Professional Documents
Culture Documents
Raheel Zafar
Department of Electrical Engineering
Lahore University of Management Sciences
raheel.zafar@lums.edu.pk
Outline
• Priority-list method
• Example 1
• Example 2
2
Priority-List Method
• The simplest unit commitment solution method consists of creating a
priority list of units.
• As we saw in the previous lectures, a simple shutdown or priority-list
scheme could be obtained after an exhaustive enumeration of all unit
combinations at each load level.
• Complete enumeration method provides the overall optimal but may be
extremely large to handle.
• For M periods, N units to commit, maximum number of possible
combinations is (2N-1)M.
• For 10-unit system, 24 hours, this value is 1.73 x 1072.
4
Example 1
• Consider a three generator system with
Example 1 cont..
6
Example 1 cont..
• A strict priority order for these units, based on the average production
cost, would order them as follows:
Example 1 cont..
8
Previous Example [Priority-List Scheme]
• Our shutdown rule is quite simple:
• When load is above 1000 MW, run all
three units.
• Between 1000 and 600 MW, run units
1 and 2.
• Below 600 MW, run only unit 1.
Example 2
10
Example 2 cont..
11
Example 2 cont..
12
Example 2 cont..
13
14
Suggested Readings
• Wood | 4.1, 4.2, 4.3
• Conejo | 7.1, 7.2
15
Thank you!
16