personnel have attended the project


Safety Orientation and relevant safety
awareness training prior to site
mobilization.

The field supervisor or foreman shall be a


certified permit receiver and to coordinate
for permit approval to Doosan const. &
safety team.

The field supervisor shall perform a daily


Non-compliance to project tool box talk addressing the site hazard and
procedure & permit system discussing risk control to all crew member

Unawareness of emergency Everyone must know the emergency


procedures assembly point and emergency contact
numbers to be posted at work area.
Area Assessment Permit
1 & Preparation
Incompetent Personnel S Project Violation 2 2 4 D 2 1 2 E
Supervisor
Ensure that competency of all personnel is
Uninspected use of verified prior perform the operation and
equipment and tools. ensure that the operators are having the
valid third-party certification with them.

All equipment & tools shall be declared


upon entry of project gate and be
coordinated with Doosan Safety team for
inspection and approval

Heavy equipment shall have safety function


device, fire extinguisher and first aid kit in
place.

Homemade tools are not allowed to be use


in the project.
TUWAIQ CASTING & FORGING FACILTY PROJECT
TUWAIQ C&F Continuous (Baseline) Risk Assessment Register

Use of leather or cut resistance hand


gloves to eliminated or prevent hand injury
for handling sharp objects.

Sharp edges Where an object requires two or more


employees to handle it, one employee
Carrying of heavy items should give the direction for lifting and
lowering the object in unison.
Work
2 Manual Handling Repetitive lifting S Personal Injury 2 3 6 C 2 2 4 D
Crew
Never attempt to lift beyond your capacity
Lifting and carrying on (20 Kg). If in doubt test the objects’ weight
uneven and / or slippery before handling it: if it appears too heavy or
ground conditions bulky, obtain a mechanical lifting aid.

The work area shall be in good condition


and free from slips. Ensure clear access is
available.
TUWAIQ CASTING & FORGING FACILTY PROJECT
TUWAIQ C&F Continuous (Baseline) Risk Assessment Register

Make sure that all tools are in good


condition, inspected and color coded by
competent person as per project standard.

Visually inspect the tools and make sure no


defects occurred. DO not use damaged
tools.

Avoid using of home-made/ Fabricated


Uninspected/ Defective tools
tools.
Home-made/ Fabricated
All involved workers shall attend manual
tools
handling and hand power tool training.
Untrained workers
All involved workers shall attend hand and
power tool and manual handling training.
Obstructed access
Ensure workers are well aware in safe
Tripping hazard
manual handling technique and type of
workplace injuries associated with manual
Pinch point
Shutter handling.
Work
Shifting, Fixing Inadequate supervision Crew
Only competent personal shall assigned for
3 and installation, S Project Violation 4 4 16 A
carrying the activity.
3 4 12 B
Fixing of Manual handling hazard Operator
Anchor bolt Adequate access shall be provided and
Work at height hazard Injury
ensure that there is no obstruction on the
to self and others
access.
Poor decision
All unwanted material shall be removed
from the work area.
Entrapment
Remove shutter one by one and keep in
Fall injury
designated area.
Cut, wound
Use appropriate PPE such as hard hat,
safety shoe, leather hand gloves, safety
Failure of operation
glass and coverall.

Identify possible pinch point hazard and


keep the body part out of line of fire.

Required close supervision.

The area shall cordon off and post


appropriate warning signs.
TUWAIQ CASTING & FORGING FACILTY PROJECT
TUWAIQ C&F Continuous (Baseline) Risk Assessment Register

Defective/ uninspected air Air blower must be in good condition,


blower inspected and color coded periodically by
Electric hazard competent person
Dust
Untrained worker Prior to start work air blower shall visually
inspect and to ensure ready to use. Do not
Wet surface use defective air blower

Obstructed access Injury to Use dust mask and double eye protection
self and others (Goggles with face shield)
Electrocution
Work
Ensure the provision of exhaust to get
Crew
Respiratory issues adequate ventilation
4 Using of air
Suffocation
S Project Violation 4 4 16 A 3 4 12 B
blower for dust Operator
Poor decision Electrical cable shall elevate 2.10 Mtr off
cleaning
from ground to eliminate tripping hazard
Electric shock and cable damage.

Entrapment Involved workers shall obtain hand and


power tool training.

Extension leads shall not lay on wet surface


and use double insulated electrical cable.

Make sure that adequate access available


and access is clear from any obstruction
TUWAIQ CASTING & FORGING FACILTY PROJECT
TUWAIQ C&F Continuous (Baseline) Risk Assessment Register

Electrocution due to Prior to start the activity Tower light must be


grounding not provided inspected by competent person and valid
inspection sticker must be posted.
Improper Manual
Handling Grounding must be provided with
separately with each Tower light
Incompetent operator
All the Electrical connecting wires must be
Noise free of cut or abrasion

Oil spillage Daily check all the connection before use.


Dip tray must be provided.
Flying particle
All connections must be performed by
Machine failure authorized Electrician/Technician

Broken Glass Injury All loose fixtures must be fixed prior to start
due to hit by blasted hose
Hard barricades must be placed with
Back injury and other signage to restrict unauthorised entry.
sprains and strains
back pain Follow manual handling techniques and
maintain proper body posture while doing
Lack of knowledge of work manual handling activity.
procedure may lead to Work
accident. Where an object requires two or more Crew
5 Night Work use S Project Violation 4 4 16 A employees to handle it, one employee 3 4 12 B
of Tower Light Hearing impairment should give the direction for lifting and Operator
lowering the object in unison. Never
Environmental pollution attempt to lift beyond the capacity. Assess
the load prior lifting. if it appears too heavy
Eye injury or bulky, obtain a mechanical lifting aid
and/or somebody to help.
Failure of operation.
All involved workers shall attend “Manual
Cut injuries handling training”.

Leaning, twisting, stooping shall be avoided


while working on elevated area.

Ensure that glares are not generated at the


place of installation

Keep fire extinguisher nearby equipment.


Only authorized personnel can do the
maintenance of the equipment.

Inspected and colour coded Fire

Extinguisher must be available.

Ensure proper illumination provided as


above 100 lux.
TUWAIQ CASTING & FORGING FACILTY PROJECT
TUWAIQ C&F Continuous (Baseline) Risk Assessment Register

Use of appropriate PPE’s.

Material must be kept clear from access


(material storage area)
Poor housekeeping
Make sure proper housekeeping done after
Work
Obstructed access completion (housekeeping to be maintained
Crew
Personnel Injury before work starts alternatively for during
6 Housekeeping
Slips/trips/falls
S 3 1 3 D
the work and after work)
2 1 2 E
Field
Supervisor
Supervisor and safety personnel must close
monitor the work crew.

After the work completion, clean the waste/


spill of concrete from the project area.