Professional Documents
Culture Documents
MANAGEMENT
Department of Tourism and Events
Management
Chapter 11, 12, 13 & Notes
OUTCOMES
In this lesson we will cover the following:
• Project Time Management (processes)
• Develop a list of activities
• Define an activity
• Estimate an activity duration
• Draw and interpret a network diagram
• Draw a Tabular Report
Faculty of Business, Department of Tourism and Events Management - 2022
INTRODUCTION
• Project Time Management includes the processes required
to manage the timely completion of the project.
• On some projects, especially those of smaller scope, defining
activities, sequencing activities, estimating activity resources,
estimating activity durations, and developing the schedule
model are so tightly linked that they are viewed as a single
process that can be performed by a person over a relatively
short period of time.
Faculty of Business, Department of Tourism and Events Management - 2022
INTRODUCTION
DEFINE ACTIVITIES
• Define Activities is the process of identifying and documenting the
specific actions to be performed to produce the project deliverables.
• The key benefit of this process is to break down work packages into
activities that provide a basis for estimating, scheduling, executing,
monitoring, and controlling the project work.
Faculty of Business, Department of Tourism and Events Management - 2022
• The Create WBS process identifies the deliverables at the lowest level
in the WBS—the work package.
• Work packages are typically decomposed into smaller components
called activities that represent the work effort required to complete
the work package.
Faculty of Business, Department of Tourism and Events Management - 2022
• The outputs for defining the activities is the activity list and
events list.
• The activity list is a comprehensive list that includes all
schedule activities required on the project.
• An event is an activity with zero duration.
Faculty of Business, Department of Tourism and Events Management - 2022
• The activity list also includes the activity identifier and a scope of work
description for each activity in sufficient detail to ensure that project
team members understand what work is required to be completed.
• Each activity should have a unique title that describes its place in the
schedule, even if that activity title is displayed outside the context of
the project schedule.
DEFINE ACTIVITIES (EVENTS LIST)
Faculty of Business, Department of Tourism and Events Management - 2022
• The critical path is the longest path in a network diagram, and therefore determines the shortest time
that it will take to complete a project.
• This systematic way of determining the critical path uses the techniques of forward pass and
backward pass.
• You use a forward pass to calculate the Early Start (ES) and Early Finish (EF) times and a backward
pass to calculate the Late Start (LS) and Late Finish (LF) times, and therefore calculate the float.
• Early Start: The earliest time that the activity can logically start.
• Early Finnish:The earliest time that the activity can logically finish.
• Late Start: The latest time that the activity can logically start without delaying the project.
• Late Finnish:The latest time that the activity can logically finish without delaying the project.
• Float: The amount of time an activity can be delayed without affecting the project schedule.
Faculty of Business, Department of Tourism and Events Management - 2022
CONTINUOUS….
1. Construct a Network Diagram for the project and calculate the activity float.
2. Determine the critical path and duration.
3. Construct a Tabular Report
4. Draw the Gantt Chart.
UNIT 2 (1 of 4) – PROJECT
INTEGRATION MANAGEMENT
Department of Tourism and Events
Management
(1 of 4) Chapter 4, 6, 23 & Notes
ND Events Management:
Project Management 2 (PGT200S)
ND Events Management:
Project Management 2 (PGT200S)
THANK YOU
ND Events Management:
Project Management 2 (PGT200S)
ND Events Management:
Project Management 2 (PGT200S)
ND Events Management:
Project Management 2 (PGT200S)
THANK YOU
ND Events Management:
Project Management 2 (PGT200S)
• Warehouse
• Accounts
• Documents Storage