PROJECT : P.O.

number:
Date of Inspection Visit: Vendor/Sub Vendor:
Inspection Notification No: Location:
Result of inspection: Satisfactory Partial Unsatisfactory
Inspection Details:
Description / Notes …
As per the Notification received from. Inspection Visit carried out.

Inspection for offered materials was performed at AASIA Steel in accordance to the Specification &
Requirements. Results found satisfactory. details are given below.

1. INSPECTION/ACTIVITY CARRIED OUT/ RESULT:

ITP Clause Activity Offered Items /Qty Serial Intervention


AS-Q-CM- /Tag Heat Nos. as per ITP /
006-004S/ Result
335 PIPING
No activities Awating Material

ITP Clause Activity Offered Items /Qty Intervention


AS-Q-CM- Serial / Tag Heat Nos. as per ITP /
006 Result
004S/335
OPTF
11.4 Applied Final Coat on the W
external surface, verified the Dry Film thickness Satisfactory
at different locations.

Weather Conditions Monitored and Reviewed the


recorded Parameters.

Verified the calibrations of all instruments used.

ITP Clause Activity Offered Items /Qty Intervention


AS-Q-CM- Serial / Tag Heat Nos. as per ITP /
006 Result
004F/335
PIPING
5.1.4 Monitored Weld Overlay of Flanges Flange W/M
Satisfactory
Verified Pre-Clad thickness of Base material of
Flanges, at each orientation and
found as per requirements.

Verified Welding Equipment’s calibration status and

: 21/03/2023
found all Machined were duly calibrated
and within due date.

Verified Inconel 625 Filler wire spool used is of


Same Batch & Brand mentioned in WPS.

Verified Pre-heat prior to cladding and found as per


approved WPS requirement.

During startup of cladding verified all weld


Parameters, Gas Flow rate and found meeting with
WPS requirements.

2. SUMMARY OF NON-CONFORMANCE / REJECTION (IF ANY):


ITP
Description of Non-conformance / Rejection Qty Serial /Tag /Heat Nos.
Clause
.
None

3. LIST OF ATTENDEES:
NAME COMPANY CONTACT No Email

SIGNATURE
Inspector Name:

SAP No:

Punch Points: NA

Punch list (PL) Yes No Description:


NCR Yes No Description:
Delivery Impact: Yes No Delivery date:
End of Report