P.O. number:
Materials Inspected:
Date(s) of visit(s):
Date of previous visit:
Date of next scheduled visit:
P.O. Status Complete Incomplete
1. ATTENDEES
3. DOCUMENTS USED
APPROVAL
DOCUMENT Nº TITLE ISSUE DATE (Rev.)
STATUS
5. MANUFACTURING
6. DELIVERY DATE
Item Nº Delivery Date Comments (inspector opinion about viability of delivery dates)
Pipes,
Spools &
Fittings
Remarks:
Calibration of measuring devices was verified and found the calibration date is still valid.
Receiving Inspection done as per ITP points mentioned as per PO, Codes &
Standard requirements.
Reviewed Material Test Certificates and found all Required Chemical,
Mechanical & NDT were meeting with Codes & Standard requirements.
Visual Inspection performed on all offered quantity for physical condition and
found free from mechanical damages.
Verified Marking and found correlating with MTC & Code marking
requirement.
Dimensions verified for all Items offered Overall length, OD, ID & Bevel Edges
and found as per required dimensions and found within tolerance limits
Verified Wall Thickness by UT thickness Gauge and found within tolerance
limits.
Performed and witnessed dimensional inspection for the, Spools & Fittings.
Results found satisfactory and accepted.
Initial Witness of weld Overlay of Pipes, Flanges & Fittings Witnessed as per
Approved Procedures & Welding Documents and found in order, hence
accepted the Initial witness to proceed with weld overlay process.
Visual inspection was performed on the Pipes, Spools & Fittings are free from
voids, Pits, Foreign inclusions, Scratch’s, worm hole and wrinkles. Results found
satisfactory and accepted.
RECOMMENDED ACTION:
Accept Non-
INSPECTION RESULT:
conformance Other
8. NON-CONFORMANCES