ASPHALT PAVEMENT

POURED ASPHALT SEALANT 30-50 MM PENETRATION CONCRETE SIDEWALK

BIT. PRIME COAT


P.C. CONCRETE PAVEMENT (7D,550F) AGGREGATE BASE COARSE

CRUSHED AGGREGATE BASE COARSE

AGGREGATE BASE COARSE BACKFILL (VOL. COMPACTED)


AGGREGATE BASE COARSE

AGGREGATE SUB-BASE COARSE

SAND CUSHION SAND CUSHION


SAND CUSHION
SUPPLY & LAYING OF ONE (1) BARREL SUPPLY & LAYING OF ONE (1) BARREL
SUPPLY & LAYING OF ONE (1) BARREL POLYETHYLENE PIPE @ 75 MM DIAM. POLYETHYLENE PIPE @ 100 MM DIAM.
POLYETHYLENE PIPE @ 75MM DIAM.

1A SINGLE BARREL ON CONCRETE PAVEMENT 1B SINGLE BARREL ON ASPHALT PAVEMENT 1C SINGLE BARREL ON CONCRETE SIDEWALK
SD - 03 SD - 03 SD - 03

ASPHALT PAVEMENT
POURED ASPHALT SEALANT 30 - 50 MM PENETRATION
CONCRETE SIDEWALK
BIT. PRIME COAT
P.C. CONCRETE PAVEMENT (7D, 550F) AGGREGATE BASE COARSE
CRUSHED AGGREGATE BASE COARSE

AGGREGATE BASE COARSE BACKFILL (VOL. COMPACTED)


AGGREGATE BASE COARSE

AGGREGATE SUB-BASE COARSE

SAND CUSHION SAND CUSHION


SAND CUSHION

SUPPLY & LAYING OF TWO (2 ) BARREL SUPPLY & LAYING OF TWO (2 ) BARREL
SUPPLY & LAYING OF TWO (2 ) BARREL
POLYETHYLENE PIPE @ 100 MM DIAM. POLYETHYLENE PIPE @ 100 MM DIAM.
P.E. PIPE @ 100 MM DIAM.

2A DOUBLE BARREL ON CONCRETE PAVEMENT 2B DOUBLE BARREL ON ASPHALT PAVEMENT 2C DOUBLE BARREL ON CONCRETE SIDEWALK
SD - 03 SD - 03 SD - 03

P.C. CONCRETE PAVEMENT (7D, 550F)


INCLUDED IN CONCRETE BLOCKING

BACKFILL (VOL. COMPACTED)


AGGREGATE BASE COARSE
BACKFILL (VOL. COMPACTED)
INCLUDED IN CONCRETE BLOCKING

SAND CUSHION
AGGREGATE SUB-BASE COARSE

SAND CUSHION SUPPLY & LAYING OF TWO (2 ) BARREL SAND CUSHION


POLYETHYLENE PIPE @ 100 MM DIAM.
SUPPLY & LAYING OF ONE (1) BARREL SUPPLY & LAYING OF TWO (2) BARREL
POLYETHYLENE PIPE @ 100 MM DIAM. POLYETHYLENE PIPE @ 100 MM DIAM.

1D SINGLE BARREL ON EARTH SURFACE 2D DOUBLE BARREL ON EARTH SURFACE E DOUBLE BARREL ON CONCRETE BLOCKING
SD - 03 SD - 03 SD - 03

TRAFFIC MANAGEMENT SYSTEM PROJECT TYPICAL CROSS-SECTION FOR THE


RESTORATION OF EXISTING
MANILA NORTH ROAD (MNR) (S00166LZ)
PAVEMENT FOR UNDERGROUND
AND PUGO - ROSARIO ROAD CONDUIT PIPE (TRENCHING)
INTERSECTION, K0214+050
2nd
La Union District Engineering Office