Professional Documents
Culture Documents
kwakuantoh@yahoo.com//0208201565; 0243225858
Learning Objectives
• Understand the concept of generator scheduling and optimum
dispatch
• Know some of the constraints considered in generator dispatch in a
power system operation
• Appreciate the conditions under which economic dispatch takes
place both in
➢a generating plant (dispatch amongst the units) and
➢in power system as a whole (dispatch amongst the plants)
• Gain an understanding of the application of Lagrange Method of
optimization in generator scheduling
• Know how to apply constraints to be able to solve some examples
of generator scheduling and economic dispatch
2
•Start of UNIT 5
3
5.1: Introduction
• A number of power plants are connected in parallel to supply
the system load by interconnection of generating stations.
4
5.1.1: Unit Commitment
Unit commitment is the allocation or apportioning of
demand/load amongst the generation units such that:
5
5.1.2: Objective of Optimum Generation Scheduling
• The objective of optimum generation scheduling for thermal
power plants is to
6
•Cost Types
7
5.1.3: Cost Types – fixed and variable
• Fixed costs:
i. capital investment
ii. interest charges on borrowed money
iii. labour costs and salary given to staff
iv. taxes and
v. other expenses that continue irrespective of the load on the power
system
• Variable costs – depend on operation and maintenance (O&M), and
are affected by
i. mechanical input (fuel or water) loading rates for the different generating units
ii. generation mix, i.e., combination of conventional hydro and thermal and
other energy sources to meet daily load requirements and
iii. control of losses caused by reactive flows
8 iv. purchase or sale of power.
•Generation Constraints
9
5.1.4: Constraints
i. Primary constraints
ii. Secondary constraints
iii. Dynamic constraints
iv. Spare capacity constraints
v. Thermal constraints of the transmission line
vi. Bus voltage and angle constraints and
vii. Operational constraints
10
5.1.4.1: Primary constraints
• The primary constraints arise out of the necessity for the system to
balance the load demand and generation at a bus
• They’re also called EQUALITY CONSTRAINTS.
• If PGi and QGi are the scheduled electrical generations
• If PDi and QDi are the respective load demands
• The following equations must be satisfied at the load bus.
PGi − PDi − Pline = M i = 0 QGi − QDi − Qline = N i = 0
j =1 j =1
11
5.1.4.2: Secondary constraints
• The secondary constraints arise due to physical and operational
limitations of the respective units and components
12
5.1.4.3: Dynamic constraints
• Dynamic constraints arise when fast changes in generation are
required for picking up the increasing load demand.
13
5.1.4.4: Spare capacity constraints
• In this constraint, the total generation available at any time
should be in excess of the total anticipated load demand and
any system loss by an amount not less than a specified minimum
spare capacity Psps
• Thus,
i =1
14
5.1.4.5: Thermal constraints of transmission lines
• These constraints arise when power injection or power
withdrawal is such that the maximum allowable heat on the line
is not exceeded.
15
5.1.4.6: Bus voltage and angle constraints
• These constraints arise in order to maintain voltage profile at
load bus and limit the overload capacity
• Hence
Vi min Vi Vi max , i = 1, 2, ..........N
ij min i ij max , j 1, j = 2, 3, ..........M
• N=number of units;
• M=number of loads
5.1.4.7: Operational constraints
• These relate to constraints that arise with the general operation
of the system components
18
5.1.5: Optimization Problem
• In a power system, a certain load demand can be met in an
infinite number of ways,
➢In this case, G2 is made to partake of the needed generation to meet extra load of 50
MW
➢The line losses now amount to 3 MW, (compare the 5 MW losses in Example 2).
➢The overall costs will be minimized at some appropriately chosen load division
between G1 and G2.
NOTE: There generally exists ONLY ONE power generation CONFIGURATION that is
OPTIMUM in terms of (i) system losses and (ii) cost minimization
•Input-Output Cost Curves
For Two Thermal Units
23
5.2 Input-Output cost curves for 2 thermal units
• Consider the input-output (cost/MW) curves of 2 thermal units
operating to share load.
25
5.3: Economic Power Dispatch for 2 units Within a
Power Pant
• To determine the economic distribution (dispatch) of load
between the various units, the variable operating costs of the
unit must be expressed in terms of the power output
• Let the load shared by (or generated at the outputs of) the two
alternators be respectively Pa , out and Pb, out
26
5.3: Economic Power Dispatch for 2 units Within a
Power Plant (2)
• For economic dispatch between the two units in a plant, the
known Lagrange condition to be satisfied is that:
27
5.4: Economic Power Dispatch for N units Within a
Power Plant – Use of Lagrange Multiplier
• For N units within a power plant, we apply the method of
Lagrange Multiplier
• Mathematically,
dF1 dF2 dF3 dFN
= = = ....... , = =
dP1 dP2 dP3 dPN
28
5.4: Economic Power Dispatch for N units Within a
Power Plant – Use of Lagrange Multiplier (2)
• Example 4.1:
• The incremental fuel costs in dollars per MW for a plant
consisting of two units are given by:
dF1 dF2
= 0.0080P1 + 8.0 = 0.0096P2 + 6.4
dP1 dP2
• Determine the following:
i. economic distribution of load between the units for plant
output of 1000 MW, and
ii. the corresponding incremental fuel cost of the plant.
29
5.4: Economic Power Dispatch for N units Within a
Power Plant – Use of Lagrange Multiplier (3)
• Solution 4.1:
• For economic distribution of a total load of 1000 MW between
the 2 units, their incremental costs must be the same.
P1 + P2 = 1000 and
0.0080P1 + 8.0 = 0.0096P2 + 6.4
= 0.0096(1000 − P1 ) + 6.4
Solving
P1 = 454.55 MW
P2 = 545.45 MW
Assume that both units are operating at all times, that total load
varies from 250 MW to 1250 MW, and that the maximum load and
minimum load on each unit are to be 625 MW and 100 MW,
respectively. Find the
a) incremental fuel cost allocation of load between the units for the minimum
cost of various total loads
b) economic distribution of load between the units for plant output of 1000 MW
31
5.4: Economic Power Dispatch for N units Within a
Power Plant – Use of Lagrange Multiplier (5)
• Solution 4.2 (a):
• At light loads, Unit 1 will operate at its lower limit of 100 MW and
have the higher incremental fuel cost given as
• When the output of Unit 2 is also 100 MW, the incremental cost for
Unit 2 is
• NOTES:
i. The different incremental costs would lead to UNECONOMIC operation.
ii. Moreover, the total minimum output from the plants would be (100 MW +
100 MW) or 200 MW, which is far from the minimum load demand of 250
MW, and this would also create frequency problems.
32
5.4: Economic Power Dispatch for N units Within a
Power Plant – Use of Lagrange Multiplier (6)
• Solution 4.2 (a)(2):
NOTES (CONTINUED):
iii. As the plant output increases, the additional load must come from Unit 2
until its incremental cost is 8.80 dollars/MW, so that economic power
dispatch will be attained.
iv. Until the point is reached when the incremental costs are equal, the
incremental fuel cost plant of the plant is determined by Unit 2 alone.
• When the plant load is 250 MW, Unit 1 will still be delivering its minimum of
100 MW and Unit 2 will have to supply the difference of 150 MW, with
incremental cost of
• This value of 7.84 dollars/MW of Plant 2 is still less than the incremental fuel
cost of 8.80 dollars/MW of Plant 1,
• And this will make the operation of the plant UNECONOMICAL.
33
5.4: Economic Power Dispatch for N units Within a
Power Plant – Use of Lagrange Multiplier (7)
• Solution 4.2 (a)(3):
NOTES (CONTINUED):
v. For the incremental cost of Unit 2 to equal 8.80 dollars/MW,
vi. And so the total plant output will be (100 + 250) or 350 MW.
vii. This means that given the incremental fuel costs of the two units of
the plant and the conditions attached, the plant can only operate
economically or optimally WHEN IT SUPPLIES A MINIMUM LOAD of
350 MW.
viii. And so as the question stands, it will be UNECONOMICAL for the
plant to supply a demand whose minimum is as low as 250 MW.
34
5.4: Economic Power Dispatch for N units Within a
Power Plant – Use of Lagrange Multiplier (8)
• Solution 4.2 (a)(4):
The Table below summarizes the scenarios given above.
Minimum Load demand PD
250 MW 250 MW 250 MW 350 MW
Unit 1 P1 100 100 150 100
1 8.80 8.80 9.20 8.80
Unit 2 P2 100 150 100 250
2 7.36 7.84 7.36 8.80
Ptotal P1 + P2 PD P1 + P2 = PD P1 + P2 = PD P1 + P2 = PD
(frequency (no frequency (no frequency (frequency will
problem) problem) problem) be maintained)
1 2 1 2 1 2 1 = 2
(uneconomical) (uneconomical) (uneconomical) (economical)
acceptable
Remarks unacceptable unacceptable unacceptable economic load
generation generation generation dispatch, but
minimum load
demand of 350
MW must be
guaranteed
35
5.4: Economic Power Dispatch for N units Within a
Power Plant – Use of Lagrange Multiplier (9)
• Solution 4.2 (a)(5):
The required output of each unit for ECONOMIC or optimum load
distribution is found by assuming various values of plant and calculating
each unit’s output and the total plant output. Typical results are shown
in Table below.
Plant Unit 1 Unit 2 Plant Load
plant P1 P2 P1 + P2
(dollars/MW) (MW) (MW) (MW)
7.84 100 150 250
8.80 100 250 350
9.60 200 333 533
10.40 300 417 717
11.20 400 500 900
12.00 500 583 1083
12.40 550 625 1175
13.00 625 625 1250
36
5.4: Economic Power Dispatch for N units Within a
Power Plant – Use of Lagrange Multiplier (10)
• Solution 4.2 (a)(6):
NOTES (CONTINUED):
ix. From the Table above, at plant = 12.4 dollars/MW, Unit 2 is
operating at its upper limit of 625 MW,
x. And so any additional load (say 625 MW) must come from Unit 1
alone, whose then determines the plant incremental cost plant.
xi. Thus for the additional 625 MW (after Unit 2 has reached its
upper limit) is as calculated:
37
5.4: Economic Power Dispatch for N units Within a
Power Plant – Use of Lagrange Multiplier (11)
• Solution 4.2 (b):
(b) For economic distribution of a total load of 1000 MW between the
2 units, their incremental costs must be the same.
Thus:
38
•UNECONOMIC (Arbitrary) Power
Dispatch
Within a POWER PLANT
39
5.5: Uneconomic Power Dispatch – With Arbitrary
Loading
• Example 5:
Determine the net fuel cost in dollars per hour for the arbitrary distribution of
a total load of 900 MW between the two units of the plant described in
Example 4, assuming the generations were equally distributed for the same
total load.
Solution 5: (NOTES)
i. Example 4 showed that for the most economic distribution of a 900 MW
load, Unit 1 should supply 400 MW and Unit 2 should supply 500 MW, and
the incremental cost for the plant was 11.20 dollars/MWh.
ii. And so, if the load is Shared Equally so that each unit supplies 450 MW, it
will tantamount to arbitrary loading, and hence UNECONOMIC.
iii. The increase in cost for Unit 1 (having to supply 450 MW instead of the
economical loading of 400 MW) is found by integrating the expression
for the incremental fuel cost for Unit 1.
40
5.5: Uneconomic Power Dispatch – With Arbitrary
Loading (2)
• Solution 5 (2):
iv. Similarly for Unit 2 (having to supply 450 MW instead of the economical
loading of 500 MW), the decrease in cost is found by integrating the
expression for the incremental fuel cost for Unit 2. Thus
vi. The net cost is dF = dF1 + dF2 = [(+570) + (–548)] = 22 dollars/h, or 192,720
dollars per year, positive value meaning an INCREASE IN COST.
41
•Economic Power Dispatch
Within a POWER SYSTEM
(Transmission losses are factored and
optimized)
42
5.6 Dispatch of N generators Within a Power System
– factoring transmission losses
• In dispatching for an entire power system, the following must
be noted:
➢we allocate the generations amongst plants (and NOT units)
➢we must factor the transmission losses
43
5.6 Dispatch of N generators Within a Power System
– factoring transmission losses (2)
• Mathematically,
dFk
Lk = system
dPk
dF1 dF2 dFk
L1 = L2 = ............ Lk = system
dP1 dP2 dPk
45
5.6 Dispatch of N generators Within a Power System
– factoring transmission losses (4)
• Solution 6:
• For a two-plant system, the transmission loss is given as
Ploss = P12 B11 + 2 P1P2 B12 + P2 2 B22
• Since all the load is directly at Plant 2 bus, varying P2 cannot affect
the transmission loss
B11 = 0.0004 MW −1
Ploss
• And = 2 P1 B11 + 2 P2 B12 = 2 P1 (0.0004) + (2 P2 0) = 0.0008P1
P1
Ploss
= 2 P2 B22 + 2 P1 B12 = (2 P2 0) = 0
P2
47
5.6 Dispatch of N generators Within a Power System
– factoring transmission losses (6)
• Solution 6 (3):
• The penalty factors are calculated as:
1 1
L1 = =
1 − Ploss / P1 1 − 0.0008P1
1 1
L2 = = = 1.0
1 − Ploss / P2 1− 0
• For the most economic loading such that the system system =$12.5/MWh
dF1 1
L1 = (0.010P1 + 8.5) = 12.5 P1 = 200 MW
dP1 (1 − 0.0008P1 )
dF2
L2 = (0.015P2 + 9.5) (1.0) = 12.5 P2 = 200 MW
dP2
48
5.6 Dispatch of N generators Within a Power System
– factoring transmission losses (6)
• Solution 6 (4):
• RESULT: Economic load dispatching therefore requires P1 = P2 = 200 MW,
i.e., in this particular case, equal division of load between the two
plants for system = $12.5/MWh.
49
•SELF ASSESSMENT
50
5.7 SELF ASSESSMENT
Q1) The incremental fuel costs in $/MWh for a plant consisting of two
units can be approximated by the following equations:
dF1 dF2
= 0.20P1 + 40.0 and = 0.25P2 + 30.0
dP1 dP2
• If both units are operating at all times and sharing a total load of 150
MW
i. what is the optimum allocation of the generation among the two
units
ii. what is the corresponding value of the plant incremental fuel
cost λ
iii. Should the load be shared equally between the two units,
comment on the change in annual fuel cost.
51
5.7 SELF ASSESSMENT (2)
Q2)Explain the term “economic power dispatch”. What conditions must
be met for economic load distribution between
i. plants in a power system
ii. generating units in a plant
Q3) The fuel cost functions (in units/MW) for each of the two generators
shown in the 2-bus system of the Fig below are:
The two units share a total load of 500 MW. Assuming the total system
losses amount 15 MW, and the transmission line loss equation is
. Determine
i. economic generation allocations to the generators
ii. actual transmission line loss at those optimum generations
iii. corresponding total fuel cost.
52
Thank You – End of Unit 5