You are on page 1of 19

HARGA BAHAN DAN UPAH TENAGA

HARGA
NO JENIS BAHAN UKURAN SATUAN KODE
(Rp.)
1 2 3 4 5 6
1. BAHAN ALAM: PASIR, BATU, KERIKIL,BATA, ASPAL
1.25 Batu Kali Belah 15/20 m3 BA-01 90,000.00
1.29 Batu Kali Pecah (Beton) 2/3 m3 BA-02 185,000.00
1.29.A Batu Kali Pecah (Beton) Kg BA-03 115.63
1.36 Batu Merah / Batu Bata Buah BA-04 450.00
1.61 Pasir Beton m3 BA-05 90,000.00
1.61.A Pasir Beton Kg BA-06 64.29
1.62 Pasir Pasang m3 BA-07 90,000.00
1.63 Pasir Urug m3 BA-08 55,000.00
1.64 PC Super Nut / Semen Warna Kg BA-09 5,000.00
1.70 Semen Portland ex. Gresik (P.C.Gresik) 50 kg Zak BA-10 50,000.00
1.70.a Semen Portland ex. Gresik (P.C.Gresik) Kg BA-11 1,000.00
1.71 Semen Portland ex. Gresik (P.C.Gresik) 40 kg Zak BA-12 40,000.00
1.72 Semen Portland ex. Gresik (P.C.Gresik) Kg BA-13 1,000.00
1.80 Tanah Urug Biasa m3 BA-14 50,000.00
1.81 Tanah Urug (Material Pilihan ) m3 BA-15 60,000.00

2. BAHAN KAYU & BAMBU

2.9 Dolken Kayu Galam Ø 8-10, p=4m Btg BK-01 20,000.00


2.20 Kayu Bekisting ( Papan Randu/Sengon ) 3/20 - 200 m3 BK-02 2,000,000.00
2.46 Kayu Meranti Balok (Mutu Kayu Klas III) 6/12, 6/15, 8/12 m3 BK-03 3,000,000.00
2.57 Plywood (120 x 240 cm) 9 mm Lbr BK-04 95,000.00

3 BAHAN PLAFOND, KERANGKA ATAP & PENUTUP ATAP

3.7 Bubungan Glasur ex. Kanmuri - Bh BP-01 25,000.00


3.9 Dinding Partisi ex. Kalsiboard (1200x2400x6)mm Lbr BP-02 75,000.00
3.25 Genteng Glasur ex. Kanmuri - Bh BP-03 12,000.00
3.35 Gypsum Tepung Kg BP-04 2,600.00
3.45 List Gypsum L = 10 cm m' BP-05 4,000.00
3.46 Papan GRC, ex Kalsiboard, setara (1200x2400x4)mm Lbr BP-06 65,000.00
3.47 Lisplank GRC 30 cm m' BP-07 15,000.00

4. BAHAN BESI / LOGAM

4.1 Aluminium Selimar, ex YKK m BS-01 90,000.00


4.2 Baja WF / Profil Siku Kg BS-02 10,000.00
4.3 Besi Beton Polos Kg BS-03 12,000.00
4.4 Besi Beton Ulir / Deformed Kg BS-04 9,000.00
4.5 Kawat Ikat Beton ( Bendrat ) Kg BS-05 12,000.00
4.6 Kawat Las Kg BS-06 40,000.00
4.7 Keni Besi (Elbouw) Ø1,5" - 6 m. Bh BS-07 75,000.00
4.8 Profil Kusen Alluminium, 5/12 ex YKK setara (5/12) m BS-08 175,000.00
4.9 Pintu Plat Aluminium ex.KM, lengkap engsel & pengunci 70 x 200 cm Unit BS-09 450,000.00
4.10 Aluminium Composite Panel, rangka besi siku m2 BS-10 175,000.00
4.11 Ralling Stainless Pagar Tangga Dia 2 m2 BS-11 450,000.00
4.12 Sun Screen Aluminium m2 BS-12 300,000.00
4.14 Main Truss C 75.35 m' BS-13 20,000.00
4.15 Reng ( TS 40.0,55) m' BS-14 15,000.00
4.16 Screw 12 - 14 x 20 bh BS-15 2,000.00
4.17 Screw 12 - 16 x 16 bh BS-16 1,500.00
4.18 Hollow Galvalume 20x40 m' BS-17 12,000.00
4.19 Compound kg BS-18 25,000.00
4.20 Cotton tape roll BS-19 15,000.00
4.21 Meja counter untuk pelayanan, bahan ACP dan Kaca m' BS-20 250,000.00
4.22 Pipa galvanish Ø3/4" (BSA) ljr BS-21 225,000.00
4.23 Door Closer bh BS-22 150,000.00
4.24 Grendel Handel bh BS-23 15,000.00
4.25 Karet sill m BS-24 2,000.00

5. BAHAN PENUNTUP LANTAI & DINDING

5.1 Tegel Keramik Dinding, ex.Asia Tile, setara 20 X 25 m2 BPLD-01 45,000.00


5.2 Tegel Keramik, Kasar 20 X 20 m2 BPLD-02 40,000.00
5.3 Tegel Keramik, Kasar 20 X 20 buah BPLD-03 1,600.00
5.4 Tegel Keramik, ex Milan, setara 40 X 40 m2 BPLD-04 65,000.00
5.5 Granit tile , ex.platinum, setara 60 x 60 m2 BPLD-05 115,000.00
5.6 Plint granit 10 x 60 bh BPLD-06 9,000.00

6. BAHAN PENGECATAN & BAHAN CAIR LAINNYA

6.1 Air Tawar m3 BC-01 200,000.00


6.2 Air Tawar Liter BC-02 200.00
6.3 Cat Tembok Vinylex ex. Nippon Paint, setara Kg BC-03 22,500.00
6.4 Cat Tembok Dulux Weathershield, setara Kg BC-04 36,000.00
6.5 Cat Dasar Anti Alkali (Alkali sealer, setara) Kg BC-05 19,000.00
6.6 Waterproof ex. SIKA setara Kg BC-06 55,000.00
6.7 Plamir Tembok Kg BC-07 20,000.00
6.8 Kertas Amplas lbr BC-08 5,000.00
6.9 Minyak Bekisting Liter BC-09 5,000.00

7. BAHAN SANITAIR

7.1 Bak Plastik Portabel 40x40 Bh BSA-01 300,000.00


7.2 Floor Drain Stailess Steel Bh BSA-02 25,000.00
7.3 Kloset Duduk Porselin Komplit ex. INA Bh BSA-03 1,850,000.00
7.4 Kloset Jongkok Porselin ex. INA Bh BSA-04 350,000.00
7.5 Pompa Air, Q=min.45ltr/s, Head 25mtr Bh BSA-05 450,000.00
7.6 Pasang Pompa Minibooster, Q=min.60 ltr/s Bh BSA-06 900,000.00
7.7 Tandon Air Stainless Steel, 1000 ltr, lengkap asesoris+AWL (otomatis) Bh BSA-07 7,500,000.00
7.8 Kran Air Baik Stainless Steel Ø 3/4" Bh BSA-08 25,000.00
7.9 Hand Shower (jet spray) Ø 1/2" Bh BSA-09 150,000.00
7.10 Rol TBA (Seal Tape) Rol BSA-10 5,000.00
7.11 Wastafel Besar Warna Muda ex. INA Bh BSA-11 250,000.00
7.12 Pengeboran Sumur Dangkal + Casing PVC Ø4" m' BSA-12 50,000.00

8. BAHAN JENIS KACA

8.1 Glass Blok Bening 20x20 Buah BJC-01 20,000.00


8.2 Daun Pintu Kaca 12 mm + asesoris (floor hinge, handel&kunci) t = 12 mm lembar BJC-02 3,250,000.00
8.3 Kaca Polos ex. Ashahimas, setara t = 8 mm m2 BJC-03 250,000.00
8.4 Kaca Rayban ex. Ashahimas, setara t = 5 mm m2 BJC-04 95,000.00
8.5 Kaca Es ex. Ashahimas, setara t = 5 mm m2 BJC-05 105,000.00
8.6 Kaca Cermin t = 5 mm m2 BJC-06 125,000.00
8.7 Sealent Kg BJC-07 160,000.00
8.8 Sealant tube BJC-08 40,000.00
11. BAHAN BETON CETAKAN

11.1 Buis Beton U Ø 30 cm Bh BBC-01 30,000.00


11.2 Paving Block, K-300 t = 6cm m2 BBC-02 90,000.00

12. BAHAN PIPA PVC

12.1 Pipa PVC Tipe AW Ø 3/4" - 400 Btg BPP-01 32,000.00


12.2 Pipa PVC Tipe AW Ø 3/4" - 400 m' BPP-02 8,000.00
12.3 Pipa PVC Tipe AW Ø 1 1/4" - 400 Btg BPP-03 45,000.00
12.4 Pipa PVC Tipe AW Ø 1 1/4" - 400 m' BPP-04 11,250.00
12.5 Pipa PVC Tipe AW Ø 1,5" - 400 Btg BPP-05 50,000.00
12.6 Pipa PVC Tipe AW Ø 1,5" - 400 m' BPP-06 12,500.00
12.7 Pipa PVC Tipe AW Ø 2" - 400 Btg BPP-07 65,000.00
12.8 Pipa PVC Tipe AW Ø 2" - 400 m' BPP-08 16,250.00
12.9 Pipa PVC Tipe AW Ø 3" - 400 Btg BPP-09 70,000.00
12.10 Pipa PVC Tipe AW Ø 3" - 400 m' BPP-10 17,500.00
12.11 Pipa PVC Tipe AW Ø 4" - 400 Btg BPP-11 85,000.00
12.12 Pipa PVC Tipe AW Ø 4" - 400 m' BPP-12 21,250.00
12.13 Stop kran 11/2" bh BPP-13 30,000.00
12.14 Stop kran 1" bh BPP-14 20,000.00
12.15 Stop kran 2" bh BPP-15 45,000.00
12.16 Valve 1,5 bh BPP-16 50,000.00

13. BAHAN JENIS PAKU

13.1 Paku Kalsiboard Kg BJP-01 30,000.00


13.2 Paku Kayu 2.5" - 5" Kg BJP-02 12,000.00
13.3 Paku Skrup 1" Kg BJP-03 25,000.00
13.4 Paku Skrup Fixer Buah BJP-04 1,500.00
13.5 Dynabolt 10 mm 10mm bh BJP-05 7,500.00

14. BAHAN PERALATAN LISTRIK

14.1 Fitting Plafon Set BPL-01 12,000.00


14.2 Isolator Keramik Bh BPL-02 1,500.00
14.3 Isolasi Bh BPL-03 1,500.00
14.4 Kabel BC 10 mm² m BPL-04 15,000.00
14.4 Kabel BC 50 mm² m BPL-05 25,000.00
14.5 Kabel NYM, 2 x 2.5 ex. Supreme m BPL-06 8,000.00
14.6 Kabel NYM, 3 x 2.5 ex. Supreme m BPL-07 12,000.00
14.7 Kabel Pompa NYY 4 x 10 mm2 m BPL-08 14,000.00
14.8 Kabel Twsited 4 x 16 mm2 m BPL-09 10,000.00
14.9 Klem Bh BPL-10 500.00
14.10 Lampu LED (13 Watt +fixture) Bh BPL-11 75,000.00
14.11 Lampu Baret (TL Ring 32 Watt + fixture) Bh BPL-12 250,000.00
14.12 Lampu Downlight Inbow (LED 13 Watt + fixture) Bh BPL-13 150,000.00
14.13 Lampu TL RMI SAKA (2 x 18 Watt + fixture) Bh BPL-14 350,000.00
14.14 Lampu TL RMI SAKA (2 x 36 Watt + fixture) Bh BPL-15 750,000.00
14.15 Exhaust Fan, type Ceiling, 10" Bh BPL-16 500,000.00
14.16 Saklar tunggal (10 A) ex : Broco Bh BPL-17 20,000.00
14.17 Saklar ganda (10 A) ex : Broco Bh BPL-18 22,000.00
14.18 Stop Kontak 1 phasa (16 A) Bh BPL-19 17,500.00
14.19 Las doof Bh BPL-20 10,000.00
14.21 Pipa Pralon 5/8 Lonjor BPL-21 14,450.00
14.22 Pipa Pralon 5/8 M' BPL-22 2,000.00
14.23 Sekering MCB Thermis 10-16 A Bh BPL-23 15,000.00
14.24 Sekering MCB Thermis 10 A Bh BPL-24 20,000.00
14.25 Sakelar / Handel Pemindah Arus Bh BPL-25 75,000.00
14.26 Stater Lampu TL Bh BPL-26 5,000.00
14.27 Stop Kontak ex. Broco Bh BPL-27 17,500.00
14.28 Sikring lengkap dengan Box Bh BPL-28 250,000.00
14.29 T Doos PVC Bh BPL-29 1,150.00
14.30 MCCB 3p 25A,10kvA Bh BPL-30 250,000.00
14.31 MCCB 3p 20A,10kvA Bh BPL-31 200,000.00
14.32 MCB 1p 10A,6kvA Bh BPL-32 150,000.00
14.33 MCB 1p 16A,6kvA Bh BPL-33 200,000.00
14.34 Panel Box MDP Bh BPL-34 1,500,000.00
14.35 Panel Box SDP Bh BPL-35 1,500,000.00
14.36 Voltmeter + switch Bh BPL-36 250,000.00
14.37 Amperemeter + ct Bh BPL-37 200,000.00
14.38 Pilot Lamp Bh BPL-38 75,000.00
14.39 Busbar set Bh BPL-39 100,000.00
14.40 Surge Arrester 3 Phasa, (3+N) Bh BPL-40 150,000.00
14.41 Batang Split 150 cm Bh BPL-41 250,000.00
14.42 Titik grounding (Pengeboran + batang elektroda) Bh BPL-42 500,000.00

15. UPAH KERJA

15.1 Mandor O-H UK-01 90,000.00


15.2 Kepala Tukang O-H UK-02 85,000.00
15.3 Tukang O-H UK-03 75,000.00
15.4 Pekerja O-H UK-04 65,000.00
15.5 tukang kayu O-H UK-05 75,000.00
15.6 tukang batu O-H UK-06 75,000.00
15.7 O-H UK-07 -
15.8 O-H UK-08 -
PEMERINTAH KABUPATEN KEDIRI
ANALISA HARGA BAHAN DAN UPAH TENAGA
TAHUN ANGGARAN 2017

PEKERJAAN PERSIAPAN
HARGA
NOMOR URAIAN KEGIATAN KOEFISIEN SATUAN HARGA
SATUAN
Pembersihan Lapangan dan Peralatan (m2)
Tenaga
UK-04 Pekerja 0.100 OH Rp 65,000.00 = Rp 6,500.00
UK-01 Mandor 0.050 OH Rp 90,000.00 = Rp 4,500.00
Jumlah = Rp 11,000.00
Dibulatkan = Rp 11,000.00
Pengukuran dan Pasang Papan Bowplank (m')
Bahan
BK-02 Kayu sengon 0.012 m3 Rp 2,000,000.00 = Rp 24,000.00
BJP-02 Paku biasa 2" - 5" 0.020 Kg Rp 12,000.00 = Rp 240.00
BK-02 Kayu papan sengon 0.007 m3 Rp 2,000,000.00 = Rp 14,000.00
Tenaga
UK-04 Pekerja 0.100 OH Rp 65,000.00 = Rp 6,500.00
UK-05 Tukang Kayu 0.100 OH Rp 75,000.00 = Rp 7,500.00
UK-02 Kepala Tukang Kayu 0.010 OH Rp 85,000.00 = Rp 850.00
UK-01 Mandor 0.005 OH Rp 90,000.00 = Rp 450.00
Jumlah = Rp 53,540.00
Dibulatkan = Rp 53,500.00

PEKERJAAN TANAH
Urug kembali bekas galian
UK-04 Pekerja 0.1920 OH Rp. 65,000.00 = Rp. 12,480.00
UK-01 Mandor 0.0150 OH Rp. 90,000.00 = Rp. 1,350.00
Jumlah = Rp. 13,830.00
Dibulatkan = Rp. 13,800.00
Penggalian Tanah Biasa (m3) kedalaman 1 m
UK-04 Pekerja 0.75 OH Rp 65,000.00 = Rp. 48,750.00
UK-01 Mandor 0.050 OH Rp 90,000.00 = Rp. 4,500.00
Jumlah = Rp. 53,250.00
Dibulatkan = Rp. 53,200.00
Mengurug 1 m3 Tanah Urug
BA-15 Tanah Urug ( Bahan) 1.20 m3 Rp 60,000.00 = Rp. 72,000.00
UK-04 Pekerja 0.3000 OH Rp 65,000.00 = Rp. 19,500.00
UK-01 Mandor 0.0100 OH Rp 90,000.00 = Rp. 900.00
Jumlah = Rp. 92,400.00
Dibulatkan = Rp. 92,400.00
Mengurug 1 m3 Pasir Urug
BA-08 Pasir Urug ( Bahan) 1.20 m3 Rp 55,000.00 = Rp. 66,000.00
UK-04 Pekerja 0.3000 OH Rp 65,000.00 = Rp. 19,500.00
UK-01 Mandor 0.0100 OH Rp 90,000.00 = Rp. 900.00
Jumlah = Rp. 86,400.00
Dibulatkan = Rp. 86,400.00

PEKERJAAN PASANGAN
Memasang 1 m3 batu kosong (aanstamping)
BA-07 Pasir Pasang 0.432 m3 Rp 90,000.00 = Rp. 38,880.00
BA-01 Batu Belah 15/20 cm 1.200 m3 Rp 90,000.00 = Rp. 108,000.00

UK-04 Pekerja 0.780 OH Rp 65,000.00 = Rp. 50,700.00


UK-05 Tukang Batu 0.390 OH Rp 75,000.00 = Rp. 29,250.00
UK-02 Kepala Tukang Batu 0.039 OH Rp 85,000.00 = Rp. 3,315.00
UK-01 Mandor 0.039 OH Rp 90,000.00 = Rp. 3,510.00
Jumlah = Rp. 233,655.00
Dibulatkan = Rp. 233,600.00
Pemasangan 1 m3 Pondasi Batu Belah Campuran 1 PC : 4 PP
BA-07 Pasir Pasang 0.520 m3 Rp 90,000.00 = Rp. 46,800.00
BA-11 Semen PC (Portland Cement) 40 kg 163.000 Kg Rp 1,000.00 = Rp. 163,000.00
BA-01 Batu Belah 15/20 cm 1.200 m3 Rp 90,000.00 = Rp. 108,000.00

UK-04 Pekerja 1.500 OH Rp 65,000.00 = Rp. 97,500.00


UK-05 Tukang Batu 0.750 OH Rp 75,000.00 = Rp. 56,250.00
UK-02 Kepala Tukang Batu 0.075 OH Rp 85,000.00 = Rp. 6,375.00
UK-01 Mandor 0.075 OH Rp 90,000.00 = Rp. 6,750.00
Jumlah = Rp. 484,675.00
Dibulatkan = Rp. 484,600.00
Pemasangan 1 m2 Dinding Batu Bata Merah (5 X 11 X 22)cm tebal 1/2 Bata Campuran Spesi 1 Pc : 6 PP
BA-04 Batu Bata Merah Kelas 1 70.000 Buah Rp 450.00 = Rp. 31,500.00
BA-11 Semen PC (Portland Cement) 50 kg 8.320 Kg Rp 1,000.00 = Rp. 8,320.00
BA-07 Pasir Pasang 0.049 m 3
Rp 90,000.00 = Rp. 4,410.00

UK-04 Pekerja 0.300 OH Rp 65,000.00 = Rp. 19,500.00


UK-05 Tukang Batu 0.100 OH Rp 75,000.00 = Rp. 7,500.00
UK-02 Kepala Tukang Batu 0.010 OH Rp 85,000.00 = Rp. 850.00
UK-01 Mandor 0.008 OH Rp 90,000.00 = Rp. 747.00
Jumlah = Rp. 72,827.00
Dibulatkan = Rp. 72,800.00
Memasang 1 m2 Plesteran 1 PC : 6 PP : tebal 15 mm
BA-11 PC (Portland Cement) 4.416 Kg Rp 1,000.00 = Rp. 4,416.00
BA-07 Pasir Pasang 0.027 m 3
Rp 90,000.00 = Rp. 2,430.00

UK-04 Pekerja 0.300 OH Rp 65,000.00 Rp. 19,500.00


UK-05 Tukang Batu 0.150 OH Rp 75,000.00 Rp. 11,250.00
UK-02 Kepala Tukang 0.015 OH Rp 85,000.00 = Rp. 1,275.00
UK-01 Mandor 0.015 OH Rp 90,000.00 = Rp. 1,350.00
Jumlah = Rp. 40,221.00
Dibulatkan = Rp. 40,200.00
Memasang 1 m2 Acian
BA-11 PC (Portland Cement) 3.200 Kg Rp 1,000.00 = Rp. 3,200.00

UK-04 Pekerja 0.150 OH Rp 65,000.00 = Rp. 9,750.00


UK-05 Tukang Batu 0.100 OH Rp 75,000.00 = Rp. 7,500.00
UK-02 Kepala Tukang 0.010 OH Rp 85,000.00 = Rp. 850.00
UK-01 Mandor 0.010 OH Rp 90,000.00 = Rp. 900.00
Jumlah = Rp. 22,200.00
Dibulatkan = Rp. 22,200.00

PEKERJAAN PEMBETONAN
Membuat 1 m3 Lantai Kerja Beton Mutu F'c = 7,4 Mpa (K100), Slump (3-6) cm, w/c = 0,87
BA-11 PC ( Portland Cement ) 230.000 Kg Rp 1,000.00 = Rp 230,000.00
BA-06 Pasir Beton 893.000 Kg Rp 64.29 = Rp 57,407.14
BA-03 Koral 1027.000 Kg Rp 115.63 = Rp 118,746.88
BC-02 Air 200.000 Liter Rp 200.00 = Rp 40,000.00

UK-04 Pekerja 1.200 OH Rp 65,000.00 = Rp 78,000.00


UK-05 Tukang Batu 0.200 OH Rp 75,000.00 = Rp 15,000.00
UK-02 Kepala Tukang 0.020 OH Rp 85,000.00 = Rp 1,700.00
UK-01 Mandor 0.060 OH Rp 90,000.00 = Rp 5,400.00
Jumlah = Rp 546,254.02
Dibulatkan = Rp 546,200.00
Membuat 1 m3 Beton Mutu F'c = 19,3 Mpa (K225), Slump (12±2) cm, w/c = 0,58
BA-11 PC ( Portland Cement ) 371.000 Kg Rp 1,000.00 = Rp 371,000.00
BA-06 Pasir Beton 698.000 Kg Rp 64.29 = Rp 44,871.43
BA-03 Koral 1047.000 Kg Rp 115.63 = Rp 121,059.38
BC-02 Air 215.000 Liter Rp 200.00 = Rp 43,000.00

UK-04 Pekerja 1.500 OH Rp 65,000.00 = Rp 97,500.00


UK-05 Tukang Batu 0.050 OH Rp 75,000.00 = Rp 3,750.00
UK-02 Kepala Tukang 0.010 OH Rp 85,000.00 = Rp 850.00
UK-01 Mandor 0.070 OH Rp 90,000.00 = Rp 6,300.00
Jumlah = Rp 688,330.80
Dibulatkan = Rp 688,300.00
Pembesian 1 kg dengan Besi Polos atau Besi Ulir
BS-03 Besi beton (Polos / Ulir) 10.500 Kg Rp 12,000.00 = Rp 126,000.00
BS-05 Kawat Beton 0.100 Kg Rp 12,000.00 = Rp 1,200.00

UK-04 Pekerja 0.070 OH Rp 65,000.00 = Rp 4,550.00


UK-05 Tukang Besi 0.050 OH Rp 75,000.00 = Rp 3,750.00
UK-02 Kepala Tukang 0.005 OH Rp 85,000.00 = Rp 425.00
UK-01 Mandor 0.004 OH Rp 90,000.00 = Rp 360.00
Jumlah = Rp 136,285.00
Harga 1 kg = Rp 13,628.50
Dibulatkan = Rp 13,600.00
Memasang 1 m2 Bekisting untuk Sloof
BK-02 Kayu Kelas III (Sengon) 0.045 m3 Rp 2,000,000.00 = Rp 90,000.00
BJP-02 Paku 5 cm - 10 cm 0.300 Kg Rp 12,000.00 = Rp 3,600.00
BC-09 Minyak Bekisting 0.100 Liter Rp 5,000.00 = Rp 500.00

UK-04 Pekerja 0.660 OH Rp 65,000.00 = Rp 42,900.00


UK-05 Tukang Kayu 0.330 OH Rp 75,000.00 = Rp 24,750.00
UK-02 Kepala Tukang 0.033 OH Rp 85,000.00 = Rp 2,805.00
UK-01 Mandor 0.006 OH Rp 90,000.00 = Rp 540.00
Utk Pek. Bangunan Material dipakai 1X Harga 1X pakai = Rp 165,095.00
Dibulatkan = Rp 165,000.00
Utk Pek.Bangunan 1 Lt. Material dipakai 2X Harga 2X pakai = Rp 117,950.00
Dibulatkan = Rp 117,950.00
Memasang 1 m2 Bekisting untuk Kolom
BK-02 Kayu Kelas III (Sengon) 0.040 m3 Rp 2,000,000.00 = Rp 80,000.00
BJP-02 Paku 5 cm - 10 cm 0.400 Kg Rp 12,000.00 = Rp 4,800.00
BC-09 Minyak Bekisting 0.200 Liter Rp 5,000.00 = Rp 1,000.00
BK-03 Balok Kayu Kelas II 0.015 m3 Rp 3,000,000.00 = Rp 45,000.00
BK-04 Plywood tebal 9 mm 0.350 Lbr Rp 95,000.00 = Rp 33,250.00
BK-01 Dolken Kayu.Galam,Ø 8-10 cm,pj. 4m 2.000 Batang Rp 20,000.00 = Rp 40,000.00

UK-04 Pekerja 0.660 OH Rp 65,000.00 = Rp 42,900.00


UK-05 Tukang Kayu 0.330 OH Rp 75,000.00 = Rp 24,750.00
UK-02 Kepala Tukang 0.033 OH Rp 85,000.00 = Rp 2,805.00
UK-01 Mandor 0.006 OH Rp 90,000.00 = Rp 540.00
Utk Pek. Bangunan Material dipakai 1X Harga 1X pakai = Rp 275,045.00
Dibulatkan = Rp 275,000.00
Utk Pek. Bangunan 1 Lt. Material dipakai 2X Harga 2X pakai = Rp 172,975.00
Dibulatkan = Rp 172,975.00
Memasang 1 m2 Bekisting untuk Balok
BK-02 Kayu Kelas III (Sengon) 0.040 m3 Rp 2,000,000.00 = Rp 80,000.00
BJP-02 Paku 5 cm - 10 cm 0.400 Kg Rp 12,000.00 = Rp 4,800.00
BC-09 Minyak Bekisting 0.200 Liter Rp 5,000.00 = Rp 1,000.00
BK-03 Balok Kayu Kelas II 0.018 m3 Rp 3,000,000.00 = Rp 54,000.00
BK-04 Plywood tebal 9 mm 0.350 Lbr Rp 95,000.00 = Rp 33,250.00
BK-01 Dollken Kayu.Galam,Ø 8-10 cm,pj. 4m 2.000 Batang Rp 20,000.00 = Rp 40,000.00

UK-04 Pekerja 0.660 OH Rp 65,000.00 = Rp 42,900.00


UK-05 Tukang Kayu 0.330 OH Rp 75,000.00 = Rp 24,750.00
UK-02 Kepala Tukang 0.033 OH Rp 85,000.00 = Rp 2,805.00
UK-01 Mandor 0.006 OH Rp 90,000.00 = Rp 540.00
Utk Pek. Bangunan Material dipakai 1X Harga 1X pakai = Rp 284,045.00
Dibulatkan = Rp 284,000.00
Utk Pek. Bangunan 1 Lt. Material dipakai 2X Harga 2X pakai = Rp 177,475.00
Dibulatkan = Rp 177,475.00
Memasang 1 m2 Bekisting untuk Plat Lantai
BK-02 Kayu Kelas III (Sengon) 0.040 m3 Rp 2,000,000.00 = Rp 80,000.00
BJP-02 Paku 5 cm - 12 cm 0.400 Kg Rp 12,000.00 = Rp 4,800.00
BC-09 Minyak Bekisting 0.200 Liter Rp 5,000.00 = Rp 1,000.00
BK-03 Balok Kayu Kelas II 0.015 m3 Rp 3,000,000.00 = Rp 45,000.00
BK-04 Plywood tebal 9 mm 0.350 Lbr Rp 95,000.00 = Rp 33,250.00
BK-01 Dollken Kayu.Galam,Ø 8-10 cm,pj. 4m 6.000 Batang Rp 20,000.00 = Rp 120,000.00

UK-04 Pekerja 0.660 OH Rp 65,000.00 = Rp 42,900.00


UK-05 Tukang Kayu 0.330 OH Rp 75,000.00 = Rp 24,750.00
UK-02 Kepala Tukang 0.033 OH Rp 85,000.00 = Rp 2,805.00
UK-01 Mandor 0.006 OH Rp 90,000.00 = Rp 540.00
Utk Pek. Bangunan Material dipakai 1X Harga 1X pakai = Rp 355,045.00
Dibulatkan = Rp 355,000.00
Utk Pek. Bangunan 1 Lt. Material dipakai 2X Harga 2X pakai = Rp 212,975.00
Dibulatkan = Rp 212,975.00
Memasang 1 m' Kolom Praktis Beton Bertulang (12/12)
BK-02 Kayu Kelas III (Sengon) 0.002 m3 Rp 2,000,000.00 = Rp 4,000.00
BJP-02 Paku 5 cm - 12 cm 0.010 Kg Rp 12,000.00 = Rp 120.00
BS-03 Besi Beton Polos 3.000 Kg Rp 12,000.00 = Rp 36,000.00
BS-05 Kawat Beton 0.045 Kg Rp 12,000.00 = Rp 540.00
BA-11 PC ( Portland Cement ) 4.000 Kg Rp 1,000.00 = Rp 4,000.00
BA-06 Pasir Beton 0.006 m3 Rp 64.29 = Rp 0.39
BA-03 Koral 0.009 m3 Rp 115.63 = Rp 1.04

UK-04 Pekerja 0.180 OH Rp 65,000.00 = Rp 11,700.00


UK-05 Tukang Batu 0.020 OH Rp 75,000.00 = Rp 1,500.00
UK-05 Tukang Kayu 0.020 OH Rp 75,000.00 = Rp 1,500.00
UK-05 Tukang Besi 0.020 OH Rp 75,000.00 = Rp 1,500.00
UK-02 Kepala Tukang 0.006 OH Rp 85,000.00 = Rp 510.00
UK-01 Mandor 0.009 OH Rp 90,000.00 = Rp 810.00
Utk Pek. Bangunan Material dipakai 1X Harga 1X pakai = Rp 62,181.43
Dibulatkan = Rp 62,100.00
Utk Pek. Bangunan 1 Lt. Material dipakai 2X Harga 2X pakai = Rp 39,769.29
Dibulatkan = Rp 39,769.29

PEKERJAAN KUSEN, PINTU DAN JENDELA


Memasang 1 m' Kusen Pintu Alluminium
BS-01 Profil Alluminium, 5/12 ex YKK setara 1.0500 m Rp. 90,000.00 = Rp. 94,500.00
BJP-04 Skrup Fixer 2.000 buah Rp. 1,500.00 = Rp. 3,000.00
BJC-07 Sealant 0.060 tube Rp. 160,000.00 = Rp. 9,600.00

UK-04 Pekerja 0.043 OH Rp. 65,000.00 = Rp. 2,795.00


UK-05 Tukang 0.043 OH Rp. 75,000.00 = Rp. 3,225.00
UK-02 Kepala Tukang 0.0043 OH Rp. 85,000.00 = Rp. 365.50
UK-01 Mandor 0.0021 OH Rp. 90,000.00 = Rp. 189.00
Jumlah = Rp. 113,674.50
Dibulatkan = Rp. 113,600.00
1 m2 Pasang daun jendela / BV. aluminium panil kaca
BS-01 Slimar Aluminium, ex YKK setara 1.100 m Rp. 90,000.00 = Rp. 99,000.00
BJP-03 Paku skrup 0.360 kg Rp. 25,000.00 = Rp. 9,000.00
BJC-03 Kaca polos 5 mm 1.000 m2 Rp. 250,000.00 = Rp. 250,000.00
BS-09 Engsel Casement 1.000 pasang Rp. 450,000.00 = Rp. 450,000.00
BS-23 Grendel Handel 1.000 bh Rp. 15,000.00 = Rp. 15,000.00
BS-24 Karet sill 3.700 m Rp. 2,000.00 = Rp. 7,400.00
Alat bantu 10.000 % Rp. = Rp. 0.00

UK-04 Pekerja 0.043 OH Rp. 65,000.00 = Rp. 2,795.00


UK-05 Tukang 0.043 OH Rp. 75,000.00 = Rp. 3,225.00
UK-02 Kepala Tukang 0.0043 OH Rp. 85,000.00 = Rp. 365.50
UK-01 Mandor 0.0021 OH Rp. 90,000.00 = Rp. 189.00
Jumlah = Rp. 836,974.50
Dibulatkan = Rp. 836,900.00
Pasang 1 m2 kaca, tebal 8 mm
BJC-03 Kaca polos 8 mm 1.05000 m2 Rp. 250,000.00 = Rp. 262,500.00

UK-04 Pekerja 0.01500 OH Rp. 65,000.00 = Rp. 975.00


UK-05 Tukang Kayu 0.15000 OH Rp. 75,000.00 = Rp. 11,250.00
UK-02 Kepala Tukang 0.01500 OH Rp. 85,000.00 = Rp. 1,275.00
UK-01 Mandor 0.00075 OH Rp. 90,000.00 = Rp. 67.50
Jumlah = Rp. 276,067.50
Dibulatkan = Rp. 276,000.00

PEKERJAAN RANGKA ATAP


Memasang 1 kg Besi Profil
BS-02 Besi Profil 1.150 Kg Rp. 10,000.00 = Rp. 11,500.00
Alat Bantu 15% Rp. 1,500.00 = Rp. 225.00

UK-04 Pekerja 0.060 OH Rp. 65,000.00 = Rp. 3,900.00


UK-05 Tukang Las 0.060 OH Rp. 75,000.00 = Rp. 4,500.00
UK-02 Kepala Tukang 0.006 OH Rp. 85,000.00 = Rp. 510.00
UK-01 Mandor 0.003 OH Rp. 90,000.00 = Rp. 270.00
Jumlah = Rp. 20,905.00
Dibulatkan = Rp. 20,900.00
Memasang 1 m2 Rangka Atap Genteng Glazur, Galvalume TRUE CORE setara
BS-13 Main Truss C 75.75 2.100 m' Rp. 20,000.00 = Rp. 42,000.00
BS-14 Reng ( TS 40.0,55) 3.8462 m' Rp. 15,000.00 = Rp. 57,692.31
BS-15 Screw 12 - 14 x 20 4.000 bh Rp. 2,000.00 = Rp. 8,000.00
BS-16 Screw 12 - 16 x 16 6.000 bh Rp. 1,500.00 = Rp. 9,000.00

UK-04 Pekerja 0.100 OH Rp. 65,000.00 = Rp. 6,500.00


UK-05 Tukang Kayu 0.100 OH Rp. 75,000.00 = Rp. 7,500.00
UK-02 Kepala Tukang 0.010 OH Rp. 85,000.00 = Rp. 850.00
UK-01 Mandor 0.005 OH Rp. 90,000.00 = Rp. 450.00
Jumlah = Rp. 131,992.31
Dibulatkan = Rp. 131,900.00
Pasang 1 m2 atap Genteng Glazur, ex Kanmuri
Bahan
BP-03 Genteng Glazur ex Kanmuri 14.0000 Buah Rp. 12,000.00 = Rp. 168,000.00
Tenaga
UK-04 Pekerja 0.1200 OH Rp. 65,000.00 = Rp. 7,800.00
UK-05 Tukang Kayu 0.0600 OH Rp. 75,000.00 = Rp. 4,500.00
UK-02 Kepala Tukang 0.0060 OH Rp. 85,000.00 = Rp. 510.00
UK-01 Mandor 0.0080 OH Rp. 90,000.00 = Rp. 720.00
Jumlah = Rp. 181,530.00
Dibulatkan = Rp. 181,500.00
Pasang 1 m' Bubungan Glasur ex Kamuri
Bahan
BP-01 Bubungan Glasur ex Kamuri 4.0000 Buah Rp. 25,000.00 = Rp. 100,000.00
BA-11 Semen Portland 8.0000 Kg Rp. 1,000.00 = Rp. 8,000.00
BA-07 Pasir Pasang 0.0320 m3 Rp. 90,000.00 = Rp. 2,880.00
Tenaga
UK-04 Pekerja 0.2400 OH Rp. 65,000.00 = Rp. 15,600.00
UK-05 Tukang Kayu 0.1200 OH Rp. 75,000.00 = Rp. 9,000.00
UK-02 Kepala Tukang 0.0200 OH Rp. 85,000.00 = Rp. 1,700.00
UK-01 Mandor 0.0020 OH Rp. 90,000.00 = Rp. 180.00
Jumlah = Rp. 137,360.00
Dibulatkan = Rp. 137,300.00
Memasang 1 m1 Listplank GRC (8 x 300)
BP-07 Lisplank GRC 30 cm 1.0500 m1 Rp. 15,000.00 = Rp. 15,750.00
BJP-02 Paku 5 cm dan 7 cm 0.100 Kg Rp. 12,000.00 = Rp. 1,200.00

UK-04 Pekerja 0.100 OH Rp. 65,000.00 = Rp. 6,500.00


UK-05 Tukang Kayu 0.200 OH Rp. 75,000.00 = Rp. 15,000.00
UK-02 Kepala Tukang 0.020 OH Rp. 85,000.00 = Rp. 1,700.00
UK-01 Mandor 0.005 OH Rp. 90,000.00 = Rp. 450.00
Jumlah = Rp. 40,600.00
Dibulatkan = Rp. 40,600.00
PEKERJAAN LANGIT-LANGIT
Memasang 1 m2 Langit-langit Kalsi board ukuran ( 1200 x 2400 x 4,5 ) mm
BP-02 Kalsi Board 0.364 Lembar Rp. 75,000.00 = Rp. 27,300.00
BJP-03 Paku Sekrup 0.036 Kg Rp. 25,000.00 = Rp. 900.00
BS-17 Rangka Hollow 20x40 3.000 m' Rp 12,000.00 = Rp. 36,000.00
BS-18 Compound 0.250 Kg Rp 25,000.00 = Rp. 6,250.00
BS-19 Cottontape 0.150 Roll Rp 15,000.00 = Rp. 2,250.00

UK-04 Pekerja 0.300 OH Rp. 65,000.00 = Rp. 19,500.00


UK-05 Tukang Kayu 0.350 OH Rp. 75,000.00 = Rp. 26,250.00
UK-02 Kepala Tukang 0.035 OH Rp. 85,000.00 = Rp. 2,975.00
UK-01 Mandor 0.015 OH Rp. 90,000.00 = Rp. 1,350.00
Jumlah = Rp. 122,775.00
Dibulatkan = Rp. 122,700.00
Memasang 1 m' List Plafon Gypsum Profil
BP-05 List Gypsum Profil 1.05 m1 Rp. 4,000.00 = Rp. 4,200.00
BP-04 Tepung Gypsum 0.15 Kg Rp. 2,600.00 = Rp. 390.00

UK-04 Pekerja 0.03 OH Rp. 65,000.00 = Rp. 1,950.00


UK-05 Tukang Kayu 0.06 OH Rp. 75,000.00 = Rp. 4,500.00
UK-02 Kepala Tukang 0.006 OH Rp. 85,000.00 = Rp. 510.00
UK-01 Mandor 0.0015 OH Rp. 90,000.00 = Rp. 135.00
Jumlah = Rp. 11,685.00
Dibulatkan = Rp. 11,600.00

PEKERJAAN LANTAI-DINDING
Memasang 1 m2 Granit Tile (60 x 60)cm
BPLD-05 Granit Tile 60x60 1.1000 m2 Rp. 115,000.00 = Rp. 126,500.00
BA-11 Portland Cement 9.600 Kg Rp. 1,000.00 = Rp. 9,600.00
BA-07 Pasir Pasang 0.045 m3 Rp. 90,000.00 = Rp. 4,050.00
BA-09 Semen warna 1.300 Kg Rp. 5,000.00 = Rp. 6,500.00

UK-04 Pekerja 0.250 OH Rp. 65,000.00 = Rp. 16,250.00


UK-05 Tukang batu 0.125 OH Rp. 75,000.00 = Rp. 9,375.00
UK-02 Kepala Tukang Batu 0.130 OH Rp. 85,000.00 = Rp. 11,050.00
UK-01 Mandor 0.130 OH Rp. 90,000.00 = Rp. 11,700.00
Jumlah = Rp. 195,025.00
Dibulatkan = Rp. 195,000.00
Memasang 1 m2 lantai Keramik (40 x 40)cm
BPLD-04 Tegel Keramik, ex. Milan, setara 1.1000 m2 Rp. 65,000.00 = Rp. 71,500.00
BA-11 Portland Cement 9.600 Kg Rp. 1,000.00 = Rp. 9,600.00
BA-07 Pasir Pasang 0.045 m3 Rp. 90,000.00 = Rp. 4,050.00
BA-09 Semen warna 1.300 Kg Rp. 5,000.00 = Rp. 6,500.00

UK-04 Pekerja 0.250 OH Rp. 65,000.00 = Rp. 16,250.00


UK-05 Tukang batu 0.125 OH Rp. 75,000.00 = Rp. 9,375.00
UK-02 Kepala Tukang Batu 0.130 OH Rp. 85,000.00 = Rp. 11,050.00
UK-01 Mandor 0.130 OH Rp. 90,000.00 = Rp. 11,700.00
Jumlah = Rp. 140,025.00
Dibulatkan = Rp. 140,000.00
Memasang 1 m2 Lantai Keramik ukuran (20 X 20 )
BPLD-03 Tegel Keramik, Kasar 26.500 Buah Rp. 1,600.00 = Rp. 42,400.00
BA-11 Portland Cement 10.400 Kg Rp. 1,000.00 = Rp. 10,400.00
BA-07 Pasir Pasang 0.045 m3 Rp. 90,000.00 = Rp. 4,050.00
BA-09 Semen Warna 1.620 Kg Rp. 5,000.00 = Rp. 8,100.00

UK-04 Pekerja 0.700 OH Rp. 65,000.00 = Rp. 45,500.00


UK-05 Tukang Batu 0.350 OH Rp. 75,000.00 = Rp. 26,250.00
UK-02 Kepala Tukang Batu 0.035 OH Rp. 85,000.00 = Rp. 2,975.00
UK-01 Mandor 0.035 OH Rp. 90,000.00 = Rp. 3,150.00
Jumlah = Rp. 142,825.00
Dibulatkan = Rp. 142,800.00
Memasang 1 m2 Keramik dinding 20/25
BPLD-01 Tegel Keramik Dinding, ex.Asia Tile, setara 1.1000 m2 Rp. 45,000.00 = Rp. 49,500.00
BA-11 PC 9.3000 Kg Rp. 1,000.00 = Rp. 9,300.00
BA-07 Pasir pasang 0.0180 m3 Rp. 90,000.00 = Rp. 1,620.00
BA-09 PC Super Nut / Semen Warna 1.5000 Kg Rp. 5,000.00 = Rp. 7,500.00

UK-04 Pekerja 0.700 OH Rp. 65,000.00 = Rp. 45,500.00


UK-05 Tukang Batu 0.350 OH Rp. 75,000.00 = Rp. 26,250.00
UK-02 Kepala Tukang Batu 0.035 OH Rp. 85,000.00 = Rp. 2,975.00
UK-01 Mandor 0.035 OH Rp. 90,000.00 = Rp. 3,150.00
Jumlah = Rp. 145,795.00
Dibulatkan = Rp. 145,700.00
Memasang 1 m' Plint/Border granit 10x60
BPLD-06 Plint Keramik Artistik 1.700 bh Rp. 9,000.00 = Rp. 15,300.00
BA-11 PC 1.140 Kg Rp. 1,000.00 = Rp. 1,140.00
BA-07 Pasir Pasang 0.003 m3 Rp. 90,000.00 = Rp. 270.00
BA-09 Semen Warna 0.100 Kg Rp. 5,000.00 = Rp.

UK-04 Pekerja 0.090 OH Rp. 65,000.00 = Rp. 5,850.00


UK-05 Tukang Batu 0.090 OH Rp. 75,000.00 = Rp. 6,750.00
UK-02 Kepala Tukang Batu 0.009 OH Rp. 85,000.00 = Rp. 765.00
UK-01 Mandor 0.005 OH Rp. 90,000.00 = Rp. 450.00
Jumlah = Rp. 30,525.00
Dibulatkan = Rp. 30,500.00

PEKERJAAN SANITASI
Memasang 1 m' Pipa Air Bersih PVC tipe AW Ø 1 1/4 "
BPP-04 Pipa PVC 1.2000 m1 Rp. 11,250.00 = Rp. 13,500.00
Perlengkapan 30.0000 % Rp. 3,375.00 = Rp. 1,012.50

UK-04 Pekerja 0.0360 OH Rp. 65,000.00 = Rp. 2,340.00


UK-05 Tukang Batu 0.0600 OH Rp. 75,000.00 = Rp. 4,500.00
UK-02 Kepala Tukang 0.0060 OH Rp. 85,000.00 = Rp. 510.00
UK-01 Mandor 0.0018 OH Rp. 90,000.00 = Rp. 162.00
Jumlah = Rp. 22,024.50
Dibulatkan = Rp. 22,000.00
Memasang 1 m' Pipa Air Bersih PVC tipe AW Ø 3/4"
BPP-02 Pipa PVC 1.2000 m1 Rp. 8,000.00 = Rp. 9,600.00
Perlengkapan 30.0000 % Rp. 2,400.00 = Rp. 720.00

UK-04 Pekerja 0.0360 OH Rp. 65,000.00 = Rp. 2,340.00


UK-05 Tukang Batu 0.0600 OH Rp. 75,000.00 = Rp. 4,500.00
UK-02 Kepala Tukang 0.0060 OH Rp. 85,000.00 = Rp. 510.00
UK-01 Mandor 0.0018 OH Rp. 90,000.00 = Rp. 162.00
Jumlah = Rp. 17,832.00
Dibulatkan = Rp. 17,800.00
Memasang 1 m' Pipa Air Kotoran PVC tipe AW Ø 4"
BPP-12 Pipa PVC 1.2000 m1 Rp. 21,250.00 = Rp. 25,500.00
Perlengkapan 30.0000 % Rp. 6,375.00 = Rp. 1,912.50

UK-04 Pekerja 0.0360 OH Rp. 65,000.00 = Rp. 2,340.00


UK-05 Tukang Batu 0.0600 OH Rp. 75,000.00 = Rp. 4,500.00
UK-02 Kepala Tukang 0.0060 OH Rp. 85,000.00 = Rp. 510.00
UK-01 Mandor 0.0018 OH Rp. 90,000.00 = Rp. 162.00
Jumlah = Rp. 34,924.50
Dibulatkan = Rp. 34,900.00
Memasang 1 m' Pipa Air Buangan PVC tipe AW Ø 3"
BPP-10 Pipa PVC 1.2000 m1 Rp. 17,500.00 = Rp. 21,000.00
Perlengkapan 30.0000 % Rp. 5,250.00 = Rp. 1,575.00

UK-04 Pekerja 0.0360 OH Rp. 65,000.00 = Rp. 2,340.00


UK-05 Tukang Batu 0.0600 OH Rp. 75,000.00 = Rp. 4,500.00
UK-02 Kepala Tukang 0.0060 OH Rp. 85,000.00 = Rp. 510.00
UK-01 Mandor 0.0018 OH Rp. 90,000.00 = Rp. 162.00
Jumlah = Rp. 30,087.00
Dibulatkan = Rp. 30,000.00
Memasang 1 buah Kloset Jongkok Porselen
BSA-04 Kloset Jongkok Porselen 1.0000 Buah Rp. 350,000.00 = Rp. 350,000.00
BA-11 Semen Portland 6.0000 Kg Rp. 1,000.00 = Rp. 6,000.00
BA-07 Pasir Pasang 0.0100 m3 Rp. 90,000.00 = Rp. 900.00

UK-04 Pekerja 1.0000 OH Rp. 65,000.00 = Rp. 65,000.00


UK-05 Tukang Batu 1.5000 OH Rp. 75,000.00 = Rp. 112,500.00
UK-02 Kepala Tukang 0.1500 OH Rp. 85,000.00 = Rp. 12,750.00
UK-01 Mandor 0.1600 OH Rp. 90,000.00 = Rp. 14,400.00
Jumlah = Rp. 561,550.00
Dibulatkan = Rp. 561,550.00
Memasang 1 buah Kran Ø 3/4"
BSA-08 Kran Air 1.0000 Buah Rp. 25,000.00 = Rp. 25,000.00
BSA-10 Seal Tape 0.0250 Buah Rp. 5,000.00 = Rp. 125.00
= Rp.
UK-04 Pekerja 0.0100 OH Rp. 65,000.00 = Rp. 650.00
UK-05 Tukang Batu 0.1000 OH Rp. 75,000.00 = Rp. 7,500.00
UK-02 Kepala Tukang 0.0100 OH Rp. 85,000.00 = Rp. 850.00
UK-01 Mandor 0.0050 OH Rp. 90,000.00 = Rp. 450.00
Jumlah = Rp. 34,575.00
Dibulatkan = Rp. 34,500.00
Memasang 1 buah Floor Drain
BSA-02 Floor Drain 1.0000 Buah Rp. 25,000.00 = Rp. 25,000.00

UK-04 Pekerja 0.0100 OH Rp. 65,000.00 = Rp. 650.00


UK-05 Tukang Batu 0.1000 OH Rp. 75,000.00 = Rp. 7,500.00
UK-02 Kepala Tukang 0.0100 OH Rp. 85,000.00 = Rp. 850.00
UK-01 Mandor 0.0050 OH Rp. 90,000.00 = Rp. 450.00
Jumlah = Rp. 34,450.00
Dibulatkan = Rp. 34,400.00
Memasang 1 m2 waterproofing
BC-06 Waterproofing agent 2.2500 Kg Rp. 55,000.00 = Rp. 123,750.00

UK-04 Pekerja 0.0200 OH Rp. 65,000.00 = Rp. 1,300.00


UK-05 Tukang Batu 0.1000 OH Rp. 75,000.00 = Rp. 7,500.00
UK-02 Kepala Tukang 0.0100 OH Rp. 85,000.00 = Rp. 850.00
UK-01 Mandor 0.0050 OH Rp. 90,000.00 = Rp. 450.00
Jumlah = Rp. 133,850.00
Dibulatkan = Rp. 133,800.00

PEKERJAAN PENGECATAN
Pengecatan 1 m2 tembok baru interior ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
BC-07 Plamir 0.100 Kg Rp. 20,000.00 = Rp. 2,000.00
BC-08 Ampelas 0.250 Lbr Rp. 5,000.00 = Rp. 1,250.00
BC-05 Cat dasar 0.100 Kg Rp. 19,000.00 = Rp. 1,900.00
BC-03 Cat penutup 2x (Ex. Vinilex) 0.260 Kg Rp. 22,500.00 = Rp. 5,850.00

UK-04 Pekerja 0.020 OH Rp. 65,000.00 = Rp. 1,300.00


UK-05 Tukang cat 0.042 OH Rp. 75,000.00 = Rp. 3,150.00
UK-02 Kepala tukang 0.005 OH Rp. 85,000.00 = Rp. 425.00
UK-01 Mandor 0.003 OH Rp. 90,000.00 = Rp. 225.00
Jumlah = Rp. 16,100.00
Dibulatkan = Rp. 16,100.00
Pengecatan 1 m2 tembok baru exterior ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
BC-05 Anti Alkali 0.100 Kg Rp. 19,000.00 = Rp. 1,900.00
BC-08 Ampelas 0.250 Lbr Rp. 5,000.00 = Rp. 1,250.00
BC-05 Cat dasar 0.100 Kg Rp. 19,000.00 = Rp. 1,900.00
BC-04 Cat penutup 2x (Weathershield, setara) 0.260 Kg Rp. 36,000.00 = Rp. 9,360.00

UK-04 Pekerja 0.020 OH Rp. 65,000.00 = Rp. 1,300.00


UK-05 Tukang cat 0.042 OH Rp. 75,000.00 = Rp. 3,150.00
UK-02 Kepala tukang 0.005 OH Rp. 85,000.00 = Rp. 425.00
UK-01 Mandor 0.003 OH Rp. 90,000.00 = Rp. 225.00
Jumlah = Rp. 19,510.00
Dibulatkan = Rp. 19,500.00
Pengecatan 1 m2 langit-langit ( Plafon )
BC-05 Cat dasar 0.100 Kg Rp. 19,000.00 = Rp. 1,900.00
BC-03 Cat penutup 2x 0.260 Kg Rp. 22,500.00 = Rp. 5,850.00
Tenaga
UK-04 Pekerja 0.020 OH Rp. 65,000.00 = Rp. 1,300.00
UK-05 Tukang cat 0.046 OH Rp. 75,000.00 = Rp. 3,450.00
UK-02 Kepala tukang 0.005 OH Rp. 85,000.00 = Rp. 425.00
UK-01 Mandor 0.003 OH Rp. 90,000.00 = Rp. 225.00
Jumlah = Rp. 13,150.00
Dibulatkan = Rp. 13,100.00

PEKERJAAN LISTRIK
Memasang titik stopkontak
BPL-07 Kabel NYM 3 x 2.5 mm 15.000 m1 Rp. 12,000.00 = Rp. 180,000.00
BPL-22 Pipa pralon 5/8 14.000 m1 Rp. 2,000.00 = Rp. 28,000.00
BPL-03 Isolasi 5.000 Buah Rp. 1,500.00 = Rp. 7,500.00
BPL-10 Klem 14.000 Buah Rp. 500.00 = Rp. 7,000.00
BPL-19 Stop kontak 1.000 Buah Rp. 17,500.00 = Rp. 17,500.00
BPL-29 T dos pvc 1.000 Buah Rp. 1,150.00 = Rp. 1,150.00

UK-04 Pekerja 0.050 OH Rp. 65,000.00 = Rp. 3,250.00


UK-05 Tukang listrik 0.540 OH Rp. 75,000.00 = Rp. 40,500.00
UK-02 kepala tukang listrik 0.005 OH Rp. 85,000.00 = Rp. 425.00
Jumlah = Rp. 285,325.00
Dibulatkan = Rp. 285,325.00
Memasang titik saklar
BPL-07 Kabel NYM 3 x 2.5 mm 15.000 m1 Rp. 12,000.00 = Rp. 180,000.00
BPL-22 Pipa pralon 5/8 14.000 m1 Rp. 2,000.00 = Rp. 28,000.00
BPL-03 Isolasi 5.000 Buah Rp. 1,500.00 = Rp. 7,500.00
BPL-10 Klem 14.000 Buah Rp. 500.00 = Rp. 7,000.00
BPL-29 T dos pvc 1.000 Buah Rp. 1,150.00 = Rp. 1,150.00

UK-04 Pekerja 0.050 OH Rp. 65,000.00 = Rp. 3,250.00


UK-04 Tukang listrik 0.540 OH Rp. 65,000.00 = Rp. 35,100.00
UK-01 kepala tukang listrik 0.005 OH Rp. 90,000.00 = Rp. 450.00
Jumlah = Rp. 262,450.00
Dibulatkan = Rp. 262,450.00
Memasang titik lampu
BPL-07 Kabel NYM 3 x 2.5 mm 13.000 m1 Rp. 12,000.00 = Rp. 156,000.00
BPL-22 Pipa pralon 5/8 12.000 m1 Rp. 2,000.00 = Rp. 24,000.00
BPL-02 Isolator 6.000 Buah Rp. 1,500.00 = Rp. 9,000.00
BPL-29 T dos pvc 1.000 Buah Rp. 1,150.00 = Rp. 1,150.00

UK-04 Pekerja 0.050 OH Rp. 65,000.00 = Rp. 3,250.00


UK-05 Tukang listrik 0.540 OH Rp. 75,000.00 = Rp. 40,500.00
UK-02 Kepala tukang listrik 0.050 OH Rp. 85,000.00 = Rp. 4,250.00
Jumlah = Rp. 238,150.00
Dibulatkan = Rp. 238,100.00
Memasang sakar tunggal
BPL-17 Saklar tunggal (10 A) 1.000 bh Rp. 20,000.00 = Rp. 20,000.00

UK-04 Pekerja 0.100 OH Rp. 65,000.00 = Rp. 6,500.00


Jumlah = Rp. 26,500.00
Dibulatkan = Rp. 26,500.00
Memasang sakar double
BPL-18 Saklar ganda (10 A) 1.000 bh Rp. 22,000.00 = Rp. 22,000.00

UK-04 Pekerja 0.100 OH Rp. 65,000.00 = Rp. 6,500.00


Jumlah = Rp. 28,500.00
Dibulatkan = Rp. 28,500.00
REKAP ANALISA HARGA SATUAN

KODE
Uraian Pekerjaan Harga Satuan (Rp.)
AHS

PEKERJAAN PERSIAPAN
Pembersihan Lapangan dan Peralatan (m2) 11,000.00
Pengukuran dan Pasang Papan Bowplank (m') 53,500.00

PEKERJAAN TANAH
Urug kembali bekas galian 13,800.00
Penggalian Tanah Biasa (m3) kedalaman 1 m 53,200.00
Mengurug 1 m3 Tanah Urug 92,400.00
Mengurug 1 m3 Pasir Urug 86,400.00

PEKERJAAN PASANGAN
Memasang 1 m3 batu kosong (aanstamping) 233,600.00
Pemasangan 1 m3 Pondasi Batu Belah Campuran 1 PC : 4 PP 484,600.00
Pemasangan 1 m2 Dinding Batu Bata Merah (5 X 11 X 22)cm tebal 1/2 Bata Campuran Spesi 1 Pc : 6 PP 72,800.00
Memasang 1 m2 Plesteran 1 PC : 6 PP : tebal 15 mm 40,200.00
Memasang 1 m2 Acian 22,200.00

PEKERJAAN PEMBETONAN
Membuat 1 m3 Lantai Kerja Beton Mutu F'c = 7,4 Mpa (K100), Slump (3-6) cm, w/c = 0,87 546,200.00
Membuat 1 m3 Beton Mutu F'c = 19,3 Mpa (K225), Slump (12±2) cm, w/c = 0,58 688,300.00
Pembesian 1 kg dengan Besi Polos atau Besi Ulir 13,600.00
Memasang 1 m2 Bekisting untuk Sloof 117,950.00
Memasang 1 m2 Bekisting untuk Kolom 172,975.00
Memasang 1 m2 Bekisting untuk Balok 177,475.00
Memasang 1 m2 Bekisting untuk Plat Lantai 212,975.00
Memasang 1 m' Kolom Praktis Beton Bertulang (12/12) 39,769.29

PEKERJAAN KUSEN, PINTU DAN JENDELA


Memasang 1 m' Kusen Pintu Alluminium 113,600.00
1 m2 Pasang daun jendela / BV. aluminium panil kaca 836,900.00
Pasang 1 m2 kaca, tebal 8 mm 276,000.00

PEKERJAAN RANGKA ATAP


Memasang 1 kg Besi Profil 20,900.00
Memasang 1 m2 Rangka Atap Genteng Glazur, Galvalume TRUE CORE setara 131,900.00
Pasang 1 m2 atap Genteng Glazur, ex Kanmuri 181,500.00
Pasang 1 m' Bubungan Glasur ex Kamuri 137,300.00
Memasang 1 m1 Listplank GRC (8 x 300) 40,600.00

PEKERJAAN LANGIT-LANGIT
Memasang 1 m2 Langit-langit Kalsi board ukuran ( 1200 x 2400 x 4,5 ) mm 122,700.00
Memasang 1 m' List Plafon Gypsum Profil 11,600.00

PEKERJAAN LANTAI-DINDING
Memasang 1 m2 Granit Tile (60 x 60)cm 195,000.00
Memasang 1 m2 lantai Keramik (40 x 40)cm 140,000.00
Memasang 1 m2 Lantai Keramik ukuran (20 X 20 ) 142,800.00
Memasang 1 m2 Keramik dinding 20/25 145,700.00
Memasang 1 m' Plint/Border granit 10x60 30,500.00
PEKERJAAN SANITASI
Memasang 1 m' Pipa Air Bersih PVC tipe AW Ø 1 1/4 " 22,000.00
Memasang 1 m' Pipa Air Bersih PVC tipe AW Ø 3/4" 17,800.00
Memasang 1 m' Pipa Air Kotoran PVC tipe AW Ø 4" 34,900.00
Memasang 1 m' Pipa Air Buangan PVC tipe AW Ø 3" 30,000.00
Memasang 1 buah Kloset Jongkok Porselen 561,550.00
Memasang 1 buah Kran Ø 3/4" 34,500.00
Memasang 1 buah Floor Drain 34,400.00
Memasang 1 m2 waterproofing 133,800.00

PEKERJAAN PENGECATAN
Pengecatan 1 m2 tembok baru interior ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup ) 16,100.00
Pengecatan 1 m2 tembok baru exterior ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup ) 19,500.00
Pengecatan 1 m2 langit-langit ( Plafon ) 13,100.00

PEKERJAAN LISTRIK
Memasang titik stopkontak 285,325.00
Memasang titik saklar 262,450.00
Memasang titik lampu 238,100.00
Memasang sakar tunggal 26,500.00
Memasang sakar double 28,500.00
No. Uraian Pekerjaan Spesifikasi Volume Pekerjaan Sat.

1 PEKERJAAN PENDAHULUAN
- Pembersihan dan Pemerataan Lahan
- Pemasangan Bowplank
2 PEKERJAAN TANAH DAN PONDASI
- Pekerjaan Galian Tanah Pondasi
- Pekerjaan Urugan Pasir
- Pekerjaan Pasangan Astaamping
- Pekerjaan Pondasi
3 PEKERJAAN PEMBETONAN
A Pekerjaan Sloof
- Pembetonan
- Pembesian
- Bekisting
B Pekerjaan Kolom Praktis 15/15
- Pembetonan
- Pembesian
- Bekisting
C Pekrejaan Ringbalok 15/15
- Pembetonan
- Pembesian
- Bekisting
D Pekerjaan Dak Beton
- Pembetonan
- Pembesian
- Bekisting
4 PEKERJAAN DINDING
- Pasangan Dinding 1/2 Bata
- Plesteran Dinding (t=1,5 cm)
- Acian Dinding
5 PEKERJAAN ATAP
6 PEKERJAAN PLAFOND
- Pasangan Plafond Gypsum
- Pekerjaan Rangka Plafond Hollow 20/40
- Pekerjaan Penutup Plafond
- List Plafond
7 PEKERJAAN KERAMIK
- Pasangan Granit 60X60
- Pasangan Keramik 20X20
- Pasangan Keramik Dinding 20/25
8 PEKERJAAN PENGECATAN
- Pengecatan Dinding Interior
- Pengecaran Dinding Eksterior
- Pengecatan Plafond
- Waterproofing
9 PEKERJAAN PINTU DAN JENDELA
A Pemasangan Pintu
- Kusen
- Pasangan Daun Pintu
B Pemasangan Jendela
- Kusen
- Pasangan Jendela
10 PEKERJAAN SANITASI
- Pasangan Jongkok
- Pasangan Keran
- Pasangan Pipa Air Bersih
- Pasangan Pipa Air Kotor
11 PEKERJAAN LISTRIK
- Pasangan Titik Lampu
- Pasangan Titik Stop Kontak
- Pasangan Titik Saklar
- Saklar Tunggal
- Saklar Ganda
- Lampu 5 Watt
Harga Satuan Total Harga