Professional Documents
Culture Documents
2016
CB : Circuit Breaker
CR : Control Room
DE : Drive End
EL : Elevation
I/O : Input/Output
IP : Internet Protocal
UL : Underwriters Laboratory
Table of Contents
FORWARD............................................................................................................................................II
KEYNOTE FROM CHIEF EXECUTIVE OFFICER.....................................................................................III
ACRONYMS.........................................................................................................................................IV
SECTION A: OPERATION MANUAL.......................................................................................................1
CHAPTER 1: SALIENT FEATURES OF THE PLANT.................................................................................2
1.1 LOCATION........................................................................................................................................2
1.2 HYDROLOGY....................................................................................................................................2
1.3 DIVERSION WEIR.............................................................................................................................3
1.4 INTAKE...........................................................................................................................................3
1.5 FISH LADDER...................................................................................................................................4
1.6 DESILTING CHAMBER.......................................................................................................................4
1.6.1 Desilter Inlet Gate...................................................................................................................4
1.6.2 Flushing Gate.........................................................................................................................4
1.6.3 Desilter Outlet Gate...............................................................................................................4
1.7 WATER CONDUCTING SYSTEM............................................................................................................5
1.7.1 Connection intake-Desilter.....................................................................................................5
1.7.2 Headrace Channel...................................................................................................................5
1.7.3 Headrace Tunnel....................................................................................................................5
1.7.4 Surge Shaft............................................................................................................................5
1.7.5 Pressure Shaft........................................................................................................................5
1.7.6 Pressure Tunnel.....................................................................................................................5
1.8 POWERHOUSE COMPLEX..................................................................................................................6
1.8.1 Power house cavern...............................................................................................................6
1.8.2 Transformer cavern...............................................................................................................6
1.8.3 Access Tunnel........................................................................................................................6
1.8.4 Emergency Exit Tunnel..........................................................................................................6
1.8.5 Tailrace Tunnel......................................................................................................................6
1.8.6 Bus duct.................................................................................................................................6
1.8.7 Main Equipment.....................................................................................................................7
1.9 TRANSMISSION LINE........................................................................................................................9
1.10 COMMISSIONING DATES..................................................................................................................9
1.11 ENERGY GENERATION....................................................................................................................10
CHAPTER 2: GENERATOR....................................................................................................................11
2.1 INTRODUCTION...............................................................................................................................13
2.2 START-UP CHECKS AT STANDSTILL....................................................................................................13
2.3 CHECKS DURING OPERATION...........................................................................................................14
2.4 SHUTDOWN...................................................................................................................................15
2.4.1 Normal shutdown.................................................................................................................15
2.4.2 Shutdown by mechanical fault (QSD 1)................................................................................15
2.4.3 Shutdown by electrical fault (QSD 2)...................................................................................16
2.5 BRAKE OPERATION.........................................................................................................................16
2.6 PRESERVATION FOR LONGER STANDSTILLS........................................................................................17
2.7 GENERATOR SETTINGS....................................................................................................................18
2.8 OPERATIONAL FAULT.....................................................................................................................18
CHAPTER 3: STATIC EXCITATION SYSTEM........................................................................................20
3.1 INTRODUCTION..............................................................................................................................20
3.2 STATIC EXCITATION SYSTEM TECHNICAL DATA...................................................................................22
3.3 EQUIPMENT DESCRIPTION...............................................................................................................22
3.3.1 Industrial PC with touch screen............................................................................................22
3.3.2 Key switch (Pad) S111 Layout & LED description...................................................................23
3.3.3 Field Circuit Breaker.............................................................................................................24
3.3.4 AC Power Circuit & Thyristor Bridges..................................................................................24
3.3.5 Over Voltage Protection......................................................................................................25
3.3.6 Voltage Supply.....................................................................................................................25
3.3.7 Excitation Transformer........................................................................................................25
3.3.8 Excitation Transformer overheating protection.................................................................25
3.3.9 Excitation Transformer Overcurrent Protection.................................................................26
3.3.10 Fans....................................................................................................................................26
3.3.11 Dynamic Braking (Electrical)...............................................................................................26
3.3.11.1 Technical data of dynamic braking.............................................................................27
3.4 OPERATION..................................................................................................................................27
3.4.1 Control.................................................................................................................................27
3.4.1.1 Conditions for switching excitation equipment “ON”:...............................................27
3.4.1.2 Conditions for switching excitation “OFF”:................................................................28
3.4.1.3 Synchronization release..............................................................................................28
3.4.2 Operation of the equipment from a control room (REMOTE).............................................28
3.4.3 Using keypad S111................................................................................................................29
3.4.3.1 Key layout....................................................................................................................29
3.4.3.2 LED layout....................................................................................................................29
3.4.4 Manual Mode......................................................................................................................30
CHAPTER 4: TURBINE & AUXILIARIES................................................................................................31
4.1 INTRODUCTION..............................................................................................................................31
4.2 TECHNICAL DATA............................................................................................................................31
4.3 DESCRIPTION................................................................................................................................32
4.3.1 Turbine Assembly.................................................................................................................32
4.3.1.1 Main Components of Turbine......................................................................................32
4.3.2 Pelton Runner......................................................................................................................32
4.3.3 Turbine Shaft.......................................................................................................................33
4.3.4 Overspeed Pendulum..........................................................................................................33
4.3.5 Speed sensing device...........................................................................................................34
4.3.6 Turbine Guide Bearing.........................................................................................................35
4.3.7 Distributor...........................................................................................................................36
4.3.8 Turbine Housing and water passage shield.........................................................................36
4.3.9 Nozzle and Deflector...........................................................................................................36
4.3.10 Brakejet and Piping............................................................................................................38
4.4 OPERATION..................................................................................................................................38
4.4.1 Checks before start-up.........................................................................................................38
4.4.2 Start-up of the turbine........................................................................................................38
4.4.3 Checks during operation.....................................................................................................39
4.4.4 Shutdown of the turbine....................................................................................................39
4.4.5 Filling the turbine................................................................................................................39
4.4.6 Draining the turbine............................................................................................................39
4.4.7 Limits of operation..............................................................................................................39
CHAPTER 5: MAIN INLET VALVE & AUXILIARIES...............................................................................41
5.1 INTRODUCTION..............................................................................................................................41
5.2 MAIN COMPONENTS OF MAIN INLET VALVE......................................................................................41
5.3 OPERATION..................................................................................................................................42
5.3.1 Filling the spherical valve and bypass line............................................................................42
5.3.2 Filling of Distributor.............................................................................................................43
5.3.3 Manual closing of the spherical valve..................................................................................43
5.3.4 Decommissioning for maintenance / revision......................................................................44
CHAPTER 6: GOVERNING SYSTEM.....................................................................................................45
6.1 HYDRAULIC GOVERNOR..................................................................................................................45
6.1.2 Technical Data:.....................................................................................................................45
6.1.3 Hydraulic Governor Components.........................................................................................46
6.1.4 Operation............................................................................................................................46
6.1.4.1 Checks to be made before the Start-up......................................................................46
6.1.4.2 Start-up of the Turbine................................................................................................47
6.1.4.3 Shutdown of the Turbine............................................................................................47
6.2 DIGITAL GOVERNOR......................................................................................................................48
6.2.1 Operation (Functionality of Touch Panel)............................................................................48
6.2.1.1 Display Overview.........................................................................................................48
6.2.1.2 Display Controller Overview........................................................................................50
6.2.1.3 Display Level Controller...............................................................................................51
6.2.1.4 Display Flow Controller...............................................................................................52
6.2.1.5 Display Power Controller.............................................................................................53
6.2.1.6 Display Speed Controller.............................................................................................54
6.2.1.7 Display Opening Limiter..............................................................................................55
6.2.1.8 Display Positioning Circuit Deflector..........................................................................56
6.2.1.9 Display Positioning Circuit Needle..............................................................................57
6.2.1.10 Display Needle Selection...........................................................................................58
6.2.1.11 Display Feedback Calibration.....................................................................................59
6.2.1.12 Display Special Functions...........................................................................................60
6.2.1.13 Display Trend Diagram................................................................................................61
6.2.1.14 Display System Control..............................................................................................62
6.2.1.15 Display Alarm Signal List............................................................................................63
6.2.1.16 Display Chronological Event List...............................................................................64
CHAPTER 7: GENERATOR STEP-UP TRANSFORMERS.......................................................................65
7.1 INTRODUCTION..............................................................................................................................65
7.2 TECHNICAL DATA...........................................................................................................................65
7.3 OPERATION..................................................................................................................................67
7.4 ROUTINE/PERIODIC INSPECTION SCHEDULE FOR TRANSFORMER:..........................................................67
CHAPTER 8: STATION AUXILIARY TRANSFORMERS........................................................................69
8.1 STATION AUXILIARY TRANSFORMER, 5MVA, 220 KV/33KV...............................................................69
8.1.1 Introduction.........................................................................................................................69
8.1.2 Transformer Rating:............................................................................................................69
8.1.3 Operation............................................................................................................................70
8.1.4 Routine/periodic inspection schedule for Transformer:.......................................................71
CHAPTER 9: 220KV GAS INSULATED SWITCHGEAR..........................................................................72
9.1 INTRODUCTION..............................................................................................................................72
9.2 TECHNICAL DATA OF 220 KV GAS INSULATED SWITCHGEAR................................................................72
9.3 OPERATION..................................................................................................................................73
9.3.1 SF6 Circuit Breaker...............................................................................................................73
9.3.2 Disconnecting Switch...........................................................................................................73
9.3.3 Maintenance Earth Switch...................................................................................................74
9.3.4 High-Speed Earth Switch (HSES).........................................................................................74
9.3.5 Daily Checklist for Operation:..............................................................................................74
CHAPTER 10: 220 KV POT HEAD YARD...............................................................................................76
10.1 INTRODUCTION............................................................................................................................76
10.2 ISOLATOR WITH EARTH SWITCHES..................................................................................................76
10.2.1 Technical Details of Isolator................................................................................................77
10.3 LIGHTNING ARRESTER...................................................................................................................77
10.3.1 Technical Details of Lightning Arrester...............................................................................77
10.4 OPERATION................................................................................................................................78
CHAPTER 11: AUXILIARY SUPPLY SYSTEM........................................................................................79
11.1 INTRODUCTION.............................................................................................................................79
11.2 OPERATION.................................................................................................................................79
11.2.1 Auxiliary Supply from External Source (220kV)...................................................................79
11.2.1.1 Charging of 220kV Bus bar at GIS................................................................................79
11.2.1.2 Charging of 33kV Power Cavern (20BBA00GH001)...................................................80
11.2.1.3 Charging of Power Cavern Main Distribution Board (20BFA00GH001)....................80
11.2.1.4 Charging of 33kV Control Building Main Distribution Board (25BBA00GH001).......80
11.2.1.5 Charging of 400V Control Building Main Distribution Board.....................................81
11.2.1.6 Charging of 400V Diversion Weir Main Distribution Board.......................................81
11.2.1.7 Charging of 400V Desilter Main Distribution Board...................................................82
11.2.1.8 Charging of 400V Surge Tank Main Distribution Board.............................................82
11.2.2 Auxiliary Supply from Generating Units..............................................................................82
11.2.3 Auxiliary Supply from Emergency Diesel Generators/ Black Start.......................................82
11.2.3.1 Extension of Supply from 400kVA DG Set.................................................................83
11.2.3.2 Extension of 160kVA DG set.......................................................................................84
11.2.3.3 Supply changeover.....................................................................................................84
CHAPTER 12: DIVERSION WEIR AND DESILTER EQUIPMENT...........................................................86
12.1 DIVERSION WEIR INTAKE GATE......................................................................................................86
12.1.1 Operation of Intake Gate....................................................................................................86
12.1.1.1 Opening of Intake Gate...............................................................................................87
12.1.1.2 Closing of Intake gate.................................................................................................90
12.1.1.3 Gate droop control (leakage recuperation)...............................................................91
12.1.2 Operation of Intake Gate without control voltage (or PLC fault).......................................92
12.1.2.1 Raising of Gate............................................................................................................92
12.1.2.2 Lowering of Gate........................................................................................................93
12.1.3 Operation of Intake Gate without power supply................................................................93
12.1.3.1 Opening of the Gate...................................................................................................93
12.1.3.2 Closing of the Gate.....................................................................................................94
12.2 DIVERSION WEIR GATES...............................................................................................................94
12.2.1 Operation............................................................................................................................95
12.2.1.1 Opening of Radial Gate 1 =51LNC11.............................................................................95
12.2.1.2 Closing of Radial Gate 1 =51LNC11...............................................................................97
12.2.1.3 Closing of Flap Gate 1 =51LNC12.................................................................................98
12.2.1.4 Opening of Flap Gate................................................................................................100
12.2.1.5 Maintenance Mode of Weir Gates...........................................................................100
12.2.1.5.1 Maintenance operation of one Radial Gate.......................................................101
12.2.1.5.2 Maintenance operation of one Flap Gate..........................................................101
12.2.1.6 Operation of the Weir Gates without control voltage (or PLC fault)......................101
12.2.1.6.1 Operation of one Radial Gate without control voltage.....................................102
12.2.1.6.2 Closing of one Radial Gate without control voltage.........................................102
12.2.1.6.3 Closing of one Flap Gate without control voltage............................................102
12.2.1.6.4 Opening of one Flap Gate without control voltage..........................................103
12.2.1.7 Operation of Weir Gates without power supply......................................................103
12.2.1.7.1 Opening of one Radial Gate without power supply..........................................103
12.2.1.7.2 Closing of one Radial Gate without power supply............................................103
12.2.1.7.3 Closing of one Flap Gate without power supply...............................................103
12.2.1.7.4 Opening of one Flap Gate without power supply.............................................104
12.3 TRASH RACK CLEANING MACHINE................................................................................................104
12.3.1 Touch Panel Control Unit...................................................................................................105
12.3.1.1 Start Screen...............................................................................................................105
12.3.1.2 Operational Display...................................................................................................106
12.3.1.3 Setting.......................................................................................................................106
12.3.1.4 Positions....................................................................................................................107
12.3.1.5 Pre-selections............................................................................................................108
12.3.2 Local control.....................................................................................................................108
12.4 DESILTER..................................................................................................................................109
12.4.1 Desilter Inlet Gate..............................................................................................................109
12.4.2 Desilter Flushing Gates......................................................................................................109
12.4.3 Desilter Outlet Gate...........................................................................................................110
12.4.4 Screen Cleaning Machine...................................................................................................110
12.4.5 Sediment Measuring System.............................................................................................110
12.4.6 Operation of Desilter Gates...............................................................................................111
12.4.6.1 Touch Panel Control Unit...........................................................................................111
12.4.6.2 Local Control boxes on the Gates............................................................................116
12.4.7 Operation of Screen Cleaning Machine..............................................................................116
12.4.7.1 Touch Panel Control Unit..........................................................................................116
12.4.7.2 Local control position of machine...........................................................................120
CHAPTER 13: FIRE DETECTION AND PROTECTION SYSTEM............................................................122
13.1 INTRODUCTION:...........................................................................................................................122
13.2 OPERATIONAL DETAILS................................................................................................................122
13.2.1 Spray System.....................................................................................................................122
13.2.2 Automatic high velocity water spray system....................................................................122
13.2.3 Operation of deluge valve.................................................................................................123
13.2.4 Auto operation of deluge valve.........................................................................................123
13.2.5 Manual operation..............................................................................................................123
CHAPTER 14: DIESEL GENERATORS.................................................................................................124
14.1 400KVA DIESEL GENERATOR.......................................................................................................124
14.1.1 Operation...........................................................................................................................124
14.1.1.1 Starting the Engine....................................................................................................124
14.1.1.2 Engine Warm-Up........................................................................................................125
14.1.1.3 Engine Shut Down.....................................................................................................125
14.2 160KVA DIESEL GENERATOR.......................................................................................................125
14.2.1 Operation..........................................................................................................................125
14.2.1.1 Starting the Engine....................................................................................................125
14.2.1.2 Stopping the engine..................................................................................................125
14.2.1.3 Operating the engine................................................................................................125
CHAPTER 15: CONTROL SYSTEMS....................................................................................................127
15.1 OVERVIEW..................................................................................................................................127
15.1.1 Locations............................................................................................................................128
15.1.2 Plant Areas –Automation Cells..........................................................................................128
15.2 CONTROL ROOM........................................................................................................................129
15.2.1 Control Room Equipment..................................................................................................130
15.2.2 Startup of Operating Station.............................................................................................131
15.3 LOCAL HMI................................................................................................................................131
15.3.1 Local HMI Equipment.........................................................................................................131
15.3.2 Startup of local HMI..........................................................................................................132
15.4 COMMUNICATION.......................................................................................................................132
15.4.1 E8000 – Field Bus...............................................................................................................132
15.4.2 S8000-E – Process Bus.......................................................................................................132
15.4.3 Site Network-Enterprise Bus.............................................................................................132
15.4.4 TCP/IP Site Network Addresses.........................................................................................133
15.4.5 S8000-E TCP/IP Unit Network Addresses..........................................................................133
15.5 DATA ACQUISITION.....................................................................................................................134
15.5.1 Cell Controller - MFC1000...................................................................................................134
15.5.2 Field Controller - CE1000....................................................................................................135
15.5.2.1 Analogous Inputs......................................................................................................136
15.5.2.2 Temperature Inputs..................................................................................................137
15.5.2.3 Digital Inputs.............................................................................................................137
15.5.2.4 Analog Outputs........................................................................................................138
15.5.2.5 Digital Outputs.........................................................................................................139
15.5.2.6 Power Supply...........................................................................................................140
15.5.2.7 Bus controller...........................................................................................................140
15.5.2.8 Bus controller Extension 10-Base T HUB..................................................................141
15.5.2.9 Bus controller Extension 100 FX HUB.......................................................................141
15.5.2.10 Bus transmitter.......................................................................................................142
15.5.2.11 Bus Receiver.............................................................................................................143
15.5.2.12 Alstom SW X20 License Module.............................................................................143
15.5.2.13 Bus Module X20BB80.............................................................................................144
15.5.2.14 Bus Module X20BM11..............................................................................................144
15.5.2.15 Bus Module X20BM01.............................................................................................144
15.6 HMI OPERATION.......................................................................................................................144
15.6.1 HMI Database....................................................................................................................144
15.6.2 Time Server / Time tagging...............................................................................................145
15.6.3 Users.................................................................................................................................145
15.6.4 LOCAL/ REMOTE Switches.................................................................................................145
15.6.5 Alarms and Events............................................................................................................146
15.6.6 Audible Alarms.................................................................................................................147
15.6.7 Naming of Mimics’............................................................................................................147
15.7 MIMIC VIEWS.............................................................................................................................148
15.7.1 Process symbol description...............................................................................................148
15.7.1.1 Status indication........................................................................................................148
15.7.1.2 Control Window and Synthetic Variable concept....................................................150
15.7.1.3 Control Window for Set points.................................................................................151
15.7.1.4 General buttons present in all mimics......................................................................152
15.7.1.4.1 Local / Remote window......................................................................................152
15.7.1.4.2 Emergency Stop Button.....................................................................................153
15.7.2 Overview mimics...............................................................................................................153
15.7.2.1 220kV Overview.........................................................................................................154
15.7.2.2 Overview Control......................................................................................................155
15.7.2.3 Overview Electrical...................................................................................................156
15.7.2.4 Overview Heating / Ventilation / Air Conditioning...................................................157
15.7.2.5 Overview Hydraulic..................................................................................................158
15.7.2.6 Overview System......................................................................................................159
15.7.3 Unit Mimics.......................................................................................................................159
15.7.3.1 Unit 110V DC..............................................................................................................160
15.7.3.2 Unit 400V Distribution..............................................................................................161
15.7.3.3 Unit Cooling Water System......................................................................................162
15.3.3.4 Unit ESD (Emergency Shutdown)............................................................................163
15.7.3.5 Unit Generator.........................................................................................................164
15.7.3.6 Unit Main Inlet Valve................................................................................................165
15.7.3.7 Unit Main Transformer.............................................................................................166
15.7.3.8 Unit Overview...........................................................................................................167
15.7.3.9 Unit Prestart Conditions (1 - 4).................................................................................170
15.7.3.10 Unit QSD (Quick Shutdown)...................................................................................172
15.7.3.11 Unit Start sequence.................................................................................................174
15.7.3.12 Unit Stop Sequence.................................................................................................175
15.7.3.13 Unit System.............................................................................................................176
15.7.3.14 Unit Turbine.............................................................................................................177
15.7.4 Power Cavern Mimics........................................................................................................178
15.7.4.1 Power Cavern 110V Common Distribution...............................................................178
15.7.4.2 Power Cavern 110V Main Distribution......................................................................179
15.7.4.3 Power Cavern 110V Transformer Distribution.........................................................180
15.7.4.4 Power Cavern 33kV...................................................................................................181
15.7.4.5 Power Cavern 400V Main Distribution....................................................................182
15.7.4.6 Power Cavern 400V Sub-distribution 1....................................................................183
15.7.4.7 Power Cavern 400V Sub-distribution 2....................................................................184
15.7.4.8 Power Cavern 400V Sub-distribution 3...................................................................185
15.7.4.9 Power Cavern Air Supply.........................................................................................186
15.7.4.10 Power Cavern System.............................................................................................187
15.7.4.11 Power Cavern Station Transformer........................................................................188
15.7.5 Dam/Desilter Mimics.........................................................................................................188
15.7.5.1 Dam 400V Distribution.............................................................................................189
15.7.5.2 Dam Hydro................................................................................................................190
15.7.5.3 Dam System..............................................................................................................192
15.7.5.4 Desilter 400V Distribution........................................................................................193
15.7.5.5 Desilter Hydro...........................................................................................................194
15.7.5.6 Desilter System........................................................................................................195
15.7.5.7 Surge Tank 400V Distribution..................................................................................196
15.7.6 Control Building Mimics....................................................................................................197
15.7.6.1 Control Building 110V Distribution............................................................................197
15.7.6.2 Control Building 33kV...............................................................................................198
15.7.6.3 Control Building 400V Distribution..........................................................................199
15.8 400V AUXILIARY SWITCHOVER...................................................................................................200
15.8.1 Interlocking......................................................................................................................200
15.8.2 Control Function...............................................................................................................201
15.8.3 Incoming Feeders and Diesel.............................................................................................201
15.8.4 Diesel Unit.........................................................................................................................201
15.8.5 Automatic switchover......................................................................................................202
15.8.6 Automatic switchover topologies....................................................................................202
15.8.7 Priority of the Auxiliary Supply........................................................................................202
15.8.8 Emergency Supply............................................................................................................203
15.8.9 Manual Operation............................................................................................................203
15.8.10 Alarm..............................................................................................................................203
CHAPTER 16: ISLANDED MODE OF OPERATION.............................................................................204
16.1. INTRODUCTION.........................................................................................................................204
16.2 OPERATION PROCEDURES...........................................................................................................204
16.2.1 Failure of 220kV Dagachhu-Tsirang line............................................................................204
16.2.2 Failures of other transmission line except our line...........................................................205
CHAPTER 17: GENERATION SCHEDULING AND SYSTEM COORDINATION....................................206
17.1 GENERATION SCHEDULING...........................................................................................................206
17.2 MESSAGE..................................................................................................................................207
17.2.1 Purpose of Message..........................................................................................................207
17.2.2 Scope of application.........................................................................................................207
17.2.3 Type of Messages..............................................................................................................207
17.2.4 Message Procedure..........................................................................................................207
17.3 PLANNED OUTAGES MANAGEMENT..............................................................................................207
17.4 COORDINATION OF SYSTEM OPERATION.......................................................................................208
CHAPTER 18: ENERGY METERING AND METER READING..............................................................209
18.1 ENERGY METERING....................................................................................................................209
18.2 ENERGY METER READING...........................................................................................................209
CHAPTER 19: BILING AND PAYMENT................................................................................................211
19.1 BILLING......................................................................................................................................211
19.2 PAYMENT...................................................................................................................................211
CHAPTER 20: DATA KEEPING AND REPORTING...............................................................................212
20.1 SHIFT CHANGE OVER...................................................................................................................212
20.2 DATA RECORDING......................................................................................................................212
20.3 PRODUCTION INCENTIVE SYSTEM (PIS) DATA PREPARATION...........................................................213
CHAPTER 21: IP CAMERA MANAGEMENT........................................................................................215
21.1 INTRODUCTION............................................................................................................................215
21.2 INDIGO VISION CONTROL CENTER.................................................................................................215
21.3 USERS AND USER GROUPS............................................................................................................215
21.4 OPERATION...............................................................................................................................216
21.4.1 How to add camera in indigovision control centre software............................................216
21.4.2 Camera setting:.................................................................................................................217
21.4.2.1 Camera encoder setting:...........................................................................................217
21.4.2.2 Camera time setting:................................................................................................218
21.4.2.3 Set login password for Camera:...............................................................................218
21.4.2.4 Set camera for video recording:..............................................................................219
21.4.3 Export recorded video to external drive:.........................................................................220
21.4.4 Create sequence for camera automatic rotation:.............................................................222
21.4.5 Network Video Recorder (NVR):.......................................................................................227
21.4.6 Archiving..........................................................................................................................228
CHAPTER 22: VENTILATION SYSTEM...............................................................................................229
22.1 INTRODUCTION..........................................................................................................................229
22.2 OVERVIEW OF HVAC SYSTEM......................................................................................................229
22.3 EVACUATION OF SMOKE DURING FIRE INSIDE POWER CAVERN..........................................................230
22.4 OPERATION PROCEDURE FOR POWER CAVERN VENTILATION SYSTEM.................................................231
22.4.1 In winter season, run the following mechanical ventilation:.............................................231
22.4.2 In summer season.............................................................................................................231
SECTION B: MAINTENANCE MANUAL....................................................264
CHAPTER 1: GENERATOR..................................................................................................................265
1.1 INTRODUCTION.............................................................................................................................265
1.2 SAFETY INSTRUCTIONS FOR MAINTENANCE.....................................................................................265
1.3 PREVENTIVE MAINTENANCE..........................................................................................................266
1.4 RECOMMENDED INSPECTIONS........................................................................................................267
1.5 RECOMMENDED OVERHAULS........................................................................................................269
1.6 OVERHAUL PLANS:.......................................................................................................................272
1.7 SAMPLE CHECKLISTS.....................................................................................................................278
CHAPTER 2: EXCITATION SYSTEM...................................................................................................285
2.1 SPU 232 PROCESSOR CARD...........................................................................................................285
2.2 CLEANING...................................................................................................................................285
2.3 CHECKING SCREWS AND BOLTS......................................................................................................285
2.4 LUBRICATION..............................................................................................................................286
2.5 MAINTENANCE OF THREE-PHASE SWITCHES, DE-EXCITATION SWITCH, ISOLATING SWITCHES AND POWER
CONTACTORS....................................................................................................................................286
2.6 FAN...........................................................................................................................................286
2.7 POWER SUPPLY UNITS..................................................................................................................286
2.8 INSPECTION................................................................................................................................286
2.9 HOW TO DETECT A SEMICONDUCTOR DEFECT..................................................................................286
2.10 OVERVIEW OF MAINTENANCE WORK.............................................................................................287
2.11 CHANGE OF HARDWARE COMPONENTS RUNNING WITH A SOFTWARE.................................................288
CHAPTER 3: TURBINE & AUXILIARIES.............................................................................................289
3.1INSPECTION AND MAINTENANCE PLAN............................................................................................289
3.1.1 Activities during operation.................................................................................................289
3.1.2 Activities during the Maintenance......................................................................................291
3.1.3 Maintenance or inspection activities..................................................................................292
3.1.3.1 Pelton Runner.............................................................................................................292
3.1.3.2 Turbine shaft..............................................................................................................293
3.1.3.3 Turbine guide bearing................................................................................................293
3.1.3.4 Nozzles and deflectors..............................................................................................293
3.1.3.5 Over speed device.....................................................................................................294
3.1.3.6 Turbine casing............................................................................................................294
3.1.3.7 Electrical devices........................................................................................................294
3.1.4 Troubleshooting................................................................................................................294
CHAPTER 4: MAIN INLET VALVE & AUXILIARIES............................................................................295
4.1 MAINTENANCE............................................................................................................................295
4.4.1 Maintenance and inspection plan......................................................................................295
4.4.1.1 Activities during operation........................................................................................295
4.4.1.2 Activities in case of Shut down machine..................................................................299
4.4.2 Troubleshooting................................................................................................................301
CHAPTER 5: GOVERNING SYSTEM...............................................................................................302
5.1 HYDRAULIC GOVERNOR................................................................................................................302
5.1.1 Safety instructions..............................................................................................................302
5.1.2 Remarks for disassembly / reassembly of hydraulic Governor Equipment.........................302
5.1.3 Maintenance and inspection plan......................................................................................303
5.1.3.1 Activities during operation........................................................................................304
5.1.3.2 Activities in case of shut-down machine...................................................................305
5.1.4 Troubleshooting................................................................................................................306
5.2 DIGITAL GOVERNOR.....................................................................................................................306
CHAPTER 6: GENERATOR STEP-UP TRANSFORMER.......................................................................307
6.1 MAINTENANCE SCHEDULE.............................................................................................................307
6.2 OIL SAMPLING............................................................................................................................307
6.2.1 Electric Strength:...............................................................................................................307
6.2.2 Moisture Content:..............................................................................................................307
6.2.3 Acidity:..............................................................................................................................307
6.3 SAMPLING PROCEDURE................................................................................................................308
6.3.1 Tools required....................................................................................................................308
6.3.2 Procedure..........................................................................................................................308
6.4 WINDING TEMPERATURE INDICATOR TESTS....................................................................................308
6.4.1 Tools and materials...........................................................................................................308
6.4.2 Procedures........................................................................................................................308
6.4.3 Calibration.........................................................................................................................309
6.5 BUCHHOLZ RELAY FUNCTIONAL TEST............................................................................................309
6.5.1 Tools and Materials Required............................................................................................309
6.5.2 Procedures........................................................................................................................309
6.6 TAP-CHANGER OPERATION...........................................................................................................309
6.7 OIL FILTRATION...........................................................................................................................310
6.8.1 Tools and Materials............................................................................................................310
6.7.2 Procedure...........................................................................................................................310
6.8 CORRECTIVE MAINTENANCE..........................................................................................................310
6.9 REMOVING AND REFIXING OF PUMPS.............................................................................................310
6.9.1 Tools and materials............................................................................................................310
6.9.2 Procedure..........................................................................................................................310
6.10 TROUBLE SHOOTING...................................................................................................................311
CHAPTER 7: STATION AUXILIARY TRANSFORMERS.......................................................................312
7.1 STATION AUXILIARY TRANSFORMER, 220/11KV, 5MVA.....................................................................312
7.1.1 Routine Inspection Schedule...............................................................................................312
7.1.2 Oil sampling........................................................................................................................313
7.1.3 Maintenance Schedule........................................................................................................313
7.1.3.1 Electric Strength:........................................................................................................314
7.1.3.2 Moisture Content:......................................................................................................314
7.1.3.3 Acidity:........................................................................................................................314
7.1.4 Sampling procedure...........................................................................................................314
7.1.4.1 Tools required.............................................................................................................314
7.1.4.2 Procedure...................................................................................................................314
7.1.5 Winding Temperature indicator tests.................................................................................315
7.1.5.1 Tools and materials.....................................................................................................315
7.1.5.2 Procedures..................................................................................................................315
7.1.5.3 Calibration...................................................................................................................315
7.1.6 Buchholz Relay Functional Test..........................................................................................315
7.1.6.1 Tools and Materials Required.....................................................................................315
7.1.6.2 Procedures.................................................................................................................316
7.1.7 Tap-changer Operation.......................................................................................................316
7.1.8 Oil Filtration........................................................................................................................316
7.1.8.1 Tools and Materials....................................................................................................316
7.1.8.2 Procedure...................................................................................................................316
7.1.9 Corrective Maintenance......................................................................................................317
7.1.10 Removing and Re-fixing of Pumps.....................................................................................317
7.1.10.1 Tools and materials...................................................................................................317
7.1.10.2 Procedure..................................................................................................................317
7.1.11 Trouble Shooting...............................................................................................................317
7.2 AUXILIARY TRANSFORMER, 33/0.4KV (800 KVA)...........................................................................317
7.2.1 Introduction........................................................................................................................317
7.2.2 Technical Data....................................................................................................................318
7.2.3 Maintenance.......................................................................................................................318
7.2.3.1 Yearly Maintenance....................................................................................................318
CHAPTER 8: GAS INSULATED SWITCHGEAR....................................................................................319
8.1 MAINTENANCE.............................................................................................................................319
8.1.1 GIS inspection over view:....................................................................................................319
8.1.2 Check List (After Maintenance) for GIS Bays:.....................................................................320
CHAPTER 9: POT HEAD YARD...........................................................................................................321
9.1 MAINTENANCE.............................................................................................................................321
9.1.1 Yearly Maintenance:............................................................................................................321
CHAPTER 10: CROSSED LINKED POLYETHYLELE (XLPE) CABLE.....................................................322
10.1 INTRODUCTION...........................................................................................................................322
10.2 TECHNICAL DETAILS OF XLPE......................................................................................................322
10.3 MAINTENANCE:..........................................................................................................................322
CHAPTER 11: AUXILIARY SUPPLY SYSTEM......................................................................................324
11.1 MAINTENANCE OF 33KV SWITCHGEAR...........................................................................................324
11.1.1 Levels of maintenance:......................................................................................................324
11.1.2 Preventive maintenance of the moving parts:..................................................................324
11.1.3 Preventive maintenance of the functional units:...............................................................325
11.1.4 Preventive maintenance of Bus bar compartment...........................................................326
11.1.5 Preventive maintenance of the High Voltage Cables compartment..................................326
11.1.6 Preventive maintenance of the Low Voltage Box..............................................................327
11.1.7 Maintenance on 33 kV Vacuum circuit breakers................................................................327
11.1.8 Maintenance on Metering and protection Instruments:...................................................328
11.1.8.1 Current transformer:.................................................................................................328
11.1.8.2 Potential transformers:............................................................................................329
11.2 MAINTENANCE OF 400V SUPPLY SYSTEM.....................................................................................329
11.2.1 Yearly/Annual maintenance...............................................................................................329
CHAPTER 12: DIVERSION WEIR AND DESILTER...............................................................................330
12.1 INTAKE GATE..............................................................................................................................330
12.1.1 Periodic Inspection and Maintenance................................................................................330
12.2 DIVERSION WEIR GATES..............................................................................................................331
12.2.1 Periodic Inspection and Maintenance................................................................................331
12.3 Trash Rack Cleaning Machine...............................................................................................332
12.3.1 Periodic Inspection and Maintenance...............................................................................332
12.4 DESILTER..................................................................................................................................333
12.4.1 Mechanic and steel structure............................................................................................333
12.4.2 Screws and fastening elements........................................................................................334
12.4.3 Control after Flooding......................................................................................................334
12.4.4 Hydraulic System..............................................................................................................334
12.4.5 Maintenance planning and inspection..............................................................................334
12.5 TROUBLESHOOTING....................................................................................................................335
12.6 REPLACEMENT OF SEAL...............................................................................................................335
CHAPTER 13: FIRE DETECTION AND PROTECTION SYSTEM...........................................................336
13.1 MAINTENANCE HYDRANTS AND HOSE REEL....................................................................................336
13.2 YEARLY INSPECTIONS:.................................................................................................................336
13.3 MAINTENANCE OF DELUGE VALVE.................................................................................................336
13.4 PERIODICAL TESTING AND MAINTENANCE OF HVW SPRAY SYSTEM..................................................336
CHAPTER 14: DIESEL GENERATORS.................................................................................................338
14.1 400KVA DIESEL GENERATOR......................................................................................................338
14.1.1 Preventive Maintenance...................................................................................................338
14.1.2 Stand-By Generator set Maintenance...............................................................................338
14.2 160KVA MAINTENANCE SCHEDULE..............................................................................................341
CHAPTER 15: CONTROL AND PROTECTION SYSTEMS....................................................................343
15.1 CONTROL SYSTEM......................................................................................................................343
15.1.1 Optimum Environmental Conditions.................................................................................343
15.1.2 Dust cleaning.....................................................................................................................343
15.1.3 Cleaning of the modules...................................................................................................343
15.1.4 Electrical checking............................................................................................................344
15.1.5 Ventilation cleaning..........................................................................................................344
15.1.6 Functional test..................................................................................................................344
15.1.7 Power sources checking....................................................................................................344
15.1.8 Stations maintenance.......................................................................................................344
15.1.9 Printer maintenance.........................................................................................................345
15.1.9.1 General cleaning.......................................................................................................345
15.1.9.2 Cleaning of the print-head.......................................................................................345
15.1.9.3 Print test...................................................................................................................345
15.1.10 Maintenance of the spare part........................................................................................345
15.1.11 Maintenance of the Ethernet network............................................................................346
15.2 AUTOMATIC SYNCHRONIZER (SYNCHROTACT 5)........................................................................346
15.2.1 Maintenance Instructions.................................................................................................346
15.2.2 Troubleshooting...............................................................................................................347
15.3 PROTECTION SYSTEM..................................................................................................................347
15.3.1 Startup of System start-up check list for Protection........................................................347
15.3.2 Visual Function Check.......................................................................................................348
15.3.3 Shutting Down Protection System...................................................................................349
15.3.4 Faults................................................................................................................................349
15.3.5 Maintenance.....................................................................................................................349
15.3.6 Maintenance period.........................................................................................................353
15.3.7 Maintenance checks.........................................................................................................353
15.3.8 Method of repair..............................................................................................................354
15.3.9 Post modification tests....................................................................................................356
15.3.10 Cleaning..........................................................................................................................356
CHAPTER 16: IP CAMERA SYSTEM...................................................................................................357
16.1 MAINTENANCE...........................................................................................................................357
CHAPTER 17: HEATING, AIR CONDITIONING & VENTILATION SYSTEM (HVAC)............................358
17.1 MAINTENANCE SCHEDULE............................................................................................................358
CHAPTER 18: DC SUPPLY SYSTEM...................................................................................................359
18.1 TECHNICAL DETAILS OF THE 110V DC, 440AH FLOAT CUM BOOST BATTERY CHARGER.................359
18.2 GENERAL FEATURES...................................................................................................................360
18.3 CHARGING WORKING PHILOSOPHY..............................................................................................360
18.4 PREVENTIVE MAINTENANCE.........................................................................................................361
18.5 ANNUAL MAINTENANCE..............................................................................................................361
18.6 TROUBLESHOOTING....................................................................................................................361
SECTION C: SAFETY AND WORK PERMIT..................................................................443
CHAPTER 1: PERMIT TO WORK-LOCK OUT/ TAG OUT....................................................................444
1.1 INTRODUCTION............................................................................................................................444
1.2 SCOPE AND FIELD OF APPLICATION.................................................................................................444
1.3 RESPONSIBILITIES........................................................................................................................445
1.4 POLICY.......................................................................................................................................445
1.5 DEFINITIONS...............................................................................................................................446
1.6 PERMIT TO WORK.......................................................................................................................448
1.7 PROCEDURE OF LOCKOUT & TAGOUT.............................................................................................449
1.7.1 Preparation of Lockout and Tagout...................................................................................449
1.7.2 Sequence of Lockout and Tagout.......................................................................................450
1.7.3 Re-commissioning / Taking back in line, of systems after maintenance.............................451
1.7.4 Lockout and Tagout Procedure involving more than one Person/group............................451
1.7.5 Lockout and Tagout Procedures Involving Shifts...............................................................452
1.7.6 Temporary Removal of Lockout/Tagout Devices...............................................................452
1.7.7 Maintenance requiring undisrupted energy supply............................................................453
1.7.8 Lockout Devices and Locks.................................................................................................453
1.7.9 Tagout and Tags.................................................................................................................454
1.7.10 Contractors.......................................................................................................................455
1.8 EXCEPTIONS.........................................................................................................................455
1.9 REVIEW OF LOTO COMPLETION....................................................................................................455
1.10 AUDIT.......................................................................................................................................455
1.11 TRAINING & RECORD KEEPING......................................................................................................455
1.12 ANNEXURES...............................................................................................................................457
CHAPTER 2: SAFETY AND OCCUPATIONAL HEALTH......................................................................463
2.1 INTRODUCTION............................................................................................................................463
2.2 GENERAL SAFETY RULES..............................................................................................................463
2.3 WORK SITE SAFETY.....................................................................................................................464
2.4 ELECTRICAL HAZARDS..................................................................................................................464
2.4.1 Dangers from Electrical Shock and its Effects....................................................................464
2.4.2 Rescue from Electric Shock................................................................................................465
2.4.3 Dangers from Arcs and Blasts............................................................................................465
2.4.4 Lockout and Tagout..........................................................................................................465
2.4.5 Fire Hazards.......................................................................................................................466
2.5 PERSONNEL PROTECTIVE EQUIPMENT............................................................................................466
2.5.1 Head Protection.................................................................................................................466
2.5.2 Eye and Face Protection.....................................................................................................467
2.5.3 Foot Protection.................................................................................................................468
2.5.4 Hand Protection................................................................................................................468
2.5.5 Hearing Protection............................................................................................................468
2.5.6 Life Jackets and Safety Belts.............................................................................................469
2.5.7 Respiratory Protection......................................................................................................469
2.6 TOOLS AND EQUIPMENT..............................................................................................................469
2.6.1 Hand Tools.........................................................................................................................469
2.6.2 Ladders- Portable..............................................................................................................469
2.6.3 Hoisting and Rigging..........................................................................................................470
2.6.4 Welding, Cutting and Brazing............................................................................................470
2.6.5 Air-Operated Tools............................................................................................................470
2.7 FIRST AID....................................................................................................................................471
2.7.1 Work Injury and Mishap Reports........................................................................................471
REFERENCES.....................................................................................................................................472
ACKNOWLEDGEMENT......................................................................................................................473
The 126 MW (2x63 MW) Dagachhu Hydropower Plant, located in the south-western part of
Bhutan under Dagana Dzongkhag, is a run-of-the-river scheme being developed on the left bank
of river Dagachhu, located between 10.5 km and 20.2 km upstream of the confluence with the
Punatsangchhu. The elevation of the project area and the catchment area ranges from 500 m to
almost 4,000 m above mean sea level. The mean annual generation from the project is 515 GWh
and 90% dependable energy production is 360 GWh.
The project was approved for implementation at an estimated cost of US$ 201.50 million,
corresponding to Nu. 8.16 billion (2008 price levels and exchange rates) at 60:40 debt equity
ratio. Taking into consideration the actual costs of award of major contracts, encountering of
poorer geology, geological surprises and assumption of the geological conditions of the
remaining length of headrace tunnel excavations, variation in quantity of supports and a stronger
US $ and Euro than at the time of decision of investment, cost to completion of the project has
been revised to Nu. 12,226.739 million. DGPC holds 59% equity, Tata Power Company Limited,
India 26% and National Pension & Provident Fund of Bhutan the remaining 15% of the equity. Asian
Development Bank is providing loan of USD 51 million for financing the civil works; RZB, Austria is
providing loan of Euro 41.23 million for financing the E&M works, and the NPPF is providing loan
of Nu. 600 million.
To meet the additional fund required for project, the Asian Development Bank has already
committed to Ministry of Finance, Royal Government of Bhutan to provide additional debt
financing to Dagachhu Hydropower project.
Besides the royalty energy, all the power from the project shall be evacuated to India through a
long-term Power Purchase Agreement with Tata Power Trading Company Limited, India.
1.1 Location
District : Dagana
1.2 Hydrology
Mean Annual Yield (usable) : 733 million m3 excluding Residual Flow and Flood
Radial Gates
Number :2
Flap Gates
Number :2
1.4 Intake
Number :2
Number of Gates :1
Invert of Intake : 838.80 m.a.s.l
1.6Desilting Chamber
Number : 3 nos.
Number : 3 nos.
Gradient : 0.25%
Number : 1 only
Inclination : 90 °
Length : 679 m
Diameter : 4.25/5.0 m
Type : Horseshoe
Turbine
Number : 2 Nos.
Capacity : 62.222 MW
Number of Nozzles :6
Generator
Rated frequency : 50 Hz
Rated power factor : 0.9
Number of Poles : 22
Number of phases :3
Transformer
Number :6
Rated Voltage, LV : 11 kV
No. of phase :1
No. of taps :4
Number :2
EOT Crane
Details Specification
Manufacturer Alstom
Normal Voltage 11 kV
Rated Frequency 50 Hz
Insulation Class F
Direction of Rotation when seen from Turbine Wheel Anti-Clockwise
Guaranteed Efficiencies:
General
To ensure the continuing operational integrity of generators, generator temperatures, vibration
and various generator auxiliary systems must be closely monitored. Any abnormalities must be
reported and investigated in a timely manner.
Start-up Operation
Prior to the start-up of the generator all the checks at stand still must be completed.
Atnotime,shouldexcitationinterlocksorrelayprotectionbedisabledormade non-
automaticforthepurposeofestablishingageneratorfield.Furthermore,agenerator
fieldshouldnotbere-establishedafteraprotectiverelayhastrippedthegeneratoruntil
athoroughinvestigationofthecausehasbeencompleted.
Ageneratorfieldshouldnotbeappliedormaintainedataturbinespeedaboveor
belowthevaluegivenbythemanufacturer.
Asmoothsynchronizationofthegeneratortothegridwillpreventhighstresseson statorandrotor.
On-line operation
Thegeneratorsshouldbeoperatedwithintheircapabilitycurves,
withlimitedloadandfieldcurrent.Operationsbeyondtheselimitswillresultingeneratoroverheating.
Duringnormaloperation,the voltageregulatorandwhereapplicable,the powersystem
stabilizer(PSS)shouldbecontinuouslyinservice.
Shut-down operation
Thereactiveandactivepowershouldbereducedto0MVAbeforeopeningthe generator
circuitbreakerandthefieldbreaker. Wicketgatesandinletvalveshould be closed.HP-
jackingoilpumpshould be switchedonandmechanicalbrakesmustbeapplied.
Theactualsettingsaredefinedinthecommissioningreport.Atstandstill,theauxiliary
systemswillbeswitchedoff(nocoolingwaterflow)andthespaceheatersareinoperation.
Preconditions
The generator is ready to restart after a normal shutdown due to plant utilization and water
availability after confirming the following preconditions:
The down time did not exceed 1week.
Auxiliary equipment is turned off.
Space heaters of the generator are in operation
The unit should be in stop stable condition.
Verify that all portable earth devices have been removed.
Check tap changer position.
Start-up sequences
Thefollowingsequencetostart-upthegeneratorshouldbeapplied.
Note:
Remainonthewalkwayaroundthestatorframewhilecarryingouttheinspection.
Donotresetalarmsandtrips,ifyoudon'tknowthecauseoftheproblem.
Generatorisonlyreadyforoperation,whenallchecksunderpointNo.1are
completedandtheresultsaresatisfactory.
1. Inspectiontouraroundandthroughthegenerator.
a) Checkforoilandwaterleakagesonthebearings.
b) Check oil levels on the bearings. Oil level must be at normal.
c)Check, if space heaters are running and if the generator is dry (no condensation).
d) Check for anomalies on the unit.
e) Check and reset alarms and trips.
f) Check, if excitation and protection system is enabled and operational.
2. HP-jacking oil system is in operation. Oil pressure is applied (feedback signal from the pressure
switch).
3. Oil mist suction system is in operation.
4. Carbon dust suction system is in operation.
5. Mechanical brake is released (feedback signal from the limit switches).
6. Cooling water is turned on (feedback signal from the flow monitors).
7. Firefighting system is ready.
8. Space heaters are turned off.
9. Start unit. Apply excitation at n > 95%.
10. Synchronize the unit to the grid.
11. Apply load.
Note: Forfurtheranddetailedstart-upsequenceinformationrefertotheplantcontrol documentation.
Tomaintaintheintegrityofoperationofthegenerator, thefollowingchecksshouldbe
routinelyperformed on hourly/daily basis duringtheinspectiontour.
1. Check cooling water flow to the stator, air/water cooler and to the bearing oil/water
cooler.
2. Check stator core temperatures.
3. Check stator winding temperatures.
4. Check cold and warm air temperatures.
5. Check bearing oil temperatures.
6. Check bearing oil levels.
7. Check bearing vibration levels.
8. Check brake air pressure.
9. Check alarm and trip annunciation. Solve problems, if annunciation board indicates alarms.
10. Check generator protection.
Anomaliesfoundduringtheroutineinspectionsshouldbemonitoredandworkorders
shouldbepreparedtoresolve the problems.
Compare actual temperature readings of the generator (stator core, stator winding, cold and
warm air and bearing oil) with the long-term temperature pattern. Deviations must be analyzed
and corrective actions must be initiated in order to prevent the generator from tripping.
2.4 Shutdown
The reactive and active power should be reduced to 0 MVA before opening the generator circuit
breaker and the field breaker. Wicket gates and inlet valve form the turbine are closing. HP-
jacking oil pump is switched on and mechanical brakes will be applied. The actual settings are
defined in the commissioning report. At standstill, the auxiliary systems will be switched off (no
cooling water flow) and the space heaters are in operation.
1. Thegeneratorbreakerandthefieldbreakerareopened.
2. Theturbineissimultaneouslyshutdownwith the governorinoperation.
Shutdown by electrical fault
1. HP-jackingoilsystemisoff.
2. Oil mist suction system is off.
3. Carbon dust suction system is off.
4. Cooling water system is turned off.
5. Check, if space heaters are in operation.
6. Investigate the cause of the shutdown by electrical fault (trip by generator protection)
7. Correct the basic cause.
8. Prepare to put back the generator into service.
Automatic braking
Thefollowingtaskshavetobeexecuted,ifthegeneratorwillnotbeoperatedbetween
one(1)andfour(4)weeks.
1. Carbonbrushesmustberemovedfromthesliprings.Carbonbrushescancause
corrosiononthesliprings.
2. Spaceheatersmustbeinoperation.Temperatureinsidethegeneratormustbe
abovethedewpointtopreventcondensation.
3. Protect slip ring covering against dust and humidity. Do not use solvents for cleaning the
areas close to the carbon brushes.
4. Dry or heat air in the power house to prevent condensation (excitation, protection and
control system).
Manual braking
Thefollowingtaskshavetobeexecuted,ifthegeneratorwillnotbeoperatedformore
thanfour(4)weeks.
1. Carbonbrushesmustberemovedfromthesliprings.Carbonbrushescancause
corrosiononthesliprings.
2. Space heaters must be in operation. Temperature inside the generator must be above the
dew point to prevent condensation.
3. Protect slip ring covering against dust and humidity. Do not use solvents for cleaning areas
close to the carbon brushes.
4. Dry or heat air in the power house to prevent condensation (excitation, protection and
control system).
5. Check bearing oil temperatures.
6. Check bearing oil levels.
7. Check bearing vibration levels.
Note:
Lock,tagoutandgroundgeneratorandexcitation(workpermit)first.
Applythenecessarysafetymeasures.
8. Check brake air pressure.
9. Check alarm and trip annunciation. Solve problems, if annunciation board indicates alarms.
10. Check generator protection.
Standstill 1 (4 weeks)
Thefollowingtaskshavetobeexecuted,ifthegeneratorwillnotbeoperatedbetween
one(1)andfour(4)weeks.
1. Carbonbrushesmustberemovedfromthesliprings.Carbonbrushescancause
corrosiononthesliprings.
2. Space heaters must be in operation. Temperature inside the generator must be above the
dew point to prevent condensation.
3. Protect slip ring covering against dust and humidity. Do not use solvents for cleaning areas
close to the carbon brushes.
4. Dry or heat air in the power house to prevent condensation (excitation, protection and
control system).
Standstill 2 (over 4 weeks)
Thefollowingtaskshavetobeexecuted,ifthegeneratorwillnotbeoperatedformore
thanfour(4)weeks.
1. Carbonbrushesmustberemovedfromthesliprings.Carbonbrushescancause
corrosiononthesliprings.
2. Space heaters must be in operation. Temperature inside the generator must be above the
dew point to prevent condensation.
3. Protect slip ring covering against dust and humidity. Do not use solvents for cleaning areas
close to the carbon brushes.
4. Dry or heat air in the power house to prevent condensation (excitation, protection and
control system).
5. Check bearing oil temperatures.
6. Check bearing oil levels.
7. Check bearing vibration levels.
Note:
Lock,tagoutandgroundgeneratorandexcitation(workpermit)first.
Applythenecessarysafetymeasures.
8. Check brake air pressure.
9. Check alarm and trip annunciation. Solve problems, if annunciation board indicates alarms.
10. Check generator protection.
Faultscanbeofmechanicalorelectricalnature.Dependingontheirseriousness,they
actuateprotectiondevices,which can causeemergencyorrapidshutdowns,loadreductions
orsimplygivealarmsignals.
Inallcases,makesurethatthereisnooperationoftheindicatororundue
measurementandinspectthecomponent,whichcausedtheunittotriporthe
protectiondevicetooperate.
Operationalfaults(mechanical)
Lubricationpressuretoolow • Checkvalves,filtersandpump
s
• Checkcoolingwaterflowrate
Pressuretoohigh • Checkpressurecontrolvalve
• Checkvalveposition
OPERATION MANUAL
CHAPTER 3
3.1 Introduction
The static excitation equipment converts a 3-phase alternating current into a direct current which
is used to generate the magnetic field in the synchronous machine. The excitation current can
influence the machine voltage, the reactive power and the cos φ. Furthermore, the active power
and/or the rotor displacement angle can be dynamically influenced (not stationary).
Manufacturer ALSTOM
The field circuit breaker in the field circuit is used to isolate the field circuit from the converter. It
is capable of switching off the synchronous machine from full load under the maximum
conditions of a 3-phase short circuit.
In addition to its main contacts, the field circuit-breaker
also has a de-excitation contact with which the field
energy stored in the field can be dissipated across the
de-excitation resistor. The de-excitation contact closes
shortly before the main contacts open so as to ensure
proper commutation of the field current from the main
contacts to the de-excitation contact when the field
breaker is switched off.
Feeding the power circuit of the equipment at the three-phase end is possible in two ways:
Supply from the medium voltage station service switchgear: The converter transformer is
connected at the primary end via the power switch to
the medium voltage supply. The converter
transformer feeds the thyristor-bridge as well as the
control transformer. The DC flows from the thyristors
via the de-excitation switch and the shunt (which
serves for measuring the controlled variable) to the
excitation winding of the synchronous machine.
Depending on the position of their firing pulses, the
thyristor supplies a continuously adjustable DC
voltage and hence a variable DC for the excitation of
the machine. The DC voltage can be continuously
adjusted between +100% and -87% with continuous DC
by adjusting the thyristor pulses.
The main incoming supply for DC60V and DC24V is routed via the 2.5KVA control transformers
and power supply converter (T112 & T114) for channel-1 and 2 respectively. One control
transformer feeds one automatic channel or the manual mode. By means of transformers &
power supply converter, DC24V and DC60V are supplied separately for automatic channel-1 and
automatic channel-2 or for the manual mode from the main excitation or auxiliary transformer.
Dry type cast coil excitation transformers are used in static excitation system to feed excitation
power to the generator. The primary of transformer is connected to the generator bus. The
secondary of the transformer is connected to the thyristor converter which provides controlled
excitation power to the generator field.
This equipment monitors the excitation transformer for overheating in the windings that could
result from over current, short-circuits, or inadequate natural cooling.
The monitoring uses temperature monitoring modules, in conjunction
with the PTC temperature sensors built into the windings. Normally,
the temperature is monitored in two stages: the first stage sets off an
alarm (120°C), the second causes a trip of the excitation (130°C).
Temperature sensors are embedded into the cast coil to measure the
temperature of the low voltage winding in each phase. Two separate
signal systems, one for alarm and the other for trip are incorporated.
Figure 3.7:Main excitation transformer temperature monitoring screen
3.3.9 Excitation Transformer Overcurrent Protection
The overcurrent protection included in the P143 relay provides four stage
non-directional/directional three phase overcurrent protection with independent time delay
characteristics. All overcurrent and directional settings apply to three phases but are
independent for each of the two stages.
I>set 0.1 In
T reset 0 ms
TMS 0.5
I>>set 1.1In
T reset 0ms
3.3.10 Fans
The thyristor cubicle is fitted with two fans which work parallel in order to cool the thyristors
bridge. The fan motors are fed via circuit breakers from the control transformers.
In addition to normal pneumatic braking, each generator is equipped with dynamic braking. This
method of braking shall bring the machine to rest quickly during normal shut down or tripped on
quick shut down (tripping inputs related to governor, bearings, etc.).
Particular Details
Type SBIFB-114198
Ur 12kV
Up 75kV
Ir 6300A
Ik 63000A
Fr 50
Ud 28
The dynamic braking system has separate transformer and stator terminal shorting cubicle. The
dynamic braking will come into action during normal shut down and quick shutdown (QSD). The
stator terminal shall be shorted at 65% of the rated speed during the normal and quick shutdown
of the generating Units.
3.4 Operation
3.4.1 Control
The following condition must be fulfilled as a precondition for switching the excitation
equipment off:
The synchronous machine may not be connected to the grid, i.e. the machine power switch must
be open.
In test mode, switching off is also possible if the power switch is closed. A "protection off" circuit
is always possible.
Protection off is possible as follows:
By the electric machine protection
Internal "protection off" from within the excitation equipment
Manual protection switch S101 on the excitation equipment.
A "release for synchronization" signal can be generated when the de-excitation switch is "on"
and if the machine voltage is greater than 80% of the nominal voltage.
As a precondition for remote control of the equipment from a control room, the key-operated
switch on keypad S111 on the equipment must be in the REMOTE (vertical) position.
If the excitation equipment communicates with a control system via a data bus, the following
functions are then exclusively available in the control room.
Excitation ON
Excitation OFF
Entering the machine voltage set point in % of the nominal machine voltage if the automatic
channel is active and if neither the reactive-power controller nor the cos-ϕ- controller are
active.
Entering the reactive-power set points directly in MVar if the reactive-power controller is
active, where a positive value corresponds to over excited and a negative value to under
excited reactive power.
Entering the cos-ϕ set point directly as a numerical value, i.e. +0.xx….+1.0 or1…-0.0,
respectively, where the range of 0.xx…1 corresponds to overexcited and the range of –0.xx
…-1 to under excited reactive power.
The value of +1 or –1, respectively, represents a reactive power of 0.
Switching between manual and automatic channel or automatic 1 to automatic 2 channel,
respectively.
Entering the excitation current set point directly in A (or %) when an excitation current
controller (manual controller) is active.
If the excitation equipment is connected to the control room by hardware, the following
functions
are then exclusively available in the control room.
Excitation ON
Excitation OFF
Set point raise*
Set point lower*
Switching between manual and automatic channel or automatic 1 to automatic 2channel,
respectively.
* The set points for machine voltage, reactive power or cos ϕand excitation current are variedwith
the set gradients. The changed set point of the control loop which is active for the timebeing comes
into effect. The other set points are readjusted a) as lower-level controllers(voltage set point with
reactive-power and/or cos-ϕcontrol) or b) by the set pointreadjustment functions of the manual
and/or automatic channels (voltage set point withmanual mode, excitation current set point with
automatic mode).
The permissible limits of machine voltage, reactive power or cos ϕand excitation current, as
wellas their gradients, are determined during commissioning, but can also be changed at a
laterstage.If the key-operated switch is not in the REMOTE positions, these functions are not
available in the control room.
LED Description
S1 ON Fault in channel 1
S2 ON Fault in channel 2
S3 Not used
S4 Not used
OPERATION MANUAL
CHAPTER 4
S8 Simulation active
The manual mode serves as emergency mode and for service or commissioning purposes.
It consists of a pure excitation current control function. Excitation limiters are not included in the
manual mode.
When the equipment is switched on in manual mode, the current set point is 0. This means that
no excitation current is initially flowing.
In the case of excitation equipment receiving is power supply from the machine leads, a small set
point is pre-set at the time of switching on.
The excitation current set point can be adjusted both in the control room and on the excitation
equipment.
If the excitation equipment is connected to the control room by hardware, the "set point raise"
or "set point lower" buttons in the control room can be used in order to set the desired
excitation current. If the excitation equipment communicates with the control room via a control
bus, the excitation current value can be entered directly as an Ampere (or %) value.
The key-operated switch on keypad S111 must be in the Remote position for this purpose. If the
key-operated switch on keypad –S111 is in the Local position, the excitation current set point can
only be varied by pressing the "set point raise" and "set point lower" buttons on keypad –S111.
4.1 Introduction
The Dagachhu hydro power plant is equipped with two vertical Pelton type turbines and the
associated governing equipment and main inlet valves.
The rotating parts of the turbine are equipped by one guide bearing which is located close to the
turbine runner. The thrust bearing is located in the generator. The water will enter the turbine
through the main inlet valve, followed by the distributor where the flow will be diverted and
guided to the six nozzles. The nozzles are fixed on the distribution pipe inside the turbine
housing. The flow and therefore discharge will be controlled by the opening of the nozzle. Each
nozzle is equipped with a separate servomotor and a deflector incl. deflector servomotor. The
water jet then will impact on the sophisticatedly designed Pelton runner buckets to ensure the
highest efficiency possible. The water is then guided by the water passage shield and the turbine
housing to the tailrace channel and exits the powerhouse.
4.2Technical data
Number : 2 Nos.
Capacity : 62.222 MW
Number of Nozzles :6
4.3 Description
The water will enter the turbine through the main inlet valve, followed by the distributor where
the flow will be diverted and guided to the six nozzles. The nozzles are fixed on the distribution
pipe inside the turbine housing. The flow and therefore discharge will be controlled by the
opening of the nozzle. Each nozzle is equipped with a separate servomotor and a deflector
including deflector servomotor. The water jet then will impact on the sophisticatedly designed
Pelton runner buckets to ensure the highest efficiency possible. The water is then guided by the
water passage shield and the turbine housing to the tailrace channel and exits the powerhouse.
The fully forged runner is made of X3CrNiMo13-4 stainless steel (1.4317) and equipped with
twenty (20) buckets.
The connection of the runner to the turbine shaft is done with fourteen (14) pre-stressed
coupling bolts.
The finished machined runner is statically balanced in order to ensure good, low-vibration
operating conditions. The weight of the finished runner is approximately 14875 kg.
Nominal shaft diameter: 700 mm, total length 5974,8 mm Weight: 19.956 kg
Forged of material C35E with integrally forged flanges for coupling to runner on the downstream
end and to generator on the upstream end.
The entire shaft is machine bored hollow to provide operating space for the runner lifting device.
Handling:
Always use rubber or other protection material when slinging the turbine shaft. Never provide
supports directly to the guide bearing area of the shaft, supporting only shall be done in the
areas near to the flanges.
For NDT Testing of transition to flange there is no painting applied in this area. NDT Testing shall
be applied for crack detection at every change or replacement of the runner Coupling of shaft to
runner and turbine shat to generator shaft is made of friction type (Ekagrip Foils 1205) with pre-
stressed coupling bolts.
Please mind at installation: The “high”-point of the plane surface of the flange shall be coupled to
the “low”-point of the counter flange of the generator shaft.
Normal operation:
In normal operation, the parts mounted on the turbine shaft (brackets 1261, handle 1263,
clamping plate 1270, holder 1275) rotate. The casing (8140) for the lock (8114) and the 3/2-way
valve (8102) remain stationary.
The gap ("S") between the handle (1263) and the lock (8114) was set during installation work.
Overspeed:
If the turbine speed is increasing, greater centrifugal force acts on the weight of the handle
(1263), the handle (1263) starts to swing out.
At the defined activating speed, the handle (1263) strikes the lock (8114).The lock (8114) changes
its position and unlocks the shaft of the springoperated3/2-way valve (8102). The limit switches
(8100-33) are activatedand change their signal status.
The turbine is shut down via the 3/2-way valve and the hydraulic governor.The limit switches
report the shutdown to the control system.
Reset:
If the turbine speed is decreasing, the centrifugal forces acting on thehandle (1263) weight also
decrease. If the pendulum has sufficient springforce, the handle (1263) returns to its starting
position.
The static part of the pendulum is not reset automatically, but must bereturned to the correct
position by means of the reset handle (8100-32).
For controlling the turbine three non-contact speed sensors (3950-1) are placed on the top of the
turbine bearing. A pole band (3950-2) fixed on the turbine shaft generates the signals.
The bearing support is part of the turbine casing and designed to transmitthe load due to the side
thrust of the runner to the turbine housing.The bearing is equipped with connections to an
external water/oil heatfor cooling of the bearing oil.The bearing is equipped with resistance
temperature detectors in the oil aswell as in the bearing segments.
To prevent an overflow of the oil due to vacuum in the area between theguide bearing cover and
the guide bearing casing this area isventilated. The labyrinth ring housing is ventilated via a filter,
too.
Installation:
Install all pads to zero and adjust then back to nominal gap of 0,4 - 0,45mm. The exact gap
shall be decided at commissioning and may be reduced if considered necessary.
The adjustment of the oil flow through the bearing can be done by number of holes in the
turbine
Watch the temperature: if temperature changes, the oil system shall be checked.
Removing of the oil shall be done by a small pump from above via the cover. The plug (Pos.
23) in the inner housing shall be used for draining completely.
Attention:
Runaway speed: After any case of full runaway speed the bearing must be checked for
soundness. The bearing pads shall be inspected visually.
Attention:
4.3.7 Distributor
The distributor pipe is made of fabricated steel construction and is completely embedded in the
concrete. It is designed to withstand the maximum internal pressure with the steel shell only.
The distributor will be supplied to site in suitable pieces for transportation and fit together by
welding at site.
The embedding in the concrete shall be directly without use of any compressible wrapping, the
distributor shall be closed with test heads and pressure of 50% of the design pressure shall be
applied during embedding/ concreting.
The distributor contains block-flanges on bottom for draining and on top for aeration.
The turbine housing, made of carbon steel, is supplied to site in single pieces as practicable for
handling and shipment, installed and welded at site and for complete embedding in concrete.
Each of the turbines is equipped with six (6) nozzles (or jets). The nozzlesare of straight flow type
with internal servomotor. The alignment of thenozzles is made at the initial installation and can
be realized by anadjustment flange for each nozzle.
The entire nozzle is completely removable from the distributor flange formaintenance.The
needle tips and the set rings are made of stainless steel. The needletips and seal rings are
removable.The nozzles are mechanically protected against splashing water by theprotection
roof.
The nozzle servomotor is a double acting cylinder balanced by a compression spring in order to
have a small work capacity of the hydraulic governor.
If no oil pressure is applied at closing or opening connection, the nozzle remains in a middle
position. Hence for filling the distributor with water, oil pressure has to be applied at the closing
connection.
Figure 4.5: Nozzle
The jet deflectors are made of massive cast material GX4CrNi13-4 and are acted by hydraulic
servomotors to deflect the jet from the runner for emergency close down.
The servomotors for the deflectors are single acting cylinders, operated by oil pressure for
opening, but closed by spring action.
Deflectors:
The jet deflectors are made of massive cast material GX4CrNi13-4 and are acted by hydraulic
servomotors to deflect the jet from the runner for emergency close down.
The servomotors for the deflectors are single acting cylinders, operated by oil pressure for
opening, but closed by spring action.
Figure 4.6:Deflector
4.3.10 Brakejet and Piping
To enable a quick standstill of the generating sets in case of a generator brake failure, in
particular to avoid turning of the generating set in the mixed friction range of the generator
bearings, the turbines are equipped with brake nozzles.
4.4 Operation
Please find here below some general remarks for start-up of the turbine. The main components
of Turbine are given below:
The automatic control system ensures that the turbine cannot be started before all requirements
for the start-up will be met. When all requirements for the start-up are met, clearance for start-up
is given.
The turbine has to be started according to the sequence of the control operations diagram (see
Unit start sequence 15.7.3.11 and Unit Turbine 15.7.3.14). The start-up command signal has to be
only accepted, when all requirements are met.
4.4.3 Checks during operation
Whenever a malfunction is indicated, the cause therefore must be detected and corrected
immediately. Inspection must be carried out during operation of the Generating Units and it is
given in table 3.1 of Maintenance Manual.
The turbine is to shut down according to the sequence of control operation diagram (see Unit
stop sequence 15.7.3.12)
Before start of the turbine the filling is done according to the sequence of the control operations
diagram (see Unit start sequence 15.7.3.11)
Draining of the distributor is done according to the sequence of the control operations diagram
(see stop sequence 15.7.3.12)
The operating range of the turbine is limited by the opening range of the nozzle programmed in
the governor. The operation personnel have to be instructed not to operate the turbine outside
the recommended limits. The operator is requested to record the relevant parameters, such as
power, head, downstream level and operating hours for the duration of the warranty period. The
supplier shall be allowed the opportunity to check these.
The turbine efficiency curve is given in Figure 4.8.
Figure 4.8:Turbine Efficiency Curve
SECTION A:
5.1 Introduction
Dagachhu Hydro Power Plant has two generating Units and each of the Pelton turbines of the is
equipped with one separate main inlet valve (MIV). The inlet valves are of the spherical valve type
and operate as conventional turbine inlet valves. The inlet valve is used for shut-off the water
flow during normal stop of the turbines. In case of an emergency it will work as a safety shut-off
valve.
The opening and closing of the valve rotor (2100) is done by oil pressure. It opens and closes by
means of 2 servomotors (4200) with oil pressure supplied by the hydraulic power unit (please
refer to operation and maintenance manual of hydraulic governor).Prior to the opening of the
valve rotor, an equalization of the pressure in the inlet pipe - upstream (8100) and the
downstream pipe (8300) is established by the by-pass line (5400).
Furthermore, the moveable seal rings (1400) must be opened prior to the opening of the valve
rotor. The opening and closing of the moveable seal rings is done by water pressure supplied
from the penstock. The valve body is bolted to the upstream pipe (8100) which is site welded to
the penstock.
For the disassembly of the butterfly valve, the connection between the downstream pipe (8300)
and the turbine distribution pipe is designed as a dismantling joint (8200) with a moveable
compensating flange.
5.3 Operation
Preconditions:
Make sure that the waterway (penstock, turbine, draft tube and tailrace cannel) is clean
and free of anything that could damage the inlet valve or the turbine. An inspection
report has to be issued.
Complete all commissioning dry tests and record the results.
Manhole in downstream pipe must be closed.
Water control system and hydraulic governor ready for operation.
Filling:
Step Activity
3 Manual de-locking of the maintenance seal locking device (1200). All five (5) locking
screws have to be opened.
7 Manual opening of the ball valves of the small by-pass line DN25
11 After filling of the spherical valve and the bypass line all connections (valves etc.) have
to be checked for tightness (visual check).
Preconditions:
Spherical valve filled according section 5.3.1.
Filling:
Step Activity
The following procedure describes the manual closing of the spherical valve for filling of the
penstock.
Step Activity
Precondition:
Step Activity
Information:
Closing of the maintenance seal
Closing of the maintenance seal can be done whether by use of the hydraulic governor or by use of
the mechanical locking device. Prior closing of the maintenance seal.
SECTION A:
CHAPTER6:GOVERNING SYSTEM
6.1.4 Operation
The automatic control system ensures that the turbine cannot be started before all requirements
for the start-up will be met and only if all preconditions for start-up are fulfilled the clearance for
start-up is given.
Prior to each turbine start the below stated items have to be considered and it has to be made
sure that the following functions are performed and the corresponding devices are in operating
position on the hydraulic governor.
The turbine has to be started according to the sequence of the control operations diagram (See
separate operation and maintenance manuals of control system).
The start-up command signal has to be only accepted when all pre-start conditions are met.
The start-up sequence on the hydraulic governor is as follows:
Energize one unloader valve MEX11/12AA001-Y01 and start corresponding governor oil
pump MEX11/12AP001-M01, de-energize unloader valve after motor reaches nominal
speed
start oil circulation pump MEX14AP001-M01
Pilot valve for hydraulic stop valve MEX16AA002-Y01 solenoid needs to be de-energized.
In this position the control oil for this valve is released to the tank and the main oil supply
valve MEX16AA001 will open by hydraulic force and pressure oil is supplied to the main
circuit of the hydraulic actuator. Position switch MEX16AA001–S01 will indicate that the
main oil supply valve is opened.
Shutdown valve MEX51AA002-Y01 and start/stop valve MEX51AA003-Y01 solenoids needs
to be energized. In this position the control pressure oil from the pressure tank brings the
hydraulic operated failsafe block of main inlet valve MEX70AA001 into operating position
and furthermore the pilot valve MEX52AA002-Y01 is supplied with control oil and main
control valve for inlet valve MEX52AA001 is ready for operation. In addition, the failsafe
blocks MEX41…46AA011 and the pilot operated check valves MEX31…36AA701of the
deflector control valves MEX31…36AA010-B01 / MEX31…36AA020 and the pilot operated
check valves MEX21…26AA710/AA711of the nozzle control valves MEX21…26AA020-
B01are brought to operation position (main control valves for deflectors and nozzles
ready for operation). This action is monitored by pressure switch MEX51CP001-S01.
Start-up of the turbine unit, by means of opening the main inlet valve by energizing the
pilot valve MEX52AA002-Y01 (command signal from unit control). If the main inlet valve is
open the deflector and nozzle servomotors operation is done by signals of the digital
governor to the pilot/main valves MEX21…26AA020-B01 and MEX31…36AA010-B01, to
bring the unit to nominal speed. When the unit is synchronized, opening and closing
signals from the digital governor will load or de-load the unit.
The turbine has to be stopped according to the sequence of the control operations diagram.
The stop-sequence on the hydraulic governor is as follows:
De-loading of the unit, main circuit breaker – “OFF” and main inlet valve closed (auto
program sequence).
When the unit is in shut-down condition the shutdown valve MEX51AA002-Y01 and start-
stop valve MEX51AA003-Y01 needs to be de-energized. Spring load of these valves forces
the control pistons to the “STOP”-position and as a consequence the pressure at the port
of the hydraulic operated failsafe plates MEX70AA001 and MEX41…46AA011 will be
released. The released pressure at the failsafe plates will hydraulically force the control
piston of main control valves MEX52AA001, MEX21…26AA020-B01 and MEX31…36AA020
to the fully closed position. That means that closing pressure is applied to the main inlet
valve servomotors, the deflector and nozzle servomotors.
When the nozzles are fully closed, and it is assured that water flow from the penstock to
the turbine is interrupted solenoid valve MEX16AA002-Y01 needs to be energized. Oil
pressure will move the piston of main oil supply valve MEX16AA001 to closed position and
main oil supply from the pressure tank is closed.
Stop governor oil pumps MEX11/12AP001 and oil circulation pump MEX14AP001-M01
The description of the overall START-STOP sequence can be found in the operating and
maintenance manuals of control system.
- Next Page
- Previous page
This detailed controller display constitutes the block diagram of the speed controller. Contrary to
the other controllers, various set-point values can be defined and modified here as a function of
current operating state. The same applies to the controller parameters K P and TN (1 and 2). The
controller parameter TD (3) does not depend on the respective operating state. Furthermore, the
gradient (4) for the readjustment of the speed set-point by using the (+) and (-) buttons (5) as
well as the permanent speed droop (6) can be altered here.
6.2.1.7 Display Opening Limiter
This detailed display constitutes the block diagram of the opening limit. Besides the actual
limitation (1) the associated gradient for the readjustment of this limit value (2) can be altered
here. This gradient be effective only in the case of abrupt changes of the opening limitation. The
opening set-point corresponds to the set-point of the positioning circuits described hereafter.
6.2.1.8 Display Positioning Circuit Deflector
This display represents the block diagram of the positioning circuit for the deflector. In this
display, not only the controller parameters K P and TD(1 and 2) can be set, also switchover to a
manual set-point for the positioning can be carried out (3). This manual set-point can be specified
individually (4).
6.2.1.9 Display Positioning Circuit Needle
7.1 Introduction
General:
Each generating unit are provided with three single phase transformers. The transformer is
connected between 220/√3 kV and 11 kV system, which is effectively earthed, and is suitable for bi-
directional power flow. The transformer is rated for 24MVA under OFWF cooling respectively.
Core and Winding:
The magnetic circuit is of three limb Step-Lap construction, each limb bearing mitered jointed
with the top and bottom yokes. The laminations are made of high grade, non-ageing cold rolled
grain oriented steel. The limbs and yoke laminations are firmly clamped together by Green belts
along with the yoke clamps.
The winding is arranged on the core limbs in a concentric manner. For mechanical rigidity under
short circuit, the winding has been wound on a rigid cylinder made of pre-compressed
pressboard. The HV winding is placed over the LV winding and HVT winding is placed over HV
winding after placement of adequate insulation. The 220/√3 kV line lead emerges from the center
of HV winding stack. The HV windings are wound by adopting intershielded disc type of winding
which gives excellent voltage gradation under impulse. Oil ducts are so arranged to provide a
maximum circulation of oil to each and every part if the winding and therefore eliminates
occurrence of any “hot-spot”.
Core and Windings together with the insulation are dried and processed under vacuum. Windings
are sized to the correct dimension and are firmly clamped under pressure.
Off circuit tap changer:
The Off-load tap changer is also provided on HV neutral side for variation of voltage from
+2x2.5%to -1x2.5% in 4equal steps. The tapping arrangement is linear type
No of phases 1
Frequency 50Hz
Connections
HV winding STAR
LV winding DELTA
Vector group -3 phase Ynd5
Maximum efficiency
After the inspection and pre-commissioning tests are successfully completed the transformer can
be energized at no load.
Oil soaking/settling duration of 1-2 days for transformers up to 245 kV class after
completion of hot oil circulation and before energizing.
Transformer shall be observed for any abnormality.
If any gas is collected inside the Buchholz relay, it shall be analyzed for its combustibility.
If gas is not combustible, it indicates air trapped inside the transformer.
All instrument should be check for any abnormalities.
Check winding temperature and oil temperature readings at least once in every shift.
Check and confirm that the tap position indicators are same in local and remote
indicators.
Check and confirm that none of the alarms is ON.
Ensure that cooler power supply isolator is ON.
Ensure that cooler control is in AUTO.
Ensure that pumps and fans are running smoothly as temperature dictates. Of the
temperature is below the ON setting neither the pump nor fan should be running.
Observe the rise in temperature of oil and winding temperature indicators.
While temperature is rising, confirm that fans and pumps are switched on automatically
at the preset temperatures.
While temperature is falling, observe that the pumps and fans are switched off at preset
temperatures.
12 Connections Monthly
OPERATION MANUAL
CHAPTER 8
CHAPTER 8: STATION AUXILIARY
TRANSFORMERS
8.1.1 Introduction
General
The Transformer is connected between 220kV and 33kV system, which is effectively earthed, and
is suitable for bi-directional power flow. The Transformer is rated for 5MVA under OFWF cooling
respectively.
Core and Winding
The magnetic circuit is of three limbsNon-Step-Lap construction, each limb being mitered jointed
with the top and bottom yokes. The laminations are made of high grade, non-ageing cold rolled
grain oriented steel. The limbs and yokes laminations are firmly clamped together by Breen belts
along with the yoke clamp.
The windings are arranged on the core limbs in a concentric manner. For mechanical rigidity
under short circuit, the winding has been wound on a rigid cylinder made of pre-compressed
pressboard. The HV winding is placed over the LV winding and HVT winding is placed over HV
winding after placement of adequate insulation. The 220kV line lead emerges from the TOP of HV
winding stack. The HV windings are wound by adopting intershielded disc type of winding which
gives excellent voltage gradation under impulse. Oil ducts are so arranged to provide a maximum
circulation of oil to each and every part of the winding and therefore eliminates occurrence of
any “hot-spot”.
Core and windings together with the insulation are dried and processed under vacuum. Windings
are sized to correct dimension and are firmly clamped under pressure.
No Load Tap Changer
Make: “TELK”
Type: Off Circuit Tap Changer
The Transformer is provided with taps in series of HV windings to vary HV voltage from -2x2.5% to
+2x2.5% in 4 steps of each 2.5% each. The tapping arrangement is linear type.
MVA : 5 MVA
Type of Cooling : OFWF
Frequency : 50Hz
Voltage Ratio (No Load)/Connections:
HV : 220kV/Star
LV : 33kV/zigzag
Phase : Three
Vector group : YNzn11
Rated Current (Amperes)
HV : 13.14
LV : 87.58
Insulation Level:
HV : LI 950 AC 395
HVN : LI 170 AC 140
LV : LI 170 AC 70
8.1.3 Operation
The Operation instruction for charging the transformer for the first time are mentioned below:
After the inspection and pre-commissioning tests are successfully completed the
transformer can be energized at no load.
Oil soaking/settling during of 1-2 days for transformers up to 245kV class and 3 days for
400kV and above classes are recommended after completion of hot oil circulation and
before energizing.
Excessive vibration if any on any part of transformer shall be located and rectified.
Transformer shall be observed for any abnormality.
If any gas is collected inside the Buchholz relay, it shall be analyzed for its combustibility.
If gas is not combustible, it indicates air trapped inside the transformer.
All instruments should be checked for any abnormal indication.
Check winding temperature and oil temperature readings at least once in every shift.
Check and confirm that the tap position indicators are same in local and remote
indicators.
Check and confirm that none of the alarms are indicated.
Ensure that the cooler power supply isolator is ON.
Ensure that the cooler control is in AUTO.
Ensure that the pumps and fans are running smoothly as temperature indicates. If the
temperature is below the ON setting neither the pump nor the fan should be running.
After watching the operation of the transformer at no load for 24 hours and confirming
that everything is normal, the transformer shall be taken on load.
Observe the rise of temperature of oil and winding temperature indicators.
While temperature is rising, confirm that the fans and pumps are witched on
automatically at the preset temperatures.
While the temperature is falling, observe that the pumps and fans are switched off at
preset temperature.
12 Connections Monthly
OPERATION MANUAL
CHAPTER 9
9.1 Introduction
The main switching operations of the generating units, auxiliary transformer and an outgoing
feeder are carried out on the Gas insulated switchgear (GIS). It consists of 4 bays: 2 incoming
bays for the 2 generating units through their respective generator transformer banks, 1 bay for
outgoing 220kV feeder/cable and an auxiliary transformer bay.
Type B105
9.3 Operation
The operation of SF6 gas insulated switchgear can be operated locally (open/close control switch
in bay module) or from remote (remote/local control transfer switch from control room control
system).
The SF6 insulated B105-CB Circuit Breaker is of single pressure type with one breaking element
per pole.
The three horizontal circuit breaker poles with their driving mechanism form a whole. The driving
mechanism is of single pole type and CB enclosure serves as an attachment base for the driving
mechanism and the structure.
The whole module is filled with SF6
gas at 6.3 bars @ 20 ⁰C. SF6 gas is
used for both insulation and arc
quenching. The tripping and closing
of the circuit breakers will be blocked
when the SF6 gas density drops
below a minimum permissible level.
The density of SF6 gas in different
compartments (GO) are monitored by
density switch which is fitted with shielded protection system that enables it to resist extreme
temperatures and external aggressions switch with two alarm levels.
The first stage alarm is set well before any dangerous condition is reached and second stage shall
initiate breaker operation blocking.
For the unacceptable over pressure there is bursting disc installed at an appropriate location on
each gas compartment to protect the enclosures of the GIS. They are metal discs equipped with a
discharge section 110 mm in diameter for the substation and 210 mm for the circuit breaker. The
circuit breaker can be operated locally (open/close control switch in local control panel) or from
remote.
The breaker controls shall operate from the two independent 110V DC systems with both the trip
coils connected. The CBs of the incoming bays, feeder bay and auxiliary transformer bay are of
2000A.
The function of the disconnecting switch is to isolate different parts of the electrical circuits. It
can establish or cut off loop currents and capacitive charging currents on parts of the substation
being switched ON or OFF.
The disconnect switch consists of three separate poles, connected by an external rod to a manual
or electrical operating mechanism. To perform the disconnect switch function, each pole
compromises a moving contact situated within the disconnector enclosure and a fixed contact
situated within the insulator of the right enclosure or the adjacent cross chamber. A visual
indicator connected to the transmission shaft by mechanical means enables checking of the
disconnector’s open/closed position.
The B105 type disconnector operating mechanism actuates disconnectors and earthing switches
of the B105 SF6 switchgear in three poles. It is attached to the mechanism housing of one pole. In
the case of three pole operating mechanism, the other two poles are operated via push-pull
linkages. The position indicator is mounted on the housing of one pole and is mechanically
coupled with the linkages.
The purpose of maintenance earthing switch is to earth de-energized SF6 switch gear sections.
The maintenance earthing switches are operated in three poles with motor operating mechanism
B105 which is mounted on one pole and connected to the other poles with linkages. It consists of
mechanism housing with shaft, lever and links for motion transmission to contact pin. Tulip
contact screwed into mechanism housing establishes the current connection to contact pin and
counter contact tulip is mounted in the electrode of a disconnector of a connecting element.
Make or break operations in service are handled electrically by the motor operating mechanism
via the control system, if no auxiliary voltage is available the earthing switch can also be actuated
manually with the crank.
The High-speed earth switches are used for the short circuit proof earthing of high voltage lines
and cables connected to SF6 switchgear and of switchgear sections. Generally, they are used as
earthing switches for feeders but can be applied anywhere else in the substations according to
requirements and they are designed to close on short circuits and to switch induced currents.
It consists of mechanism housing with shaft, lever and links for motion transmission to contact
pin. Tulip contact screwed into mechanism housing establishes the current connection to contact
pin. Counter contact tulip is mounted in the electrode of a disconnector or a connecting element.
1 Status of Units
/feeder (in service
/ standby /PTW)
2 Any alarms
indication?
3 Is DC (A& B)
healthy?
6 Any alarms in
annunfascia?
Visual/
Physical/Peripher
7
al check of the
components for
anything unusual
8 CB Counter
Reading
OPERATION MANUAL
CHAPTER 10
10.1 Introduction
Details Specification
Type Horizontal Centre Break (HCB), one arm with male contact and
other with female contact.
Details Specification
LD discharge class 3
Discharge current 10 KA
MCOB 56 kV
10.4 Operation
The operation of the isolators and earth switches can be operated locally only. However, we will
be able to see the position indications of earth switch and isolators in Control System.
SECTION A:
OPERATION MANUAL
CHAPTER 11
11.1 Introduction
Here at Dagachhu Hydro Power plant, we have three sources to supply the auxiliary power for
the generating units and its auxiliaries. The supply is also extended to outdoor locations such as
Diversion Weir, Desilter, Surge Shaft, Chhurachhu side adit and face 4 side adit.
11.2 Operation
The operation of all the auxiliary supply equipment can be perform either locally (local panels) or
remotely (control System).
During the initial starting of the Generating Units, we can either supply the Generating Units’
auxiliaries through external source or through the emergency diesel generator installed at Power
house premises. We will discuss the external source first.
Preconditions:
The earth switches (00ADD20GS401) at Pot head yard should be in “open” position.
The isolators (00ADD20GS301) at Pot head yard should be closed.
High speed electrical earthing switch (00ADD00GS421) at GIS should be in “open”
position.
Electrical earthing switch (00ADD00GS411 and 00ADD00GS401) at GIS should be in
“open” position.
Electrical disconnector switch (00ADD00GS311) at GIS should be closed.
220kV Station Transformer Circuit Breaker should be open.
Charging:
Step Activity
1 Ask Tsirang Substation to extend the 220kV supply through 220kV Dagachhu-Tsirang line.
2 After getting the 220kV supply till GIS Circuit Breaker end, close the circuit breaker
(00ADD00GS100) at GIS. Now there should be 220kV supply at 220kV Bus bar.
Preconditions:
Step Activity
1 Close the 220kV Station Transformer circuit breaker (20ADD00GS100) after charging the
220kV bus bar. Now the 220/33kV Station Transformer will be charged.
2 Close the 33kV Station Transformer circuit breaker (20BBA00GS111). Now the Power
Cavern 33 kV bus will be charged.
Preconditions:
Step Activity
1 After charging the Power Cavern 33kV, either close 33kV Auxiliary Transformer 1 circuit
breaker (20BBA00GS121) to charge the 800kVA Auxiliary Transformer 1 or 33kV Auxiliary
Transformer 2 circuit breaker (20BBA00GS141) to charge 800kVA Auxiliary Transformer
2.
2 Close the 400V Auxiliary Transformer incomer 1 Circuit Breaker (20BFA00SG101) if 33kV
Auxiliary Transformer 1 circuit breaker (20BBA00GS121) is closed and close 400V Auxiliary
Transformer incomer 2 circuit breaker (20BFA00GS102) if 33kV Auxiliary Transformer 2
circuit breaker (20BBA00GS141) is closed.
Note: The sub-distribution boards and motor control cabinets circuit breaker are already closed, so
after charging the Power Cavern 400V Main Distribution the sub-distribution boards and MCC panels
connected from this board should also be charged.
Preconditions:
Charging:
Step Activity
1 Close the 33kV Tunnel Feeder circuit breaker (20BBA00GS151) at Power Cavern 33kV
Main Distribution Board.
2 Close the 33kV Tunnel Feeder circuit breaker (25BBA00GS111) at Control Building 33 kV
Main Distribution Board. Now the Control Building 33kV Main Distribution Board will be
charged.
Step Activity
1 Close the 33kV Auxiliary Transformer circuit breaker (25BBA00GS121) to charge the
Auxiliary Transformer in Control Building.
2 After Charging the Auxiliary Transformer, close 400V Auxiliary Transformer incomer
circuit breaker (25BFA00GS101) at 400V Control Building Main Distribution Board.
Step Activity
1 Close the 33kV overhead line (OHL) 2 circuit breaker (25BBA00GS151) in 33kV Control
Building Main Distribution Board
2 Close the Dam 400 V incomer circuit breaker (51BFA00GS011) at 400V Main Distribution
Board.
Step Activity
1 Close the 33kV overhead line (OHL) 2 circuit breaker (25BBA00GS151) in 33kV Control
Building Main Distribution Board
2 Close the Desilter 400 V incomer circuit breaker (52BFA00GS011) at 400V Main
Distribution Board.
Preconditions:
The 400V Surge Tank Main Distribution Board circuit breaker should be closed as it is not
motorized.
Charging:
Step Activity
1 Close the 33kV overhead line (OHL) 1 circuit breaker (25BBA00GS141) in 33kV Control
Building Main Distribution Board.
After starting the Generating Units and synchronizing with the grid, supply the auxiliary supply
through 5MVA Station Transformer from our own Generating Units.
The Black Start is an emergency condition when normal sources of power from our 5MVA Station
Transformer and external power supplies from Tsirang (i.e. Supply through 220kV Dagachhu-
Tsirang line as well as 33kV Tsirang-Dagapela-Dagachhu line) are unavailable and the power
required for essential loads for starting of generating unit has to be met from 400kVA DG set
installed at Power House.
Dagachhu Hydropower Corporation Limited has also 160kVA DG set installed at Diversion Weir for
supplying the essential power supply to the various equipment/systems installed at Diversion
Weir and Desilter and 400kVA DG set at Power House for supplying the essential power supply to
the equipment/systems at Power House.
Preconditions:
There should not be any alarms due to possible faults like earth faults, reverse power, etc.
Steps Activity
1 Start the 400kVA Emergency Diesel Generator. The 400kVA emergency diesel
generator will be started automatically if above conditions are fulfilled. However, the
DG set can also be started locally or manually through control system. The 400V DG set
circuit breaker (25BFA00GS214) will also close automatic and the 400V Control Building
Main Distribution Board will be charged.
2 Close the 400V DG set circuit breaker (25BFA00GS214) to charge the 400V Control
Building Main Distribution Board. However, the circuit breaker will automatically close if
above preconditions are fulfilled.
3 Open all the 33kV Feeder Circuit Breaker like control building 33kV Auxiliary
Transformer circuit breaker (25BBA00GS121), Tunnel Feeder circuit breaker
(25BBA00GH111), Overhead line 1 circuit breaker (25BBA00GS141), Overhead line 2
circuit breaker (25BBAGS00GS151) and Power Cavern Auxiliary Transformer 1 circuit
breaker (20BBA00GS121) and Power Cavern Auxiliary Transformer 2 circuit breaker
(20BBA00GS141).
4 Make sure that the incomer from 5 MVA Station Transformer 33kV side circuit breaker
(20BBA00GS111) is OPEN. This is very important.
5 Close the 400V Auxiliary Transformer incomer circuit breaker (25BFA00GS101) to charge
the 800kVA Auxiliary Transformer.
6 Close the incomer from Control building Auxiliary Transformer circuit breaker
(25BBA00GS121) and you will have voltage in Control Building 33kV Main Distribution
Board.
7 Close the Control Building Tunnel Feeder CB (25BBA00GH111) and you should get
voltage at Power Cavern 33kV System.
8 Either close 33kV Auxiliary Transformer 1 circuit breaker (20BBA00GS121) to charge the
800kVA Auxiliary Transformer 1 or 33kV Auxiliary Transformer 2 circuit breaker
(20BBA00GS141) to charge 800kVA Auxiliary Transformer 2.
9 Close the 400V Auxiliary Transformer incomer 1 Circuit Breaker (20BFA00SG101) if 33kV
Auxiliary Transformer 1 circuit breaker (20BBA00GS121) is closed and close 400V
Auxiliary Transformer incomer 2 circuit breaker (20BFA00GS102) if 33kV Auxiliary
Transformer 2 circuit breaker (20BBA00GS141) is closed. Now Power Cavern 400V Main
Distribution Board will be charged.
The essential power supply to the equipment at Diversion Weir and Desilter can be supplied from
160kVA Diesel Generator installed at Diversion Weir.
Preconditions:
Steps Activity
1 Start the 160kVA Emergency Diesel Generator. The 400kVA emergency diesel generator
will be started locally or remotely from control room or in Auto.
2 Close the 400V Emergency Diesel Generator circuit breaker (51BFA00GS021). Now the
400V Diversion Weir Main Distribution Board will be charged.
4 Close Desilter 400V Dam circuit breaker (52BFA00GS021) and now 400V Desilter Main
Distribution board will be charged.
Note: Now the generating units are ready to start. However, only one of the generating unit can be
started because Diesel Generators will be overloaded if both the generating units are started
simultaneously. Start the next unit only after changing the supply to 5MVA Station Transformer.
After starting any one of generating and synchronizing with the grid, auxiliary supply should be
changeover to 5MVA Station Transformer to start the next unit.
Preconditions:
Steps Activity
1 Close the 220kV Station Transformer circuit breaker (20ADD00GS100). Now the
SECTION A:
OPERATION MANUAL
CHAPTER 12
2 Keeping everything in AUTO mode, manually open the 400V Auxiliary Transformer
incomer circuit breaker and simultaneously close the 33kV Station Transformer circuit
breaker (20BBA00GS111). Now 400kVA DG set will incomer breaker will get open
automatically and subsequently stop the DG set.
3 Close the 400V Auxiliary Transformer incomer circuit breaker. Now everything will be
normal in Power house premises.
4 Close overhead line 1 circuit breaker (25BBA00GS141) to supply the 400V Surge Tank
Main Distribution board.
5 Close overhead line 2 circuit breaker (25BBA00GS151) to supply the 400V Diversion Weir
Main distribution board and 400V Desilter Main distribution board.
6 Stop the 160kVA diesel generator and open the DG set breaker (51BFA00GS021). Also,
open the Dam 400V Desilter circuit breaker (51BFA00GS031) and Desilter 400V Dam
circuit breaker (52BFA00GS021).
7 Close the Dam 400 V incomer circuit breaker (51BFA00GS011) to supply the 400V
Diversion Weir Main distribution board and also close Desilter 400 V incomer circuit
breaker (52BFA00GS011) to supply the 400V Desilter Main Distribution Board.
General
All Gates at the Diversion Weir and Intake, which means
One Intake Gate
Two Weir Radial Gates and
Two Weir Flap Gates
are operated hydraulically by means of Hydraulic Cylinders fed by one common Hydraulic Power
Unit for oil supply, located in the Operation and Maintenance building.
The Intake Gate is actuated by means of two double acting Hydraulic Cylinders.
Each of the Weir Radial Gates as well as the Weir Flap Gates are actuated by means of two single
acting Hydraulic Cylinders. All Hydraulic Cylinders are fed by one common Hydraulic Power Unit
located in the Operation and Maintenance building. All parts of the hydraulic hoisting system are
designed and calculated according to EN 19704.
The intake is equipped with one Slide Gate. This gate is capable toclose the intake against
full flow in case of turbine over speed orpenstock rupture.
During normal operation, the intake gate is in the opened position.For filling the
penstock, the gate will be lifted into the crack openposition, lifting height approx. 10cm
above the sill.
The gate is actuated hydraulically by means of two double acting hydraulic cylinders,
connected to the gate.
For electrical control of the equipment a local control cubicle(=51LNY10 GH001), located
in Operation and Maintenance building isprovided. The local control cubicle is common
for the Intake gate andthe Weir gates.
Hydraulic control is achieved via a Hydraulic Power Unit. The gateposition is monitored
via a mechanical position indicator; individualpositions are detected by a position
transmitter.
The gate position is monitored via an integrated measuring system inthe hydraulic
cylinders. Stroke measuring system is of the magneto restrictive type, make “Balluff”
with analog output.
General
Operation of the hydraulic equipment will be executed by means of the pushbuttons and the
selector switches of the local control board.
The Intake Gate is operated by two double-acting hydraulic cylinders acting simultaneously on
both sides of the gate.
The cylinders are equipped with an integrated position measuring system to ensure simultaneous
operation of the two hydraulic cylinders.
The hydraulic circuit for the two cylinders of the Intake Gate hoist is provided with 3/2-way
poppet valve AA111 (-Y01) and 2-way flow control valve+ rectifier sandwich plate NG6 AA011 of the
servomotor left side AS010 and 3/2-way poppet valve AA112 (-Y01) and 2-way flow control valve+
rectifier sandwich plate NG6 AA012 of the servomotor right side AS020 and together the main
directional valve AA110 (-Y01 and –Y02) which, in conjunction with the integrated piston
measuring system CG010-B01 of the servomotor left side and CG020-B01 of the servomotor right
side, are synchronizing the motion of the hydraulic cylinders and ensure levelled raising and
lowering of the gate.
Preconditions:
Preconditions:
12.1.2 Operation of Intake Gate without control voltage (or PLC fault)
If the control voltage of the valves or the power supply of the PLC fails, the hydraulic system can
be operated manually. That means, all valves have to be actuated by means of their manual
actuating advices and the electric motors have to be switched on manually via the appertaining
selector switch.
During manual operation of the Gate, the pressure gauges have to be monitored very carefully. If
the oil pressure exceeds
blocking of Gate or
the Gate reached the opened or closed position or a failure occurred at the hydraulic
system
Furthermore, it has to be mentioned that the pressure during operation should not fall below
15bar. Low pressure during operation may be caused by
a pipe is broken or
a failure occurred at the hydraulic system
The electric motors can be switched on directly by the selector switches motor pump #1 (51LPX10
AP001-M01) selector switch –S11 and
motor pump #2 (51LPX10 AP002-M02) selector switch –S12.
These switches have the positions AUTO – OFF – MANUAL. To switch on the motor pumps, the
selector switches have to be switched in position MANUAL.
Note:For operation, only one pump has to be switched on!
The normally solenoid operated main directional valve 51LPB10 AA110 has to be actuated
manually by means of the manual actuation devices attached to the solenoid –Y02. Due to this
actuation, the main directional valve is shifted into position 3, lifting position. After this, the
pressure relief valve AA301 has to be actuated manually by means of the manual actuation
devices attached to the solenoid –Y01 of the valve.
If the pressure relief valve is actuated, the Gate starts raising. To stop the raising motion, switch
off the pumps or remove the manual actuation of the pressure relief valve and remove the
actuation of directional valve AA110.
Caution: During this operation, the limit switches, the pressure transducer, the oil level
switch as well as the position indication are not active as the PLC is overridden. By this,
increased attention is necessary!
The electric motors can be switched on directly by the selector switches motor pump #1 (51LPX10
AP001-M01) selector switch –S11 and
motor pump #2 (51LPX10 AP002-M02) selector switch –S12.
These switches have the positions AUTO – OFF – MANUAL. To switch on the motor pumps, the
selector switches have to be switched in position MANUAL.
Note: For operation, only one pump has to be switched on!
The normally solenoid operated main directional valve 51LPB10 AA110 has to be actuated
manually by means of the manual actuation devices attached to the solenoid –Y01. Due to this
actuation, the main directional valve is shifted into position 2, lowering position.
After this, the pressure relief valve AA301 has to be actuated manually by means of the manual
actuation devices attached to the solenoid –Y01 of the valve.
If the pressure relief valve is actuated, the Gate starts lowering. To stop the lowering motion,
switch off the pumps or remove the manual actuation of the pressure relief valve and remove the
actuation of directional valve AA110.
Caution: During this operation, the limit switches, the pressure transducer, the oil level
switch as well as the position indication are not active as the PLC is overridden. By this,
increased attention is necessary!
Turn the motor pump selector switches –S11 / -S12 into “OFF” position.
In this position the selected motor pump is switched off.
For maintenance purposes, etc. the Intake Gate may be raised by operated the manual pump
KP003.
The shut-off valve 51LNX10 AA501has to be closed.
The normally solenoid operated main directional valve 51LPB10 AA110 has to be actuated
manually by means of the manual actuation devices attached to the solenoid –Y02. Due to this
actuation, the main directional valve is shifted into position 3, lifting position.
Actuate hand pump KP003.
The gate starts lifting.
Caution: During this operation, the limit switches, the pressure transducer, the oil level
switch as well as the position indication are not active as the PLC is overridden. By this,
increased attention is necessary!
Turn the motor pump selector switches –S11 / -S12 into “OFF” position.
In this position the selected motor pump is switched off.
For maintenance purposes, etc. the Intake Gate may be lowered by operated the manual pump
KP003.
The shut-off valve 51LNX10 AA501has to be closed.
The normally solenoid operated main directional valve 51LPB10 AA110 has to be actuated
manually by means of the manual actuation devices attached to the solenoid –Y01. Due to this
actuation, the main directional valve is shifted into position 2, lowering position.
Actuate hand pump KP003.
The gate starts lowering.
To stop the lowering motion, remove the manual actuation of directional valve AA110.
Caution: During this operation, the limit switches, the pressure transducer, the oil level
switch as well as the position indication are not active as the PLC is overridden. By this,
increased attention is necessary!
General
All Gates at the Diversion Weir and Intake, which means
One Intake Gate
Two Weir Radial Gates and
Two Weir Flap Gates
are operated hydraulically by means of Hydraulic Cylinders fed by one common Hydraulic Power
Unit for oil supply, located in the Operation and Maintenance building.
The Intake Gate is actuated by means of two double acting Hydraulic Cylinders.
The Weir Radial Gates is actuated by means of two single acting Hydraulic Cylinders. Each of the
two Weir Flap Gates is actuated by means of one single acting Hydraulic Cylinder. All Hydraulic
Cylinders are fed by one common Hydraulic Power Unit located in the Operation and
Maintenance building. All parts of the hydraulic hoisting system are designed and calculated
according to EN 19704.
The Diversion Weir structure includes 2 Weir bays each with a clear width of 9,1 m. Each
Weir bay is equipped with a radial gate. The radial gate is driven by 2 hydraulic cylinders.
According to the design specifications the max. water level is at EL.843.30m. The sill
beam of the radial gate is located at EL. 824.633m. Hence a water pressure of 18,667m
rests on the closed gate.
The position of the Weir Radial and Weir Flap Gate is monitored via a gravity pendulum
transducer measuring the turning angle of the gates. Within the software of the
transducer a linearization is implemented to convert the turning angle into a linear
opening signal. This linear opening signal is transmitted to the local cubicles.
The Weir Radial Gate can be dogged in its fully opened position for inspection or
maintenance. In the fully opened position, both dogging devices can be moved manually
from the storage position into the dogging position.
For electrical control of the equipment a local control cubicle (=51LNY10 GH001), located
in Operation and Maintenance building is provided. The local control cubicle is common
for the Intake gate and the Weir gates.
12.2.1 Operation
Operation of the hydraulic equipment will be executed by means of the pushbuttons and the
selector switches of the local control board and also through Control System at Control room.
Notice: It is not foreseen to operate Diversion Weir 1 and 2 Gates simultaneously. It is only foreseen
to open both flap gates at one time.
Preconditions:
No relevant fault indicated at the alarm list of the touch panel –A02
By pressing the illuminated push button –S24/-H24 one of the two pump groups AP001 or AP002
is switched on.
The hydraulic pump KP001 or KP002 is delivering oil without pressure via:
check valve AA701 for motor pump AP001 or
check valve AA702 for motor pump AP002,
opened pressure relief valve AA301
pre-stressed check valve AA705 and
return line filter AT001
back to the oil reservoir BB001.
By starting the pump groups, the solenoid –Y02 of 4/3-way valve AA112 will be energized as well.
After a programmed period, which corresponds to the motor run-up time of 3,0s, the pressure
relief valve AA301 is closed by energizing the pilot operation valve AA101-Y01.
Pressurized oil is delivered now via
check valve AA701 respectively AA702,
check valve AA703,
the shut off valve AA510,
pressure piping BR001,
the shut off valve AA511,
the main directional valve AA112,
check valve AA711,
the pressure piping BR001,
the branch piping BR011/BR021
shut off valve AA513/AA523,
shut off valve AA514/AA524,
check valve AA710/AA720 and
shut off valve AA510/AA520
into the lower part of the two servomotors AS010 and AS020. The Gate is starting to lift.
Synchronization of the two servomotors is achieved via symmetrical arrangement of the
hydraulic piping.
The oil above the piston of the hydraulic cylinders is displaced via
shut off valve AA516/AA526,
shut off valve AA515/AA525,
the branch piping BR012/BR022,
the return piping BR002,
pre-stressed check valve AA705 and
return line filter AT001 back into the
oil reservoir BB001.
The Weir Radial Gate is lifted with a speed of approx. 0,3m/min until the limit switch CG001-GW2
GATE OPENED is reached or the “Stop” command is initiated.
Caution:Observe the minimum opening height of 300mm! Opening heights lower than
300mm may cause damage of the structure. For emergency cases the Gate can be
stopped if the STOP button is pressed for more than 5 seconds.
As far the limit switch CG001-GW2 is reached or the “Stop” command is triggered, the pilot
operation valve AA101-Y01 of pressure relief valve AA301 is de-energized.
1,5s delayed the solenoid –Y02 of main directional valve AA112 is de-energized and the electric
motor –M01 or –M02 is switched off 2,0s delayed.
In the opened position the illuminated push button –S24/-H24 is illuminated permanently.
In the opened position of the Radial Gate an automatic leakage control is active.
12.2.1.2 Closing of Radial Gate 1 =51LNC11
Preconditions:
Preconditions:
No relevant fault indicated at the alarm list of the touch panel –A02
By pressing the illuminated push button –S29/-H31 one of the two pump groups AP001 or AP002
is switched on.
The hydraulic pump KP001 or KP002 is delivering oil without pressure via:
check valve AA701 for motor pump AP001 or
check valve AA702 for motor pump AP002,
opened pressure relief valve AA301
pre-stressed check valve AA705 and
return line filter AT001
back to the oil reservoir BB001.
By starting the pump groups, the solenoid –Y01 of 3/2-way poppet valve AA110 will be energized
as well.
After a programmed period, which corresponds to the motor run-up time of 3,0s, the pressure
relief valve AA301 is closed by energizing the pilot operation valve AA101-Y01.
Pressurized oil is delivered now via
check valve AA701 respectively AA702,
check valve AA703,
the shut off valve AA510,
pressure piping BR001,
the shut off valve AA511,
3/2-way poppet valve AA110,
check valve AA710,
pressure piping BR001,
shut off valves AA511 and AA512 and
throttle/check valve AA011
into the lower part of the servomotor AS011. The Gate is starting to lift (close).
The oil above the piston of the hydraulic cylinder is displaced via
the shut off valve AA514 and AA513,
return piping BR002,
pre-stressed check valve AA705 and
return line filter AT001 back into the
oil reservoir BB001.
The Weir Flap Gate is lifted (closed) with a speed of approx. 0,34m/min until the limit switch
CG001-GW2 GATE CLOSED is reached or the “Stop” command is initiated.
As far the limit switch CG001-S02 is reached, the pilot operation valve AA101-Y01 of pressure relief
valve AA301 is de-energized.
1,5s delayed the solenoid –Y01 of the 3/2-way poppet valve AA110 is de-energized and the electric
motor –M01 or –M02 is switched off 2,0s delayed.
In the closed position the illuminated push button –S29/-H31 is illuminated permanently.
In the any closed position of the Flap Gate an automatic leakage control is active
Preconditions:
No relevant fault indicated at the alarm list of the touch panel –A02
By pressing the illuminated push button –S28/-H30 the solenoid –Y01 of 3/2- way poppet valve
AA111 will be energized.
Due to the load pressure of the dead weight of the flap gate and the water load the oil below the
piston of the hydraulic cylinder is displaced via
throttle check valve AA011,
shut off valves AA512 and AA511 and
pressure piping BR001,
shut off valve AA512/AA511,
3/2-way poppet valve AA111,
return piping BR002,
shut off valves AA513 and 514 and
throttle valve AA011
into the upper part of the servomotor AS011 due to the pre-stressed check valve AA705.
Excessive oil flows via
return piping BR002,
pre-stressed check valve AA705 and
return line filter AT001 back into the
oil reservoir BB001.
The Gate is starting to open (lowering). The Gate is opening with a speed of approx. 0.34 m/min
until the limit switch CG001-S01 GATE OPENED is reached or the “Stop” command is initiated.
The opened position is detected by means of limit switch CG001–S01, which is activated shortly
before the gate reaches the sill and the falling oil pressure in the hydraulic cylinders, which is
detected by the pressure transducer (CP011-B01). Both signals (limit switch and programmed
pressure value) at one time indicate that the Gate is fully opened.
Preconditions:
Pendant control =51LNC00 GK001-A01 is plugged-in into relevant socket =51LNC11 GF002-
XS04 respectively =51LNC21 GF002- XS04
No relevant fault indicated at the alarm list of the touch panel –A02
By pressing the push button –S11 at the pendant control the relevant Radial Gate is opened until
the limit switch CG001–S01 GATE FULLY OPENED is reached. Opening procedure is the same as
described in item 6.2.1 “Opening of Weir Radial Gate”.
By pressing the push button –S12 at the pendant control the relevant Radial Gate is closed until
the limit switch CG001–S03 GATE CLOSED is reached or the STOP command by pressing the push
button –S13 at the pendant control is initiated. Closing procedure is the same as described in item
12.2.1.2 “Closing of Weir Radial Gate”.
Preconditions:
Pendant control =51LNC00 GK001-A01 is plugged-in into relevant socket =51LNC12 GF002-
XS04 respectively =51LNC22 GF002- XS04
No relevant fault indicated at the alarm list of the touch panel –A02
By pressing the push button –S11 at the pendant control the relevant Flap Gate is opened until
the limit switch CG001–S01 GATE OPENED is reached or the STOP command by pressing the push
button –S13 at the pendant control is initiated.
Opening procedure is the same as described in item 6.2.6 “Opening of Weir Flap Gate”.
By pressing the push button –S12 at the pendant control the relevant Flap Gate is closed until the
limit switch CG001–S02 GATE CLOSED is reached or the STOP command by pressing the push
button –S13 at the pendant control is initiated.
Closing procedure is the same as described in item 12.2.1.3“Closing of Weir Flap Gate”.
12.2.1.6 Operation of the Weir Gates without control voltage (or PLC fault)
If the control voltage of the valves or the power supply of the PLC fails, the hydraulic system can
be operated manually. That means, all valves have to be actuated by means of their manual
actuating advices and the electric motors have to be switched on manually via the appertaining
selector switch.
The electric motors can be switched on directly by the selector switches motor pump #1 (51LNX10
AP001-M01) selector switch –S21 and
motor pump #2 (51LNX10 AP002-M02) selector switch –S22.
These switches have the positions AUTO – OFF – MANUAL. To switch on the motor pumps, the
selector switches have to be switched in position MANUAL.
Note: For operation, only one pump has to be switched on!
The normally solenoid operated main directional valve AA112 has to be actuated manually by
means of the manual actuation devices attached to the solenoid –Y02. Due to this actuation, the
main directional valve is shifted into position 3, lifting position.
After this, the pressure relief valve AA301 has to be actuated manually by means of the manual
actuation devices attached to the solenoid –Y01 of the valve.
If the pressure relief valve is actuated, the Gate starts raising. To stop the raising motion, switch
off the pumps or remove the manual actuation of the pressure relief valve and remove the
actuation of directional valve AA112.
The electric motors can be switched on directly by the selector switches motor pump #1 (51LNX10
AP001-M01) selector switch –S21 and
motor pump #2 (51LNX10 AP002-M02) selector switch –S22.
These switches have the positions AUTO – OFF – MANUAL. To switch on the motor pumps, the
selector switches have to be switched in position MANUAL.
Note: For operation, only one pump has to be switched on!
The normally solenoid operated main directional valve AA112 has to be actuated manually by
means of the manual actuation devices attached to the solenoid –Y01. Due to this actuation, the
main directional valve is shifted into position 2, lowering position.
After this, the pressure relief valve AA301 has to be actuated manually by means of the manual
actuation devices attached to the solenoid –Y01 of the valve.
If the pressure relief valve is actuated, the Gate starts lowering. To stop the lowering motion,
switch off the pumps or remove the manual actuation of the pressure relief valve and remove the
actuation of directional valve AA112
The electric motors can be switched on directly by the selector switches motor pump #1 (51LNX10
AP001-M01) selector switch –S21 and
motor pump #2 (51LNX10 AP002-M02) selector switch –S22.
These switches have the positions AUTO – OFF – MANUAL. To switch on the motor pumps, the
selector switches have to be switched in position MANUAL.
Note: For operation, only one pump has to be switched on!
The normally solenoid operated 3/2-way poppet valve AA110 has to be actuated manually by
means of the manual actuation devices attached to the solenoid –Y01. Due to this actuation, the
3/2-way poppet valve is shifted into lifting position.
After this, the pressure relief valve AA301 has to be actuated manually by means of the manual
actuation devices attached to the solenoid –Y01 of the valve.
If the pressure relief valve is actuated, the Gate starts raising. To stop the raising motion, switch
off the pumps or remove the manual actuation of the pressure relief valve and remove the
actuation of 3/2-way poppet valve AA110.
The normally solenoid operated 3/2-way poppet valve AA111 has to be actuated manually by
means of the manual actuation devices attached to the solenoid –Y01. Due to this actuation, the
3/2-way poppet valve is shifted into lowering position.
To stop the lowering motion, remove the actuation of the 3/2-way poppet valve AA111.
If the power supply fails (or in case of locking/unlocking) of the Radial Gates) the hydraulic
system can be operated manually. That means that the manual pump has to be used for lifting.
Turn the motor pump selector switches –S21 / -S22 into “OFF” position.
The shut-off valve 51LPX10 AA501has to be opened.
The normally solenoid operated main directional valve AA112 has to be actuated manually by
means of the manual actuation devices attached to the solenoid –Y02. Due to this actuation, the
main directional valve is shifted into position 3, lifting position.
Actuate hand pump KP003. The gate starts lifting.
Turn the motor pump selector switches –S21 / -S22 into “OFF” position.
Open shut off valve AA512 at the control manifolds for Weir Gates.
The gate starts lowering. To stop the lowering motion of the gate, close shut off valve AA512.
Turn the motor pump selector switches –S21 / -S22 into “OFF” position.
The shut-off valve 51LPX10 AA501has to be opened.
The normally solenoid operated 3/2-way poppet valve AA110 has to be actuated manually by
means of the manual actuation devices attached to the solenoid –Y01. Due to this actuation, the
3/2-way poppet valve is shifted into lifting position.
Actuate hand pump KP003. The gate starts lifting (closing).
The normally solenoid operated 3/2-way poppet valve AA111 has to be actuated manually by
means of the manual actuation devices attached to the solenoid –Y01. Due to this actuation, the
3/2-way poppet valve is shifted into lowering position.
The gate starts lowering.
To stop the lowering motion, remove the actuation of the 3/2-way poppet valve AA111.
General
The rake cleaning machine is inserted into the site clearance of the trash rack with the weir
intake.
The removal of the cleaning debris occurs with the sheet folds in a cleaning debris container,
which is connected with the RCM and is carried with it. The container can be decoupled from the
RCM at the end of the running rail and then switched out or emptied.
The system is conceptualized in such a way that it can be operated automatically (without
manning) or manually controlled. However, inspections in intervals of around a week are to be
performed.
The machine is executed as a mobile rake cleaning machine, type RCM-KA-f.
It consists of the following components:
1. Undercarriage with running gear and running rail
2. Platform with wheel house and balance weight
3. Main arm
4. Articulated-arm
5. Cleaning level
6. Hydraulic Unit
7. Electrical switch and control system
8. Cleaning debris container
The running rails consist of stable I-bearers with welded galvanized flat steel, mounted directlyon
the foundation.
The undercarriage basically consists of a manufactured metal sheet made of a base frame with
aconsole mounted on it and both wheel carriers. In the wheel carriers, where the wheel blocks
aremounted, receive the forces which are freed during the cleaning process, in order words they
leadthem over the running rails back into the foundation.
The main arm and articulated-arm are built onto the. Both arms consist of stable hollow
profiles.They can be moved independently of one another with the hydraulic cylinders.
The platform is mounted on the wheel carriers. The wheel house and balance weight are built
onthe platform. In the wheel house, you can find the hydraulic unit as well as the switch and
controlsystems. The local operation of the machine can be found on the wheel house.
The cleaning level is screwed on the lower end of the articulated-arm and gears into the
clearedrake with the tooth blades.
The cleaning debris gripped by the cleaning level is pulled up over the rake and the folds and
thrown in the cleaning debris container.
Generally, all turquoise buttons are for switching between images. With the violet button, the
procedures can be released and numerical values can be changed in yellow colored fields.
Display of system date and time (this time information is also used for alarms).
Display of the hours of operation (of the hydraulic unit).
12.3.1.2 Operational Display
Display from horizontal (X-) and vertical (Z-) positions, measured from the axis of the
main arm,
Display of the angle of the main arm to the horizontal,
Display of the angle of tilt, 0° according to the cleaning position, positive to the left,
negative to the right,
Display of the cleaning position in mm,
The range of the values is written beside the displays.
Display of the hydraulic oil temperature,
Display of whether or not the hydraulic is running,
Operating button for the switching to the mode “stop log set”,
Operating button for the switching in “local automatic “, button changes with active
“local automatic” to the color green (only possible in mode of operation “local”),
Operating button for the starting of a cleaning cycle in “local automatic”,
Operating button for rotating in the cleaning cycle in “local automatic”,
Operating button for the drive of the 4-cleaning position as well as unload position in
“local automatic”. The set point of the positions is displayed below the buttons.
12.3.1.3 Setting
The screen change buttons are in the lower image edge and operate a change to the named
image,
respectively.
Operator panel for the setting of the speed in manual operation, acts on the knob button
of the control pendant.
Screen selection for the setting of the lever position
Screen selection for the meeting of pre-selections
Figure 12.3: Settings
12.3.1.4 Positions
12.3.1.5 Pre-selections
Button for the deactivation of the cleaning procedure on the machines 1, 2 and 3. On the
green colored button is the cleaning process allowed!
2 buttons for the starting of the cleaning cycle of the respective machine.
4 buttons for the deactivation of single panels. (panel 1/1…panel 2/3)
4 indication panels for the count of the occurred mistake with the corresponding button
for acknowledgement/(Reset)
panels for the input of the interval time with indication of the current elapsed time.
The Track rack cleaning machine can be operated locally using pendent connected to it.
12.4 Desilter
The intake gate sits on the entrance of the desilter in order to close it. The gates basically consist
of the table, the reinforcement with the crossbeam as well as thehydraulic cylinders which are
positioned on it, the limit switch unit and the position encoder.
The gate table is a steel construction which consists of a retaining wall and a welded
stiffeninggirder out of I-profiles.
The bearing and guiding pads are made of synthetic material. The sealing occurs on both
sidesand on the front with a double emergency rubber profile. The base sealing occurs with a
flatgasket.
The lifting and lowering occur with two hydraulic cylinders. The table can be locked in the upper
position using two levers.
Limit switches are built on for the detection of the end position table opening and table
closing.The limit switch unit is mounted on the main head.
The activation of the limit switch occurs with the switching cams on a switch rod which is
carriedwith the table.
A rope pull giver is built on the main head for the detection of the position of the table. The
ropeis fastened using a connecting link on the table.
12.4.2 Desilter Flushing Gates
The flushing gates sit on the end of the desilter under the strainer screen in order to be able to
flush the sediment out of the desilter into the flushing canal.
The gates basically consist of the table, the reinforcement with the crossbeam as well as the
hydraulic cylinder which is situated on it and the limit switch unit.
The gate table is a steel construction consisting of a retaining wall and welded on stiffening
girder out of I-profiles.
The bearing and guiding pads are made out of synthetic material. The sealing occurs on both of
the sides and on the front with an emergency rubber profile. The base sealing occurs with a flat
gasket.
The lifting and lowering occurs with a hydraulic cylinder.
The table can be locked in the upper position using two levers.
Limit switches are fitted on for the detection of the end position table opening and table closing.
The limit switch unit is mounted on the main head. The activation of the limit switch occurs with
the switching cams on a switch road with which the table is carried. The flushing of the Desilting
Chambers is given in Annexure 02.
12.4.3 Desilter Outlet Gate
The outlet gates sit on the exit of the desilter in order to close it. The gates basically consist of
the table, reinforcement with the crossbeam as well as the hydraulic cylinder situated on it, the
limit switch unit and the position encoder.
The gate table is a steel construction which consists of a retaining wall and welded on stiffening
girder out of I-profiles.
The bearing and guiding pads are made out of synthetic material. The sealing occurs on both of
the sides and on the front with a double emergency rubber profile. The base sealing occurs with a
flat gasket.
The lifting and lowering occur with a hydraulic cylinder.
The table can be locked in the upper position using two levers.
Limit switches are fitted for the detection of the end position table opening and table closing.
Thelimit switch unit is mounted on the main head.
The activation of the limit switch occurs with the switching cam on the switch rod with which
thetable is carried.
A Seilzuggeber is built on the main head for the detection of the table. The road is fastened using
a connecting link.
The rake cleaning machine inserted to the site clearance of the strainer screen. The rake debris is
transported through the cleaning lever in the rinsing channel and from there flushed out using
the flushing pump in the flushing canal.
The system is conceptualized in such a way that it can be operated automatically, without
occupation. However, inspections within an interval of a week are to be performed.
The machine is a hydraulic rope pull rake cleaning machine, executed with swiveling levers.It
consists of a stable mount with a drive head fixated on it with cleaning lever, steel folds a lever
guides.
Limit switches are fitted on the drive head for the detection of the end position “lever swivel in”
and “lever swivel out”, which can be activated with switch rods on the swivel arm.
The detection of the end position “lever up” and “lever down” occur through a gears-cam-
limitswitch which is mounted on the drive cable of the rope drum.
The monitoring of the stroke rope is realized through the cable pulley, which is activated with
therope breakage of a limit switch.
The operation can occur on two touch panels. The first is installed in the switch cabinet
Upstream, the other in the switch cabinet Downstream. The operation occurs as far as possible in
the same efficiency. Therefore, only one panel will be described here. Differences between the
individual images will be pointed out extra.
Generally, all gray buttons are for switching between images. With the green button, the
procedures can be released and numerical values can be changed in yellow colored fields.
Start Screen:
The current sediment level of the 3 desilters in the upper area, in the middle and in the lower
area.
Activate the button “calibrate” in the image in order to reach the setting of the probes of the
respective basin.
Sediment Probe Settings:
The identically constructed images are described here for the setting of the probes for desilters 1,
2 and 3.
The current level in the upper area, in the middle and in the lower area. Please note that it
concerns the water-level. Sand deposited on the sediment scales falsify the display.
the corrected level values
and the corrected values for the probes. This can be inserted signed. Lead a flushing cycle
through in order to be sure that there are not any deposits on the sediment scales. Close the
outlet gate and wait until the water-level calms. Measure the water-level and insert the
corrected value in a way that the corrected value agrees with the water-level.
Generally, all gray buttons are for switching between images. With the green button, the
procedures can be released and numerical values can be changed in yellow colored fields.
Start Screen:
With the “alarm” button, the occurring malfunction is displayed in the image, with the
button “acknowledge” you can acknowledge malfunctions.
Display of system date and time (this time information is also used for alarms).
Hydraulic SCM Image:
13.1 Introduction:
Hydrant system consist of a large network of pipes both underground and above ground which
feeds to a number of indoor and outdoor hydrant valves located throughout the area as specified
in the scope. These hydrants are located throughout the power station to meet requirements. In
case of fire these hoses shall be coupled to the respective hydrant valves through instantaneous
coupling and jet of water shall be directed on the equipment on fire.
It is always required that in the event of fire in any area, the water shall be available at the seat of
each hydrant valve with sufficient pressure so that, the firefighting operation shall be carried out
by opening the respective hydrant.
Necessary valves are provided on the ring mains for the purpose of isolation and maintenance.
The hydrant posts are installed on the hydrant ring main and these are min.1m above graded
levels.
The hydrant system has rightly termed as the backbone of entire firefighting system since a well-
designed and well laid installation, effectively fight fires of serious proportions and of all the class
of risk. Piping being buried underground or placed aboveground, it still continues to be in
operation in utility area even when part of effected building structure etc. have collapsed.
Moreover, jet of water effectively screens off the adjoining properties of fire, simultaneously
cooling the risk, affected by the fire to prevent and further spread of fire.
As the efficiency of the hydrant system ultimately depends upon the manner and speed with
which its efforts are directed, squad consisting of watch and ward personnel; departmental
supervisors trained in the operation of the fire service must be maintained in the premises
around the clock.
The spray system is used protect plant-equipment structure and machinery against fire that may
involve highly flammable liquids, gases and solids by the application of water by most effective
manner, in the correct quantity and at the right place.
The equipment is permanently installed around the risk and, where practicable, installations
should be automatically controlled for immediate operation in the event of fire certain special
installations are designed with only manual controlled but wherever possible the system is
designed to respond automatically to the heat of a fire, with freedom from human element.
Charging
1. During the charging of deluge valve, ensure that the discharge valve for dry line is in closed
position.
2. Charge the detection line by opening the globe valve.
3. Open the suction valve for deluge.
4. Ensure that the pressure is in detection line and suction line.
5. Open the discharge valve.
Under working conditions, the wet/dry detection system is filled with pressurized water by the
spray pipe network. The pressure keeps the deluge valve closed. That means, the water pressure
in the upper chamber deluge valve keeps the valve towards the feed pipe tight. One of the
strategically distributed detectors in the area protected by the deluge valve is exposed to an
arising fire, the glass bulb will burst and the pipe will release the water from the detection
system. The rapidly dropping pressure allows the piston valve now the area protected by the
deluge valve will be completely covered with a fire water spray.
Deluge valve shall be activated by using the manual lever or by breaking the glass of DVCP panel.
Resetting of Deluge valve
SECTION A:
OPERATION MANUAL The valve towards the feed pipe must be closed. Ensure that the
valve is drained by pushing the knob of the drip check valve. Then
CHAPTER 14
open the inspection cover and clean the internal parts from all dirt
and soil.
Cummins heavy-duty engines are designed to operate successfully at full throttle under transient
conditions down to peak torque engine speed (RPM). This is consistent with the recommended
operating practices for good fuel economy.
Excessive full throttle operation below peak torque rpm will shorten engine life to overhaul, can
cause serious engine damage, and is considered engine abuse. Peak torque RPM varies from
1,100 RPM, depending upon rated engine speed.
14.1.1 Operation
General
Correct care of your engine will result in longer life, better performance and more economical
operation.
The engine requires clean air and fuel to be supplied to the combustion chambers in proper
quantities at the correct time.
Caution: While staring the engine, do not touch the throttle or throttle lever
Normal Staring Procedure
Warning: Before starting, check to make sure everyone is clear of engine and equipment to prevent
accidents.
If fuel system is equipped with over speed stop, push “Reset” button before attempting to start
engine.
1. On units equipped with air activated prelube device, open air valve until oil pressure is
registered on oil pressure gauge to activate piston in prelube device which will lubricate all
moving parts in engine.
2. Set throttle for idle speed and disengage driven unit.
3. Open manual fuel shut down valve, if so equipped. Electric shut down valves operate as
switch is turned on. A manual override knob provided on forward end of electric shut-down
valve allows valve to be opened in case of electric power failure. To use, turn fully clockwise;
return to “run” position after electric repair.
4. Press starter button or turn switch key to “Start” position and crank the engine till it fires.
5. At the initial start or after oil or filter changes and after engine has run for a few minutes,
shut it down and wait for 15 minutes for oil to drain back into pan. Check engine oil level
again, add oil as necessary to bring oil level to “H” mark on dipstick. The drop in oil level is
due to absorption by oil filters
When the engine is started, it takes a while to get the lubricating oil film re-established between
shafts and bearing and between pistons and liners. The most favorable clearance between
moving parts are obtained only after all engine parts reach normal operating temperature. Avoid
seizing pistons in liners and running dry shafts in dry bearings by bringing the engine up to
operating speed gradually as it warms up.
Allow the engine to idle three to five minutes after a full load operation before shutting it
off. This allows the engine to cool gradually and uniformly.
Turn the ignition key switch to the OFF position. If the engine fails to stop running, rotate
the manual fuel shutoff thumb screw counter-clockwise to make sure the valve is not
bearing held open by the manual override screw.
14.2.1 Operation
Remove the load from the engine. Run the engine few minutes before routine shut down, on no
load.
It will allow the lubricating oil and coolant to carry heat away from the combustion chamber,
bearings, shafts etc. This is especially important for Turbocharged engines.
14.2.1.3 Operating the engine
Do not operate the engine at full throttle below peak torque engine speed for extended
periods (More than 1 minute) of time.
Allow the engine to idle 3 to 5 minutes before shutting it off after a full load operation.
Monitor the oil pressure and coolant temperature gauges frequently. Shut off the engine if oil
pressure or coolant temperature does not meet specifications.
Continuous operation of the engine with low or high coolant temperature can damage the
engine.
Most failures give an early warning. Look and listen for changes in performance, sound or
engine appearance that can indicate service or engine repair is needed. Some changes to look
for are as follow:
Engine misfires
Vibration
Unusual engine noise
Fuel, oil or coolant leakage
Sudden change in engine operating temperature or oil pressure
Excessive smoke
Loss of power
An increase in oil consumption
An increase in fuel consumption
SECTION A:
OPERATION MANUAL
CHAPTER 15
15.1 Overview
The control and monitoring system is defined to operate the HPP DAGACHHU including the 220kV
switchyard and the dam area from the control room in the power station.
In addition, there are local HMI systems related to the different plant areas which are as follows:
Unit 1
Unit 2
Power Cavern
Dam
Desilter
Following equipment is controlled by the control system:
i. Controlled/monitored equipment for each unit:
Spherical valve
Turbine and governor
Generator and excitation
11 kV bus ducts
Transformer unit
Cooling water equipment
All auxiliary equipment
ii. Controlled/monitored equipment for the general services of the power plant: Electrical
auxiliaries:
Auxiliary supply systems: 110 V DC, 24 V DC
230 V, 50 Hz and uninterruptable power supply system (UPS)
Station services: 33 kV, 11 kV and 400/230 V 50 Hz AC systems
Emergency diesel generator unit
iii. Mechanical auxiliaries:
Ventilation and air conditioning
General compressed air supply
Fire detection
iv. Hydraulic auxiliaries:
Water level measurement
Drainage water system
Cooling water system
Bottom outlet valves
Intake gates
Valve chambers
Spillway Gates
v. Controlled/monitored equipment for the switchyards:
220 kV GIS switchyard
The control and monitoring system enables supervision and control of all controllable
mechanical, hydro-mechanical and electrical equipment of the Dagachhu Hydro Power Plant.
15.1.1 Locations
There are the following main locations within the HPP DAGACHHU facility:
U1 Unit 1 01
U2 Unit 2 02
PC Power Cavern 20
CB Control Building 25
DAM Dam 51
DESI Desilter 52
The control and monitoring system is divided into the following plant areas. Each plant area has
its own automation cell.
UNIT1 Unit 1
UNIT2 Unit 2
DAM Dam
DESI Desilter
One automation cell is used for each plant area. The automation cells consist of the following
parts:
…HMI local HMI system based on CENTRALOG C10 (not for location CBCOM)
…CL cell controller for the processing of the control functions of the plant area based on
MFC1000
…IO for analogue and digital inputs and outputs the CE1000 is used
For the locations UNIT1, UNIT2, CBCOM and PCCOM there are additional MODBUS connections to
other systems.
The plant will generally be operated from the three operator stations.
The CVS station uses the C30 stations as interface to the process. The software functions of the
CVS are based on the CENTRALOC C30 system.
The status of the processes is represented on the visual display units (VDU) in the form of
processdisplays (Mimic views). Elements such as dynamic objects, trends, alarms, event lists,
messages, color changes and flashing symbols are used to draw the attention of the operator to
changes in theprocess and departure from normal and given general information.
The displays will be presented on high-resolution color monitors. This function together with
windowoverlapping capabilities will provide a uniquely powerful operating environment.
Displaying the status of the process and the presentation are done by the following:
Process displays
Overview and group displays
Object displays
Curve displays
Alarm and event list
Status list
The displays are organized in that way that the required information can be found quickly. It is
possible for the operator to view different displays on the two VDUs simultaneously. The
operator is able to control from both VDUs by means of a keyboard and mouse. With dedicated
keys on the keyboard or moving the cursor using the mouse device, the operator is able to select
which VDU is currently active for operation.
The operator station contains only information that is related to the presentation and to manual
control operations. The control functions itself are provided within the cell controllers of the
different plant areas.
Within the control room there is the following equipment for the operation of the Dagachhu
Hydro Power Plant facility:
Computers:
Printers:
Two printers are part of the control system
Control building:
HISTORIAN-S
OPC-S
STORAGE-S
HMI
HMI-WEB
C30 Operator Station 2 with the following functions:
HISTORIAN-S
OPC-S
STORAGE-S
HMI
HMI-WEB
CVS (Central View Station) Operator station with the following functions:
HMI
The STORAGE-S function enables the storage of the historian data. The HISTORIAN-S function
enables the access to the historian information. The OPC-S enables an OPC-Server on the Station
allowing OPC-Connections. The HMI function enables the Human Machine Interface (HMI) on the
Station to allow the operation of the HPP DAGACHHU facility. The HMI-WEB function enables a
web server on the station to allow remote access to the HMI
Engineering Station:
The engineering of the control system software is done with a CONTROCAD (CCAD) station. The
CCAD station is based on a notebook computer.
After power up of the Operating Station Windows XP is starting. In addition, the CENTRALOG
software is also started.
After starting of the CENTRALOG the ALSPA HMI will open and the Login is requested. With
successful login, the initial view is started and the Operating Station can be used.
Local HMI systems utilizing touch screen technology are provided to operate the various plant
areas and units at a local level. The software functions are based on the CENTRALOC C10 system.
For the following plant areas are local HMI systems available:
The local control functions are only used during commissioning, maintenance and
emergencies.The information is limited to the process area where the touch panel is
implemented.
Displaying the status of the process and the presentation are done by the following:
Process displays
Overview and group displays
Object displays
Curve displays
Alarm and event list
Status list
The handling of the operation provided by the local HMI is similar to that of the operator stations
in the control room.
The Local HMI systems allowing operation of the local plant areas of the HPP DAGACHHU facility
consists of:
C10 Operator Station with the following functions:
HISTORIAN-S
OPC-S
HMI
HMI-WEB
The HISTORIAN-S function enables the access to the historian information. The OPC-S enables an
OPC-Server on the Station allowing OPC-Connections. The HMI function enables the Human
Machine Interface (HMI) on the Station to allow the operation of the local area of the Dagachhu
Hydro Power Plant facility. The HMI-WEB function enables a web server on the station to allow
remote access to the HMI.
After power up of the Local HMI station Windows XP is starting. In addition, the ALSPA HMI and
the MY-TSOFT program are starting. MY-TSOFT provides a touch screen software keyboard
function.
After starting of the CENTRALOG software the ALSPA HMI will open and the Login is requested.
With successful login, the initial view is started and the local HMI can be used.
15.4 Communication
The communication within each automation cell is done via the E8000 Field Network. The
E8000network is based on the Ethernet power link standard.
The communication between the different automation cells and as well with the control
roomequipment is done via the S8000-E Unit Network. The S8000-E network is based on
Ethernet standard.
Communication between the control room equipment is done via the Site Network. The Site
Network is based on Ethernet standard.
The addresses of the S8000-E Unit Network equipment are defined as follows:
The ALSPA MFC1000 is a real-time Multi-Function Controller of the ALSPA Control System.
Itprovides the following main automation cell functionalities:
UNIT1 Unit 1 01
UNIT2 Unit 2 02
DAM Dam 51
DESI Desilter 52
The cell controller is connected to the S8000-E network and to the E8000 (EPL) field bus of the
automation cell. For the cell controller UNIT1, UNIT2, PCCOM and CBCOM the MODBUS port
isalso used to acquire data from external systems.
The ALSPA CE1000 I/Os allows connecting a large range of distributed I/Os modules thanks to
aBus Coupler interface. ALSPA CE1000 distributed I/O provides a large range of best of class
Inputsand Outputs modules like Digital, Analog, Thermocouple, RTD, Counters, …
The distributed CE1000 field controllers are connected with high performance bus couplers over
theE8000 field bus to the MFC1000 cell controller.
ALSPA CE1000 Technology features:
Transducers are used to measure electrical or mechanical values within the plant. The
transducerscreate 4..20 mA current signals related to the measurements.
The current signals from the plant are connected to the control system by input cards. The input
cards are installed in the cell- or field controllers.
The used cards are of the type X20AI4622. There are 4 inputs on one card with 12 bits resolution.
Within the controllers a range from 0…32767 is used to represent the measurement by means of
variables (model EPL_AI).
There are LED indicators on the module X20AI4622, which provide module and user supply status.
15.5.2.2 Temperature Inputs
PT100 sensors are used to measure temperature values within the plant.
The temperature signals from the PT100 sensors are connected to the control system by input
cards.
The used cards are of the type X20AT4222. There are 4 inputs on one card.
Within the controllers a range from -2000 to 8500 is used to represent a temperature from -200°C
to 850°C by means of variables (EPL_AI). Within the local HMI and the operator station a range of
-50°C to 200°C is used.
There are LED indicators on the module, which provide module and user supply status.
Digital signals of sensors, switches, circuit breakers, conductors etc. are connected to the control
system by input cards.
DC24V are used to supply the sensors. The DC24V are fed from the DC/DC converter of the
relatedcontroller. Sometimes interposing relays are used.
The used cards are of the type X20DI9371. There are 12 inputs on one card for 24VDC. Within the
controllers the inputs are represented by means of Boolean variables (Model EPL_DI). This
multivariable model transfers the signal and the validity value within the system.
There are LED indicators on the module X20DI9371, which provide module and user supply status.
The output cards are installed in the field controllers. The card can handle output signals from
0…20mA, 4…20mA, 0…10V, –10V…10V.
The used cards are of the type X20AO4622. There are 4 outputs on one card with 12 bits
resolution.
The following ranges can be used:
mA0…20mA = 0…32767
4…20mA = 6553…32767
V -10V…10V = -32767…32767
0V…10V = 0…32767
It is possible to select for every output one of the two different kinds of signals:
Current (0…20mA)
Voltage (-10V…10V)
There is no difference between 0…20mA and 4…20mA or 0…10V and -10V…10V.
The selection is done by the respective range of the output variable (see above).
-32767…32767 is used to represent the measurement by means of variables (Model EPL_AO).
If the controller fails or the communication is lost, the output is set to 0.
There are LED indicators on the module X20AO4622, which provide module and user supply
status.
15.5.2.5 Digital Outputs
Digital commands or signals are connected from the control system by output cards to control or
supervise different systems.
DC24V are used to supply the output card. The DC24V are feed from the DC/DC converter of the
related controller. The output card provides for each channel DC24V and 0VDC. Therefore, the
card is foreseen for the activation of interpose relay.
The used cards are of the type X20DO9322and X20DO8332. There are 12 outputs with 24VDC for
X20DO9322and 8 outputs with 24VDC for X20DO8332. The X20DO8332is used on the Desilter
only.
Within the controllers the outputs are represented by means of Boolean variables (Model
EPL_DO).
If the controller fails or the communication is lost, the output is set to 0.
There are LED indicators on the module, which provide module and user supply status.
15.5.2.6 Power Supply
The supply module X20PS9400 is used together with an X20 bus controller. It is equipped with a
feed for the bus controller, the X2X Link, and the internal I/O supply.
Supply for the bus controller, X2X Link, and internal I/O supply
Feed and bus controller / X2X Link supply electrically isolated
Redundancy of bus controller / X2X Link supply possible by operating multiple supply
modules simultaneously
RS232 service interface
The X20BC0083 bus controller makes it possible to connect X2X Link I/O nodes to POWERLINK
V1and V2. It is also possible to operate the X2X Link cycle synchronously 1:1 or synchronous to
POWERLINK using a prescaler.
POWERLINK is a standard protocol for Fast Ethernet with true real-time properties.
POWERLINK V1/V2
I/O configuration and firmware update via the fieldbus
Integrated hub for efficient cabling
Usually the bus controller is used together with the power supply X20PS9400 which are the base
of an I/o station. After the power supply all necessary I/O may be placed to fulfill the process
needs.
The X20HB2880 standalone hub is equipped with a modular hub expansion. Depending on the
bus base used, one or two additional slots are available. The HB2880 hub expansion module is
equipped with an integrated 2x hub. The Ethernet connections are made using RJ45 connectors.
The module and network status is indicated using LEDs.
The X20HB2880 module is connected over the X20BB81 or X20BB80 base with the X20BC0083.
So, it is really a 2 port Ethernet extender.
The X20HB2881 POWERLINK standalone hub is equipped with modular hub expansion.
Depending on the bus base used, one or two additional slots are available. Take note that
thehardware rev. of the BC8083 and the HB8880 must be ≥F0.
The hub expansion module HB2881 is equipped with two 100 Base-FX ports. The
Ethernetconnection is made using 62.5/125 μm or 50/125 μm glass fiber multimode cable with a
duplex LC connection. The module and network status is indicated using LEDs.
The X20HB2881 module is connected over the X20BB81 or X20BB80 base with the X20BC0083.
So, it is really a 2 port Ethernet extender.
The bus transmitter X20BT9100 provides for the seamless expansion of the X20 System. The
stations can be up to 100 m away from each other.
The bus receiver X20BR9300 is used to connect the X20 System to the X2X Link. The module is
equipped with a feed for the X2X Link as well as the internal I/O supply.
The software license card X20ZF0001-K01 enables the download from the MFC to theX20BC0083
I/O station. It should be every time placed on the end of the I/O station. The reason forthis is the
non-existing board identification in CONTROCAD. So, if an additional I/O card has to
beimplemented, it should be before the X20ZF0001-K01card.
15.5.2.13 Bus Module X20BB80
The X20BB80 bus module is used as a socket for a base module and a power supply module.
Base Module:
X20BC0083
X20HB2880
X20HB2881
Power Supply:
X20PS9400
The X20BM11 bus module serves as the base for all 24 VDC X20 I/O modules. The internal I/O
supply is interconnected.
The X20BM01 bus module is the base for all X20 power supply modules like X20PS9400.
The configuration of each CENTRALOG C30/C10 system is defined in the CCAD engineering tool.
Each system has an HMI Database to keep the configuration data.
There are the following databases defined for the Dagachhu Hydro Power Plant:
U1 Unit 1 C10_1 1
U2 Unit 2 C10_2 2
SP1 Spare 4
SP2 Spare 7
SP3 Spare 8
ALSPA system ensures reliable time tagging through a stable reference time source and the
corrective action. The LANTIME GPS time server (synchronized by GPS) is the synchronization
source of the ALSPA system.
The synchronization and time stamping is realized from the GPS or IRIG-B master clock,
whichelaborates several kinds of synchronizing tops notably 5s tops for the MFC1000 head of
cells. The automation cell is synchronized thanks to its MFC1000 synchronized by hardwired link.
Protocols allowing exchange of time tagged data are IEC 104, IEC 101 and OPC DA. IEC 104 data
can be time-tagged by the MFC for example. Other protocols such as Modbus or Profibus don’t
allow exchanging time tagged data.
Consequently, the Profibus and Modbus data are time tagged at the MFC level. The GPS or IRIG-B
master clock also elaborates time synchronization by network time protocol (NTP) for Control
room stations, display panels through the ALSPA Ethernet Process Bus and for other systems.
15.6.3 Users
The CENTRALOG system is protected against unauthorized access by username and password.
For the ALSPA HMI the following users are configured.
There are three different levels of authorization:
ALSTOM with maximum access level
OPERATOR with medium access level
OBSERVER with minimum access level
On each C10 system and on the C30 system there is the CAC function. The CENTRALOG
ADMINISTRATION CENTER (CAC) is used for manual starting up and shut down of the system and
for updating the configuration of the system. The CAC is not needed for the operation of the
plant. The CAC is also protected against unauthorized access by a defined username and
password.
2 C30 Control room or CVS Remote Station Software memory in cell controller
Power Cavern Control selectable by local HMI or operator
station
1 C10 Local HMI: Local HMI Control Software memory in cell controller
selectable by local HMI or operator
U1, U2, PC, DAM, DESI
station
Commands or set points can be activated only if the related selection switches are in the correct
position for the related level of operation.
A selection of local mode on one level blocks the operation of all levels higher than the selected
level.
For example, if the local mode is selected for a feeder, operation of this feeder is not allowed by
the local HMI or the operator station in the control room.
The hardware switches are situated near the equipment. In local mode the commands are
connected hardwired to the devices. These commands work without control and monitoring
system and are used for test and commissioning only.
Commands out of the hardware will be indicated by the feedback of the device only in the
controlsystem. The commands itself are not reported to the event log.
Commands and set points given by the operator station or the local HMI will be indicated within
the related event log. The integration of the different commands and set points of the different
systems will be done at cell controller level.
The selection of operation mode out of the control room or local HMI can be fetched by each
level.
Errors, faults and other malfunctions within the equipment or the control system of the HPP
DAGACHHU facility will be reported to the operator’s staff by means of alarms. All alarms are
reported to the control room for indication on the operator stations. In addition, alarms are
indicated to the related local HMI. Some equipment has additional alarm indicators on the
equipment itself.
Alarms are indicated on the different alarm views. Level 1 Alarms are system critical alarms
thatcause a shutdown of the unit. Level 2 Alarms are all other alarms. Each alarm has to be
acknowledged by the operator.
To enable a comfortable operation of the plant there are the following categories or “SETS”,
ofalarms based on the location:
All Set 1
Unit 1 Set 2
Unit 2 Set 3
Common Set 4
DAM/DESI Set 5
System Set 6
In addition to the alarms, events are reported on the operator stations in the control room and
on the local HMI. Events need no acknowledgment.
Depending on the configuration of the variable the rising or falling signal creates an alarm.
Depending on the configuration of the variable the rising only - respectively the falling only - or
both movements are reported to archive and printer.
Alarm signals may be delayed or blocked by other signals to avoid alarms in case of normal
operation.
Each operator station within the control room and each local HMI are equipped with audible
alarm(klaxon). The volume can be controlled by the Windows volume control.
The klaxon of the operator stations is started by each alarm rising within the whole facility.The
klaxon of the different local HMI systems is started by the alarms rising within the
relatedautomation cell.
The related icon of the operator station or local HMI is used to stop the klaxon.
Within the different locations of the HPP DAGACHHU facility there are installed horn devices to
give audible alarm in case of a new alarm rising.
There are the following locations defined:
Unit 1
Unit 2
Power Cavern
Control Building
Dam / Desilter
Only the horns of the related location will be started. The common controller of the related
locationcontrols the horn. The horn devices will be stopped after 5 seconds automatically.
The horn of the local HMI area will be started only if the respective Remote Station
Control/LocalHMI Control software-switch is in position Local HMI Control.
The Mimic name consists of an ID and the name of the system shown on the Mimic.
ID's:
OVE Overview
U1 Unit 1
U2 Unit 2
PC Power Cavern
DAM Dam
DESI Desilter
CB Control Building
Each Cell can be controlled from the C30 Operating Station in the Control room or from the
LocalHMI.
To control a Cell from local via the Local HMI Touch Panel the operator has to select "Local
HMIControl" via the touch screen.
See picture below.
The pictures below describe the used Touch Panel Process Symbols and their status indications.
Forexample, a green condition means opens in most case (depending on the device), a faulty
conditionis indicated red.
In most of the pictures some CB, DIS, valves, motors, sub systems… are shown. If you touch/click
on the CB one individual control window will appear where it is possible to operate.
Warning:
If you try to operate a local HMI and the "Local HMI Control" is not selected, you are not able to open
the control window. Same applies to the Operating Station if not in "Remote Station Control".
The Synthetic Variable:
ALSPA P320 system brings a new remarkable concept to the operating power plant system. The
socalled synthetic variable is an operative unit that brings to the operator the reason why he
cannot make his desired action.
In other words, thanks to the synthetic variable, the operator knows why his system is
interlocked and he can act in order to unlock the system.
Example:
When the interlocks are active, which means there is one or several signals missing to make the
requested action, a yellow warning symbol appears.
By clicking on this yellow warning symbol, the operator knows what signal is missing. In the
example
here after, the operator cannot switch On the Disconnector because it is not in remote.
Make sure that all the releases are ok then the yellow triangle will turn gray and the drive can be
operated.
By clicking/touching the setpoint value or the setpoint command button a single setpoint control
window will appear where it is possible to operate.
The operator can use the green arrows to increase or decrease the set point. He can also use the
slide bar to set the desired set point and accept it with the green hock. Another possibility to
enter the desired set point is to click in the white box with the set point value. A calculator
window will appear where the set point can be entered or calculated and confirmed with the
green hock. The requested set point, if the system accepts the value will appear in orange. The
blue value corresponds to the current value.
If the set point is locked the control buttons in the set point window will appear in grey and a red
exclamation mark is shown to the right.
Use this window to switch from Local (C10 local touch panel) to remote control (Control room
C30)
The operator cannot make any action in local if the "Remote Station Control" is selected.
The operator cannot make any action form the control room if the "Local HMI Control" is
selected.
15.7.1.4.2 Emergency Stop Button
The operator has the possibility to access the "Emergency Stop" Button on each mimic to reduce
thedelay between a dangerous situation and the unit shut down. Each unit has its own
"Emergency
Stop" Button. On the overview mimics the "Emergency Stop" Buttons for both units are shown
(seeright picture). On the unit, related mimics only the "Emergency Stop" Button for the
respective unit is shown. After clicking the "Emergency Stop" Button the emergency stop control
window will open.
When pressing the arrow down button and confirming with the green hock, the emergency shut
down for the respective unit starts.
Warning:
It is advising to push the “EMERGENCY STOP” button only in case of Electrical emergencyfailure. It is
advised to avoid the emergency shut down for mechanical emergency failure. A normal shut down
of the unit should be done for mechanical emergencies.
The mimics are only shown on the Operating Station and the Local HMI of the Power Cavern.
All mimics where it is possible to operate are equipped with a Local/Remote window.
15.7.2.1 220kV Overview
Use the Button "JOINT CONTROL ACTIVATION" to run both units in joint control.
In joint control the operator can change the global value for water level, voltage and
produced active and reactive power by assigning the set points. Both Units will share the
load.
The "CONTROL MASTER" indicates which unit is master in joint control (automatic)
The individual mode, status and setpoints for the units are for indication only. The
individual setpoints, mode and status of the related unit can be set only on the Unit
Overview.
Use the “EMERGENCY STOP” button to initiate an emergency shutdown of the related unit.
Use the “EMERGENCY CLOSE” button to initiate an emergency close of the inlet gate and the
desilter 1-3 outlet gate.
Warning:
Pushing the “EMERGENCY CLOSE” button will also activate the quick shut down for both units!
15.7.2.3 Overview Electrical
Green = 220kV
Brown = 33kV
Red = 11kV
White = 400VAC
Telemagenta (183) = 110VDC
Telemagenta (185) = 24VDC
No possibility to interact with the circuit breakers represented in the squares. Only their status
isavailable.
The circuit breaker ON is displayed in the color of its respective network. When the CB is OFF, it is
represented in black. If the square is gray the indication is invalid.
Use the “EMERGENCY STOP” button to initiate an emergency shutdown of the related unit.
15.7.2.4 Overview Heating / Ventilation / Air Conditioning
Brown pipes represent the oil system originated from the Governor System.
Green pipes represent the water system.
The pressure before and after spherical valve is displayed. If the pressure is not equalized, the
pressure alarm is displayed and the opening of the spherical valve will not be permitted.
The Bypass Valve, Service Seal Valve and Spherical Valve can be switched to AUTO/MANUAL
mode and in manual mode they can be OPENED or CLOSED.
The spherical valve positions are shown by digital inputs. From fully close 0°, 30°, 98° to 100° fully
open position.
The presence or absence of water before, in and after the spherical valve is also displayed.
It is possible to switch to the Turbine/Governor view.
The operator can visualize if:
Stop (ST)
has to be selected.
It's possible to switch from Generator Operation to Spinning Reserve or from Spinning Reserve
to Generator Operation.
The Unit Control Mode window shows the actual unit mode. There are three possible modes:
Step-by-Step
Automatic
Joint
The Joint Mode can only be activated from the Control Overview.
The "AUTOMATIC/STEP/NEXT STEP" button activates the Automatic or Step-by-Step mode for
the Unit. In the Step-by-Step mode, it's possible to switch manually to the next step in the start
or stop sequence.
Excitation:
Use the “EXCITATION” button to turn ON/OFF manually the EXCITATION or to switch to
AUTO/MANUAL mode. The area below shows the status of the EXCITATION.
Use the “Q / 11KV U / IE CONTROL” button to choose manually if Excitation will run in Voltage
(VOLT), Current (EXCI) or Reactive Power (REA) Control mode.
In the Excitation Regulation area use the U (Voltage), IE (Current) or Q (Reactive Power) Set
point
Change button to assign the respective set point. The change of the set point is authorized only if
the right mode is active, otherwise it will be shown grayed out.
For the "Energize High Voltage Line" mode the button "VOLTAGE UP/DOWN COMMAND" is used
to increase or decrease the voltage. In other operating modes, it's shown grayed out.
Electrical Overview:
This part shows the Electric Overview of the Unit. Disconnectors, earth disconnectors and circuit
breakers are represented and can be turned to AUTO/MANUAL mode or switched ON/OFF.
Software and hardware interlocks are foreseen between the devices.
The unit circuit breaker cannot be switched on directly; the final ON command is released by the
Synchronization.
The neutral point earth switch for the main transformer can be turned to AUTO/MANUAL mode
or switched ON/OFF.
The line voltage and frequency is shown on top. For the Unit, the excitation voltage and current
as
well as the Unit voltage, current, frequency, cos phi, speed and active/reactive power output is
shown.
If the Unit is tripped the “DEBLOCK” button gets yellow and the unit start is prohibited. The
“DEBLOCK” button is used to reset the Unit after a Trip. This is only possible if the Trip is not
active anymore. If the reset of the Unit is successful, the “DEBLOCK” button gets grey and the
start of the unit is permitted.
The electrical breaking switches and the excitation supply switches can also be operated from
this overview.
Synchronization:
This area shows the status of the synchronization.
Governor:
Use the “GOVERNOR” button to turn ON/OFF manually the GOVERNOR or to switch to
AUTO/MANUAL mode. The area below shows the status of the GOVERNOR.
Use the “P / N / F / L CONTROL” button to choose manually if the Governor will run in Power PC),
Speed (NC), Flow (FC) or Level (LC) Control mode.
In the Governor Regulation area use the P (Power), F (Flow) or L (Level) Set point Change button
to assign the respective set point. The change of the set point is authorized only if the right mode
isactive, otherwise it will be shown grayed out.
In Speed Control mode no Set point can be assigned, the Frequency is kept constantly at 50 Hz.
In the Governor, Additional Functions area, the "LOAD TAKE UP" and the "NOZZLE FREEZING"
can be switched ON and OFF. The Governor "PRIMARY CONTROL" can be turned ON/OFF or
switched to AUTO/MANUAL mode.
Brown pipes represent the oil system originated from the Governor System.
Green pipes represent the water and cooling water system.
Blue pipes represent the high-pressure air system.
The bearing vibration indication and bearing oil system with temperature indication is
represented.The turbine speed, nozzles and deflectors position, distributor and penstock
pressure is shown.
From the Governor, the Start/Stop valve, the Shutdown valve, the Jet Brake valve and the
Pressure Tank Isolation valve can be switched to Auto/Manual mode and in Manual Mode
Opened/Closed.
The two Governor Pumps can be switched to Auto/Manual mode and in Manual mode turned
On/Off. In addition, the main Governor Pump for the automatic mode can be selected. The
governor oil tank with temperature, level and oil in water alarms is displayed.
In the oil circulation system, the circulation pump can be switched to Auto/Manual mode and in
Manual mode turned On/Off. The cooling water valve and the heating valve of the oil
circulationsystem can be switched to Auto/Manual mode and in Manual Mode Opened/Closed.
The pressure tank has a pressure indication and level and pressure alarms.
The air make-up valve for the pressure tank can be switched to Auto/Manual mode and in Manual
Mode Opened/Closed.
It is possible to switch to the Main Inlet Valve, Cooling Water System, Air Supply and Generator
view.
The operator can visualize if:
The mimics are only shown on the Operating Station and the Local HMI of the Power Cavern. All
power cavern mimics have a Local/Remote window
Station Transformer
both Power Cavern 400V supplies
connection to Control Building
For the busbar the voltage and frequency is indicated.
The CBs are operable from the display and can be turned to AUTO/MANUAL mode or switched
ON/OFF. The status of the hardware Local/Remote switch for each CB is also displayed.
Warning:Each earth switch is not operable from the display and will not be switched off
automatically when its respective CB is Open for security reason. Even if CB is OFF, there is a
possibility to supply the line from downstream. The earth disconnector has to be switched ON
manually with precaution.
For each action on devices software interlocks are shown in the synthetic variables.
It's possible to select one of the two 400V supplies as the desired supply source for the
automatic AUXILIARY SUPPLY SWITCH OVER.
It's also possible to allow to separate the 33kV control building connection for the automatic
AUXILIARY SUPPLY SWITCH OVER.
Warning:For the automatic AUXILIARY SUPPLY SWITCH OVER all Circuit Breakers have to be in AUTO
mode. Otherwise an AUXILIARY SUPPLY SWITCH OVER alarm will be displayed.
The AUXILIARY SUPPLY SWITCH OVER can be switched to AUTO/MANUAL mode. The question
mark aside shows the conditions that have to be fullfilled to successfully switch to AUTO mode. If
the AUXILIARY SUPPLY SWITCH OVER was switched to AUTO mode successfully the AUTO
indication turns green.
The Fire System Control and the Standstill Cooling Selection for the Station Transformer is also
shown.
It is possible to switch to the Overview 220kV and to the Control Building 33kV view and to the
downstream Power Cavern 400V Distribution view and also to the Station Transformer view.
33kV Supply
Emergency Diesel Supply
Desilter Connection
Local Connection
can be turned to AUTO/MANUAL mode or switched ON/OFF. The 24V DC control voltage for this
circuit breakers are also indicated.
The electrical protection for the 33kV supply transformer (MICOM) and the lights/heating MCB
isindicated. The high/low voltage alarm for the 33kV supply and the voltage available for the 400V
busbar is also shown.
All displayed fuses are for indication only.
The status of the 24V DC supply is indicated.
The Emergency Diesel Generator can be turned to AUTO/MANUAL mode and switched ON/OFF.
The status panel shows the status of the Emergency Diesel Generator. The current of the
EmergencyDiesel Generator is also indicated.
From this view, it's possible to switch to the Control Building 33kV and to the Desilter 400V
Distribution view.
33kV Supply
Spare
can be turned to AUTO/MANUAL mode or switched ON/OFF. The 24V DC control voltage for this
circuit breakers are also indicated.
The electrical protection for the 33kV supply transformer (MICOM) and the lights/heating MCB is
indicated. The high/low voltage alarm for the 33kV supply and the voltage available for the 400V
busbar is also shown.
All displayed fuses are for indication only.
The status of the 24V DC supply is indicated.
From this view, it's possible to switch to the Control Building 33kV and to the Dam 400V
Distribution view.
15.7.5.5 Desilter Hydro
For the 400V auxiliary supply of the HPP DAGACHHU power station see single line diagram
AUZ024286.
There are two 400V bus bars (+20BFA00 and +25BFA00) with coupling circuit
breaker(20BFA00GS120 and 25BFA00GS120). The coupling of both 400V bus bars is limited by
100kVA.
The power cavern 400V section is connected over 2 auxiliary transformers (+20BFT10
or+20BFT20) with the power cavern section of the 33kV bus bar +20BBA00. The control
building400V section is connected over 1 auxiliary transformer (+25BFT10) with the control
building section of the 33kV bus bar +25BBA00.
Both 33kV bus bars can be coupled by 20BBA00GS151 and 25BBA00GS111.The power cavern
section of the 33kV bus bar +20BBA00 is supplied by one transformer+20BBT00 from the 220kV
switchyard. The control building section of the 33kV bus bar +25BBA00 can also be supplied by
the 33kV line over 25BBA00GH141.
The 33kV feeder 25BBA00GH151 distribute the energy from the control building 33kV bus bar to
auxiliaries which are outside the power house (dam, desilter, side adit,…).
In addition, the supply of the control building 400V bus bar +25BBA00 can be provided from
incoming feeder 25BFA00GS112 of the diesel unit.
15.8.1 Interlocking
At the same time, all incoming CB can feed the 400V bus bars.
+20BBA00GS121
+20BBA00GS141
+25BBA00GS121
+25BFA00GS112
The coupling CB can be closed, if at least one side of the 400V is without voltage.
In emergency cases the coupling between the two 400V bus bar can be closed. But the limit on
theenergy supply is 100kVA.
The outgoing circuit breakers on the 400V side can be switch on or off if there is no fault on
thefeeder without any interlocking.
Each circuit breaker is equipped with a Local/Remote switch and On/Off control buttons for
manual operation within the distribution panel. The hardwired interlocking of the circuit breakers
is always activated.
Local operation of the feeders is only possible if the Local/Remote switch is in Local position.
Thisposition deactivates the automatic switchover.
The circuit breakers of both 400V bus bars are controlled from the common controllers.
Operation is possible from the Power Cavern Local HMI and from the Operator Stations in the
control room. Within the control system the Remote Station Control/Local HMI Control software
switch of the Dagachhu Hydro Power Plant is used.
Within the control system there is an Automatic/Manual software-switch for each of the feeding
circuit breakers to enable the automatic switchover and On/Off control buttons to operate the
circuitbreakers on touch screen respectively on operator station.
Manual operation enables manual On and Off commands, if the interlocking release the
command.
The circuit breaker of the coupling and the diesel unit are controlled by the control system of
thediesel unit.
There are the following modes of operation:
The selection of the mode is possible at the diesel unit only. A ready signal is provided by the
diesel if operation is possible.
Automatic function takes care for the correct feeding of the bus bar depending on the different
situations of supply.
The normal operation is divided into 4 different types of 220kV / 33kV / 400V topology
By default, the auxiliary is taken over from the 220kV by the auxiliary transformer +20BBT00
which feeds the 33kV power cavern section. From there the auxiliary transformers
+20BFT10/+20BFT20 or +25BFT10 take the energy to supply the 400V bus bars.
For emergency supply the operation mode of the diesel unit has to be in automatic and the
system has to be ready.
Recovery after emergency supply:
If one of the 33kV feeders reports voltage O.K. the related circuit breaker is switched on.
With voltage O.K. on the normal service bus bar, incoming feeder of the diesel unit will be
switchedoff and the coupling circuit breaker will be switched on. After a delay for cooling the
diesel will bestopped.
An automatic / manual switch supervises the 400V auxiliary supply switch over automatic. If one
of the CB which is included in the switch over is set to manual control of operation, the complete
switch over will be set to manual. By setting the general switch over selection switch again to
automatic mode, all CB which are included in the switch over will be transfer also to automatic
mode of operation.
If the CB is in manual mode on and off commands can be activated and executed according the
interlocking.
15.8.10 Alarm
Alarms will be generated if there is an automatic switch over and if a section of the bus bar is
without voltage. If the switch over cannot be successfully fulfilled, an alarm signal will be
generated by the program and the switch over will be set to manual.
SECTION A:
OPERATION MANUAL
CHAPTER 16
16.1. Introduction
The Generating Units of Dagachhu Hydro Power Corporation Limited is designed to feed the
station auxiliary supplies even during the time of grid failures. The Unit circuit breakers will not
open during the transmission line faults or grid failures, instead it will continue to feed the station
auxiliary supply or other substation if there are no faults in that particular substation and its
feeders. This mode of operation is called the “Islanded Mode of Operation” and during this
mode, governor mode of control will automatically switch over to the Speed Control mode and
all the nozzles will open according to the generation.
During the Islanded Mode of Operation, our generator will feed the station through our 5MVA
station transformer. The operation procedure for the operators during the time of Islanded
Mode of Generation are given below:
First of all, check why the Unit has switched to Islanded Mode of Operation? And check whether
our line CB is in OPEN/CLOSE position at both ends. If our 220kV has opened at either end and
unit is in Islanded Mode of Operation follow the following procedure:
i) Make a call to nearest substation i.e. Tsirang Dhajay Substation or National Load Dispatch
Centre (NLDC) and confirm the cause of interruption and duration of
malfunction/interruption.
ii) And in the meantime, check whether the auxiliaries are working or not and if it is not
working, manually ON the auxiliaries from the control system. If it is not getting ON from
control system, you have to locally put ON or if this too is not working you have to inform
the Maintenance Team.
iii) Open our 220kV Line CB if it has not opened during the time of system interruption. But note
that we will open the CB only if 220kV line CB at the Tsirang end has opened.
iv) Call and inform the relevant head of the Units/Divisions (Head, Operation & Maintenance
Division, Head, Operation Unit and Head, Maintenance Unit).
v) Upon receiving the confirmation of normalization of the grid from Tsirang Dhajay
Substation, make them extend the line from Tsirang end.
vi) Confirm whether we are receiving the rated line voltages or not. Also, confirm whether our
line is free of fault by checking the whether the line is sustaining more than 5 minutes or not.
vii) Now If the line is sustaining more than 5 minutes, change our unit control to Spinning
Reserve (SN) and we will have black out.
viii) Close the 220kV line circuit breaker (00ADD00GS100) manually from control system and if it
is not closing from control system, go to the Power Cavern common panel (20CJA10GH001)
and locally close the line CB by changing the selection key to manual mode. Now you will
have voltage in the 220kV Bus.
ix) Close the 5MVA Station Transformer circuit breaker at 220kV Side after getting the bus
voltage and bus frequency.
x) Now close the station service transformer CB (20BBA00GS111) from power cavern 33kV
mimic in control system. Note that you will close only if this CB is open.
xi) Check the Auxiliary Transformer 1 CB (20BBA00GS121) and Auxiliary Transformer 2 CB
(20BBA00GS141). Note that either one of the Auxiliary Transformer’s CB should be closed.
Close either one of the Auxiliary Transformer CB if neither one is in closed position.
xii) Now check the subsequent CB at Power cavern 400V Main Distribution panel
(20BFA00GH001). Note that the 400V CB (20BFA00101) should be closed only if the Auxiliary
Transformer 1 CB (20BBA00GS121) is closed and 400V CB (20BFA00102) should be closed
only if the Auxiliary Transformer 2 CB (20BBA00GS141) is closed.
xiii) Now by this time you will have power supply to all auxiliaries in power cavern but you should
put ON the illumination though the normal light command window (20SLA00GS101_FP).
xiv) Check the auxiliaries like pumps and flaps of the Generating Unit and give ON command
from control system if the auxiliaries have stopped working. Some of the auxiliaries needed
to be checked are Main Transformer oil circulating pumps, cooling water pumps, governor
oil pumps, governor oil circulating pumps, oil vapor extraction system pump, carbon dust
suction device flap, etc.
xv) Check the 33kV power supply for control building, and check whether the control building
400V CB (25BFA00GS101) is OPEN/CLOSED? Close the breaker if it is in OPEN position.
xvi) Now go to Unit Overview Mimic and change the Unit control back to Generator Operation
(GE) Mode and note the time of Unit synchronization with the grid.
Our Generating Units will automatically go to Islanded Mode of Operation whenever there are
failures of grid or line fault at transmission lines. If the Unit goes to Islanded Mode of Operation
with our 220kV line still healthy you should follow the following procedures:
xvii) Call the National Load Dispatch Centre and Tsirang Dhajay Substation and confirm the cause
and duration of interruption. Also, make calls to relevant substations.
xviii)Upon getting the confirmation from the concerned substation regarding the normalization
of the system, check whether our Unit is still in Islanded Mode of Operation of not. If it is still
in Islanded Mode of Operation call and confirm again.
xix) And if our Unit is not in Islanded Mode of Operation, change the Governor regulation control
to Power Set point mode and increase the power and check whether it is increasing or not.
If it is increasing keep the Generation as per the schedule and grid frequency.
SECTION A:
OPERATION MANUAL
CHAPTER 17
The effective operation of the Power plant requires the understanding of the system to which
the plant is connected to. DHPC generating units are connected to both eastern and western grid
of Bhutan. The Transmission network in Bhutan is owned by Bhutan Power Corporation Limited
(BPC). The Eastern Region Load Dispatch Center (ERLDC) is an apex body in the region entrusted
to ensure integrated operation of the power system in the Eastern Region, India. The body
directs the safe and efficient operation of the bulk power transmission, interconnection
operation, and security and performance analysis.
DHPC is linked with numbers of Sub-stations and neighboring generating stations. For the safe
and smooth operation, proper coordination among these stations is very important.
Dagachhu Hydro Power Plant is in ABT (Availability Based Tariff) based power system wherein,
we have to schedule our generation for next 24 hours in advance as DC (Deliverable Capability) to
dispatch Centre i.e. National Load Dispatch Centre (NLDC) at Thimphu, Bhutan. Our scheduling
should reach to business partner TPTCL latest by 10:00 hours (BST) through National Load
Dispatch Centre (NLDC), Thimphu as per the form 4.5 of Annexure 04.
Dagachhu, represented by TPTCL is into the power market under “Short Term Open Access Bi-
lateral Day-ahead Transaction”.
As per Power Purchase Agreement (PPA), Generation planning should be daily, monthly and
quarterly (every three months). Twenty hour (24) hours in advance for daily, not later than 15
days for monthly and not later than 30 days for quarterly.
The following instructions and guide lines shall provide the Control Room operators to effectively
manage the generation forecasting.
a) Ensure that the communication facilities connecting Control Room and various Sub-stations
and BPSO/NLDC are functioning perfectly at all times.
b) Predict the next day’s availability based on status of units and on historical data (previous
inflow) and send the ex-bus schedule as per the form 4.5 of Annexure 04.
c) The daily generation forecast/ ex-bus schedule shall be conveyed to BPSO/ NLDC latest by
10:00 hour, daily.
d) The variations in generation from schedule arising due to unforeseen events shall be
communicated to BPSO/NLDC and TPTCL on real time basis for change in schedule.
e) In case of any of unscheduled outage of a generating units or feeders, the shift In-charge
shall inform BPSO/NLDC of any change in availability, with valid reasons.
f) The planned outage of Units shall be informed to BPSO/NLDC well in advance for
approval/concurrence.
g) For the management of the grid, BPSO/ NLDC conduct the System Coordination Committee
(SCC) meeting and Protection Coordination Committee (PCC) meetings inBhutan on regular
basis. The minutes of each meeting is circulated to all the stake-holders for follow up and
compliance.
17.2 Message
i. If the nature of the work is planned, the notification shall be made well in advance allowing
the stake-holders to prepare for the opportunity shutdowns.
ii. If the shutdown is unplanned and necessitated by the conditions of the equipment,
notification shall depend on the severity and critically of the equipment in service.
a) Planned outage program shall be put up for shutdown approval from BPSO in advance. The
shutdown proposal shall be prepared as per the form 4.4 of Annexure 04.
b) The Shift In-charge control room shall ensure that a written shutdown approval is received a
few days or a day ahead of the proposed date of shutdown.
c) On the shutdown day, final switch off clearance for feeders or final shutdown clearance shall
again be obtained from BPSO/ NLDC before taking up the shutdown operations.
d) Until and unless the written message of final switch off clearance is not received, the
shutdown of equipment shall not be initiated.
e) At the time of shutdown, proper interaction and coordination among the duty stations is very
important.
f) Similarly, the unplanned shutdowns, which are not emergent in nature, required to be
attended urgently shall be put up for approval.
g) Once the equipment is cleared for bringing back into service, notification shall be given to
BPSO/NLDC. The equipment shall be normalized through proper coordination with the
corresponding duty stations.
OPERATION MANUAL
CAPTER 19
As per metering philosophy, energy meters of uniform technical specifications are provided on
feeder side. One as main and other as check meter. As standardized, ERLDC recommended us to
install L&T make SEM (Special Energy Meter). Desired by ERLDC standard, we have also installed
Standby meters of similar make and specifications on LV side of Generator Transformers.
On both sides of Generator Transformers, one each of power logic series and L&T make energy
meters are installed so that energy and losses are accounted properly cross checking each other.
Energy Meter Readings are to be taken with due diligence. The final energy meter reading of
Generators for the day is done @ 24:00 hrs. and realized actual generation achieved for the day.
Actual generation may vary from scheduled generation depending upon unforeseen outages and
inflow
Operation personnel should cross-check the correctness of energy meter readings in a way of
keeping following check points in mind while energy updating @ 24:00 hours daily:
Seeing that energy achieved by main energy meter and its corresponding check energy
meter is within permissible limit of percentage error.
Percentage error should be within + - 0.6% as per grid code for meters’ accuracy class of
0.2.
If the difference is beyond permissible limit, matter to be reported to concerned officer
in-charge without delay.
Energy generated should be always more than energy exported in normal conditions.
Energy meters are getting counter overflow (re-set) after having run upto certain values.
To get cumulative energy, number of counter overflown should be kept tracing.
Ensure that energy meter is running/recording energy during round checks.
Based on actual generation achieved, Daily Generation Report (DGR) in the format provided by
DGPC is prepared and sent daily.
The power from Dagachhu is deemed delivered to consumers after deducting 2% losses within
Bhutan system through export meters of CHP and THP.
JEMR (Joint Energy Meter Reading) is taken @ 12:30 Hrs.(BST) on every 1 st date of the month in
presence of DHPC, BPC and DGPC- Basochhu.
As per Bhutan Electricity Authority, Bhutan Grid Code 28.03.2008, the results of JEMR should be
within permissible percentage error of + - 0.6% between main energy meter and its corresponding
check energy meter of accuracy class of 0.2. If percentage error exceeds limit, then meters
should be taken out for joint calibration.
The report is sent especially to Chhukha Hydropower Plant and Tala Hydropower Plant to deduct
Dagachhu power from their total export meters.
SECTION A:
OPERATION MANUAL
CHAPTER 20
19.1 Billing
As per PPA signed between DHPC and TPTCL, India, DHPC shall raise monthly bill to TPTCL for
supply of electricity for the particular month on or before 3 rd day of each month. The billing is
convened in the format developed in line with PPA wherein, there are total energy exported, 2%
rebate from the billed amount and amount payable for the month.
The monthly bill should be supported by following supporting documents:
19.2 Payment
Payment for the bill becomes due on the 10th day of the bill dated. If due date falls on Sunday or
Government holiday, due date shifts to next working day as per PPA. If TPTCL makes full payment
within 10 days from the delivery of bill, rebate of 2% is allowed. The payment is @ INR 2.90/unit.
The tariff escalation will be @ 2% per year as agreed in PPA. The energy bill of Dagachhu Hydro
Power Corporation Limited in given in Annexure O5.
SECTION A:
OPERATION MANUAL
CHAPTER 21
For the safe operation of Power Plant, monitoring the parameters of generating units and their
auxiliaries is of outmost importance. In every shift, routines checks shall be performed on various
equipment for abnormalities.
It is necessary for operators to know the status and conditions of equipment under their
jurisdiction. It is equally important to know the status of the subs-stations and generators to
which Dagachhu is connected. The status information has to be collected from various locations
from time to time. These data, some of which need not be logged, are required to operate the
station efficiently and safely. The Shift In-charge and the Shift staff shall perform the following
checks and collect the information right after assumption of the charge of the shift.
B) On changeover of the shift, shift in charge shall collect the weather conditions at Dagana
through weather man deputed by Department of Hydro-Met Services, MOEA and status of
the power house, Diversion Weir, Desilter and switchyards along with the signing of the
handing and taking over register.
C) The operators shall check all the equipment parameters (oil and water pressures,
temperatures) and equipment conditions and record on hourly basis.
D) The operators shall go inside the power cavern for the inspection right after taking the taking
over the shift.
E) The operators shall check the condition of all the equipment which ever necessary in every
shift.
F) The Operators shall obtain the status of the grid (whether we are connected to Eastern grid
or to West grid) through System operators right after taking over the shift.
a) The equipment parameters such as load, currents, active and reactive power, temperatures,
and energy meter readings for Units and Feeders shall be recorded hourly.
b) The energy meter recording of feeders at every 24:00 hours.
c) The Daily Data Report of the Plant shall be prepared from the hourly data recorded as per the
4.1 of Annexure o4.
d) The Daily Data Report shall be submitted via e-mail to the Chief Executive Officer and O&M
Department, DGPC at 10.00 hrs. of the following day.
e) Daily Plant availability data shall be submitted via e-mail to PSCC, TPC and Chief Executive
Officer, DHPC as per form 4.3 of Annexure o4.
f) The monthly data to Royal Monetary Authority (RMA) and Department of Hydro Power
Service shall be submitted by Head, Operation Unit as per the form 4.4 of Annexure 04.
g) The Energy Generation and Consumption report shall be submitted to O&M Department,
DGPC as per the form 4.7 of Annexure 04.
h) Any abnormalities observed on equipment, parameters and actions taken by the staff shall be
clearly reflected with time in the defect register at Control Room.
i) Every tripping report/Event information report shall be prepared right after the event and
submitted to the Chief Executive Officer and BPSO.
Monthly Generation Target = (Total energy equivalent for the month given by utilizable
inflow) – (Uncontrollable losses) – (losses due to machine non-availability due to planned
shutdown)
vii. The actual generation achieved in a month will then be computed as a percentage of the
target generation and performance of the plant shall be determined.
viii. Uncontrollable losses shall mean loss in generation due to faults in grid and transmission,
abnormal flooding of river necessitating shutdown of plant and other natural calamities and
uncontrollable factors. Losses due to forced outages arising from within the plant shall not
be deducted.
ix. Losses due to non-availability of machines shall arise only if machines are already under
shutdown for planned works when the inflow rises beyond the generation of the other
machines in service and water has to be spilled. Depending on the urgency, planned
shutdown of a machine shall be deferred by some reasonable period if inflow is high enough
and requires the machine to be in operation.
x. Schedules for planned works for any year shall be finalized and approved at the beginning of
the year.
xi. In the summer months, the maximum generation capacity shall be 126 MW.
≥ 99 % Excellent 18 % 20 %
≥ 99 % Very Good 15 % 17 %
OPERATION MANUAL
21.1 Introduction
Control Center allows users to manage IP Cameras, sites, video recordings and the recording
schedule. In Control Center, a site can include cameras from many different geographical
locations and networks.
Control Center enables user accounts to be organized into user groups. Access permissions for
cameras and other objects can be applied to user groups so that all users in the group inherit the
same permissions, eliminating the need to set up permissions for each user account. User groups
can have full administrator, restricted administrator or no administrator rights. Control Center
users can be linked to Windows user accounts. This means that users can have the same login
and password for Windows and Control Center.
Control Center’s diagnostic tools allow you to monitor the health of all devices in your site. This
means that you can ensure that each device is functioning as expected.
For NVRs, Control Center alerts the user when a disk, redundant power supply or network
connection fails; it also displays status information. Control Center displays NVR disk usage
information for each camera which has recordings on that NVR. Information such as recording
start and stop times, total recording time and total recording size and rate is displayed for each
camera and recording.
21.4 Operation
IP camera system uses Encoder 1 for Live viewing and Encoder 2 for Recording video.
Select the camera and click configure to login inside the camera using password
"powerdhpc" as shown in figure 3.
Select encoder 1 and change the resolution as per requirement SIF, 2SIF and 4SIF as
shown in figure 4.
Figure 21.4: setting of resolution
Click on submit to take effect of the required changes. Then click encoder 2 and make the
same setting as encoder 1.
The SIF and 2SIF are normal and medium resolution (Image quality) setting respectively, 4SIF is
for high resolution, so we select 4SIF for both the encoders.
Camera time has to be synchronized with GPS to get real time video recordings.
Click on Date & Time configuration and select Network time protocol.
Type server IP address (192.168.0.51) and choose the time zone as (GMT +06:00) Astana,
Dhaka for our system and submit.
Figure 21.5: Date and Time configuration
First login to camera to be assign password in control center software and click on Network
security configuration option.
Setting for video recording must be done after adding camera in the system because it will only
display the video without recording the video in the system server. So the settings are done as
follows:
i. Open IndigoVision control center software and click on setup menu.
ii. Select added camera and click on recording schedule as shown in figure 6.
i. Open IndigoVision control center software and click on playback option as shown in figure 9.
iii. Type camera name you would like to create sequence and click ok as shown in figure 13.
Figure 21.14: Creating sequence
iv. Right click on left side empty screen and select add cameras as shown in figure 14.
Figure 15.15: Adding cameras for creating new sequence
v. From the list of cameras select camera name you want to create sequences, then click ok.
Note: If you want to create 3 sequences to the camera, you have to add same camera 3 times inside
the sequence (Repeat the above procedure).
Figure 21.16: Creating the additional sequence
vi. Then double click on Preset Position and select preset 1 (Camera focusing position),
preset 2 for next sequence and so on.
Figure 15.17:Setting the preset position for creating sequence
vii.Then again double click on Dwell Time to set the preset time.
viii. Set Dwell Time as per your requirement (5,10…..seconds) and click ok.
Figure 21.18: Setting of dwell time for sequence
ix. Now click to Live option and drag the same camera to lift side screen as shown below. Click
on Switch between normal and edit preset modes button shown below and select the preset
position i.e. preset 1.
Figure 21.19: Setting of additional pan for the sequence
x. Now click on the camera screen (PTZ option) and set the camera focusing position for preset
1 and save it.
xi. Select preset 2 for next sequence and also change the camera focusing position, again save
it. Repeat the procedure for as many sequences as you want.
xii. After allocating final sequence to the camera, select the same camera from the list shown in
setup menu. Right click on the camera and click on view in pan to start the sequences,
camera will start to rotate automatically in the given preset position and record.
Figure 21.20: Selecting the camera for view in Pane
OPERATION MANUAL primary pair, disks 1 & 2 for secondary pair. Primary pair for
current recorded videos storage and secondary pair is for
CHAPTER 25
21.4.6 Archiving
Heating Ventilating and Air Conditioning (HVAC) system in Underground Power House is one of
the most important factors for maintaining thermal comfort and acceptable indoor air quality.
Ventilation system is also the process of exchanging or replacing air in any space for temperature
control, removal of excessive moisture, unpleasant smells, heat, smoke and dust. The ventilation
and Air conditioning of the underground hydropower station is not only associated with the
health of personal working inside the power house, but also with equipment’s natural working.
It has direct effect on the efficiency of workers and running machine. Dagachhu Hydro Power
Corporation Limited underground power house has 15 numbers of mechanical ventilation fans
installed at different locations.
Figure 1.1: Overall Mimic layout of DHPCL power house ventilation System
The mechanical ventilation fans rated capacity, quantity & location are tabulated as below:
Sl.
Capacity(kW) Qty. Location Purpose
No.
2 at Transformer cavern
(71SAA00GS006, & 7).
2 30 4 3 nos. are smoke exhaust during
1 at Machine hall at EET fire inside power cavern.
top. (71SAA00GS008)
(Exhaust fan)
1 at Machine Hall at EET
side. (71SAA00GS005) To supply fresh air
Generally, transformer is considered as the active source of fire in Electric Power Plant. If the fire
starts from transformers, the firefighting system will trigger automatically and water will spray
over it to extinguish and control the fire before spreading to other equipment’s. Since
transformer is located underground cavern, smoke will accumulate easily.
Hence, designer has taken care of smoke evacuation in such way that firefighting systems Deluge
Valve (DV) operates when input signal trigger from either smoke detector or electrical fault
(PRD/Buchholz relay), then, transformer on fire alarm appears in fire control penal at control
building and in control system as well. Any of the transformer’s deluge valve is activated, the
control relay K1, K2, K3, K4 energize and gives start command to smoke exhaust fan, 30kW
(71SAA00GS005, 006 & 008) and automatically stop all other air supply fans.
ANNEXURE
(OPERATION MANUAL)
SECTION A:
The filling of the entire water conductor system shall be through the intake. A discharge of about
0.5 - 1.0 m3/sec is to be maintained by suitably lifting the intake gate. The filling rate can vary
between the above given limit, though in all subsequent paras, a filling rate of 0.5 m 3/sec is
mentioned. The probable extent of opening of the intake gate for this purpose, under various
heads are indicated in Table 1. During the filling of the water conductor system, the reservoir level
should not exceed El 843.30 m. The rise in reservoir water level should be regulated by operating
the spillway radial gates. The filling and testing of the various components of the water
conductor system may be divided into various stages and carried out in the order indicated
below.
Sl.No. Water Level Assumed Height of Head over upper Discharge (m3/sec)
(m) opening (m) nappe profile (m)
Table 1.1:Showing the opening heights of intake gate and corresponding discharges
i) Close one radial gate and regulate other radial gate in such a way that the filling rate is not
more than 0.5m/hour upto EL 835.00 m
ii) After reaching water level at EL835 m, close the intake gate and flap gates and continue
filling up the reservoir at 0.5m/hour up to EL 843.30 m
iii) Regulate using the flap gates and radial gates and maintain the level at EL 843.30 m
1.1.2 Stage 2 – Filling up of the WCS upto Desilter Inlet Gate): Volume (approx.) = 14,000
m3
In this stage, the WCS will be filled up to the desilter inlet gate up to El 841.0 m in the following
manner:
i) Close all the three desilter inlet gates. Keep all the desilter flushing gates open.
ii) Start filling the open channel system by allowing 0.5 m 3/sec by regulating the intake gate
according to the opening height as indicated in table 1.1.
Desilter shall be partially filled in this stage upto the sill level of the outlet gate (i.e. El 837.90 m.
Filling of the desilter shall be done one after another.
i) Close the desilter flushing gate of desilter-1 and open the corresponding inlet gate so that 0.5
m3/sec flows through it based on the gate opening given in table 1.2, keeping the other two
inlet gates closed.
ii) Keep raising the desilter inlet gate at a slow rate till it is fully open. Thereafter, start filling the
desilter by allowing 0.5 m3/sec by regulating the intake gate. Let water fill up to El 837.90 m.
iii) Likewise, deilster-2 and desilter-3 can be filled up one after another.
Sl. Water Level Assumed Height of Head over upper Discharge (m3/sec)
No. (m) Opening (m) nappe profile (m)
Table 1.2:Showing the opening heights of the Inlet gate and its corresponding discharges
In this stage, the HRT shall be partially filled up to an elevation corresponding to the invert level
of HRT at surge shaft and the valves provided at side adit shall be tested.
i) Close all the desilter flushing gates. Desilter inlet and outlet gates should be open at this time.
ii) The side adit access door should be properly closed.
iii) Keep both the valves (i.e., HRT drain valve and gravel flushing valve) at side adit open.
iv) Start filling the HRT by allowing 0.5 m3/sec by regulating the intake gate.
v) After some time, water will be coming out of the lower pipe i.e. the gravel flushing pipe
provided at side adit. Allow flow of water through this pipe until the water is clean. When it is
observed that the water coming out is clean, the valve on the gravel flushing pipe shall be
fully closed.
vi) Again, after some time, it will observe that water will be coming out of the upper pipe i.e. the
drainage pipe provided at side adit. Allow flow of water through this pipe forabout 10
minutes and close it fully.
vii) Continue filling the HRT at the rate of 0.5 m 3/sec until water in the HRT reaches El 803.75 m.
viii) When the water level reaches El 803.75 m in the HRT, stop filling for 24 hours and check the
following:
1. Leakage at the desilter flushing gate, valves at side adit and side adit accessdoor.
2. Leakage at the ATH junction.
3. Any marked decrease in pressure measurement at pressure gauges installed near the
HRT drain and gravel flushing valves at side adit.
4. The HRC hill slope.
5. The hill slopes near Face-1 particularly the first 600 m of HRT-North.
6. The hill slope near ATH and surge shaft.
7. Monitor the water table in the wells, streams and springs along the tunnel alignment
especially in the valley portions and report.
i) Close the Main Inlet Valve (MIV) provided in the power house.
ii) Keep the penstock drainage pipe open.
iii) Start filling the pressure shaft by allowing 0.5 m3/sec by regulating the intake gate.
iv) Close the penstock drainage pipe after allowing water to flow though it for about 10 minutes.
v) Close the intake when water in the pressure shaft reaches El 637.00 m (water level to be
ascertained with the help of water pressure gauge installed in MIV) and stop filling for 24
hours and check the following:
a) The entire check list under Para 1.4.
b) Any marked decrease in the pressure measurement at MIV.
c) Any sign of distress near the Powerhouse hill slope.
d) Any leakage of the MIV seals.
e) Observe readings of all the geotechnical instruments installed in Powerhouse and
Transformer caverns
i) Continue filling the pressure shaft by allowing 0.5 m 3/sec through the intake gate.
ii) Close the intake when water in the pressure shaft reaches El 737.00 m and stop filling for 24
hours and check the entire list given in Para 1.5.1.
i) Similarly, continue filling the pressure shaft by allowing 0.5 m 3/sec through the intake gate.
ii) Close the intake when water in the pressure shaft reaches El 803.75 m and stop filling for 24
hours and check the entire list given in Para 1.5.1.
iii) Special attention should be given to observe leakage through the cavity formation in
pressure shaft between El 754 m to El 774 m.
1.1.6 Stage – 6 (Filling up of the balance HRT and Surge Shaft): Approximate Volume =
92,150 m3
The balance HRT and surge shaft shall be filled up in the following four stages:
i) Start filling the balance HRT and surge shaft by allowing 0.5 m 3/sec through theintake gate.
ii) Close the intake when water in the surge shaft reaches El 815.00 m and stop fillingfor 24
hours and check the entire list given in Para 1.5.3.
1.1.6.2 Stage – 6B (Filling up of the HRT and surge shaft upto El 825.00 m)
i) Continue filling the WCS by allowing 0.5 m3/sec through the intake gate.
ii) Close the intake when water in the surge shaft reaches El 825.00 m and stop fillingfor 24
hours and check the entire list given in Para 1.5.3.
1.1.6.3 Stage – 6C (Filling up of the HRT and surge shaft upto El 835.00 m)
i) Continue filling the WCS by allowing 0.5 m3/sec through the intake gate.
ii) Close the intake when water in the surge shaft reaches El 835.00 m and stop fillingfor 24
hours and check the entire list given in Para 1.5.3.
1.1.6.4 Stage – 6D (Filling up of the HRT and surge shaft upto El 841.0 m)
i) Continue filling the WCS by allowing 0.5 m3/sec through the intake gate.
ii) Close the intake gate when water in the surge shaft reaches El 841.0 m and stop filling for 24
hours and check the entire list given in Para 1.5.3.
Emptying of the WCS may be required in case of emergency or maintenance and repair. Since,
the WCS consists of various sections, emptying may be required only for a particular section or
whole of it depending on the nature of emergency or inspection/repair.
The following are the possible scenarios while emptying the WCS:
i) Case-1: Emptying of the WCS up to desilter outlet gate
ii) Case-2: Emptying of the desilter only
iii) Case-3: Emptying of the WCS downstream of desilter but not pressure shaft
iv) Case-4: Emptying of the pressure shaft only
v) Case-5: Emptying of the whole WCS
The procedure for emptying the WCS in each of the above case is described below. In each of the
case, before any of the described activity is begun, it is assumed that the turbine is standstill and
the MIV is fully closed.
i) Close the intake gate and desilter outlet gates to isolate the section between them.
ii) Start opening the desilter flushing gate slowly and allow passage of water at the rate of 0.5
m3/sec.
iii) There can be two variants in this case i.e. emptying of the WCS upstream of the desilter or
including the desilter depending on the requirement. In the first case, empty water from the
desilter up to the desired level, say El 834.00 m. In the second case empty whole of the water
from the desilter.
i) Close the desilter inlet and outlet gates for that desilter which is required to be emptied. This
will hydraulically isolate the particular desilter.
ii) Start opening the desilter flushing gate slowly and allow passage of water at the rate of 0.5
m3/sec until all the water is drained.
1.2.3 Case-3: Emptying of the WCS downstream of desilter but not pressure shaft
Follow the steps (i) through (iii)-(d) described in Case-3. After that follow the steps givenbelow. It
is to be noted that from here on emptying will be through the penstockdrainage valve provided
near the MIV.
For the penstock dewatering a two-valve arrangement is foreseen right before the MIV as shown
below:
Figure 1.1:Drawing showing the dewatering valves of Penstock
Pos. 1 – Wedge Gate Valve DN100, PN63 – is directly mounted on MIV-inlet pipe. This valve is a
kind of maintenance valve and shall NOT be used for regulating purpose.
Pos. 2 – Globe Valve DN100, PN63 – is mounted right after the wedge gate valve and can be used
for regulating purpose as well as for opening/closing under full pressure.
Important:
For discharging water of the penstock, first the wedge gate valve (pos. 1) has to be opened and
afterwards the globe valve (pos. 2) has to be opened.
When discharging needs to be stopped, first the globe valve (pos. 2) has to be closed and afterwards
the wedge gate valve (pos. 1) has to be closed.
The discharged water shall not contain hard and abrasive particles as this could damage the seating
surfaces and bring about untightens!!
The main step are as follows:
a) Continue emptying the part HRT and surge shaft up to El 795.00m by operating the
penstock drainage pipe provided near the MIV so that flow rate is approximately 0.5
m3/sec and hold for 24 hours.
b) Continue emptying up to El 750.00 and hold for 12 hours.
c) Continue emptying up to El 700.00 and hold for 12 hours.
d) Continue emptying up to El 650.00 and hold for 12 hours.
e) Continue emptying up to El 600.00 and hold for 12 hours.
f) Continue emptying up to El 560.00 and hold for 12 hours.
g) Continue emptying until whole of the water from the pressure shaft is drained.
1.2.5 Case-5: Emptying of the whole WCS
This is a combination of Case-1, Case-3 and Case-4 described above and they shall be
followed in that order only.
During the process of emptying or during the hold period, the following shall be checked
andreported.
i) Any sign of distress on hill slope all along the WCS in general.
ii) Any sign of distress on hill slope near Face-1 particularly the first 600 m of HRTNorth.
iii) Any sign of distress on the hill slope near ATH and surge shaft.
iv) Monitor the water table in the wells, streams and springs along the tunnel alignment
especially in the valley portions and report.
SECTION A:
2.1 Introduction
Flushing of the Desilter can becarried out either in Auto and Manual Mode.
In this mode, it can be either be based on time or in height of the gravel deposits. The setting has
to be done at the cubicle +52LPAGH002 (Andrtiz Panel).
This mode based on the time interval set by the operator at the touch screen at cubicle
+52LPAGH002 and is shown in figure 1 and the setting can be done as below:
i. Punch the required time in set point in hours,
ii. Give the flushing time in minutes,
iii. Check the Time Control by clicking it on the ON button and will become green after
selecting,
iv. Put the setting of Desilter in AUTO Mode,
v. Follow the same process for Desilter 2 and 3 too.
The Desilting Chamber will start flushing when the actual time reaches the set point.
Figure 2.1:Showing the touch panel to set the time for triggering the flushing
2.2.2 Gravel Based
This is based on the actual deposits of sand / gravel in the chamber and operator can set up the
height of gravel at which the flushing can happen and is shown below:
i. Punch the height of the gravel in cm to trigger the flushing in Trigger Flushing box,
ii. Give the flushing time in minutes (this is the duration if flushing),
iii. Check the Gravel Control by clicking it on the ON button and will become green after
selecting,
iv. Put the setting of Desilter in AUTO Mode,
v. Follow the same process for Desilter 2 and 3 too.
The Desilter Chamber will start flushing when the actual gravel height reaches the set value.
Other the automatic mode, the flushing can be done in manual mode locally or through remote
from Control System.
For this mode of operation, we don’t need to set up anything in the touch panel as it purely
depends on the operators and the step are as follows:
i. Select the touch panel in Manual Mode,
ii. Lower the Desilting Chamber Gates i.e. Inlet and Outlet Gate,
iii. When both Inlet and Outlet gate are fully closed, open the flushing gate of that particular
chamber 10 cm (Use stop watch and 15 seconds corresponds to 10 cm opening),
iv. After 30 minutes, open the flushing gate another 10 cm (15 seconds),
v. After another 30 minutes, open the flushing gate fully,
vi. When the flushing gate is fully opened, open the Inlet Gate of the Chamber to its flushing
position i.e. 8 cm and let it flush all the sand and gravels from that chamber,
vii. Close the flushing gate fully after completion of flushing of the sand and gravel from that
chamber,
viii. After fully closing the flushing gate, fill the chamber by keeping the Inlet gate opened in
its flushing position i.e. 8 cm until the water level of that chamber equals the water level
of other Desilter or Desilter Outlet water level,
ix. After reaching the water level of that chamber same as that of Desilter Outlet, wait for
five minutes and start opening the Inlet and Outlet gate fully,
x. When both the gates are fully open, but the Desilter in Auto Mode.
The flushing of the Desilter can also be carried out from the control room at Power House
through the Control System. For this mode of operation, the Desilter should be in Auto Mode and
the flushing time should be pre-set up in the touch panel and can be carried out by clicking it on
the flushing button shown in figure 3:
3.1 Precondition:
a) The shift in-charge shall shutdown the Unit at after consultation with the System operator
and the Scouring Team at Diversion Weir.
b) Maintenance staff shall go to Diversion Weir with adequate tools and relevant safety gadgets.
c) Maintenance Unit shall depute an operator at Chhurachhu side adit to monitor the pressure
readings.
a) Scouring Team shall fully close the Weir Intake gate after getting confirmation from Shift in-
charge that the Generating Units are at stand still. However, the operator at Power house will
constantly monitor the Headrace channel (HRC) level and note the readings hourly.
b) The operator at Chhurachhu side adit will measure the water pressure readings at Chhurachu
upon getting instruction from Scouring Team.
c) The Scouring Team will also note the readings of Head Water Level, Desilter water levels, HRC
water level, Surge Tank level, Penstock pressures and the river inflow after closing the intake
gate.
d) Scouring Team shall fully open the Weir Flap Gates.
e) Scouring Team shall open the Radial Gates one by one at its minimum opening i.e. 30 cm.The
Scouring Team shall gradually increase the opening of the Radial Gatesaccording to
procedure given in Annexure 01.
f) The Scouring Team will start the scouring activities after fully opening the radial gates. The
scouring duration will depend on the amount of the silt deposits and the river inflow during
the time of scouring.
g) Scouring Team may either build up or deplete the water level of the Weir to adequately flush
the sand and silt deposits according to the Annexure o1.
3.3 Normalization:
a) After completion of scouring, Team shall fully close one Radial Gate and fill the reservoir by
regulating the other gate.
b) The rate of filling will be accordance with the procedure given in Annexure 01.
c) After water level reaching its normal operating level of EL 841.00 m, the team shall take the
readings from different locations of the power plant like head water level, Desilter water
levels, HRC water level, Surge tank water level, penstock pressure and river inflow,
d) The operator at Chhurachhu will also measure and note the water pressure at Chhurachhu
after getting instruction from Team Scouring.
e) Scouring Team will fully open the intake gate.
f) Up on normalizing the water conductor system, the Scouring Team shall communicate with
the shift in-charge at Power house and accordingly the start the generating Units.
g) The Shift in-charge will start and synchronize the generating unit after getting proper
approvals from the National Load Dispatch Center (NLDC).
SECTION A:
Date:
1 Generation/Import:
D Import (MU)
2 Energy Export/Sale:
Standby/Running/
19 STATUS OF UNITs
Shutdown
A Unit - I
B Unit - II
On account of Grid
Iii
Disturbance/System
Month Monthly Target (MU) Daily Target (MU) Target so far (MU) Actual so far (MU)
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Total
Hours Dam Level Radial Gate Radial Gate 2 Flap Gate 1 Station load Station load
Bus Frequenc
(m) 1 Discharge Discharge Discharge 2016 (MW) 2015 (MW)
Voltage y
(M3/s) (M3/s) (M3/s)
01:00
24:00
Averag
e
Max
Min
MTD YTD
Station (Capacity) DTD
(126 MW) (126 MW)
Peak MW
MU's
Availability (%)
Major Events/Remarks
1 GENERATION: -
i) Installed capacity = MW
2 PEAK GENERATION: -
i) Unit 1 = MW
ii) Unit 2 = MW
3 TOTAL ENERGY AVAILABLE: -
i) DHPC Generation = MU
Total =
4 DISTRIBUTION: -
5 REVENUE: -
6 PEAK LOAD: -
UNIT I
UNIT II
TOTAL
Conditions of shutdown:
1. Before actually switching off the element prior clearance may be availed from concerned
authority.
2. The shutdown must be normalized within the approved period.
3. Affected customers should be informed through media well in advance before taking the
shutdown.
Copy To:
Signature:
Designation:
Date:
4.5 Ex-Bus Schedule form:
Format for boundary conditions:
Trader TPTCL
Exchange code
2.00%
FROM TO EX-Bus (MW)
Quantum after loss (MW)
00:00 00:15
00:15 00:30
23:30 23:45
23:45 24:00
TOTAL
DATED: (Name)
(To be sent to System Operator by utility as per Grid Code Regulation 2008, Clause No. 6.15)
Date: Time:
Antecedent Conditions:
Communicatio
Frequency (Hz):
n Status:
Weather Condition:
Normalization:
Date: Time:
Sequence of Tripping with Time (If any other line or unit or transformer … etc. failure due
to this event):
Copy to:
Signature:
Name:
This report may be faxed but a soft copy should follow to SCO
Month Actual Scheduled Line Aux. Loss Total Energy Sold Royalty *Actual **Actual Total Energy
Energy Ex-Bus Losses (MU) Energy to TPTC as Energy Internal Aux. Energy Consumption
Generation Energy (MU) (MU) Sold to per (MU) Consumption Consumption (MU)
(MU) TPTC as JEMR(MU) (MU) (MU)
per billing at DHPC end
(MU) (@12:30)
BST
January
February
March
April
May
June
July
August
Septembe
r
October
November
December
Total
OPERATION MANUAL
ANNEXURE 05
To
Tata Power Trading Co.Ltd.
Tata Power Company Ltd., C – 43, Sector 62, Noida 201 307
Uttar Pradesh, India
OPERATION MANUAL
ANNEXURE 06
2 Rate Rs./kWh
Amount in words:
6.1 Introduction
The contingency Plan and Operating Procedures document shall be dynamic document which
shall be modified with change in power system network. The modification shall be carried out
after through discussion in the Protection Coordination Committee (PCC) and approved by the
Bhutan Power System Coordination Committee (BPSCC).
This document shall be also reviewed periodically by PCC members on yearly basis.
6.5.2 Failure of 220kV Rurichhu – Semtokha Line and 220kV Tsirang – Jigmeling Line
If the 220kV Rurichhu – Semtokha line fails along with the failure of 220kV Tsirang – Jigmeling
line, the Power System Operator shall instruct Dagachhu Hydropower Corporation Ltd. (DHPC)
and BHP to back down its generation till its total generation is equal to power carrying capacity
of the 66kV Rurichhu – Lobeysa line depending upon priority.
6.5.3 Failure of 220kV Chhukha – Semtokha Line and 220kV Rurichhu – Tsirang Line
If 220kV Chhukha – Semtokha line and 220kV Rurichhu – Tsirang line fails during the lean
generation, Basochhu pondage shall be utilized to meet the Thimphu load including the Lobeysa
load.
6.5.4 Failure of 220kV Chhukha – Semtokha and 66kV Chhukha – Semtokha Line
During the above line failure in the lean seasons, the western load on priority shall be fed from
Basochhu and Eastern Grid. However, for synchronization, the Power System Operator shall
coordinate with the Shift In-charge of Semtokha, BHP and CHP to extend the power to Chhukha
and synchronize at Chhukha end once one of the above lines is restored.
6.5.6 Failure of any one of the 220kV Chhukha – Birpara Line during peak generation
During the peak generation, when one of the 220kV Chhukha – Birpara Feeder trips, the 220kV
bus coupler at Malbase substation shall automatically open by inter-tripping protection scheme
for equal sharing of load between the 220kV Chhukha – Birpara line and 220kV Chhukha –
Malbase line. However, this scheme shall be disabled during lean season as per the instruction of
Power System operator. In general, the following procedures shall be followed:
a) Immediately after the tripping of one of the 220kV Chhukha – Birpara line, the Power System
Operator shall inform the Shift In-charge of Malbase substation regarding the failure of line.
b) If the de-coupling of 220kV bus coupler at Malbase leads to overloading of 66kV Chhukha –
Gedu line, the Shift In-charge of Phuentsholing substation shall open the 66kV Phuentsholing
- Malbase line.
c) After the normalization of the 220kV Chhukha – Birpara line, Power System Operator shall
instruct the Shift In-charge of Malbase substation to close the 220kV bus coupler.
d) Power System Operator shall instruct the Shift In-charge of Phuentsholing substation to close
the 66kV Phuentsholing – Malbase line after closing the 220kV bus coupler at Malbase.
6.5.10 Failure of Both 132kV Motanga – Rangia and 132kV Gelephu – Salakati Line
Till the interconnection of Eastern and Western Grid, during the failure of above lines
simultaneously, Power System Operation shall instruct Shift In-charge of Jigmeling substation to
extend the western power supply to Eastern Grid for faster restoration of KHP generating units.
SECTION B: MAINTENANCE MANUAL
1.1 Introduction
gathering together and getting ready at an early time the replacement parts and the special
equipment that will be needed, and/or ordering them from the manufacturer of the
generator;
keeping the time required for the inspection short by means of detailed planning and
workmanlike carry through on those plans.
Timely and close cooperation between the operator and the manufacturer of the generator is an
essential prerequisite for success in this respect.
Importantnotes
Alllocalsafetyandenvironmentalregulationsregardingtheplaceofoperationandtheenvironmentmus
tbeobserved.
Targetaudienceandqualificationofpersonnel
Allworkonthegeneratormustbecarriedoutbyspeciallytrainedandauthorized personnel
only.Itishighlyrecommendedtohaveanyworkoncriticalpartscarriedout bythemanufacturerorinco-
operationwiththemanufacturerrespectively.
Prior to starting any maintenance work, the operating and maintenance staff must have read and
understood the safety instructions.
The owner/operator and the supervisor(s) must also be familiar with all applicable safety
instructions and are responsible for the maintenance personnel to observe all safety instructions.
Specificsafetymeasures
Risks when the machine is running:
Whilethemachineisrunning,therearebothmechanicalandelectricalhazards present.
Applyextremecareandavoidtouchingtheslipringsand/oranyrotatingparts.
Topreventaccidentsofanelectricalkinditisabsolutelyessentialtofollowtheappropriateinstructionsin
themaintenancesectionwhenchangingthecarbonbrushes.
Onlyvisualinspectionsandchecksarepermitted
Risks when the machine is at standstill:
Itisessentialthatthemachinecannotbeputintooperation
Besurethattheexcitationcannotbeswitchedonwhilethemachineisatstandstill.
Toensurethegeneratoriskeptinasafeandefficientcondition,periodicinspections
mustbeperformed.Theseinspectionsareplannedactivitiesdesignedtodetermineand
evaluatethecurrentstatusofthegeneratorandaredesignatedClassA(first),ClassB
(minor)andClassC(major).
ClassA,ClassB andClassCoverhaulsaredesignedtocheckforchangesinstatusor
conditioninstructuralcomponentswhichwould,incaseoffailure,negativelyaffectthe
operatingsafetyand/orreliabilityoftheplant.
Inordertokeepdowntimeduetoforeseeablewearortodamagethatcanbeidentified
atanearlystagetoaminimum,plannedandscheduledoverhaulsareabsolutely necessary.
Atthesametime,thedowntimerequiredforsuchoverhaulsmustbekeptwithin
economicallyjustifiablelimits thatinturnrequires:
Doingtheoverhaulsatthecorrectpointintime,
Gatheringtogetherandgettingreadyatanearlytimethereplacementpartsandthe
specialequipmentthatwillbeneeded,and/ororderingthemfromthemanufacturerofthegene
rator.
Keepingthetimerequiredfortheoverhaulshortbymeansofdetailedplanningand
workmanship plans.
Timelyandclosecooperationbetweentheoperatorandthemanufacturerofthe
generatorisanessentialprerequisiteforsuccess.
Note:Duetoeconomicconsiderations,theintervalsbetweenoverhaulsshouldbecoordinatedwiththosef
ortheturbine.
Caution:
Thefollowinginspectionsandoverhaulsarerequiredforthesafeoperationofthe generator:
Generalinspectionsbytheoperator
Minoroverhauls
Majoroverhauls
General inspection recommendations
Inspectionworkcarriedoutcarefullyandatthecorrecttimehelpstopreventfaultsor
damageduringoperation.Therefore,inspectionsareanimportantfactortoensure trouble-
freeandsmoothoperationtoavoidcost-intensiverepairs.
Sincetheoperatingconditionsofthemachinescandiffer widely,theintervalsgivenin
theinspectionplanscanbeadaptedtothenormaloperatingconditions.Intheeventof
faultsorextraordinaryoperationconditions(e.g.overload,shortcircuit,asynchronous
operation,excessivespeed)whichresultinanelectricalormechanicaloverloadofthe
machine,thetestsandmaintenanceworkproposedmustbecarriedoutassoonas possible.
Duringoperationofthemachine,allthesystemsandequipmentmustbeconstantly
monitored.Thedisplaysfortemperature,pressure,flowandtheelectricalconditions
mustbecontinuouslychecked.
Partsthatareimportantforoperation–suchastheslidingsurfacesofslip-rings,carbon
brushes,sealingelements–mustbecontinuouslyinspectedvisually.
Exceedingthemaintenanceintervalsreferredtonormaloperationcanadverselyaffect
smoothoperationandresultindamage.Topreventsuchdamage,itscausesshouldbe
rectifiedasquicklyaspossible.
Maintenanceandservicingworkmayonlybecarriedoutbypersonswhohave
appropriateexperienceoflarge-scalegeneratorsandarefamiliarwiththiswork.The
appropriatesafetyinstructionsforallmaintenanceandservicingworkmustbeobserved
andtheprescribedmeasurements should be carriedout.
Itisintheinterestoftheoperatortoreportanychanges and
checksshouldbecarriedouttoastrictscheduleandappropriatechecklists.Checks
shouldbecarriedoutbysuitableinstructedpersonnel,ifpossiblealwaysbythesame
people.Thisisanappropriatewaytoensureearlydetectionofabnormalsymptoms.
Note:
Yearsoffaultlessoperationshouldneverbeareasonforslackeninginspectionprocedureorlessfrequentch
ecks.
Daily/weeklyinspection
Monthlyinspection
Typesofinspections
Typeofinspection Characteristic
Daily/weeklyinspection Inspectionsandobservationsonthegeneratorduringoperation
Monthlyinspection Visualinspectionsofthegeneratorandcomponentsatstandstill
Component Activity
Sliprings • Checkslipringsparking
Carbonbrushes • Checkconditionofcarbonbrushes
Brushgear • Checkbrushgearforsmoothandsilentoperation
Airfilters • Checkairfiltersfordirtcontamination
• Checksystemforleakages
Watercoolingsystem • Checkcoolingwaterflow
• Checkvalvesforsignsofleakage
Bearings • Checkbearingtemperatures
Component Activity
Generator • Checkoperationalparameters
• Checkbearingtemperatures
• Checkoilseparatorsanddrainifnecessary
Sliprings • Checkconditionofslipringsurfaces
Carbonbrushes • Checkconditionofcarbonbrushes
Brushgear • Checkbrushwear
Airfilters • Checkairfiltersfordirtcontamination
Bearings • Checkoillevels
Watercoolingsystem • Checksystemforleakages
• Checkcoolingwaterflow
• Checkvalvesforsignsofleakage
Brakingandjackingsystem • Checkbrakingandjackingfordirtdeposits
• Checkbrakingandjackingsystemforleakage
Standstillheating • Checkfunctionofstandstillheating
Overhaulsareplanned,scheduledchecksonpartsoftheplantoronthewholeplant,
andaremadewiththeobjectofavoidingplantoutagescausedbydamagedpartsor
systems.Whenmadeatprescribedintervals, theoverhaulsenabledetectionofwear,
theearlyrecognitionofdamage,andthetimelyreplacementofdefectiveparts.
Theavailabilityofthemachineisnotonlyaffectedbyoperationalfaults,butisalso
significantlyaffectedbythedurationandfrequencyofplannedshutdown.Theplanned
shutdownsmustthereforebeheldwithineconomicallyviablelimitsandtheworkmust
beplannedforoptimumoverhaulresults.Thesegoalsarepossibleunderthefollowing conditions:
Schedulingoftheoverhaulforthepropertime.
Accuratepredictionoftheworktobedone.
Comprehensiveoverhaulplanningandcompetentperformanceofthework,
resultingintheshortestpossibleshutdowntime.
Overhaulplanningrecommendations
About12monthsbeforestartingtheoverhaul,theplantmanagementshouldcontactthe
manufacturer,ifnecessaryalsotheinsurancecompany(e.g.overhauldiscussion,
servicediscussion)and,takingtheobservationsmadeduringoperationandthe
insurancetermsintoaccount,determinetime,typeanddurationoftheoverhaul.Duringthisservicediscu
ssion,thefollowingitemsshouldbeclarified.
Scopeof overhaul
Withtheaidoftheobservationsmadeduringoperation and aswellasoftheoverhaul plans,
theoverhaulscopementionedabovemust possiblybeextended.
Replacement requirement
Theprospectivesparepartsrequirementcanbedeterminedaccordingtothescopeof theoverhaul.
Sparepartsrequirement
Withregardtotherequirementthesparepartsstocksaretobecheckedfor
completenessandgoodcondition.Sparepartsneededadditionallyshouldbeprovided onduetime.
Toolsanddevices
Itistobe ensured that the necessarytoolsanddevices are ready and in stock.
Personnelemployment schedule
Theplantmanagement should drawupapersonnelschedule.
Workschedule
Aworkscheduleistobedrawnupshowingwhichworkistobedoneintheworkshop,andwhichistobedo
neinthoseofthemanufacturer/parts supplier.
Capacityplanning
Theplantmanagementandifnecessary spare partsmanufacturer/suppliershouldhavethenecessary
workshopandmachinecapacityavailable.
Furtherrequests
Induecoursebeforetheoverhaul,the plant/manufacturer/suppliershouldestablishtheactual
generatorconditionsbycheckmeasurements(e.g.pressures,vibrations,foundation
displacement,generatorheat-up,etc.).
Forthediagnosis,theactualgeneratorconditionsarethencomparedtotheoriginal
(desired)conditionsformakingadiagnosis.
Inthiscontext,thepersonnelrequirement,therequiredpersonnelqualification,
compositionoftheoverhaulteamandtheirworkingtime(manufacturers/suppliers,plants
andoutsidepersonnel)shouldbeestablished.
Itisadvisabletodraw-upatimetablefortheentireoverhaulprocedure(barchart,
networkdiagram).Itshouldbenotedthatquickdismantlingaffordsearlyfindings,which
allowsunforeseenworktobeperformedwithintheplannedoutageperiod.
Factorsforoverhaulintervals
Theoverhaultimingisgovernedessentiallybythenumberofoperatinghoursand
starts.BothfactorsarecombinedtoformtheequivalentoperatinghoursTe.
Timingformula
Te=To+ ns×Ts
Overhaul timing factors
Factor Description
Te Equivalentoperatinghours(EOH)
To Numberofoperatinghours
Ns Numberofstarts
Ts Operatinghourstobeenteredforastart.Accordingtocurrent
knowledge10hperstartforsynchronoussalientpolemachines.
Table 1.4: Overhauling timing factors
Values for Te
ThefollowingvaluesaretakenintoaccountforTe:
Ageing
Wear
Dirt contamination
Shutdown periods
ThenumberofstartsnsintheequivalentoperatinghoursTeshouldbe
enteredforthegeneratoraccountsforeachstart-upand shutdown.
Additionalvalues
Expansion and friction factors on winding and insulation by temperature and centrifugal force
cycles.
Special vibration loading when transiting the natural frequencies of various generator parts.
Thesevaluesmustbeaddedforeachstart-upandshutdown.Sincethesevaluesare
dependingonthespecialoperatingconditionsthesystematicsurveillanceandrecordingoftherelevant
operatingparametersisessential.
Typesofoverhauls
Accordingtotheamountofworkinvolved,adistinctionismadebetween
1. Firstoverhaul(A)
2. Minoroverhaul(B)
3. Majoroverhaul(C)
Type of overhauls
Table: Overhaulintervals
Stator Overhaulinterval
Statorframe Checkfor
X X x
Cleanliness
Cracks
Statorbolts Checktightnessofallboltsandpins
Checkstatorjointsfor x x
frettingandclearance
Statorfeet Checkforcorrosionandmovements X X x
Stator Checkfordamages
foundation Checkfoundationanchors x x x
Statorcore Checklaminationfor
X X x
Corrosion
Fretting
Buckling
Pressfingers Checkpressfingersfor
X X x
Corrosion
Movements
Tightness
Pressplates Checkpressplatesfor x
Tightness
Airducts Checkairductsfor
x
Cleanliness
Deformation
Clampingbolts Checkclampingboltsfor
x
Tightness
Locking
Insulation Checkinsulationfor
X x
Cracksand damages
Corona movements
Statorwindingco Checkfor
vers X x
Cleanliness
Cracks
Statorwinding Checkforfirmseatingof
X X x
Windingbarsintheslots
Checkbarendsatnon-connectionsidefor
X X x
Cleanlinessand cracks
Corona anddiscoloration
Checkbarendsat connectionsidefor
X X x
Cleanlinessand cracks
Corona and discoloration
Checkbar-andinterconnections
x X x
Cleanlinessand cracks
Corona and discoloration
Checkslotwedgesfor
x X x
Tightness
Movements
Checkwindingfor
Cleanliness
Moisture
Overhaulplan– Rotor
Rotor Overhaulinterval
Checkkeysets,spider/rimfor
x X x
Corrosion
Movements
Rotorspider
Checkcoverplatesfor
Corrosion
x X x
Movements
Check tightness of cover plates
Checkcleanliness
x X x
Checkfor
Rotorrim Corrosion
Movements
Checkrotorrimboltsfor
x X x
Tightness
Locking
Checkbraketrackforcleanliness
Checkfor
x X x
Discoloration
Cracks
Braketrack Deformation
Movements
Checkbraketrackclampingboltsfor
x X x
Tightness
Locking
Checkpolecoilsandinsulationfor
x X x
Cleanliness
Cracks
Movements
Checklockingofterminalsandinsulation X X x
Checkterminalsandinsulationfor
x x x
Cracks
Rotorpoles
Discoloration
Checkcoilsupportsfor
x x x
Cracks
Discoloration
Checkpolewedgesfor
x x x
Corrosion
Movements
Checkdamperwindingfor
x
Discoloration
Deformation
Checkinsulationandsupportfor
x x x
Cleanliness
Cracks
Movements
Rotorexcitationl
eads Checkbarsfor
x x x
Cleanliness
Movements
Checkexcitationjointsfor
x x x
Tightness and locking
Checkconditionofslipringsurfaces
Checkfor
Sliprings
Cleanliness
x x x
Oilcontamination
Corrosion
Scores and damages
Polarity wear
Displacementandlooseness
Checkinsulatingpartsfor
x x x
Cleanliness
Outer damages
Check
Cleanliness
Spring pressure
Brushholders
Check clearancebetween slip
x x x
ringsandbrushholders
Carbonbrushes Checkbrushwear x X x
DE Bearing Overhaulinterval
Checkbearingfor
x x x
Leakages
Outerdamages
Checkbearingsupportfor
x X x
Movements
Tightness
Checkbearingsegmentsfor
X x
Cracks
Damages
Checkconditionofbearingsurfaces X x
Check
x X x
Bearing oil
Bearing clearance
Checkpumpringsfor
X x
Wear
Clearance
Checkfor
x X x
Cleanliness
Movements
Bearingbracket
Checkweldedjointsfor
x x x
Corrosion
Cracks
Overhaulplan– Auxiliaries
Auxiliaries Overhaulinterval
Checkoilcoolersandpipingforleakagesan
Oilcoolingsyste dcorrosion x
m Check flow meter function andtightness x x x
Instrumentation Checkprotectivedevices x x
Signal Transmission
Tripping action
Checklist- Statorframeandstatorcore
Stator
Repairnee
Repairdon
CheckedO
ded
K
Component Activity
Statorframe Check for
Cleanliness
Cracks
Stator Winding
Repairnee
Repairdon
CheckedO
ded
Component Activity
e
Checkforfirmseatingof
StatorWinding
Windingbars intheslots
Checkbarendsatnon-
connectionsidefor
Checkbarendsatconnectionsidefor
Checkbar-andinterconnections
Tightness
Movements
Checkwindingfor
Cleanliness
Moisture
Rotor
Repairnee
Repairdon
CheckedO
ded
K
Component Activity
Check key sets, spider/rim for
Corrosion
Movements
Rotorspider
Check cover plates for
Corrosion
Movements
Check tightness of cover plates
Check cleanliness
Check for
Rotorrim Corrosion
Movements
Tightness
Locking
Discoloration
Braketrack Cracks
Deformation
Movements
Tightness
Locking
cleanliness
cracks
Rotorpoles
movements
Cracks
Discoloration
Check coil supports for
Cracks
Discoloration
Corrosion
Movements
Discoloration
Deformation
Cleanliness
Cracks
Rotorexcitationl
Movements
eads
Check bars for
Cleanliness
Movements
Repairdon
CheckedO
ded
K
Component Activity
Check for
Cleanliness
Oil contamination
Corrosion
Scores and damages
Polarity wear
Displacement and looseness
Check insulating parts for
Cleanliness
Outer damages
Check
Cleanliness
Brushholders
Spring pressure
Check clearance between slip
rings and brush holders
Carbonbrushes Checkbrushwear
Repairnee
Repairdon
CheckedO
ded
Component Activity
K
e
DE/NDEBearing Check bearing for
Leakages
Outer damages
Movements
Tightness
Cleanliness
Cracks
Cracks
Damages
Check
Bearing oil
Bearing clearance
Check pump rings for
Wear
Clearance
Cleanliness
Movements
Corrosion
Cracks
Auxiliaries
Repairdon
CheckedO
Repairne
eded
K
e
Component Activity
Check for
Leakages
Highpressuresyst Oil level
em
Perform pressure test
MAINTENANCE MANUAL
CHAPTER 2
CHAPTER 2: EXCITATION SYSTEM
With this card, the SRAM and a battery (type CR 1/3N Varta) exist as separate components. The
service life of the battery totals around 4 years. The battery must be replaced after 4 years at the
latest.
The battery must be replaced within 5 seconds in order to avoid loss of data. If a reserve card is
used which was previously stored for an extended period of time (more than one year), the
battery should be replaced by a new one prior to using the reserve card.
2.2 Cleaning
The equipment must be cleaned whenever inspection work is carried out. The plug-in cards must
be pulled and carefully cleaned approximately every 5 years (depending on the degree of dirt
accumulation and exposure). If the doors are fitted with air filters, these filters must be cleaned
once a year and replaced after around 5 years.
The air filter can be cleaned using compressed air if dry dust only has to be removed. Synthetic-
fiber replacement filter mats, self-extinguishing, class F according to DIN 53438, must be used.
Replacement filter mats: type SK3335.200 Order No. 3173.100 029.211 826
The screws and bolts (terminals, bus bar, etc.) must be checked approximately every 5 years
(after 2 – 3 years in the case of new equipment). Recommended torque are as follow:
Thread Torque in NM
M5 3
M6 6
M8 12
M10 24
M12 48
M16 96
Moving mechanical parts, such as de-excitation switches, door hinges, etc., must be oiled or
greased, respectively, whenever inspection work is carried out.
2.6 Fan
The fan bearings must be replaced after around 50,000 operating hours. For this purpose, the
fans must be dismantled and sent to the manufacturer.
For excitation equipment only:
Since excitation equipment is fitted with two redundant fans per converter, it is possible to
dismantle onefan at a time. This can be done without interrupting operations. If no reserve fan is
(can be) fitted, theremaining opening must be covered by a clean piece of sheet metal or a
similar device in order to avoiddrawing in secondary air and foreign matter.
We recommend replacing all the electrolytic capacitors in the power supply units or the complete
power supply units after 8 years at the latest.
2.8Inspection
We recommend having the entire electrical functionality checked by an expert every 5 years and
in no case, later than every 10 years.
Lubricate X
Power contactors X
Inspection X
Hardware like control units (SPU, ICP), touch display, WAGO bus terminals or fieldbus coupler
have to be loaded with a software when they are replaced.
SECTION B:
MAINTENANCE MANUAL
CHAPTER 3
CHAPTER 3: TURBINE & AUXILIARIES
3- monthly
6-monthly
2- Yearly
Monthly
Revision
Weekly
Yearly
Daily
1 Pelton runner
2 Turbine shaft
6 Turbine casing
9 General checks
Abnormal sound x
Abnormal vibration x
Bearing temperatures ok x
Note/
Observation
Interval s
Sl. Maintenance
No. Inspection
6-Monthly
3-Monthly
Monthly
Revision
2-Yearly
Weekly
Yearly
Daily
After one
Check pretension of year, then
X
coupling bolts every two
years
After one
Check surface year, then
X
protection every two
years
After one
Inspection of the year, then
X
flange transition radius every two
years
after every
Visual check of bearing 30,000
segments operating
hours
Check tightness of
nozzle flanges and x
pipings (oil system)
Check fixation of
protection roof, brake X
jet, deflector
Check feedback
X
transmitters
After one
Visual check of inside year, then
x
area every two
years
Visual check
A visual check of the babbit liner of the bearing segments has to be done after every 30.000
operating hours.
Thermometers
The contacts for the Pt100-resistance thermometers and the accuracy of the thermometers of
the turbine guide bearing have to be checked yearly.
Oil quality
The oil quality has to be checked and an oil analysis (ppm, acid contents, viscosity and water
content) has to be performed yearly.
Oil level
The oil level in the guide bearing has to be checked weekly.
Visual check
A visual check for leakage of the nozzle and the deflector servomotor has to be done weekly.
Also, the drainage piping to the outside of the concrete massives have to be checked.
Servomotors
The opening and closing times of the servomotors have to be checked every two (2) years.
Needle tip and seal Ring
The condition of the whole nozzle as well as the needle tip and needle seal ring have to be
checked regarding erosion yearly. The nozzle tip disassembly is given in Annexure M7.
Tightness
The nozzle flanges and the fitting of the piping (oil system) have to be checked regarding
tightness every two (2) years.
Fixation
The fixation of the protection roof, the protection plate, the brake jet, the deflector and the
deflector servomotor have to be checked yearly.
Feedback Transmitters
The feedback transmitters for the nozzle servomotor and the deflector servomotor have to be
checked for correct and proper function.
Safety systems
The unit has to be stopped once a year by a trigger action on the hydraulic valve, to check if all
safety systems are working well.
Access door
The access doors and closing levers for the turbine casing have to be checked for proper function
and water tightness yearly.
Visual check
A visual check of the inside area of the pit liner regarding painting has to be done every two (2)
years. A touch up painting has to be applied if necessary.
Functional control
A check and functional control of all limit switches, pressure switches, temperature transmitters,
solenoid valves etc. for correct and proper function has to be performed every year.
3.1.4 Troubleshooting
The malfunctions and troubleshooting related to Turbine and auxiliaries is given in Annexure M6.
SECTION B:
MAINTENANCE MANUAL
CHAPTER 4
CHAPTER 4: MAIN INLET VALVE &
AUXILIARIES
4.1 Maintenance
Maintenance and periodic overhauls of all machine parts and systems delivered are of utmost
importance for smooth and uninterrupted operation of the plant. Routine inspections must
therefore be carried out due to the operating time or acc. to fixed time schedules. Routine
checks should be carried out at short intervals, more thorough checks at greater intervals and at
times of low water supply.
Overhauls of the total plant should be planned at approx. 10 - 15 year intervals. These intervals
should be precisely fixed on the basis of operating experiences.
The periodic work listed in these operating instructions are proposals which have been worked
out based on many years’ experiences in the operation of hydraulic steel structures, water
turbines and closing organs, with the aid of feedbacks received from our customers.
Due to changed operating conditions, it may be necessary to adjust the present instructions.
Therefore, any changes, adjustments or irregularities of the operation are to be constantly
recorded. It is the operating personnel’s responsibility to immediately introduce any changes in
maintenance work.
We consider it essential and indispensable that measurements of settings and alignments in
connection with maintenance and overhaul work are recorded systematically.
These measurements must be compared with those measurements made during initial erection,
and/or initial start-up.
Note/
Observation
Interval s
Sl. Maintenance
No. Inspection
6-Monthly
3-Monthly
Monthly
Revision
2-Yearly
Weekly
Yearly
Daily
During
operation,
the checking
hole for
tightness is
kept open. If
any leakage
is detected,
Visual tightness the checking
X
test of double seals hole
isclosed;
With
nextrevision,
the damaged
O-ringseal
need to
beexchange
d.
Flushing of the
moveable seal ring
X
chambers (2-5
minutes)
5 Anchorage DAG09-SVI-1700
Greasing of the
foundation plates
by use of the
greasing nipples X
Servomotors DAG09-SVI-4200
7
Opening and Compare
closing time with list of
comparison x adjustments
Visual check for
tightness of the
servomotor x
Flushing of the
filters X
9
Visual check for
leakage X
Monitoring instruments
Air vent
14
Visual and acoustic
check X
15 Manipulation
(Close & open or
open & close) X
Pipe fittings
18
Check for leakage X
Pressure tank
Hydraulic unit
Servomotors
21 Opening and
closing time
comparison x
22
Visual inspection,
leakage check X
25 Check and
compare to
nominal data X
Check and X
compare to
nominal data
Check emergency
shut down
27 operation (only if
the valve is suitable
for this
operation) X
Note/
Interval Observations
Sl. Maintenance
6-Monthly
3-Monthly
No. Inspection
Monthly
Revision
2-Yearly
Weekly
Yearly
Daily
MT examination X
of tensioning
shafts for cracks
Removal of
slurries in
operating and x
maintenance seal
ring chamber
Greasing the
grease nipples on x x
the cover 1202
4 Servomotors DAG09-SVI-4200
Complete venting
of the servomotor To be done after
oil chamber after every oil filling to
oil filling prevent damages
Firm tightening x x
Visual inspection
for wear, erosion,
cavitation,
damage by
foreign bodies,
cracks, deposits
of foreign mater,
damage to the
paint coats X
Servomotors DAG09-SVI-4200
Bearings
8
Change x
9 Seals
Change x
The possible malfunction and troubleshooting related to the main inlet valve and its auxiliaries is
given in Annexure M8.
SECTION B:
MAINTENANCE MANUAL
CHAPTER 5
CHAPTER 5: GOVERNING SYSTEM
Service inspections and maintenance operations carefully done according to the following
instructions are of vital importance for keeping the plant and all its components in a reliable
operating condition.
Service inspections are intended to detect incipient defects and malfunctions early enough to
ensure that by taking immediate remedial action such as repair and replacement of defective
components, etc.
Consequential damage and hence extended periods of standstill of the machine unit will be
avoided.
Maintenance operations contribute towards keeping the plant components in a reliable
operating condition for an extended period of time.
It is recommended to contact Andritz HYDRO in good time whenever major repairs or
replacements of components will be necessary.
Common Instructions:
Oil level: The visual check of the oil level in the sump tank is necessary due to the fact that a
decreasing oil level can cause rising oil temperature.
Therefore, missing oil must be replaced immediately (same type/brand of used oil) and the
reason for the oil loss has to be investigated.
Oil temperature: Excessive oil temperature is a common sign for faulty hydraulic system (i.e.
pump wear, wrong type of hydraulic oil, etc.).
Therefore, a temperature control via thermometer and temperature switches is necessary. The
oil temperature should be between 20°C (minimum) and 50°C (maximum). The reason of
temperature rise above maximum value should be investigated. Please consider that system oil
temperature will rise with a higher ambient air temperature.
Hydraulic oil: Please avoid a change of oil type/brand used for the control system. If a change of
oil type is absolutely necessary, the whole system should be flushed with the new oil type
carefully. Change of hydraulic oil depends on oil aging and contamination. Therefore, it is
necessary to make an oil analysis once a year. If the oil contamination class is higher than 18/16/13
acc. ISO 4406 (class 7 acc. to NAS 1638), clean the oil or change it (flushing necessary).
Pressure and return oil filter: Clean hydraulic oil will ensure a reliable, proper and long lasting
function of all hydraulic parts. Therefore, it is necessary to watch the contamination indicators on
the hydraulic filters regularly. Please note that the check should be done only if the oil
temperature is normal (about 40°C). A low oil temperature will increase the differential pressure
in the filter (because of the higher oil viscosity). If the contamination indicator is activated the
filter should be switched over to the second element (using the handle, this can be done during
unit operation). The contaminated filter element must not be cleaned, but it has to be replaced
by a new one.
Oil filling and air breather: The used oil filling and air breather should be changed every three (3)
years. The oil filling mesh should be checked for cleanliness after each oil-filling. If contaminated,
the breather should be disassembled and cleaned with compressed air.
Silica gel filter: The used silica gel (RD-GEL 25000) has red indicating pellets, these pellets
changing the red colour due to water absorption to transparent/grey. After that the silica gel
should be changed or regenerated soonest.
Proportional valve: Please read the attached operating and maintenance instructions of the
manufacturer (REXROTH) carefully. All repair / maintenance work on proportional valves needs
skilled personnel and a special servo-valve test stand. Therefore, this work can only be done by
the original supplier REXROTH. For the storage of the spare valve a dry, dust free place with low
humidity is required. The appropriate storage has to be checked from time to time. Attention:
The protection plate, mounted on the spare valve should be replaced only right before assembly.
The spare proportional valve is filled with protection oil and is therefore ready for long storage
time.
At Weekly intervals
At Monthly intervals
Annually
Monitoring instruments Functional test for correct Proceed step by step using
tripping (pressure, temperature the settings made during
and level switches) the commissioning
Sump tank Check and clean air breather Renew the oil charge
according to result of oil
analysis
Painting of areas exposed to Check for damage and corrosion See painting specification
air attack.
If necessary, repair/renew.
Screws and other monitoring Check for tight fit Manually check
elements on device
components and pipe work
5.1.4 Troubleshooting
The possible malfunction and troubleshooting related to Hydraulic Governor is given in Annexure
M4.
5.2Digital Governor
Visually check and clean the digital governor Siemens SICAM TM 1703 ACP, I/O modules,
VibroControl 6000, signal insulators, MCCBs, Convertors, relays, fans, heaters, HMI
panels, etc.
Check the tightness of all cable terminations.
The alarms and troubleshooting of the digital governor is given in Annexure M3.
SECTION B:
MAINTENANCE MANUAL
CHAPTER 6
6.1Maintenance Schedule
6.2Oil sampling
Oil sampling should be tested for the following and results recorded:
If the dielectric strength of oil in transformer is less than 60 kV at 2.5 mm gap, the oil
must be filtered to improve the characteristics.
For transformer of voltage class up to 245kV, if the moisture content is found to have
increased beyond 25 ppm oil should be filtered.
6.2.3 Acidity:
If the acidity is increased beyond 0.5 m KOH/g, then the oil needs filtration.
After draining the oil completely from the transformer core, winding, insulation and
interior of tank should be washed by hot oil jet. The oil being used for washing internal
body also must be drained completely.
Refilling of oil in transformer must be done under vacuum.
Spanner set
Thermometer
Steel sampling bottles with polyethylene cone caps.
Silicon rubber tubing 10 mm bore - 1 m long.
Clean synthetic sponge.
Polyethylene sheet - 1 m square
Clean cloths
Self-adhesive labels
6.3.2 Procedure
The sampling bottles shall be labelled and marked with information like source of sample,
date and time & sample temperature.
Sample bottle shall not be opened before it is needed for testing.
Sampling point should be cleaned by using sponge.
Blanking plate of sampling valve shall be removed by using spanner.
Clean the silicon rubber tubing thoroughly and fit to sampling pointnipple.
Rinse the bottle in oil stream and reduce the rate of oil flow to 1litre/minute.
Put the end of rubber tubing to sampling bottle and fill the bottle frombottom.
No air bubble shall be introduced into the bottle.
The bottle is allowed to overflow before it is closed.
Measure and record the temperature of oil sample as soon as it istaken.
Put back and tighten the blanking plate.
Remove all tools, excess oil container and oil sample from the area.
Arrange for testing oil sample at laboratory.
6.4.2 Procedures
The purpose of this check is to confirm that the winding temperatures Indicators are
functioning accurately.
The transformer shall be isolated and earthed.
Rotate the indicator pointers slowly to the alarm set value and confirm from the control
room that the alarm signal has been received.
Rotate the pointer still further and confirm from the control room that trip signal is
received.
6.4.3 Calibration
Remove the thermal sensing bulbs from the transformer and insert itinto the hot oil bath.
Check the winding temperature readings up and down the scale atintervals of 5 °C.
Confirm from control room that remote temperature readings aretallying with the local
readings.
Replace the sensing element into the transformer pocket.
Multimeter
Nitrogen cylinder with regulator and pressure gauge or air supply (4kg/cm²)
Bucket
10 mm polythene tube, 10 meters.
6.5.2 Procedures
Purpose of this maintenance is to improve the unsatisfactory conditionof oil found during
sampling. Transformer shall be isolated and earthed.
6.7.2 Procedure
Remove the blanking plate from filter valves and connect the oil inlet hose to top filter
valve and oil outlet hose to the bottom filter valve.
Open the filter valves and start circulation of hot oil. Oil temperatureshall be 55°C to 70°C.
Circulate the oil for 4 full passes.
Re sample and arrange to test.
Continue until oil condition is acceptable.
6.9.2 Procedure
The trouble shooting of the Generator Step-up Transformer is given in Annexure M11.
SECTION B:
MAINTENANCE MANUAL
CHAPTER 7
12 Connections Monthly
Oil sampling should be tested for the following and results recorded:
1. Electric Strength:
If the dielectric strength of the oil in the transformer is less than 60kV at 2.5mm gap, the
oil must be filtered to improve the characteristics.
2. Moisture Content
For transformers of voltage class up to 245kV, if the moisture content is found to have
increased beyond 25 ppm oil should be filtered.
3. Acidity
If the acidity increases beyond 0.5 mg KOH/g, then the oil needs filtration.
After draining the oil completely from the transformer, core, winding, insulation and
interior of the tank should be washed by hot oil jet. The oil being used for washing of the
internal body also must be drained completely.
Refilling of oil in transformer should be done under vacuum.
If the dielectric strength of oil in transformer is less than 60 kV at 2.5 mm gap, the oil
must be filtered to improve the characteristics.
For transformer of voltage class up to 245kV, if the moisture content is found to have
increased beyond 25 ppm oil should be filtered.
7.1.3.3 Acidity:
If the acidity is increased beyond 0.5 m KOH/g, then the oil needs filtration.
After draining the oil completely from the transformer core, winding, insulation and
interior of tank should be washed by hot oil jet. The oil being used for washing internal
body also must be drained completely.
Refilling of oil in transformer must be done under vacuum.
Spanner set
Thermometer
Steel sampling bottles with polyethylene cone caps.
Silicon rubber tubing 10 mm bore - 1 m long.
Clean synthetic sponge.
Polyethylene sheet - 1 m square
Clean cloths
Self-adhesive labels
7.1.4.2 Procedure
The sampling bottles shall be labelled and marked with information like source of sample,
date and time & sample temperature.
Sample bottle shall not be opened before it is needed for testing.
Sampling point should be cleaned by using sponge.
Blanking plate of sampling valve shall be removed by using spanner.
Clean the silicon rubber tubing thoroughly and fit to sampling pointnipple.
Rinse the bottle in oil stream and reduce the rate of oil flow to 1litre/minute.
Put the end of rubber tubing to sampling bottle and fill the bottle frombottom.
No air bubble shall be introduced into the bottle.
The bottle is allowed to overflow before it is closed.
Measure and record the temperature of oil sample as soon as it istaken.
Put back and tighten the blanking plate.
Remove all tools, excess oil container and oil sample from the area.
Arrange for testing oil sample at laboratory.
7.1.5.2 Procedures
The purpose of this check is to confirm that the winding temperatures Indicators are
functioning accurately.
The transformer shall be isolated and earthed.
Rotate the indicator pointers slowly to the alarm set value and confirm from the control
room that the alarm signal has been received.
Rotate the pointer still further and confirm from the control room that trip signal is
received.
7.1.5.3 Calibration
Remove the thermal sensing bulbs from the transformer and insert itinto the hot oil bath.
Check the winding temperature readings up and down the scale atintervals of 5 °C.
Confirm from control room that remote temperature readings aretallying with the local
readings.
Replace the sensing element into the transformer pocket.
Multimeter
Nitrogen cylinder with regulator and pressure gauge or air supply (4kg/cm²)
Bucket
10 mm polythene tube, 10 meters.
7.1.6.2 Procedures
Purpose of this maintenance is to improve the unsatisfactory conditionof oil found during
sampling. Transformer shall be isolated and earthed.
7.1.8.2 Procedure
Remove the blanking plate from filter valves and connect the oil inlet hose to top filter
valve and oil outlet hose to the bottom filter valve.
Open the filter valves and start circulation of hot oil. Oil temperatureshall be 55°C to 70°C.
Circulate the oil for 4 full passes.
Re sample and arrange to test.
Continue until oil condition is acceptable.
7.1.10.2 Procedure
Three three-phase 8,00 kVA, 11/33 kV dry type power transformers are provided as additional
sources of station power supply of the powerhouse The primary is connected as delta and the
secondary (LV side) is connected as star with its neutral solidly earthed.
Off load tap changing links are provided on HV side for variation of voltage from –5% to +5% in 4
equal steps 5 position.
No of phases 3
Frequency 50Hz±3%
Connections
HV winding (kV) Delta
LV winging (kV) Star
Vector group -3 phase Dyn5
Cooling AN type
Frequency 50 Hz±3%
% impedance 7.60
7.2.3 Maintenance
Transformer being dry type, no major maintenance is carried out. However, during annual
shutdown of the generator, the following maintenance shall be carried out.
a. Clean and blow out the dust from inside and outside the transformer.
SECTION B:
8.1 Maintenance
Make Proof
Circuit Disconnector/ Performed
Action SF6-Gas Earthing
Breaker Earthing Switch by
Switch (HSES)
Visual - Station
Once a year Once a year Once a year Personnel
Inspection
- Manufacturer
Every 12 to
Every 12 to 18 or specially
18 years or
Major years or after trained
after 5000 -
Inspection 5000 switching personnel of
switching
cycles station
cycles
operator
B
Table 8.2:Surge
counter measurement reading
9. Is there any gas leakage from compartments? Yes/No.
10. Are there any alarm indications in the LCC panel? Yes/No.
11. Are all the earth connections properly made? Yes/No
SECTION B:
MAINTENANCE MANUAL
CHAPTER 9
9.1 Maintenance
MAINTENANCE MANUAL
CHAPTER 10
10.1 Introduction
Crossed Linked Polyethylene (XLPE) cable of 220 kV, 400 sq.mm, aluminum is connected between
220kv GIS and Point of Transmission Head (POT Head) to evacuate power from Dagachhu
Hydropower Plant through the double circuited transmission towers.
Details Specification
Type 127/220 kV
Make SUDKABEL
Frequency 50HZ
Table 10.1:Technical data of Cross Linked Polyethylene Cable
10.3 Maintenance:
Though the cables are maintenance-free, the following basic activities are carried out yearly to
ensure trouble-free operation of the cables throughout the year.
MAINTENANCE MANUAL
CHAPTER 11
Definition Levels
To ensure safe operation and to prolong the lifespan of circuit breaker in efficient condition,
preventive maintenance must be performed.
1. Clean and blow out the dust from the control panel.
2. Check the electrical terminations for any looseness and tightened if required.
3. Check the interlocks.
4. Check all the indications for their correctness.
5. Measure and record the IR value/resistance of closing and trip coil.
6. Recondition/ replace silica gel.
7. Cleaning of breaker cubicles and MCCs.
8. Check the availability of DC supply for trip circuit.
9. Check HV and LV bushing connection and ensure no loose contact.
10. Measure and record the IR for all the auxiliaries Transformer.
SECTION B:
MAINTENANCE MANUAL
CHAPTER 12
The equipment is largely maintenance-free. Special care should be taken that everything is kept
as clean as possible particularly while making any adjustments or replacements and during first
filling with hydraulic oil or subsequent oil change.
To prevent corrosion, it is recommended to inspect the equipment once a year and to repair any
damaged coating.
Required information regarding dismantling respectively fixation (fastening torque) are given in
the relevant data sheet.
Apply O-ring grease on all O-rings before fitting them in place, (extended useful service life) use
only appropriate O-Ring grease!
To seal Joint flange-faces use Loctite 573, as sealing medium for oil and water. Check number of
spare parts and their correct function before start of dismantling.
Monthly Visual control of the entire equipment for loose bolts or parts.
Record all important instrument readings and check if values are plausible
Visual control of servomotors especially at the piston rod passage for traces
of oil.
Visual control of filling quantity of hydraulic power unit
Detection of leakages
The equipment is largely maintenance-free. Special care should be taken that everything is kept
as clean as possible particularly while making any adjustments or replacements and during first
filling with hydraulic oil or subsequent oil change.
To prevent corrosion, it is recommended to inspect the equipment once a year and to repair any
damaged coating.
Required information regarding dismantling respectively fixation (fastening torque) are given in
the relevant data sheet.
Apply O-ring grease on all O-rings before fitting them in place, (extended useful service life) use
only appropriate O-Ring grease!
To seal Joint flange-faces use Loctite 573, as sealing medium for oil and water.
Check number of spare parts and their correct function before start of dismantling.
Record all important instrument readings and check if values are plausible
Visual control of servomotors especially at the piston rod passage for traces
of oil.
Detection of leakages
Monthly Visual control of the entire equipment for loose bolts or parts.
Record all important instrument readings and check if values are plausible
Visual control of servomotors especially at the piston rod passage for traces
of oil.
Detection of leakages
12.4 Desilter
The fastening screw are to be controlled regularly for loosening. With the declaration of defects
of this type, consultation with the manufacturer is absolutely required for confirmation of action.
After flooding, the system should be cleared of large wood or rather gear establishment. This is
valid for the area directly before and after the inlet rake.
The components of the hydraulic system are generally maintenance-free. The maintenance work
concentrates on the filter element and oil changes. Both in the sense of the cleanliness of the
system. Premature outages and repairs can be prevented with the monitoring and periodic
maintenance of the system.
As needed
1/2 Yearly
Monthly
Object / Components
Yearly
test
Steel Construction V
Corrosion Prevention V
Screws/Fastening Elements P
Hydraulic Liquid P
Hydraulic Oil Level P
Sealing-Hydraulic System V
Operating Pressure P
Stroke Rope V N
12.5 Troubleshooting
The errors and troubleshooting the problems related to Diversion Weir Intake Gates and Weir
Gates, Desilter Gates, Trash Rack Cleaning Machine and Screen Cleaning Machines are given
Annexure M1.
The replacement of seals for the Diversion Weir Gates, Desilter Gates and Stop Log gates are
given in Annexure M4.
SECTION B:
MAINTENANCE MANUAL
CHAPTER 13
Monthly inspection:
1. Check all the valves are in correct operating position as follows.
2. Check that all hydrant valves are accessible and that all required operating handles are lifted
and secure.
3. By visual inspection, check for leaks on all valve and lookout for leaks on the pipe flanges and
from valve spindles.
4. Check all the required hoses are supplied with correct fittings and are properly use. Generally,
check that all equipment and storage cabinets are in good repair.
5. Check water is available to fire hydrant and hose reel.
1. Examine all piping generally for signs of corrosion or leak. Repair pipe finish or replace piping
as necessary.
1. Water spray system requires competent and effective care and maintenance to assure that
they will perform their purpose effectively at the time of fire. System shall be serviced and
tested periodically by personnel trained in this work. Maintenance contract with a qualified
agency for service test and operation at regular intervals is recommended.
2. Make sure operating and maintenance instruction and layout shall be available at the fire
station. Plant personnel be trained and assigned the task of operating and maintenance.
3. The equipment shall be checked weekly or other frequently regular schedule for various
defects.
4. At least once a week the readings of pressure gauges of various deluge valves are recorded.
5. The piping shall be examined thoroughly at an interval not more than one year.
6. The functioning of all the deluge valve and automatic detection equipment shall be examined
and serviced by qualified personnel annually.
7. Discharge test of sprayers shall be made at least quarterly. After each operation projector
nozzles with individual cleaner shall be removed and cleaned thoroughly.
8. Manual tripping devices shall be operated at least twice annually.
9. When normally open valves are closed following the system operation or test, suitable
procedure shall be followed to ensure that they are reopened and the system is promptly
restored to full normal operating condition.
10. All projectors/nozzles shall be inspected for proper positioning or test external loading
corrosion and cleaned if necessary based on experience but at least in three months. The
entire system shall be flushed at least once a year. It is important to ensure that the sprinkler
bulbs detectors are kept free from dust or paint. All items pertaining to the spray system shall
be painted at least once in two years, if required.
SECTION B:
MAINTENANCE MANUAL
CHAPTER 14
Preventive maintenance is the easiest and least expensive type of maintenance. It permits the
Maintenance Division to do work at convenient time.
a. A good Maintenance Schedule depends on Engine application: Actual operating environment
of the engine governs the maintenance schedule. The suggested check-sheet on the
following page indicates more checks have to be performed more often under heavy dust or
other special conditions.
b. Using the suggested schedule check sheet: The maintenance schedule check-sheet is designed
as a guide until adequate experience is obtained to establish a schedule to meet a specific
operation. A detailed list of component check is provided through several check periods;also
a suggested schedule basis is given for hours of operation, or calendar of time. A
maintenance schedule should be established using the check-sheet as a guide; the result will
be a maintenance program to fit a specific operation. The check-sheet shown can be
reproduced by any printer. The person making each check can then indicate directly on the
sheet that the operation has been completed. When a complete column of checks is
indicated, the engine will be ready for additional service until the next check is due.
c. Storage for Engines out of Service: If an engine remains out of service and its use is not
immediately forthcoming, special precautions should be taken to prevent rust as per
procedure given in section 1.
d. Scheduled Maintenance: For maintenance schedule of all other engines are given below:
Annually
Monthly
Weekly
Daily
43 clean engine x
47 grease bearing x
49 clean generator x x
51 check instrumentation x
52 check power distribution wiring x x
whichever is early
Daily
Components/objects
Clean Breather x x
MAINTENANCE MANUAL
CHAPTER 15
The overall control system of Dagachhu Hydropower Plant is ALSPA series 6. However, we have
Siemens S7 control system for Diversion Weir and Desilter.
Correct environmental conditions are vital to the reliable operation of all electrical equipment.
Carry out the following operations:
Measure the temperature at the following points:
Ambient temperature within the cabinet
Temperature near the aircraft evacuation exits located at the back of the rack
Ambient temperature within the network cabinet.
The temperatures are
cabinet, with the doors closed and the ventilators running.
Measure the degree of hygrometry in all premises where hardware is installed.
Check that there is no sign of corrosion or condensation on the cabinet and rack walls.
Once you switch off and take all necessary precautions relative to shutting off power, remove
the dust with a low power suction cleaner on:
The inside and the outside of the cabinets
The racks
The peripherals.
Clean the protection ventilator grills.
If there is too many dust on the modules, complete the dust removal with the cleaning of the
modules.
Only clean the
complicate the restart of the equipment.
Before you extract a module, locate its position on the rack and check if its cable is well identified.
Never use aerosol to clean the modules.
Cleaner aerosols leave a thin layer of grease which can alter the functioning of the modules.
Clean rack by rack, starting from the top level. For each rack:
Disconnect the first module and put it on a clean and dust-free anti-static support
Repeat the operation for every module of the rack
Remove the dust at the bottom of the rack, on the connectors and on card- guides with a low
suction cleaner.
Remove the dust on the modules with a brush and an appropriate product.
Once you check and clean the modules, reconnect and lock each module in its original
location.
Plug in and lock every connection.
Move away any electrical equipment which could create electromagnetic disruptions;
Check that the internal light in the cabinet is working correctly;
Check that the door contact in the cabinet is working correctly;
Check that the door grounding braid is properly attached;
Check that the chassis earth connection is properly attached;
Check that the cableway insulation is not damaged in any way.
Accomplish the following actions once you replace the sources and restart the hard ware:
Check that the hardware is operational
Restart the various application programs.
Inspection of the power sources involves checking all of the different power sources required for
the hardware to function correctly;
Measure the voltage on each operating cabinet
Corrective action must be taken wherever tolerances are exceeded
Measure the polarities according to the description of each equipment and compare the
results with its technical characteristics.
The print test allows checking the print quality. Follow this procedure to execute the print test:
Load paper
Switch the printer off (the self-test carries on)
Launch a print test
Control the print quality
In case of poor quality print replace the print cartridge according to the indications. The
printer is now operational and ready to print.
Some printers require a periodical print in order to clean the nozzles.
Both the generating units are provided with SYNCHROTACT 5 used to automatically synchronize
and connect generators to the power system or to connect power systems which are already
synchronized. The field of application extends from straight forward synchrocheck tasks to fully
automatic double-channel paralleling.
The purpose of the device in synchrocheck applications (MAN operating mode) is to prevent
incorrect switching by manual or automatic paralleling equipment. The device's output contact is
closed within the prescribed limits permitting closing of the circuit-breaker and allows the
paralleling command to pass. When being used for automatic synchronization and paralleling
(AUTO operating mode), the device performs all the functions needed to safely connect plant
and systems, e.g. detection of asynchronous, synchronous and dead bus states on both sides of a
circuit-breaker, matching of voltage and frequency at the correct rate for the item of plant or
system to be synchronized, precision paralleling while taking proper account of paralleling time
etc. All the parameter settings involved in a paralleling operation are contained in a single
parameter set. The settings determine the conditions for paralleling and the response of the
voltage and frequency matching functions. The settings are entered by means of the buttons on
the front of the device and are displayed on a two-line LCD. The light emitting diodes (LED's) on
the front plate signal all important operating states.
SYNCHROTACT has been designed for simple fast installation in switch panels. All the external
connections are made at the rear via non-screw coded connectors. All parameter settings can
also be viewed on a PC connected to the RS232 serial interface using the "Terminal" function
provided with MS Windows. The device includes comprehensive self-monitoring functions which
ensure high operational reliability and availability. Its high-quality digital components and
processing exclude inaccuracies due to the influences of temperature and ageing. The highest
possible security against incorrect paralleling is achieved by a system with two independent
devices operating in a double-channel configuration. The measurement, the computation of the
optimum instant for paralleling and the auxiliary supplies of the two devices are completely
independent and paralleling is only permitted if both the channels come to the same conclusion.
15.2.1 Maintenance Instructions
The device does not require any maintenance. Before leaving the works every unit is subjected to
thorough final testing. Experience has shown that in the majority of cases problems during
commissioning are to be found in the external wiring as a consequence of mistakes while
performing commissioning procedures. Should a disturbance occur during operation, it is
important to ascertain whether the problem is in the device itself or in the external circuit.
For the replacement of defective SYNCHROTACT unit, refer Annexure M9.
15.2.2 Troubleshooting
All most all the protective relays installed at the Power House are of Numerical type. These are
microprocessor-based relays in contrast to other relays that are electro-mechanically controlled.
These relays provide great precision and convenience in application. By combining several
functions in one case, numerical relays also save capital cost and maintenance cost over
electromechanical relays.
Caution: Before energizing, check that all cubicle doors are locked and that all equipment is insured
and free of maintenance Permits to Work.
a. Preconditions for Protection Cubicles
1. Permit to Work on protection systems
cleared and signed off by all relevant parties
2. 110VDC Power supply MCBs 01CHE01-F1 for F100 closed
01CHE01-F2 for F200 closed
01CHE01-F3 for binary input closed
3. Rotor earth fault device MR627 in operation 01CHE01-S3 for G01 Pos. On
4. AC supply is on
b. Checking the CT connections
The CT’s must be connected in strict accordance with diagram supplied with the equipment.
The following checks must be carried out to check the CT’s and CT circuits:
polarity check
primary injection test
plot the excitation curve
CT circuit grounding.
The polarity check (as close as possible to the protection equipment) not only checks the current
input circuit as a whole, it also checks the phase-angle of the CT.
Primary injection checks for a ratio error and the wiring to the protection equipment. Each phase-
to-neutral and phase-to-phase circuit should be injected. In each case, the phase currents and the
neutral current should be measured.
The relative polarities of the CT’s and their ratios can also be checked using load current.
Plotting the excitation curve verifies that the protection is connected to a protection core and
not a metering core.
c. Checking the VT connections
The VT’s must be connected in strict accordance with diagram supplied with the equipment.
The following checks must be carried out to check the VT circuits:
polarity check
wiring check
VT circuit grounding.
The rated voltage of an E/F protection scheme is defined as the voltage which occurs between
the terminals “e” and “n” for a solid phase-to-ground fault. An E/F of this kind, e.g. on T phase
(see Figure 15.1), causes the voltages of R and S phases to increase from phase-to-neutral to
phase-to-phase potential and these add vectorially to produce a voltage between terminals “e”
and “n", which is three times the phase-to-neutral voltage.
After shutting down has been completed, one or more components are isolatedand earthed and
available for maintenance and major inspection.
Details of several unit shut downs to follow from control system descriptions
15.3.4 Faults
15.3.5 Maintenance
Because of the self-testing and monitoring features included, the equipment requires neither
special maintenance nor periodic testing.
Where testing is considered necessary, the following procedure is recommended:
Measure the currents and voltages in the secondary of the main CT’s and VT’s and
compare the results with the values displayed by the MMC.
Test the external circuits using the test functions provided by the MMC.
The life of the wet electrolytic condensers is about 20 years. This assumes a mean ambient
temperature outside the casing of 40 °C.
a) Initial Problem Identification
Use table 15.1 below to find the description that best matches the problem experienced, then
consult the section referenced to perform a more detailed analysis of the problem.
Symptom Refer to
Relay power ups but indicates error and halts Table 15.3
during power-up sequence
1 Measure auxiliary voltage on terminals If the auxiliary voltage is present and correct,
1 and 2. Verify the voltage level and go to test 2. Otherwise check the wiring and
polarity against rating the label on fuses in the auxiliary supply
front. Terminal 1 is -dc and 2 is +dc
2 Do LEDs/ and LCD backlight illuminate If they illuminate or the contact closes and no
on power-up, also check the N/O error code is displayed, then error is probably
watchdog contact for closing in the main processor board (front panel). If
they do not illuminate and the contact does
not close, then proceed to test 3.
3 Check Field voltage output (normally If field voltage is not present, then the fault is
48V DC) probably in the relay power supply module.
2 Record displayed error, then remove Record whether the same error code is
and re-apply relay auxiliary supply. displayed when the relay is rebooted. If no
error code is displayed, then contact the local
service center stating the error code and relay
information. If the same code is displayed
proceed to test 3.
The last 4 digits provide details on the Other error codes relate to problems within
actual error. the main processor board hardware or
software. It will be necessary to contact
Alstom Grid with details of the problem for a
full analysis.
4 The relay displays a message for The power up tests have detected corrupted
corrupt settings and prompts for relay settings. Restore the default settings to
restoration of defaults to the affected allow the power-up to complete, then re-
settings. apply the application specific settings.
5 The relay resets when the power up is Error 0x0E080000, programmable scheme
complete. A record is error code is logic error due to excessive execution time.
displayed Restore default settings by performing a
power up with <= and => keys depressed,
confirm restoration of defaults at prompt
using 󠇯enter key. If relay powers up
successfully, check programmable logic for
feedback paths.
Other error codes will relate to software
errors on the main processor board, contact
Alstom Grid.
1 Using the relay menu confirm If the setting is enabled, then disable the test mode and
whether the commission test make sure the out of service LED is OFF.
/ test mode setting is
enables. If it is not enabled,
go to test 2.
2 Select View Records, then Check for H/W Verify Fail this indicates a discrepancy
view the last maintenance between the relay model number and hardware;
record from the menu. examine the “Maint. Data”, this indicates the causes of
the failure using bit fields.
Bit Meaning
It is recommended that products supplied by ALSTOM GRID receive periodic monitoring after
installation. As with all products some deterioration with time is inevitable. In view of the critical
nature of protective relays and their infrequent operation, it is desirable to confirm that they are
operating correctly at regular intervals.
Alstom Grid protective relays are designed for life in excess of 20 years.
The P34x generator relays are self-supervising and so require less maintenance than earlier
designs of relay. Most problems will result in an alarm so that remedial action can be taken.
However, some periodic tests should be done to ensure that the relay is functioning correctly and
the external wiring is intact.
If the customer’s organization has a Preventative Maintenance Policy, the recommended product
checks should be included in the regular program. Maintenance periods depend on many factors,
such as:
Although some functionality checks can be performed from a remote location using the
communications ability of the relays, these are predominantly restricted to checking that the
relay is measuring the applied currents and voltages accurately, and checking the circuit breaker
maintenance counters. Therefore, it is recommended that maintenance checks are performed
locally (that is at the substation itself).
Before carrying out any work on the equipment, the user should be familiar with the contents of
the Safety and technical data sections and the ratings on the equipment’s rating label.
a. Alarms
Check the alarm status LED to identify if any alarm conditions exist. If the LED is ON, press the
read key [ ] repeatedly to step through the alarms. Clear the alarms to switch the LED OFF.
b. Opto-isolators
Check the relay responds when the opto-isolated inputs are energized.
c. Output relay
Check the output relays operate.
d. Measurement accuracy
If the power system is energized, compare the values measured by the relay with known system
values to check they are in the approximate expected range. If they are, the relay is performing
the analog/digital conversion and calculations are being performed correctly. Alternatively, check
the values measured by the relay against known values injected into the relay using the test
block, if fitted, or injected directly into the relay terminals. These tests prove the calibration
accuracy is being maintained.
If the relay develops a fault while in service, depending on the type of the fault, the watchdog
contacts change state and an alarm condition is flagged. Due to the extensive use of surface-
mount components faulty PCBs cannot be repaired and should be replaced. Therefore, either the
complete relay or just the faulty PCB, identified by the in-built diagnostic software, can be
replaced. The preferred method is to replace the complete relay. This ensures the internal
circuitry is protected against electrostatic discharge and physical damage at all times and avoids
incompatibility between replacement PCBs. However, it may be difficult to remove an installed
relay due to limited access in the back of the cubicle and rigidity of the scheme wiring. Replacing
PCBs can reduce transport costs but requires clean, dry conditions on site and higher skills from
the person performing the repair. However, if the repair is not performed by an approved service
center, the warranty will be invalidated.
a. Replacing the complete relay
The case and the rear terminal blocks are designed to ease removal of the complete relay,
without disconnecting the scheme wiring. Before working at the rear of the relay, isolate all
voltage and current supplies to the relay. MT Note: The MiCOM ALSTOM range of relays have
integral current transformer shorting switches which will close when the heavy-duty terminal
block is removed.
1. Disconnect the relay earth connection from the rear of the relay.
15.3.10 Cleaning
Before cleaning the relay ensure that all ac and dc supplies, current transformer and voltage
transformer connections are isolated to prevent any chance of an electric shock while cleaning.
Before cleaning the relay ensure that all ac and dc supplies, current transformer and voltage
transformer connections are isolated to prevent any chance of an electric shock whilst cleaning.
Only clean the equipment with a lint-free cloth dampened with clean water. Do not
usedetergents, solvents or abrasive cleaners as they may damage the relay’s surface and leave a
conductive residue.
SECTION B:
16.1 Maintenance
Our IP Camera system plays a key role in monitoring the various unmanned sites of the power
plant. Functioning of all the cameras round the clock is required to assist the numerous sites of
the power plant. Maintenance work must be carried out to ensure all the cameras are in good
condition all the time. While performing the maintenance work, all the safety measure should
have followed at the work place for the safety of equipment and the person working at site.
Frequency of
maintenance work.
Sl. Preventive maintenance work Remarks
No.
6 months 1 year
Frequency of
maintenance work.
Sl. No. Preventive maintenance work Remarks
½ year 1 year
18.1 Technical details of the 110V DC, 440AH FLOAT CUM BOOST Battery Charger
We have two battery banks inside the Powerhouse Cavern and another at the Control Building.
All the ratings are same and the technical details are given below:
Nominal AC Input
Battery Details
No. of Cells : 55
AH Capacity : 440 AH
Following are the general features of the Battery Charger. These are provided in the battery
charger to make it sturdy and reliable DC source with necessary protections for ease of operation
and maintenance.
1. The charger is protected on the AC & DC side by SFU.
2. RC Surge suppressors protect diode and SCRs against line surges.
3. In the event of AC power failure, the DC emergency contactor gets energized and
connects the totally battery bank across the load and maintains load supply.
4. The 80 % battery tap is permanently connected to the load to maintain DC continuity to
the load even during the period when DC contactor energizes.
5. DC current limit is provided to protect charger against DC Overload.
6. Heavy filters are provided after rectification to provide almost ripple free DC.
7. SCR controlled Boost chargers constant current charging of batteries should be carried
out.
The rectified output is obtained from Three-phase controlled rectifier bridge consisting of six
SCRs with individual RC networks across each device. Separate surge suppressor is provided
before the bridge to protect the rectifier against voltage surges.
Phase angle controlled rectification is the working principle of the Charger. SCR is a three-
terminal device, namely Anode, Cathode and Gate. Phase angle control pulses are applied
between Cathode and Gate. Depending on the position of pulse the SCR conducts and thereby
the magnitude of DC
voltage is controlled. A minimum current equal to latching current should flow through SCR to
retain it in conduction so the latching resistor is provided. The SCR will not conduct till the gate
pulse is applied.
As its name signifies charger is designed to operate in either Float or Boost mode depending on
the requirement of the system. During Float mode operation of charger besides delivering to the
DC load of the DCDB, it is used to trickle charge the battery bank. Trickle charging of battery is
important to keep battery in live & healthy condition. Whereas Boost mode is to be used when
batteries are deeply discharged, and trickle charging is not sufficient to bring battery bank to the
fully charged condition.
Boost mode of the charger is constant current i.e. rated regulated current is maintained across
battery terminals and depending upon the state of the battery voltage will build up gradually
once the batteries set voltage reaches 132.0 V DC. Batteries have reached fully charged state,
boost charging of batteries are terminated and charger switches to Float mode or operation
which is constant voltage mode, and is set at 123.7 V DC which calculates to 2.25 V/Cell equivalent
to trickle charging voltage of the battery. To prevent excess overload, regulator module is
provided with current limit feature. This feature becomes essential part of the system as it
provides voltage drooping effect if current drawn is beyond the factory set limit to safeguard
charger components. Moreover, to prevent any overloading, overload relays are provided on the
AC side and thus prevents from damaging main transformers.
System provides other features like automatic changeover from Boost mode to float mode once
battery is fully charged. It is important as overcharging of batteries might damage them and
reduce its life.
The following checks should be carried out every month and recorded for future references. Any
defect found should be noted and attended.
1. Measure the Voltage of all the 55 cells of all the chargers. If the cells are not healthy,
replace the defective cell.
2. Check the charging voltage and current of station battery.
18.6 Troubleshooting
(MAINTENANCE MANUAL)
SECTION B:
The type of malfunctions and remedial measures for Weir Intake gate is given below:
Loose bolts are detected Tight the bolt/nut. Observe the fastening torque in
accordance with the relevant drawing/data sheet
Monitoring instruments are faulty Check power supply (if any), check measuring circuit,
(electrically) replace instrument
Monitoring instruments are faulty Check actuation mechanism, check hydraulic pressure (if
(mechanically) any), replace instrument
Hydraulic filters are contaminated Replace the filter element. Observe isolation instructions!
Silica gel air filters are saturated Reactivate silica gel by heating (130°C).
Valves are leaking Check if valves are fully closed. Replace sealing if required.
Gate servomotors are leaking For replacing the seals please contact ANDRITZ Hydro
Filling volume of hydraulic power Check for water in the reservoir, drain oil
unit is too high
Hydraulic piping is leaking Try too tight the leaking fitting WITH PRESSURELESS
SYSTEM without any increased effort. If the fitting is still
leaking replace the sealing ring (if any) or replace the
cutting ring (if any)
Hydraulic oil is contaminated by Entire oil system has to be drained and cleaned (all parts).
water Oil filling has to be treated or replaced
All alarms are indicated at the touch screen panel –A02 on the local control cubicle with clear text
provided with time stamp. All alarms are latched and is given below:
Common Alarms
Common - 230V Auxiliary Systems AC Failure – Check the motor space heaters –E01 and –
F02 E02 for short circuits
Common - 230V Auxiliary Systems AC Failure – Check the equipment for short circuits
F04/-F05/-F06
Common - 24VDC Control voltage failure –F11/- Check the appertaining equipment for
F12/-F13 short circuits
Check the appertaining 24VDC equipment
for overload
Common - 24VDC Valve supply voltage failure Check the appertaining equipment for
–F14 short circuits
Check the appertaining 24VDC equipment
for overload
Intake - Motor no.1 overload Check the equipment for short circuits
Check the electric motor
Intake - Motor no.2 overload Check the equipment for short circuits
Check the electric motor
Intake - Motor no.1 not in AUTO mode Check position of selector switch –S11
Intake - Motor no.2 not in AUTO mode Check position of selector switch –S12
Intake - Gate not in REMOTE mode Check position of selector switch –S13
Intake - Oil level low Check the hydraulic system for leakages
Refill oil
Intake - Oil level too low Check the hydraulic system for leakages
Refill oil
Intake - Pump pressure low – motor pump Check if the hydraulic system for rupture
no.1 of a pipe
Check if the hydraulic system for rupture
of a hydraulic hose
Check function of pressure relief valve
AA301 (incl. pilot operation valve AA101-
Y01)
Intake - Pump pressure low – motor pump Check if the hydraulic system for rupture
no.2 of a pipe
Check if the hydraulic system for rupture
of a hydraulic hose
Check function of pressure relief valve
AA301 (incl. pilot operation valve AA101-
Y01)
Intake - Operation pressure low – pipe rupture Check if the hydraulic system for rupture
of a pipe
Check if the hydraulic system for rupture
of a hydraulic hose
Intake - Level Sensor after Trash rack 1 Failure Check the pressure sensor
Check the cabling of pressure sensor
Replace the pressure sensor
Intake - Level Sensor after Trashrack 2 Failure Check the pressure sensor
Check the cabling of pressure sensor
Replace the pressure sensor
Intake – Crack open limit switch failure Check the limit switch CG002-S01
All alarms are indicated at the touch screen panel –A02 on the local control cubicle with clear text
provided with time stamp.
Weir - Motor no.2 overload Check the equipment for short circuits
Check the electric motor
Weir - Motor no.1 not in AUTO mode Check position of selector switch –S21
Weir - Motor no.2 not in AUTO mode Check position of selector switch –S22
Weir - 230V Auxiliary Systems AC Failure –F03 Check the motor space heaters –E01 and –
E02 for short circuits
Weir - 230V RIO Auxiliary Systems AC Failure – Check the equipment for short circuits
F07
Weir - 24VDC RIO supply voltage failure –F15 Check the appertaining equipment for
short circuits
Check the appertaining 24VDC equipment
for overload
Weir RIO - 24VDC Control voltage failure – Check the appertaining equipment for
F111/-F112/-F113 short circuits
Check the appertaining 24VDC equipment
for overload
Weir RIO - 230V Auxiliary Systems AC Failure – Check the equipment for short circuits
F101
Weir - Oil Level Low Check the hydraulic system for leakages
Refill oil
Weir - Oil Level Too Low Check the hydraulic system for leakages
Refill oil
Weir – Return line filter no.1 clogged Replace the filter element
Weir – Return line filter no.2 clogged Replace the filter element
Weir - Pump pressure low – motor pump no.1 Check if the hydraulic system for rupture
of a pipe
Check if the hydraulic system for rupture
of a hydraulic hose
Check function of pressure relief valve
AA301 (incl. pilot operation valve AA101-
Y01)
Weir - Pump pressure low – motor pump no.2 Check if the hydraulic system for rupture
of a pipe
Check if the hydraulic system for rupture
of a hydraulic hose
Check function of pressure relief valve
AA301 (incl. pilot operation valve AA101-
Y01)
Radial Gate 1 - 24VDC Valve supply voltage Check the appertaining equipment for
failure –F114 short circuits
Check the appertaining 24VDC equipment
for overload
Radial Gate 1 - Operation pressure low – pipe Check if the hydraulic system for rupture
rupture of a pipe
Check if the hydraulic system for rupture
of a hydraulic hose
Radial Gate 1 - Opening pressure high Check if the gate is stuck physically
Check if one or more shut off valve is
closed by error
Radial Gate 1 - Closing pressure low Check if the gate is stuck physically
Check if one or more shut off valve is
closed by error
Flap Gate 1 - 24VDC Valve supply voltage Check the appertaining equipment for
failure –F114 short circuits
Check the appertaining 24VDC equipment
for overload
Flap Gate 1 - Operation pressure low – pipe Check if the hydraulic system for rupture
rupture of a pipe
Check if the hydraulic system for rupture
of a hydraulic hose
Flap Gate 1 - Closing pressure high Check if the gate is stuck physically
Check if one or more shut off valve is
closed by error
Flap Gate 1 - Opening pressure low Check if the gate is stuck physically
Check if one or more shut off valve is
closed by error
Radial Gate 2 - 24VDC Valve supply voltage Check the appertaining equipment for
failure –F115 short circuits
Check the appertaining 24VDC equipment
for overload
Radial Gate 2 - Operation pressure low – pipe Check if the hydraulic system for rupture
rupture of a pipe
Check if the hydraulic system for rupture
of a hydraulic hose
Radial Gate 2 - Opening pressure high Check if the gate is stuck physically
Check if one or more shut off valve is
closed by error
Radial Gate 2 - Closing pressure low Check if the gate is stuck physically
Check if one or more shut off valve is
closed by error
Flap Gate 2 - Operation pressure low – pipe Check if the hydraulic system for rupture
rupture of a pipe
Check if the hydraulic system for rupture
of a hydraulic hose
Flap Gate 2 - Closing pressure high Check if the gate is stuck physically
Check if one or more shut off valve is
closed by error
Flap Gate 2 - Opening pressure low Check if the gate is stuck physically
Check if one or more shut off valve is
closed by error
Possible Malfunction related to Trash Rack Cleaning Machine are given below:
fault profinet connection [3] The Profinet connection is Check the radio
module and the rest of the
broken up
Profinet lines
voltage control 400VAC [8] El. provisions mistake, phase Find mistake, acknowledge
after troubleshooting
cancelled, security
circuit breaker control Control fuse fail Find mistake, acknowledge
after troubleshooting
voltage [9]
emergency stop [10] Emergency off relay deleted. Unlock possible activation of
Isthe case when:One of the the emergency off switch, set
emergency off switches is back with the blue button in
activated, Tensionon the cabinet or on the switch
gear cabinet
emergency pull cord [13] Additional information f. Rip cord line unlocked using
emergency off: rip cord in buttons on the casing. See
mistake emergency off [0010]
drive direction right released
emergency stop control unit Additional information f. Unlocked with turning. See
mistake emergency off [0010]
[15] emergency off: emergency off
Check to see if the control
control pendant active
pendant is pulled in.
circuit breaker hydraulic Motor overloaded or defect Check pump, turn back on
pump [33]
hydraulic pressure min [34] Pump defect, leakage, hose Check pump (pressurization),
check line
Break
circuit breaker fan [35] Motor overloaded or defect Check exhauster, turn back
on
warning hydraulic filter Drop pressure too big over Change filter cartridge
clogged [169]
Filter
hydraulic oil level fault [41] Hydraulic switches off due to Check system for leakage,
refill oil
oil deficiency
hydraulic oil temp. max [43] Oil temperature > approx. Check cooler, clean, let cool
70°C, Cooler could be defect
or contaminated
positioning fault drive [58] The positioning is failed Check the chassis, rails and
linear measuring system
linear encoder driving fault Travel path sensors report Control if the read head calls
[59] implausible value or SPS is set correctly over the code
rail. Possible service call.
reports encoder mistake or
mistake of the SPS entry.
time fault driving [60] time fault driving [60] Check travel drive using
manual and local automatic
operation, restart automatic
cycle and observe
time fault leak oil control [82] The leakage oil movement Check arm movement using
manual and local automatic
takes too long. Defect in the
operation, start automatic
arm travel (valve, etc.) cycle and observe
angle measuring system main Angle encoder reports Can only be tested through
arm fault [88] implausible value or SPS experimental exchanges of
the
reports encoder mistake or
encoder. Possible service call
mistake of the SPS entry
angle measuring system flex Angle encoder reports Can only be tested through
arm fault [104] implausible value or SPS experimental exchanges of
the
reports encoder mistake or
encoder. Possible service call
mistake of the SPS entry
analogue output proportional SPS reports mistake on the Check output signal, cable
and
valves arm [107] analog output. Output defect,
connected FU-entry
not correctly switched, short
or open
3 Cleaninfaults Pos 1 [120] This cleaning of panel 1 is Find the cause locally (too
broken up 3 times through big/heavy/unwieldy cleaning
debris on the rake). Remove
time exceedances of the
cleaning debris manually or
cleaning cycle. The panel will with another method. Check
not drive for further cleaning the panel with local
automatic operation of free
procedures. clearance.
Possible malfunction related to Desilter Inlet, Outlet and Flushing Gates are given below:
Desilter Downstream
mcb hydraulic pump DES [88] Motor overloaded or defect Check components, turn back
on
Motor overload switch defect
mcb backup pump DES [89] Motor overloaded or defect Check components, turn back
on
Motor overload switch defect
system pressure min Desilter Cable break, hydraulic pump Check system for cable
[94]
or valve defect break/leakage, check valve
with manual operation
24V circuit breaker fall [104] Circuit breaker fall Search mistake, turn back on
after troubleshooting and
acknowledge
emergency stop [106] Emergency power-off button Assure that the cause of the
pressed emergency power-off has
beeneliminated, release the
emergency power-off button,
acknowledge
Desilter 1 Downstream
position measuring system Analog input reports not Check encoder signal, entry
card.
outlet gate 1 fault [120] plausible value, senor or
analog input defect.
both end switches outlet gate Limit switch for the end Check limit switch, repair, set,
1[121]
position open/close defect, remove foreign material or
replace it.
manipulated or occupied
through a foreign material.
overload lift outlet gate 1 Pressure switch reports Check gate movement in
[122] overload lifting. Possible manual operation, possible
inhibited floating debris,
inhibited floating debris.
check possible valve or
pressure switch, set, replace.
overload lower outlet gate 1 Pressure switch reports Check gate movement in
manual operation, possible
[123] overload lowering. Possible
inhibited floating debris,
inhibited floating debris. check possible valve or
pressure switch, set, replace.
time overflow lift outlet gate Lift gate (automatic Check gate movement in
1[124] operation)does not function, manual operation, possible
gate isblocked mechanically, inhibited floating debris,
valvesnags or defect. Limit possible valve or limit switch
switchoccupied or defect.
check, set, replace.
time overflow lower outlet Lower gate (automatic Check gate movement in
manual operation, possible
gate 1 [125] operation) does not function,
inhibited floating debris,
gate blocked mechanically, possible valve or limit switch
valve snags or defect. check, set, replace.
both end switches flushing Limit switch for the end Check limit switch, repair, set,
gate 1 [113] position open/close defect, remove foreign material or
replace.
manipulated or occupied with
aforeign material.
overload lift flushing gate 1 Pressure switch reports Check gate movement in
overload lifting. Possible manual operation, possible
[114]
inhibited floating debris,
inhibited floating debris
check possible valve or
pressure switch, set, replace
overload lower flushing gate 1 Pressure switch reports Check gate movement in
manual operation, possible
[115] overload lowering. Possible
inhibited floating debris,
inhibited floating debris check possible valve or
pressure switch, set, replace.
time overflow lift flushing Gate lowering (automatic Check gate movement in
gate1 [116] manual operation, possible
operation) does not function,
inhibited floating debris,
gate blocked mechanically, check possible valve or limit
valve snags or defect, limit switch, set, replace.
switch occupied or defect.
Desilter 2 Downstream
position measuring system Analog input reports not Check encoder signal, entry
card
outlet gate 2 fault [136] plausible value, sensor or
analog input defect
both end switches outlet gate Limit switch for the end Check limit switch, repair, set,
2[137]
position open/close defect, remove foreign material or
replace.
manipulated or occupied by a
foreign material.
overload lift outlet gate 2 Lift gate (automatic Check gate movement in
[138] operation)does not function, manual operation, possible
gate blockedmechanically, inhibited floating material,
valve snags ordefect, limit check possible valve or
switch occupied ordefect.
limit switch, set, replace.
overload lower outlet gate 2 Pressure switch reports Check gate movement in
manual operation, possible
[139] overload lowering. Possible
inhibited floating material,
inhibited floating material. check possible valve or
pressure switch, set, replace.
time overflow lift outlet gate Lift gate (automatic Check gate movement in
2[140] operation)does not function, manual operation, possible
gate blockedmechanically, inhibited floating material,
valve snags ordefect, limit check possible valve or
switch occupied ordefect.
limit switch, set, replace.
time overflow lower outlet Lower gate (automatic Check gate movement in
manual operation, possible
gate 2 [141] operation) does not function,
inhibited floating material,
gate blocked mechanically, check possible valve or
valve snags or defect, limit limit switch, set, replace.
switch occupied or defect.
both end switches flushing Limit switch for the end Check limit switch repair, set,
gate 2 [129] position open/close defect, remove foreign material or
manipulated or occupied by a replace.
foreign material.
overload lift flushing gate 2 Pressure switch reports Check gate movement in
manual operation, possible
[130] overload lifting. Possible
inhibited floating material,
inhibited floating material. check possible valve or
pressure switch, set, replace.
overload lower flushing gate Limit switch reports overload Check gate movement in
2[131] manual operation, possible
lowering. Possible inhibited
inhibited floating material,
floating material. check possible valve or
limit switch, set, replace.
time overflow lift flushing Lift gate (automatic Check gate movement in
gate2 [132] operation)does not function, manual operation, possible
gate blockedmechanically, inhibited floating material,
valve snags ordefect, limit check possible valve or
switch occupied ordefect.
limit switch, set, replace.
time overflow lower flushing Lower gate (automatic Check gate movement in
manual operation, possible
gate 2 [133] operation) does not function,
inhibited floating material,
gate blocked mechanically, check possible valve or
valve snags or defect, limit limit switch, set, replace.
switch occupied or defect.
Desilter 3 Downstream
position measuring system Analog input reports not Check encoder signal, entry
card.
outlet gate 3 fault [152] plausible value, sensor or
analog input defect.
both end switches outlet gate Limit switch for the end Check limit switch repair, set,
3[153]
position open/close defect, remove foreign material or
replace.
manipulated or occupied by a
foreign material.
overload lift outlet gate 3 Lift gate (automatic Check gate movement in
[154] operation)does not function, manual operation, possible
gate blockedmechanically, inhibited floating material,
valve snags ordefect, limit check possible valve or
switch occupied ordefect.
limit switch, set, replace.
overload lower outlet gate 3 Pressure switch reports Check gate movement in
manual operation, possible
[155] overload lowering. possible
inhibited floating debris,
inhibited floating debris. check possible valve or
pressure switch, set, replace.
time overflow lift outlet gate Lift gate (automatic Check gate movement in
3[156] operation)does not function, manual operation, possible
gate blockedmechanically, inhibited floating debris,
valve snags ordefect, limit check possible valve or limit
switch occupied ordefect. switch, set, replace.
time overflow lower outlet Lower gate (automatic Check gate movement in
manual operation, possible
gate 3 [157] operation) does not function,
inhibited floating debris,
gate blocked mechanically, check possible valve or limit
valve snags or defect, limit switch, set, replace.
both end switches flushing Limit switch for the end Limit switch check, repair,
set,foreign material removes
gate 3 [145] position open/ close defect,
or replace.
manipulated or occupied with
foreign material.
overload lift flushing gate 3 Pressure switch reports Check gate movement in
manual operation, possible
[146] overload lifting. possible
inhibited floating debris,
inhibited floating debris. check possible valve or
pressure switch, set, replace.
overload lower flushing gate Pressure switch reports Check gate movement in
3[147] manual operation, possible
overload lowering. possible
inhibited floating debris,
inhibited floating debris. check possible valve or
pressure switch, set, replace.
time overflow lift flushing Lower gate (automatic Check gate movement in
gate3 [148] manual operation, possible
operation) does not function,
inhibited floating debris,
gate blocked mechanically, check possible valve or limit
valve snags or defect, limit switch, set, replace.
switch occupied or defect.
oil filter glogged DES [186] Oil filter contaminated Change oil filter
Desilter Upstream
mcb hydraulic pump DES Inlet Motor overloaded or defect Check components, turn back
on
[8] Motor overload switch defect
mcb backup pump DES Inlet Motor overload or defect Check components, turn back
on
[9] Motor overload switch defect
mcb oil cooler DES Inlet [10] Motor overload or defect Check components, turn back
on
Motor overload switch defect
oil level min fault [12] Hydraulic turns of because of Check system for leakage
check, refill oil.
lack of oil
system pressure min [14] Cable break, hydraulic pump Check system for cable
or valve defect break/leakage, check valves
with manual operation.
oil temp max fault [15] Hydraulic turns off because Let it cool down
oiltemperature is > approx.
70°C
24V circuit breaker fall [24] Circuit breaker fall Find malfunction, after
troubleshooting turn back on
and acknowledge
Desilter 1 Upstream
time overflow raise inlet gate Lift gate (automatic Check gate movement in
1[40] operation)does not function, manual operation, possible
gate blockedmechanically, inhibited floating debris,
valve snags ordefect, limit check possible valve or limit
switch occupied ordefect. switch, set, replace.
time overflow lower inlet Lower gate (automatic Check gate movement in
gate1 [41] manual operation, possible
operation) does not function,
inhibited floating debris,
gate blocked mechanically, check possible valve or limit
switch, set, replace.
valve snags or defect, limit
switch occupied or defect.
both end switches raise / Limit switch for the end Limit switch check, repair,
lower1 [42] set,remove foreign material
position open/ close defect,
or replace.
manipulated or occupied with
foreign material.
overload raise inlet gate 1 [43] Limit switch for the end Limit switch check, repair,
set,remove foreign material
position open/ close defect,
or replace.
manipulated or occupied with
foreign material.
overload raise inlet gate 1 [43] Pressure switch reports Check gate movement in
manual operation, possible
overload lifting. possible
inhibited floating debris,
inhibited floating debris check possible valve or
pressure switch, set, replace.
overload lower inlet gate 1 Pressure switch reports Check gate movement in
manual operation, possible
[44] overload lowering. possible
inhibited floating debris,
inhibited floating debris check possible valve or
pressure switch, set, replace.
fault position measuring Analog input reports not Check encoder signal, entry
card
system inlet gate 1 [47] plausible value, sensor or
analog input defect
Desilter 2 Upstream
time overflow raise inlet gate Lift gate (automatic Check gate movement in
2[56] operation)does not function, manual operation, possible
gate blockedmechanically, inhibited floating debris,
valve snags ordefect, limit check possible valve or limit
switch occupied ordefect. switch, set, replace.
time overflow lower inlet Lower gate (automatic Check gate movement in
gate2 [57] manual operation, possible
operation) does not function,
inhibited floating debris,
gate blocked mechanically, check possible valve or limit
valve snags or defect, limit switch, set, replace.
switch occupied or defect.
both end switches raise / Limit switch for the end Check limit switch, repair, set,
lower2 [58]
position open/ close defect, remove foreign material or
replace.
manipulated or occupied with
foreign material.
overload raise inlet gate 2 Pressure switch reports Check gate movement in
[59] manual operation, possible
overload lifting. possible
inhibited floating debris,
inhibited floating debris check possible valve or
pressure switch, set, replace.
overload lower inlet gate 2 Pressure switch reports Check gate movement in
manual operation, possible
[60] overload lowering. possible
inhibited floating debris,
inhibited floating debris check possible valve or
pressure switch, set, replace.
fault position measuring Analog input reports not Check encoder signal, entry
card
system inlet gate 2 [63] plausible value, sensor or
analog input defect
Desilter 3 Upstream
time overflow lower inlet Lower gate (automatic Check gate movement in
gate3 [73] manual operation, possible
operation) does not function,
inhibited floating debris,
gate blocked mechanically, check possible valve or limit
valve snags or defect, limit switch, set, replace.
both end switches raise / Limit switch for the end Check limit switch, repair, set,
lower3 [74]
position open/ close defect, foreign material removes or
replace.
manipulated or occupied with
foreign material.
overload raise inlet gate 3 Pressure switch reports Check gate movement in
[75] manual operation, possible
overload lifting. possible
inhibited floating debris,
inhibited floating debris check possible valve or
pressure switch, set, replace.
overload lower inlet gate 3 Pressure switch reports Check gate movement in
manual operation, possible
[76] overload lowering. possible
inhibited floating debris,
inhibited floating debris check possible valve or
pressure switch, set, replace.
fault position measuring Analog input reports not Check encoder signal, entry
card
system inlet gate 3 [79] plausible value, sensor or
analog input defect
The possible malfunctions related to Screen Cleaning Machine and its remedial measures are
shown below:
mcb hydraulic pump SCM [8] Motor overloaded or defect Check components, turn back
on
Motor overload switch defect
mcb backup pump SCM [9] Motor overloaded or defect Check components, turn back
on
Motor overload switch defect
mcb oil cooler SCM [10] Motor overloaded or defect Check components, turn back
on
Motor overload switch defect
oil level min fault [12] Hydraulic turns off due to lack Check system for leakage,
refill oil
of oil
system pressure min SCM [14] Hydraulic turns off due to lack Check system for leakage,
refill oil
of oil
system pressure min SCM [14] Hydraulic turns off due to lack Check system for leakage,
refill oil
of oil
system pressure min SCM [14] Line break, hydraulic pump or Check system for line break /
leakage, valve through
valve defect
manual operation
oil temp max fault [15] Hydraulic turns off due to oil Let cool
temperature > approx. 70°C
24V circuit breaker fall [24] Control fuse fall Find mistake, turn back on
after troubleshooting and
acknowledge
emergency stop [26] Emergency shutoff button Be sure that the reason for
the
pressed
emergency off has been
eliminated, unlock emergency
shutoff button, acknowledge
time overflow raise rake 1 Lift lever (automatic Check lever movements in
[40] operation)does not function, the manual operation,
leverblocked mechanically, possible inhibited cleaning
valvesnags or defect, limit debris or remove, possible
switchoccupied or defect valve or limit switch, set,
replace
time overflow lower rake 1 Lower lever (automatic Check lever movements in
themanual operation,
[41] operation) does not function,
possible inhibited cleaning
lever blocked mechanically, debris or remove, possible
valve snags or defect, limit valve or limit switch, set,
replace
switch occupied or defect
both endswitches raise / Gear cam switch for the end Check gear cam switch, repair
lower1 [42] or replace
position up/down defect
time overflow rake swivel in 1 Lever close (automatic Check lever movements in
themanual operation,
[44] operation) does not function,
possible inhibited cleaning
lever blocked mechanically, debris or remove, possible
valve snags or defect, limit valve or limit switch, set,
replace
switch occupied or defect
time overflow rake swivel out Lever open (automatic Check lever movements in
themanual operation,
1 [45] operation) does not function,
possible inhibited cleaning
lever blocked mechanically, debris or remove, possible
valve snags or defect, limit valve or limit switch, set,
replace
switch occupied or defect
both end switches swivel in / Limit switch for the end Check limit switch, repair, set,
out 1 [46] positions open/close defect, remove or replace foreign
material.
manipulated or occupied by
foreign material
x times slake line during Cleaning lever could not be Check lever in the manual
lower1 [32] operation or other large
lowered 3 times in a row,
parts, free up, remove, rope
slackrope switch defect or
and slack rope switch
manipulated
slake line during raise (abort) Rope ripped, slack rope Check rope and slack rope
1[33] switchdefect or manipulated. switch
x times overload 1 [34] Cleaning cycle interrupted 3 Free up lever in the manual
times in a row due to operation, remove other
pressureswitch overload, large parts
lever blockedmechanically
overload with swiveled out Overload occurs by open Free up lever in the manual
lever, lever blocked
rake 1 [35] operation, remove other
mechanically
large parts
time overflow start hydraulic The hydraulic takes too long Can only appear with another
1[38] toturn on
mistake of the hydraulic
time overflow leak oil control The drive in the ground Check lever movements in
themanual operation,
1 [39] position (automatic
possible inhibited cleaning
operation)does not function,
debris or remove, possible
leverblocked mechanically,
valve or limit switch, set,
valvesnags or defect, limit
replace
switchoccupied or defect
time overflow lower rake 2 Lower lever (automatic Check lever movements in
themanual operation,
[57] operation) does not function,
possible inhibited cleaning
lever blocked mechanically, debris or remove, possible
valve snags or defect, limit valve or limit switch, set,
replace
switch occupied or defect
both end switches raise / Gear cam switch for the end Check gear cam switch, repair
lower2 [58] or replace
position up/down defect
time overflow rake swivel in 2 Lever close (automatic Check lever movements in
themanual operation,
[60] operation) does not function,
possible inhibited cleaning
lever blocked mechanically, debris or remove, possible
valve snags or defect, limit valve or limit switch, set,
replace
switch occupied or defect
time overflow rake swivel out Lever open (automatic Check lever movements in
themanual operation,
2 [61] operation) does not function,
possible inhibited cleaning
lever blocked mechanically, debris or remove, possible
valve snags or defect, limit valve or limit switch, set,
replace
switch occupied or defect
both end switches swivel in / Limit switch for the end Check limit switch, repair, set,
out 2 [62] positions open/close defect, remove or replace foreign
material.
manipulated or occupied by
foreign material
x times slake line during Cleaning lever could not be Check lever in the manual
lower2 [48] operation or other large
lowered 3 times in a row,
parts, free up, remove, rope
slackrope switch defect or
and slack rope switch
manipulated
slake line during raise (abort) Rope ripped, slack rope Check rope and slack rope
2[49] switchdefect or manipulated. switch
x times overload 2 [50] Cleaning cycle interrupted 3 Free up lever in the manual
times in a row due to operation, remove other
pressureswitch overload, large parts
lever blockedmechanically
overload without swiveled Overload occurs by open Free up lever in the manual
lever,lever blocked
rake 2 [51] operation, remove other
mechanically
large parts
time overflow start hydraulic The hydraulic takes too long Can only appear with another
2[54] toturn on
mistake of the hydraulic
time overflow leak oil control The drive in the ground Check lever movements in
themanual operation,
2 [55] position (automatic
possible inhibited cleaning
operation)does not function,
debris or remove, possible
leverblocked mechanically,
valve or limit switch, set,
valvesnags or defect, limit
replace
switchoccupied or defect
time overflow raise rake 3 Lift lever (automatic Check lever movements in
operation)does not function, themanual operation,
[72]
leverblocked mechanically, possible inhibited cleaning
valvesnags or defect, limit debris or remove, possible
switchoccupied or defect valve or limit switch, set,
replace
time overflow lower rake 3 Lower lever (automatic Check lever movements in
themanual operation,
[73] operation) does not function,
possible inhibited cleaning
lever blocked mechanically, debris or remove, possible
valve snags or defect, limit valve or limit switch, set,
replace
switch occupied or defect
both end switches raise / Gear cam switch for the end Check gear cam switch, repair
lower3 [74] or replace
position up/down defect
time overflow rake swivel in 3 Lever close (automatic Check lever movements in
the
[76] operation) does not function,
manual operation, possible
lever blocked mechanically,
inhibited cleaning debris or
valve snags or defect, limit remove, possible valve or
switch occupied or defect limit switch, set, replace
time overflow rake swivel out Lever open (automatic Check lever movements in
the
3 [77] operation) does not function,
manual operation, possible
lever blocked mechanically,
inhibited cleaning debris or
valve snags or defect, limit remove, possible valve or
switch occupied or defect limit switch, set, replace
both end switches swivel in / Limit switch for the end Check limit switch, repair, set,
out 3 [78] positions open/close defect, remove or replace foreign
material.
manipulated or occupied by
foreign material
x times slake line during Cleaning lever could not be Check lever in the manual
lower3 [64] operation or other large
lowered 3 times in a row,
parts, free up, remove, rope
slack
and slack rope switch
rope switch defect or
manipulated
slake line during raise (abort) Rope ripped, slack rope Check rope and slack rope
3[65] switchdefect or manipulated. switch
x times overload 3 [66] Cleaning cycle interrupted 3 Free up lever in the manual
times in a row due to operation, remove other
pressure large parts
switch overload, lever
blocked
mechanically
overload with swiveled out Overload occurs by open Free up lever in the manual
lever,lever blocked
rake 3 [67] operation, remove other
mechanically
large parts
time overflow start hydraulic The hydraulic takes too long Can only appear with another
3[70] toturn on
mistake of the hydraulic
time overflow leak oil control The drive in the ground Check lever movements in
the
3 [71] Position (automatic
operation)does not function, manual operation, possible
leverblocked mechanically, inhibited cleaning debris or
valvesnags or defect, limit remove, possible valve or
switchoccupied or defect limit switch, set, replace
Warnings
RCD safety switch fall [168] FI protective switch fall Find mistake and turn back on
possible ground connection
or overload
oil level min warning [169] Oil lever too low, possible Refill oil, Check system for
sealing
Leakage
oil filter glogged SCM [170] Oil filter contaminated Change oil filter
MAINTENANCE MANUAL
ANNEXURE M 2
These circuits are simple and extremely rugged in design as they consist of only passive
components. In case the charger does not deliver the rated voltage and or current it is required
to check the circuit as per the circuit diagram.
PLEASE ENSURE TO DISCONNECT THE BATTERIES AND LAOD WHILE CARRYING OUT FAULT-
FINDING PROCEDURE.
ONLY IF THE PERSONNEL IS CONVERSANT WITH THE SYSTEM SHOULD THE PROCEDURE BE
CONDUCTED WITH BATTERY AND LOAD CONDUCTED AS THIS MAY RESULT INTO SERIOUS
DAMAGE TO SELF, EQUIPMENT CONNECTED AS WELL AS CHARGER.
Testing procedure of the charger are given below:
1. Physical Testing.
2. Electrical Testing.
Physical Testing of the charger has to be carried to ensure that all the components mounted in
the cubicle as well as on the door of the cubicle are in the healthy condition. Following points
must be followed for the physical check:
1. Turn off the incoming supply i.e. 3 Ф, 415 V, 50 Hz. And remove battery connection +ve, -
ve and 80 % from the terminals.
Caution:
Physical testing of the charger components should not be done under live supply condition. It is
dangerous and accident prone.
2. Check all the connection for any loose connections this can be done by pulling gently
each wire and after checking this tighten each connection.
3. Check that all the components mounted in the charger cubicle, on the mounting plate is
firmly fixed using proper screw / Nuts and bolts. This was done at the factory but after
transportation, it becomes essential to check their tightness.
4. Each component of rectifier mounted on the top of the mounting plate can be verified
using multimeter.
As shown in the drawing, rectifier bridge consists of six thyristors and one freewheeling diode:
Checking Thyristor using multimeter
a) Anode.
b) Cathode.
c) Gate.
Resistance shown between 1 and 2 = Mega ohms.
Resistance shown between 2 and 3 = 20 to 50 ohms.
This test can be conducted by removing gate wires from the connection and ensuring that
component under test has no electrical connection. Checking diode using multimeter: (Diodes to
be isolated from bridge for this checking
a) Anode.
b) Cathode.
Multimeter used must have diode-checking mode
When positive probe of multimeter is kept on heat sink and negative on cathode:
Multimeter shows = 0.545 to 0.745 => diode is healthy else diode is failed.
Multimeter shows = 0.000 => diode is faulty.
When positive probe of multimeter is kept on cathode and negative on heat sink:
Multimeter shows = open indication => diode is unhealthy.
Multimeter shows = 0.000 => diode is faulty.
5. Putting multimeter in continuity mode can test continuity of fuses. This can be done by
removing fuse sockets and putting probes of multimeter across the fuse link and testing
continuity – if buzzing sound is heard from the multimeter than fuse is healthy else fuse
must be rated with similar rating and make.
6. DC / DC Converter is used for power supply of the protection module and it cannot be
tested in cold condition- test to check healthiness of this module will be discussed later.
7. Electronic cards cannot be tested under cold condition. Details for the testing of
electronic card is discussed later.
8. All the fuses can be tested as mentioned point 7.
9. For all the indicating meters, zeroing of the meter is very necessary in cold condition,
meters must indicate zero if not than meters must be calibrated.
10. Turning its knob and checking respective contacts can check all the control switches on
the front doors.
11. MCBs and input isolation switch also can be tested in similar way by checking continuity.
After performing above-mentioned steps, one can ensure that charger is physically healthy and
can be powered up.
Follow the Flow chart given below, all major and important checks have been listed. This
will help in troubleshooting as well as providing vital feedback to the service department
of the manufacturer in case it has to be referred to them.
2.2.1 Automatic Voltage Regulator (AVR): (ES-FWFCAVR-5106) (E2 & E3)
Check the card for loose connections, dry solders and burnt components.
Check Transformer Primary: 415 V, Secondary: 16-0-16 V power supply and16 V synchronizing
voltages at input terminals. Also,check availability of reference voltage at terminals.
Check terminal voltages as per the table given below.
28 28 -VE FEEDBACK-
34 34 -
35 35 -
TP103
TP203
TP303
TP403
TP503
TP603
TP604 B’ Phase final formed pulse
TP5 -
TP6 -
Check the card for loose connections, dry solders and burnt components.
Check terminal voltages as per the table given below:
2.2.3 Fuse failure detection card (ES-PROTFFD-4106) (E4, E5, E6, E9 & E10)
Check the terminal voltages on the card E4 as per the table given below:
P4 7,8 NA System
Check the terminal voltages on card E5 as per the table given below:
Check the terminal voltages on card E6 as per the table given below:
Check the terminal voltages on card E9 as per the table given below:
P3 5,6 NA System
P4 7,8 NA System
Check the terminal voltages on card E10 as per the table given below:
P4 7,8 NA System
Check the card for loose connections, dry solders and burnt components.
Check the terminal voltages as per the table given below:
1 1
2 2
3 3 - 0.0 V
Check the test point voltages as per the details given below:
TP16 GND
MAINTENANCE MANUAL
ANNEXURE M 3
1 Change donator
3 Check scaling
4 Check Wiring
5 Change Module
8 Check hydraulics
Short-term oil flow, then no flow. check function of level switch / automatic
No flow in spite of rotating motor: control. Trace oil leakage and repair. Refill
oil.
level switch “too low” was NOT change pump / motor unit. Repair of pump
switching off the motor and the pump / motor unit by supplier.
was emptying the tank
motor / pump shaft broken
Pump is running but pressure too check function of pressure gauge / switch.
low: Attention: Pressure switch monitors only
the pressure tank pressure, NOT the pump
pressure gauge or pressure switch defect pressure!
pressure relief valve of pump is faulty or check pressure relief valve
wrong adjusted
MAINTENANCE MANUAL
ANNEXURE M4
Pressure oil contents air bubbles: Tighten screw connection of suction pipe
air entering pump suction pipe check if suction pipe is partly blocked
flow resistance in suction pipe too high check oil level “too low” level switch.
suction pipe only partly below oil level Trace oil leakage and repair. Refill
pump shaft seal faulty hydraulic oil.
pump cover not tight renew shaft seal ring. Smooth shaft
surface if necessary.
check O-ring
Oil leakage from pump shaft: replace shaft seal and smooth possible
grooves on shaft
shaft seal damaged
clear drainage line
internal drainage line blocked
replace oil pump
major defect of oil pump
Table 4.4:Noise
MAINTENANCE MANUAL
ANNEXURE M 5
5.3 Process for Seals of Powerhouse, Flap Gate & Downstream Stop log gates
1. Clean seal base surface on stoplog.
2. Countercheck the holes of the clamp bars with the holes of the stoplog.
3. Protect the surface of the stoplog, so that tools, etc. can´t damage the coat of paint.
The rubber seals are supplied with over length on both sides.
4. Cut the sill seal to final length. (See step Cutting the seals)
5. Adjust the sill seal exactly, use the clamp bar as template and start drilling the holes. Use
special rubber drill LENOX SKU 30001_ 1L (Adjustable pilot bit) + SKU 30010_10L (Drill)
After a connection is glued, no further cutting or bending of the rubber gaskets shall be done.
11. After the seals are installed and glued, grind/cut the side seals. The end must be exact in one
line with the sill seal.
Alignment must be done acc. sketch above. If necessary, use grease Molykote 55M to ease the
adjustment.
Note:The rubber seals are supplied with over length on both sides.
Never cut through the Teflon coated rubber!! Check length of PTFE. After a connection is glued, no
further cutting or bending of the rubber gaskets shall be done.
4. Cut the sill seal to final length. (See step Cutting the seals)
5. Adjust the sill seal exactly, use the clamp bar as template and start drilling the holes.
Note: Use special rubber drill LENOX SKU 30001_ 1L (Adjustable pilot bit) + SKU 30010_10L (Drill)
6. The screws can be tightened. (20-30Nm)
Note: Seal every clamp bolt with Terostat MS 935.
(~150 screws can be sealed with 310ml)
7. Cut the over length of the lintel seal on both sides
8. Cut one over length (next to lintel seal) of the first corner piece
9. Adjust these two pieces exactly
10. Cut one over length (next to lintel seal) of the second corner piece to final length
11. Cut the remaining over length (next to side seal) of both corner pieces
12. Cut one over length of the side seals (next to corner piece)
13. Cut the second over length of the side seals (next to sill seal), but not to final length.
Approx.5mm beyond/above the sill seal.
14. Glue the connection of the rubber gaskets. (See step Bonding the rubber gaskets
15. Glue the connection between the side seals and the sill seal. (See step Bonding the rubber
gaskets)
16. Adjust the seals exactly, use the clamp bars as template and start drilling the holes.
Note: Use special rubber drill LENOX SKU 30001_ 1L (Adjustable pilot bit) + SKU 30010_10L (Drill)
17. Tighten screws as described in 6.
18. After the seals are installed and glued, grind/cut the side seals. The end must be exact in one
line with the sill seal.
Alignment must be done acc. sketch above. If necessary, use grease Molykote 55M to ease the
adjustment.
4.5 Process for Seals of Pressure Door
The rubber seals are supplied with over length on both sides.
After a connection is glued, no further cutting or bending of the rubber gaskets shall be done.
4. Cut one overlength of lower corner pieces. (See step Cutting the seals)
5. Cut one over length (next to first lower corner piece) of the lower seal.
6. Adjust these two pieces exactly and glue the connection of the rubber gaskets. (See step
Bonding the rubber gaskets)
7. Adjust the first lower corner piece and lower seal exactly, use the clamp bar as template and
start drilling the holes.
Note: Use special rubber drillLENOX SKU 30001_ 1L (Adjustable pilot bit) + SKU 30010_10L (Drill)
8. The screws can be tightened. (20-30Nm)
Note: Seal every clamp bolt with Terostat MS 935.
(~150 screws can be sealed with 310ml)
9. Glue the connection of second lower corner piece
10. Cut one overlength (next to lower corner pieces) of side seals.
11. Glue the connection of the rubber gaskets. (See step Bonding the rubber gaskets)
12. Use the clamp bar as template and start drilling the holes.
Note: Use special rubber drill LENOX SKU 30001_ 1L (Adjustable pilot bit) + SKU 30010_10L (Drill)
13. Cut over length of the upper corner pieces to final length and adjust these two pieces exactly
14. Cut the second over length of the side seals (next to upper corner piece)
15. Glue the connection of the rubber gaskets. (See step Bonding the rubber gaskets)
16. Adjust the seals exactly, use the clamp bars as template and start drilling the holes.
Note: Use special rubber drill LENOX SKU 30001_ 1L (Adjustable pilot bit) + SKU 30010_10L (Drill)
17. Tighten screws as described in 8.
18. Cut one overlength of the upper seal and glue the connection to one upper corner piece.
19. Cut second overlength of upper seal and glue the connection so second corner piece
20. Adjust the seals exactly, use the clamp bars as template and start drilling the holes.
21.
Note: Use special rubber drill LENOX SKU 30001_ 1L (Adjustable pilot bit) + SKU 30010_10L (Drill)
22. Alignment must be done acc. sketch above. If necessary, use grease Molykote 55M to ease
the adjustment.
SECTION B:
1 Abnormal noise
1.2 Loose bolts. Locate area and fasten bolts. After fastening of
bolts secure them with a mechanical lock
(welding point) or other means (e.g. Loctite).
2 Heavy Vibration
2.3 Loosening of clamping bolts e.g. Fasten clamps and bolts, mechanical locks.
bearing bracket, bearing body.
2.5 Problems with the bearing gap. Check the nozzles, opening may be unequal.
3.3 Too much oil quantity. Adjust the quantity of oil to specified normal
level. Check if water is in the oil, possibly from
the cooling water system.
4.1 First action. Stop unit and restart the unit while watching
the temperature rise.
4.2 Failure at cooling water supply Check cooling water system, motor-valves,
system. filters, pumps, and water level in sump pit.
4.3 Bearing oil system faulty, extraneous Check bearing for extraneous parts.
parts blocking oil flow.
4.4 Bearing oil dirty and/or water in oil. Check oil, oil cooler and piping. Analyze the oil
quality for water content, suspended particles.
purify the oil.
4.5 Wear of bearing segments. Check runout and clearances of shaft. Check
bearing alignment and gap.
7. Turbine over speed pendulum released mechanically, electrical over speed was not
released.
7.1 Digital governor fault. Check governor functions on the MIPREG and
electrical system, cables, connections, etc.
8.1 Needle and/or seat ring eroded or Stop unit, close spherical valve and replace
damaged. needle and/or seat ring.
9.2 Pressure taps (orifices) clogged. Flushing the pressure taps and the piping.
9.4 Electrical fault at control panel Check the analog input signal from the level
transmitter between terminalbox and control
panel.
Check the internal signal at the control panel.
Replace the damaged instrument in the
control panel
Table 6.1:Possible malfunction and remedial measures for Turbine and auxiliaries
SECTION B:
0. Assembled condition
Oil Leakage Check the oil piping/ hydraulic power unit for
tightness
Oil losses on hydraulic piping lines to Search leakage points and eliminate them
servomotors / HPU
Penstock valve – Control Unit faulty Check function of control unit and replace
faulty valves, etc.
By-pass service valve position feedback faulty Readjust position switch or replace by a new
one
Position switch faulty
Balanced pressure signal not available Readjust pressure switch or replace by a new
one
Differential pressure switch faulty
If the SYNCHROTACT 5 is defective switch it off and replace with new one or put the defective
one after repairing. The Generating Units can be synchronized with the grid in Manual Mode
using the synchrocheck even without SYNCHROTACT. However, the operator has to go to local
panel to synchronize with the grid. The replacement of the SYNCHROTACT is given below:
1. Install new SYNCHROTACT 5 on the Panel.
2. Install the SyncView Software (ABB Sync-View 4.0) in your PC.
3. After installation configure your PC IP address. The IP Address can be in range 192.168.0.X
and where X can be any free IP Address. E.g. 192.168.0.250 or 192.168.0.251…)
Figure 9.6:Showing the settings comparison between the SyncView and Synchrotact
9. Write the setting in the Synchrotact Relay by clicking it on “write” button.
001 Auxiliary voltage on. After the electronics power supply is connected.
011 Data change. This event is displayed when the device changes from
READY or OPERATING status into BLOCKED status, i.e.
following a write or blocking command.
028 Paralleling command End of the paralleling command (in Synchrocheck mode: end
contact opens. of paralleling release).
029 Blocking active. Blocking signal to one of the configurable inputs has
interrupted synchronizing process.
030 Blocking cancelled. Blocking signal has released the synchronizing process
again.
050 ΔU outside tolerance If these messages are not desired, they can be blocked by
band setting the total
061 No stop command within At least one paralleling Automatic stop signal is not
t tot. command has been given. functioning.
However, the expected
Command circuit is broken
Stop signal has not been
generated.
071 Synchronization fault. Collective alarm following i. Check the limit values for
expiry of total paralleling the parameter.
time t tot. ii. With SYN 5202: check
synchro-check parameters
(channel2) and whether
they match channel 1. Loss
or error of phase in one of
both channels.
iii. Read out other events
which may have been
displayed at the same
time. Try to identify the
fault on the basis of the
combination.
11.1 Troubleshooting
Following table 11.1 shows some of the symptoms, possible causes andremedies in case of
abnormal situations.
If the abnormality is of a major nature, the manufacturer should becontacted at the address
given elsewhere in this Manual. When thematter is referred to the manufacturer it shall contain
the following: -
Transformer Rating.
Voltage Rating.
Manufacturers Indent No. / Serial No.
Year of Manufacture.
Date / Time of failure.
Brief description of the problem.
Checks done and their results.
High Winding/ Oil Over voltage Change the circuit voltage or transformer
Temperature connections to avoid over excitation.
Deterioration/ sludge Use filter press to wash off the core and coils.
formation of oil Filter oil to remove sludge
Short circuited core Testing for exciting current and no load loss.
Ifhigh inspect core and repair. See
ElectricalTroubles, below.
When the operation of a protective device does not clearly indicate an internal fault, it is
desirable to conduct the preliminary measurements and analysis before dismantling the
transformer.
Conditions before and after the development of fault should be taken intoconsideration
in arriving at a conclusion.
1 Pressure Relief When the internal pressure increases beyond the presetvalue
Device of PRD it operates. This may also happen if thebreather
connection is choked. Judgment based on theinspection of
other protective relays is essential
2 Differential Relay This relay detects the internal defects by comparing theinput
current and the output current of the transformer. Ifit
functions simultaneously it indicates internal fault.Please note
that this relay sometimes operates due to inrush current when
transformer is energized and this isnot an internal fault.
6 Human Sense Human sense can play an important role in detection offaults.
a. Discoloration or odour of insulating oil. If pieces
ofinsulating materials or copper are found in oil, aninternal
fault can be suspected.
b. Abnormal noise or vibration.
Oil Leak Loose joint Tighten the joint evenly, of the leak does not
stop, renew the gasket.
Valves can’t be Gland packing notfitted Renew the gland packing and adjust
operated correctly. glandpacking nuts evenly.
11.5 Pumps
Pump Motor Impeller binding Remove the pump and investigate the
over heated problem
Pump motor Impeller damaged Remove pump and investigate the reason
vibration
Motor bearings worn Remove pump and investigate the reason
Table 11.5:Pumps
Rapid Alarm Air or inert gas Major leak due to Fracture of tank,
operates mechanical fault pipe, or Buchholz
and relaycasing or
repeats faulty
after oilcirculating
releasing pump.
gas
O2 Oxygen
N2 Nitrogen
CO Carbon Monoxide
H2 Hydrogen
CH4 Methane
C2H2 Acetylene
C2H4 Ethylene
C2H6 Ethane
C3H6 Propylene
C3H8 Propane
Nominal value of dissolved Ley Concentration limits in oil of Power Transformer in service (parts
per Million-ppm) is shown in table 11.12.
Note:
A sudden increase in key gases and the rate of gas generation are more important in evaluating
a transformer/Reactor than the amount of gas.
Conditions TDCG level or TDCG Sampling intervals and operating actions for
highest Generation Gas Generation Rates
individual gas Rates
(ppm/day) Sampling Continue normal operation
Interval
>30 Monthly
H2, CH4, C2H6, C2H4 andC2H2 High energy Metal fusion, (poorcontacts
present in largeamounts. If discharges(arcing). in tap changer orlead
C2H2 is beinggenerated, it connections).Weakened
indicatescontinuance of insulation, fromageing and
arcing. COwill be present if electricalstress. Carbonized
paper isbeing heated. oil.Paper over
heating/destruction if it is in
the arcpath.
H2, CO, CH4, C2H6 and Thermal fault between 300 °C Paper insulationdestroyed.
and 700 °C Oil heavilycarbonized.
C2H4
All the above gases High energy electrical arcing Same as above with metal
andacetylene in 700°C and above. discoloration. Arcing may
largeamounts. have caused a thermalfault.
OPERATION MANUAL
CHAPTER 1
CHAPTER 1: PERMIT TO WORK-LOCK OUT/
TAG OUT
1.1 Introduction
This procedure is intended to be used for the protection of Personnel while servicing or
performing maintenance on equipment / pipelines / valves / control systems. This is a general
procedure that shall be used as the minimum requirements for isolation of equipment, pipelines,
machines, system from all possible sources of hazardous energy and / or material such as
Pressurized water, Compressed Air, any other process fluid / chemical energy /Mechanical energy
or Electrical energy.
This procedure specifies the mandatory requirements for controlling hazardous energy. It also
describes
i) how to achieve and maintain the security of any isolation made and
ii) releasing the equipment from lockout.
This procedure applies whenever an employee is servicing or performing maintenance activities
on machinery or equipment in a manner which requires the removal or bypass of guards or other
safety devices or in a manner that requires the employee to place any part of his or her body into
an area on a machine or piece of equipment where work is actually performed upon the material
being processed (point of operation) or where an associated danger zone exists during a
machine operating cycle, or in a manner that otherwise exposes the employee to electrical,
mechanical, heat, radiation, chemical gas /liquid or steam hazards in the event the machinery or
equipment or system is accidentally re-energized during maintenance or service work. Here are
some examples;
1. Work on electric motors and circuits.
2. Work on Pumps, valves and seals.
3. Work on air conditioning and ventilation equipment.
4. Work on Cooling oil/water system pipe lines/gauges.
5. Work on permanently wired machinery or equipment.
6. Work on workshop and laboratory equipment.
7. Work on compressed air or gas (chemical) lines.
8. Work on hydraulic/pneumatic systems.
9. Work on elevators/hoists, etc.
Caution: All sources of hazardous energy / materials shall be identified prior to initiating any
lockout / tagout.
Equipment specific procedures shall be made unless all of the following elements exist(s)–
i) The machine or equipment has no potential for stored or residual energy or re-accumulation of
stored energy after shutdown that could endanger Personnel.
ii) The machine or equipment has all energy sources that can be readily identified and isolated.
iii) The isolation of the energy source(s) will completely de-energize and deactivate the machine or
equipment.
iv) The machine or equipment is isolated from the energy source and locked out during servicing or
maintenance.
v) The keys to the locks are under the exclusive control of the Permit Acceptor, Permit issuer and
employee performing the work.
vi) The servicing or maintenance does not create hazards for other Personnel.
vii) There has been no incidence involving the unexpected activation or restarting of the machine or
equipment during servicing or maintenance.
The practices that have been identified here are applicable within Dagachhu Hydropower
Corporation Limited only.
1.3 Responsibilities
All Shift In-charge/Team leader and their teams dealing in LOTO shall be responsible for
adhering to the procedure during job involving exposure to hazardous energy / materials.
These include the contractors and their work force if availed.
Plant HOD shall be responsible to ensure that a system is in place to ensure that all concerned
in the plant are trained in LOTO procedure.
Permit Acceptor shall be responsible to ensure that only trained and authorized people are
deployed for the jobs.
Person In-Charge/Shift In-Charge (Permit Issuer) shall be responsible for identifying specific
procedures for isolation/discharging / draining / blinding / venting of equipment before
releasing it for maintenance / inspection in their respective areas.
Maintenance supervisors shall be responsible for arranging / preparing discharge rod/slip
plates / blanks, etc., as per the process requirements and use of Personal protective
equipment while carrying out discharging /blinding / de-blinding activities as per the specific
instructions.
Person In-Charge/Shift In-Charge Electrical Officer/Technician shall be responsible for
electrical lockout and tag out (Danger).
Executing Person or Team Leader shall be responsible for provision of Locks.
Note: Refer Annexure S2 for details of Responsibility Matrix
1.4 Policy
Lockout devices and Tagout devices shall be singularly identified; shall be the only device(s) used
for controlling hazardous energy sources and shall not be used for any other purposes.
No Personnel shall perform job on any equipment or machine unless it has been locked out and
tagged out, to prevent inadvertent release of hazardous energy sources.
No device to be operated or moved when a tag, Caution or danger, or lock is attached.
The steps outlined in this procedure shall be considered as the minimum requirements.
Note:- Refer section – 8.0 for exceptions to this procedure.
1.5 Definitions
Affected Person— Any Person who operates or maintains or works on machinery or equipment,
which is subjected to lockout/ tagout.
Authorized Person— A Person trained and authorized in the lockout/tag out procedure to make
and verify isolations.
Note: In some cases, the authorized Person can be the executing Person.
Caution Tag – is placed with intent of warning the affected Person that operation of the device
will cause harm to the equipment / system / machinery/ personnel.
Complex lockout—Lockouts that may involve multiple:
Crafts/Disciplines
Contractors/Employers
Hazardous energy sources
Lockout points
People
Shifts
Control device —a device used to execute a system change by manual, remote, automatic, or
partially automatic means (e.g., push buttons, emergency buttons or stops, selector switches,
and other control-circuit type devices).
Release Tag – is placed only on an energy-isolating device with intent of alerting the affected
Person that operation of that energy-isolating device will cause harm to the life of the Personnel
inside the hazard zone.
Electrical Engineer/Technician — A qualified Person trained and authorized in the electrical
lockout/tag out procedure to make and verify isolations.
Energy-isolating device—a mechanical device that physically prevents the transmission or
release of energy, including but not necessarily limited to, the following:
Electrical hazards are present when conductors or components that may be electrically
energized could cause injury to Personnel or damage to property.
Mechanical hazards are present when the unexpected start-up of the system, equipment,
or machine, or the release of stored energy while adjusting, maintaining, or servicing
systems, equipment, or machines could cause injury to Personnel or damage to property.
Process hazards are present when the unexpected release of gases, liquids, or solids
could cause injury to Personnel or damage to property. These hazards can exist during
such tasks as installation, fabrication, servicing, or maintenance of pipelines, vessels, or
associated equipment
Isolation—Separation of the equipment, machinery or area where work is to occur from sources
of hazardous energy or materials in such a way that only a conscious and deliberate act can
restore the connection.
Lock—one of three types of locking mechanisms:
Discrete—Locks that are different from one another; each can only be opened by one
key.
Personal—a discrete lock, individually keyed, issued to an individual for his or her use in
securing isolations.
Series or system—A group of locks that are opened by a single key and are used in area/
complex lockouts. Various sets of locks may be in use; however, only one key can open
any given lock in a particular set.
Locking—placing a lockout device on a hazardous-energy-isolating device at a point of Isolation.
Lockout—Isolation of a source of hazardous energy, including releasing any residual hazardous
energy that might be present, and securing an isolation point by locking it.
Lockout device— A piece of equipment that prevents the unauthorized or accidental operation
of a hazardous-energy-isolating device. Locks are an essential element of a lockout device.
Maintenance - Workplace activities such as constructing, installing, setting up, adjusting,
inspecting, modifying, and maintaining and/or servicing machines or equipment. These activities
include, but not necessarily limited to, lubrication, alignment, cleaning or unjamming of machines
or equipment and making adjustments or tool changes, where the Person may be exposed to the
unexpected energization or startup of the equipment or release of hazardous energy.
Maintenance Engineer – A Person who is solely responsible for the execution of the intended
maintenance activity. Normally he will be the permit acceptor.
Person In-Charge/Shift In-Charge – A Person who is the custodian or owner of the area or
process and or associated equipment. He / She are authorized by the management to exercise his
/ her exclusive rights for the operation and use of the process and or its associated equipment in
the designated area. Also, referred as “Proprietor / Owner” in the Dagachhu Hydropower
Corporation Limited LOTO Standard.
Permit to Work - The written or printed document that is issued by the Owner to execute job as
per Permit to work procedure applicable at Dagachhu Hydropower Corporation Limited only.
Refer Annexure S1 for Permit to Work used at Dagachhu Hydropower Corporation Limited.
Qualified Person— A Person trained and authorized to work with the equipment and who
understands the hazards involved.
Stored energy—Hazardous energy that can continue to exist after equipment is isolated (e.g.,
the hazardous energy contained in springs, flywheels, pressurized fluids or gases, pneumatically
controlled devices, capacitors, or gravity).
Tagging—placing a specific tag on a lock or point of isolation to identify who placed the lock and
when it was placed.
Tagout—Placement of Release tag (Release Order\Release Notice – “HOLD”. “MEN AT WORK”)
(without a lock).
Team Leader— A qualified and authorized Person who shall undertake overall responsibility for a
lockout/tagout to place and keep all hazardous energy sources under lockout/tagout and to
account for all Persons working with him on the job or task. He is normally expected to lead the
executing team at the work location.
Testing —A process in which a qualified Person checks the machine / equipment to verify
whether its performance meets the intended need.
Troubleshooting— A process for identifying malfunctioning components within a system that is
done in both energized and de-energized systems.
Try/trying— proving the effectiveness of isolation by attempting to make a machine, system, or
equipment operate without being inhibited by interlocks or other means that would impede the
“try” step.
Work Permit Issuer -A Person, but not necessarily limited to Person In-Charge/Shift In-Charge,
who is authorized to verify that all conditions for carrying out the assigned job have been met, to
define ongoing precautions to maintain safe working conditions during the work, to authorize
the work to occur, and to cancel the permit.
Work Permit Acceptor – A Person, but not necessarily limited to Maintenance Engineer, who
accepts the work permit and controls the overall execution of the job in the field, in compliance
with permit to work procedure of Dagachhu Hydropower Corporation Limited.
1.6 Permit to Work
The Permit to Work is a written or printed document that is issued by the Owner/DHPC to
execute job as per Permit to work procedure applicable at Dagachhu Hydropower Corporation
Limited only. The Permit to Work should be availed for any maintenance work within Dagachhu
Hydropower Corporation Limited. We use two types of Permit to Work at Dagachhu Hydropower
Corporation Limited and are as follows:
i) Permit to Work through SAP system: For this, permit requester/availer should request the
Permit to Work through their SAP user ID and inform the permit issuer/Shift In-charge
through SAP mail or through any other means of communication. The lockout and tagout
should be done after the permit issuer issue the permit.
ii) Permit to Work in hard copy: It is also mandatory to maintain the Permit to Work in hard
copy as well and it is given in Annexure S1.
The Permit to Work should be closed/cancelled after the maintenance work is completed and
after recommissioning the system/equipment to its original state.
This procedure covers the minimum requirements for lockout and tagout of energy- isolating
devices to protect any Person from hazardous energy including electrical, mechanical, hydraulic,
pneumatic, or other energy.
This shall be used as a general procedure for isolating all potentially hazardous energy
(lockout/tagout) before energization, start-up, or release of stored energy that could cause
injury. This procedure, when used in conjunction with specific information concerning individual
machines, provides the necessary information for lockout/tagout of machines with multiple
energy sources.
This procedure shall be followed in conjunction with the requirements of the Dagachhu
Hydropower Corporation Limited Safety Manual.
Caution: Specific individual procedures are required for all servicing and maintenance of
equipment, machines or systems requiring lockout/tagout of more than one energy source.
Before work is started on any equipment, System or process, the Person In-Charge/Shift In-
Charge shall be responsible for Preparation for Lockout / Tagout.
He / She shall ensure that all hazardous energy sources are identified (Chemical, Electrical,
Mechanical or other) to determine which switches, valves or other energy-isolating devices apply
to machinery or equipment to be locked and tagged out.
Where stored or residual energy (such as that in capacitors, springs, elevated machine members,
rotating flywheels, hydraulic systems, water pressure, etc.) may be encountered, identification of
such type(s) of stored or residual energy shall be ensured. Appropriate methods of dissipating or
restraining such energy (by methods such as, but not necessarily limited to, grounding,
repositioning, blocking, bleeding down, etc.) shall be ensured.
For equipment preparation, pertaining to plant operational processes involving line breaks, the
prime consideration shall be of proving that isolations are intact giving a tight shut off.
Caution: Each case must be carefully considered by the Person In-charge/Shift In-charge, taking
into account the hazardous properties of the materials involved and the details of plant design.
Person In-Charge/Shift In-Charge shall ensure that all the type of energy that the System or
equipment utilizes, shall understand the hazards of the energy, and shall know the methods
to control the energy. In cases where complex lockout or multiple energy sources are
involved the Person In-Charge/Shift In-Charge shall generate an energy source identification
sketch (a computer generated, hand written or in any other form) to properly identify all
energy sources.
Field operator/Operation Engineer shall ensure the equipment is not in operation and shall
switch off the equipment from LCS/ local Push Button/ASLPA Control System / remote
pushbutton. She/he shall provide an appropriate CAUTION Tag on the LCS or another control
device. (Refer Annexure S4)
Person In-Charge/Shift in-charge shall submit Release notice tag for isolation of electrical
energy. Operation Engineer shall identify electrical energy source(s). He / She shall switch off
the source(s) and test the absence of voltage to equipment. All such energy isolation points
shall be provided with lockout device (Hasp) and ‘Release Notice’ tag (Refer Annexure S5).
Simultaneously the Maintenance Engineer or Team Leader shall provide his lock on the Hasp
and retain the key to the lock till the job is over. Refer Annexure S6 for recommended LOTO
methods for electrical energy sources. Field Operator/Operation Engineer shall use the
energy source identification sketch wherever applicable and now isolate all energy sources
by operating the valve, or other energy-isolating device(s) so that the equipment is isolated
from its energy source(s). (Refer Annexure S3 for guidelines for positive isolation and special
precautions).
Field Operator/Operation Engineer shall ensure that stored energy (such as that in springs,
elevated machine members, rotating flywheels, hydraulic systems, and air, gas, steam, or
water pressure, etc.) shall be dissipated or restrained by methods such as, but not necessarily
limited to repositioning, blocking, draining, venting, bleeding down, etc.
All such energy isolation points shall be provided with lockout device (Hasp) and ‘Release
Notice’ tag. (Refer Annexure S5)
After energy source(s) isolation, the equipment shall be cleared by /purging / draining /
depressurizing / decontaminating and ensuring that the equipment / line is totally free of
hazardous material. All such /drain / vent points shall be provided with ‘Release Notice’ tag.
(Refer Annexure S5)
The Maintenance Engineer or Team leader shall provide the lock on each of the field energy-
isolating device, as per the energy source identification sketch, wherever applicable, and
retain the key to the lock till the job is over.
After ensuring that no Persons are exposed to any hazard, Field Operator/Operation Engineer
shall remove the CAUTION tag from the LCS or another control device. As a check on having
disconnected the machinery or equipment from the energy sources, the Operation Engineer,
in presence of Maintenance Engineer or Team Leader, shall operate (TRY) the push button or
other control device to make certain that the machinery or equipment will not operate.
‘RELEASE ORDER’ tag shall then be placed on LCS or another control device.
Caution:Return the LCS or other control device to the “off” position after the test. Put the
RELEASE ORDER tag back on till the equipment is restored. “TRY” step shall be attempted with all
interlock / other controls, etc. and no interlock / other controls shall be disturbed till the
completion of the job.
The equipment or machine or system is now locked out and tagged out.
Caution: Verify that LCS or other control devices are in “off” position. All blinds/ blocks, etc. shall
be removed prior to removal of locks.
Maintenance Engineer or Team leader shall remove all locks provided on lockout devices
(Hasps) at the energy-isolating points, including electrical energy source and clear his
‘Release Permit’.
Field Operator/Operation Engineer shall check & inspect the integrity of the equipment and
remove the Release Notice Tags and Release Order Tags.
The equipment is now released for restoration into operation according to the restart up
procedure.
1.7.4 Lockout and Tagout Procedure involving more than one Person/group
When servicing or maintenance on any equipment or machine is performed by more than one
Person or more than one group, each group shall utilize a procedure which affords the Person a
level of protection equivalent to that provided by the implementation of a Personal lockout and /
or tagout device.
Each of such group shall have a Team Leader who shall have the identification of each individual
Person (DHPC employee or Contractor employee) working in that group. The Team Leader, on
behalf of each individual Person, shall fill up a written declaration to the Person In-Charge/Shift In-
Charge stating his overall responsibility to place Lockout / Tagout for the group and keep all
hazardous energy sources under lockout/Tagout till the end of the job or task. (Refer Annexure
S7 for Team Leader’s declaration)
The Team Leader shall impart the necessary information to each Person of the various sources of
hazardous energy and the method of isolation. He / She shall inform the group about the location
of energy isolation device. After the required information is imparted, each Person in the group
shall acknowledge their acceptance for LOTO to be placed by the Team Leader on their behalf.
The Person In-Charge/Shift In-Charge shall authorize the Team Leader to provide a Lock on behalf
of his group after receipt of the completed declaration.
Caution: A fresh declaration has to be made if any changes take place to the details of the
submitted declaration. (e.g.– change of job scope, change of equipment, etc.) except change of
Personnel within the group excluding Team Leader.
If multiple group are working on same equipment or machine requiring isolation, then as many
isolation tags as the number of permits shall be generated by the Person In-Charge/Shift In-
Charge. Each Team Leader shall provide his / her lock, on behalf of the group. Unless all locks are
removed, restoration of any energy source shall not be done.
An orderly transfer of Lockout or Tagout devices between Person leaving the workplace and
relieving Person shall be ensured in order to minimize exposure to hazards from the unexpected
energization or startup of machinery or equipment, or the release of stored energy.
Proper information about LOTO on jobs undertaken shall be communicated through operation
log book entries/proper documentation & handing over the keys to the next shift. This
responsibility lies with executing Persons/Team leader of both shifts who shall ensure smooth
carryover of the job to the next shift. Refer Annexure S8 for Record of LOTO Transfer in Shifts.
(Optional to log book entries).
In situations where the energy sources are locked and tagged, and there is a need for temporary
re-energizing for testing / taking trial of the equipment, machine or part thereof, the following
shall be mutually agreed upon between the Person In-Charge/Shift In-charge and the Executing
Persons/ Team Leader:
Scope of testing
Testing procedure
Duration of testing
Person In-Charge/Shift In-Charge shall ensure that all Persons inside the hazard zone are
informed that equipment / machinery needs to be re-energized for testing / trial.
Person In-Charge/Shift In-Charge shall ensure that all Persons (all persons in case multiple
groups are working) on the job, safely clear the job to enable testing / trial and remove
their lockout temporarily before moving out of the hazard zone.
After getting final clearance from Person In-Charge/Shift In-Charge, the executing Person/
Team Leader shall re-energize the equipment / machinery for testing / trial under
‘Operating Permit’ Tag. (Refer Annexure S5A)
After completion of testing / trial, ‘Operating Permit’ shall be cleared by the executing
Person/ Team Leader. Person In-Charge/Shift In-Charge shall de-energize the equipment /
machinery.
For complex situations (as judged by Person In-Charge/Shift In-charge) the Person In-Charge/Shift
In-charge shall require and ensure that a specific written procedure covering all of the above
points is prepared and reviewed with all Persons involved in the testing.
The Person In-Charge/Shift In-charge shall issue ‘Caution ‘tag to a qualified Person who
shall keep the machine / equipment (e.g. – Control panel, Remote Control unit, Circuit
Breaker, Switches, etc. from where the machine can be activated) under his exclusive
control throughout the duration of the job.
The qualified Person shall ensure that all executing Person must be in his clear sight or in
direct communication with him at all times till the duration of the job.
The qualified Person shall ensure that all executing Person must be beyond the reach of
the machine / equipment part which may move / actuate and cause exposure to
hazardous energy / material.
If the qualified Person has to leave the operating station, the equipment / machine must
be de-energized till the same or another qualified person resumes control of the
machine / equipment.
During repairs when the machine / equipment parts are to be adjusted / replaced, the
qualified Person shall ensure that the machine / equipment must be de-energized /
disconnected from its energy source.
After the job, the qualified Person shall ensure that all executing Person on the job, safely
clear out from the hazard zone and clear the ‘Caution’ tag before testing / trial.
Caution: Each case must be carefully considered by the Person In-charge/Shift In-charge, taking
into account the hazard involved and the details of equipment design and equipment specific
procedure shall be made as needed.
1.7.8 Lockout Devices and Locks
Person in-charge/Shift in-charge shall be the only agency that will control and shall ensure
necessary provision for providing field hasp including hasp for electrical Lockout.
Plant control room shall have a comprehensive procedure of monitoring and control of field
through proper documentation and shift-to-shift communication so that no device(s) remain left
out unnoticed.
All hardware used for hazardous energy control must be durable enough to withstand the
workplace environment and must be used solely for the purpose of control of hazardous energy.
If there is a loss of key, the concerned person shall inform the Person In-charge/Shift In-Charge by
a formal written communication about the facts. The Plant HOD shall be the only approving
authority for breaking any locks of the energy-isolating device.
For ease of identification of the department to which the executing Persons/Team leader is
associated, the locks shall be identified by defined colors as mentioned below-
If an energy-isolating device is not capable of being locked out, a tagout procedure (Tagging
system) shall be followed.
Where Tagout procedure (tagging System) is used for hazardous energy control, the Persons
must be fully aware of the following limitations of tags:
Tags are essentially warning devices affixed to energy-isolating devices, and do not
provide the physical restraint on those devices that is provided by a lock. Tags may evoke
a false sense of security, and their meaning needs to be understood well.
When a tag is attached to an energy-isolating means, it shall not be removed without
authorization of the authorized Person responsible for it, and it is never to be bypassed,
ignored, or otherwise defeated.
Tags must be securely attached to energy-isolating devices so that they cannot be
inadvertently or accidentally detached during use. Tags must be legible and
understandable by all Persons, whose work operations are or may be in the area, in order
to be effective.
Tags and their means of attachment must be made of materials, which will withstand the
environmental conditions encountered in the workplace.
CAUTION Tags shall be provided to indicate that no change must be made to the state of the device /
valve / control unit / etc. (Refer Annexure S5)
RELEASE Tags shall be provided at the point of isolation of Hazardous energy source. (Refer
Annexure S5)
OPERATING PERMIT tag shall be provided for trial /testing operations of the equipment. (Refer
Annexure S5A)
Caution: Either type of RELEASE tags cannot be substituted by CAUTION tags and hence shall be
tagged as per the right intent.
1.7.10 Contractors
Whenever outside servicing Persons (e.g., contractors, vendors, Equipment Service Engineers,
etc.) are to be engaged in activities covered by the scope and application of these procedures,
the Maintenance Engineer shall inform and ensure implementation proper lockout or tagout
procedures.
All outside servicing Personnel (e.g. contractors, vendors, Equipment Service Engineers, etc.)
must comply with all applicable Lockout /Tagout standards or requirements.
Contractor Supervisor shall ensure that their employees understand and comply with the
applicable Lockout /Tagout standards or requirements.
1.8 Exceptions
Work performed on cord & plug connected portable electric equipment as long as the
equipment is unplugged during servicing & the Person performing the servicing maintains
exclusive control of the plug.
Lamp replacement job done in non-operational area.
Area owners shall audit their respective areas once every month to identify Lockout / Tagout left
since last audit and identify root cause for non-release. Such cases shall be resolved on case-to-
case basis by registering a target date / regularizing through other established procedures.
1.10 Audit
Multi-disciplinary audit team shall be formed by plant HOD in consultation with the custodian.
Audit shall be carried out on once a month within the plant. The audits must be performed by
Personnel other than the one actually performing work on the equipment at the time of the
audit.
The audit shall be focused on the following aspects
Personnel must initially be trained on identification of Hazardous energy sources associated with
the job. Specific training including risk assessment for specific jobs shall be conducted.
Authorized Persons (DHPC employee) must receive initial training and special instructions
concerning the scope, purpose, authorization, rules and techniques for lockout/tagout of
hazardous energy sources including, but not necessarily limited to:
Permit No:
Work on energized equipment or installations / Maintenance activity on any Machine
Reminder: A Permit to Work shall be issued for any work (maintenance, servicing, etc.) where lock out / tag out is required
A. Application
☐ Review of equipment technical ☐ Identification of all energy isolation devices ☐ identification of all lock out
documentation ☐ Identification of emergency devices
☐ Others (describe)………
shutdown devices
1) Equipment:
☐ Lock out tags ☐ Insulated steps/platform ☐ Rescue hook ☐ Lock out box
2) Electrical (PPEs):
☐ Electrical safety boots ☐ Electrical safety gloves ☐ Others (describe)…………
3) Other PPEs:
1. ☐ ☐ ☐ ☐ ☐
2. ☐ ☐ ☐ ☐ ☐
F. Verification before
All the equipment shutdown by normal stopping ☐ Yes Adequate rescue means available ☐ Yes
procedure
☐ Yes All personnel affected by machine/equipment ☐ Yes
All energy sources isolated
shutdown ☐ Yes
All energy isolating equipment “Lock out” with ☐ Yes
adequate lock out device notified
☐ Yes
All energy isolating sources tagged ☐ Yes Adequate PPE worn by all concerned person
All potentially hazardous sources or residual ☐ Yes
☐ Yes All PPEs in good condition
energy purged/ dissipated ☐ Yes
Verification of effectiveness of isolation ☐ Yes Work area clear and demarcated
Nearby workers informed of work to be performed
G. Permit Issue
The work permit has been issued for the works to proceed subjected to conditions specified above.
Availing Authority
Issuing Authority
Permit No:
Work on energized equipment or installations / Maintenance activity on any Machine
H. Lock out device removed
Identification of energy isolation Type of lock out devices Identification code of lock out
equipment device
1.
2.
3.
4.
5.
6.
7.
I. Completion of Work
All works requiring the lock out / tag out are finished ☐ Yes All tags have been removed ☐ Yes
All safety devices of the equipment are operational All personnel affected by
☐ Yes ☐ Yes
machine/equipment switched ON notified
All lock out devices have been removed ☐ Yes Nearby workers informed of ☐ Yes
All energy isolating equipment are operational machine/equipment switched ON
☐ Yes
J. Permit Closure
I, hereby declare that all workers under my charge have been withdrawn from the equipment and advised them not to do any job
further. All the tools and temporary earthings which were provided by me were cleared from the equipment. The equipment is fit for
energisation. The work permit is hereby cancelled.
Availing Authority
Cancelling Authority
Annexure S2
Responsibilities Matrix:
Annexure S3
Guidelines for Positive Process Isolation
The most positive method of isolation is the complete physical disconnection of the line with
blind flange or blank put on the live end. Where there is work on pressurized hydraulic system
or entry into a vessel, physical disconnection is the mainly recommended method of isolation.
If this method is not reasonably practical, then, as a next best method, the insertion of a slip
plate with the correct size, specific MOC and appropriate pressure rated blind is preferred for
the purpose of authorizing a confined space entry.
In many situations, remotely operated valves and motor operated valves (MOV) are the only
isolations. Basically, for these on-off type valves the correct procedure is to positively disable
it, by either disconnecting the instrument air supply or remove the actuating signal wires or in
the case of MOVs electrical lockout / tag out is to be ensured.
Having achieved line/equipment isolation by the closure of single or double isolation valves,
this valve isolation must remain effective until the purpose of the isolation has been achieved
and the Work Permit signed off. To ensure this, the valve or valves must be locked/ tagged in
the closed position or open position in the case of vent/drain valves.
Special Precautions
For equipment like pump / blowers etc. where shafts / blades may rotate even after handing
over, are to be locked suitably against rotation using locking device before taking up
maintenance work.
Existing slip plates should not be relied upon for positive isolation since they may be
corroded. They should be removed, inspected & replaced where necessary by new ones.
Process and service lines, or equipment, e.g., a pump casing, relying on valve isolations must
not be left with open ends. Blanks must be fitted to the open ends immediately after the
section of the line or part of the equipment that is removed.
Always ensure that slip plates compatible with the process materials confirm to the piping
design standards to which the plant was designed and these should be fitted as close as
possible to the equipment to be isolated. Always ensure that blind detail is entered in the
blind register.
Where cutting or welding is to take place, the line or equipment must be purged and either
slip plates must be fitted after the section or item has been isolated or the item of the
equipment must be removed and open ends leading to other process equipment blanked off.
Equipment containing corrosive chemicals must be washed or steamed out, where possible
after depressurizing and draining. Where residual contamination is unavoidable, full
protective clothing should be worn.
In case isolation is required again due to some problem (like change in DOR), then this
procedure is to be followed afresh.
For work on an Electrical distribution system, all Lockout / Tagout activities will be the same.
However, to avoid back feeding of power, isolations shall be ensured from all possible paths
(Upstream and downstream).
While working on electrical installation, after lock out / tag out is done, equipment shall be
discharged safely of all its residual energy. If required, special care may be taken to keep the
terminals earthed till the completion of the job.
Diesel engine driven / battery operated equipment shall be made inoperable by disconnecting
and removing battery cables safely.
For isolation of electrical source where lock out provision is absent, physical disconnection of
outgoing power conductors shall be ensured.
Annexure S6
Electrical Isolation Method:
2 33kV and 11kV Breakers/Isolators on Lock Out & Switch Off, Isolate
respective locations Tag Out Control Supply and
/panels Rack out
3 415V Source MCC / PDB feeder Lock Out & Rack out / Fuse
Tag Out removal
4 415V or less Source DB / Power points / Lock Out & Fuse removal
with LO provision Control Panels Tag Out
5 415V or less Source DB / Power points / Lock Out & Switching OFF
without LO provision Control Panels Tag Out power from
MCB/ELCB/ Isolator
OPERATION MANUAL
CHAPTER 2
8 110V DC MCC / PDB feeder Lock Out & Rack out / Fuse
Tag Out removal
2.1 Introduction
Occupational safety and health forms an integral function of a company and is concerned with
protecting the safety, health and welfare of people engaged in work or employment. The
management and employees are responsible and accountable for creating a safe working
environment and adhering to safe working practice.
Occupational health should aim at the promotion and maintenance of the highest degree of
physical, mental and social well-being of workers in all occupations; the prevention amongst
workers of departures from health caused by their working conditions; the protection of workers
in their employment from risks resulting from factors averse to health; the placing and
maintenance of the worker in an occupational environment adapted to his physiological and
psychological capabilities.
Most mishaps are caused by careless or thoughtless acts by workers. Workers must always be
cautious and deliberate in their actions, and always notify their co-workers before carrying out
works that are potentially hazardous. Unsafe equipment, tools, and conditions must be reported
immediately and corrected. Good house-keeping is also important for safety.
Mishap prevention is a basic responsibility of every worker. All workers have an individual
responsibility to work and act safely at all times and ensure safety of their co-workers. Safety
takes precedence over work production.
Safety rules and regulations are established to protect people and property from injury or
damage. All employees should adhere to the following general safety rules and should develop a
sense of pride for the safety and health in their respective workplaces. There is no substitute for
the use of common sense and good judgment when it comes to safety.
i. Each worker shall wear suitable clothing including approved gloves and approved footwear
appropriate for working conditions. Do not wear loose clothing when working on or near
moving machinery. Long hair must be secured under the hard hat
ii. Do not wear metal jewelry (including but not limited to wristbands, watch chains, rings,
bracelets and body jewelry) when working on or near electrical equipment and near
moving machinery
iii. Promptly report all injuries to your supervisor; administer first aid promptly. (In case of
serious injury, do not move the person until medical aid arrives, unless in a dangerous
location)
iv. Read and observe all signs and warnings
v. If you are in doubt about the safe or proper way to perform a job, get instructions from
your supervisor
vi. Correct or report any unsafe workplace conditions to your supervisor as soon as possible
vii. Report fires immediately, sound the alarm, evacuate the building utilizing standard fire
alarm protocol
viii. Know the location of emergency exits and locations of portable fire extinguishers and
other emergency equipment in the Power House complex. Keep emergency exit paths
clear
ix. All work areas shall be kept free of recognizable hazards. Material stacking or storage must
be arranged to prevent its falling or creating trip hazards
x. Oily and dirty rags must be stored and disposed of in proper containers
xi. Fluids spilled on floor areas must be cleaned up immediately
xii. Use the right tools for the right job
Maintaining acceptable work site safety involves proper behavior, good housekeeping,
maintenance of protective measures, and avoiding unsafe actions.
Typical unsafe actions are listed as under:
i. Operating without authority
ii. Operating or working at unsafe speeds
iii. Making safety devices inoperative without proper authorization
iv. Using unsafe equipment or equipment unsafely
v. Taking unsafe positions or postures
vi. Working on moving or dangerous equipment
vii. Distracting, teasing, abusing or startling
viii. Failing to use safe personal protective devices
ix. Failing to lock-out energized circuits
Electrical personnel involved in operating and maintaining electrical systems can be injured and
equipment can be damaged whenever electrical systems and components are not handled safely.
The adoption of safe electrical practices will reduce the hazards to personnel.
Electric shock results from setting up an electric current path within the human body. The current
flows because there is a potential gradient (voltage difference) between an energized object and
the grounded worker.
Remember that it is the current which causes damage to the living tissue and not the voltage.
Low voltage under wet conditions can cause fatal accidents. Contact with high voltage circuit
results in deep burns instantly resulting in disappearance of the protection afforded by the skin
resistance, and hence greater damage.
The value of dangerous currents for various individuals varies according to body constitution. For
women, it is approximately two-third of that for men and for children half of that for men.
Current values and its effects on human beings are given in the table below:
100 to 200 mA Ventricular fibrillation (certain): A heart condition that results into
instant death, no known remedy
Above 200 mA Severe burns, severe muscular contractions - too severe that chest
muscle clamps heart and stop it during duration of shock
Arcs result from the passage of electric current through air, when the air fails as an insulator and
serves as a conducting medium for ionized gases. Blasts result when the metal at the arc site
expands and vaporizes. Water expands 1670 times when it becomes steam; copper expands
67000 times when it vaporizes. High energy arcs can be fatal even at a distance of 3 meters.
Adequate fire prevention measures have been taken for all areas/facilities in
the underground Power House to minimize chances of occurrence of fire.
However, in the event of fire in the underground Power House complex,
following needs to be adhered to:
i. Inform the Fire Officer, Safety Officer and higher authorities immediately about the incident
of fire.
ii. Ensure that all emergency escape routes are clear for passage and sufficient illumination
available.
iii. If the fire is minor, initiate action for putting off the fire with the help of Fire Personnel
deployed in the Power House.
iv. In case of fire, ensure closing of fire dampers in Transformer Chambers, blowers and
ventilation fans to avoid spread of fire.
v. Ensure that all portable fire extinguishers are properly filled and its standard pressure
maintained.
Protecting workers from potential head injuries is a key element of any safety program. A head
injury can impair a worker for life or it can be fatal. Wearing a safety helmet or hard hat is one of
the easiest ways to protect a worker’s head from injury. Hard hats can protect workers from
impact and penetration hazards as well as from electrical shock and burn hazards.
Hard hats should able to protect workers under following work situations:
i. If objects fall from above and strike, then on the head
ii. When workers bump their heads against fixed objects, such as exposed pipes or beams
iii. When there is a possibility of accidental head contact with electrical hazards
iv. In general, protective helmets or hard hats should do the following:
v. Resist penetration by objects
vi. Absorb the shock of a blow
vii. Be water-resistant and slow burning
viii. Have clear instructions explaining proper adjustment and replacement of the suspension
and headband
A personal hearing protection device (or hearing protectors) is any device designed to reduce the
level of sound reaching the eardrums. Ear muffs, ear plugs and ear bands are the main types of
hearing protectors.
Ear plug
Ear muff
Noise is measured in units called “decibels”, abbreviated as “dB”. Noise levels can range from 1
dB (near silence) to 60 dB (quiet conversation to 140 dB (a jet engine). Scientific studies have
shown that people exposed to noise levels of 85 dB and above over 8 hours or longer will
gradually lose their hearing over time. If you have to shout to be heard by another person 3 feet
from you, the noise level is probably above 85 dB. Noise levels above 140 dB will cause immediate
hearing loss. Therefore, everyone should wear hearing protection all the time when working
around noise levels above 115 dB. Hearing protection must be worn when employees are exposed
to 8-hour average noise levels of 85 dB or greater.
Some noise levels of commonly used equipment are given as under for reference:
i. Employees, who work in a location where there is a possibility of falling into water, shall be
provided with and wear a suitable life jacket or they shall be protected by a fall arrest
system that will hold the employee form falling into water
ii. Employees using boat or watercraft shall wear suitable life jackets at all times
iii. Employees working at heights such as towers and on EOT cranes shall wear safety belts.
The safety belts shall be inspected for strength and healthiness by individuals before
wearing them
All hand tools used shall be of approved make and shall be free from any form of defects.
Defective tools shall be immediately removed from service, tagged and reported to the
supervisor.
For any specific instructions, manufacturer’s manuals shall be referred to.
When the work warrants use of ladders, following basic precautions may be adhered:
i. Suitable fiber glass ladders shall be used while working near energized lines and in locations
which contain live electrical apparatus
ii. Ensure that legs of portable ladders are secured properly to avoid slippage of ladders,
thereby
iii. When extending ladder to working height, both locking dogs on the moving section must
be engaged on a rung
iv. Portable ladders shall not be placed in front of a door that opens toward the ladder, unless
the door is locked, blocked or guarded
A designated person shall be responsible for safe loading/ unloading of materials. Proper and
correct use of ropes, chains, cables, slings, jacks, skids and other hoisting and rigging apparatus
shall be ensured. All hoisting apparatus shall be periodically inspected by the Safety Officer for
their strength and defects.
The intense light associated with welding operations can cause serious and sometimes
permanent eye damage if welders do not wear proper eye protection. The intensity of light or
radiant energy produced by welding, cutting or brazing operations varies according to a number
of factors including the task producing the light, electrode size and the arc current. As such,
hazards associated with these operations pose an unusual combination of safety and health risks.
Following precautions and safe practices shall be adopted while carrying out welding, cutting or
brazing operations:
i. Welders and their helpers shall wear protection equipment appropriate for the job to guard
the eyes, face, neck and hands when engaged in welding, cutting or brazing operations.
This protection shall include welding helmets, welding caps, insulated gloves, leather
aprons, spectacles or goggles and respirators where required
ii. Welding, cutting or brazing operations shall not be performed in a confined space. Proper
ventilation is required to protect the operator from the evolving noxious fumes and gases
iii. Do not weld on dirty plate or plate contaminated with unknown material. The fumes and
gases which are formed could be hazardous to health. Remove all paint and galvanized
coatings before welding. All fumes and gases should be considered as potentially
hazardous
iv. Keep welding cables dry and free of oil or grease Keep cables in good condition, and, at all
times, take appropriate steps to protect them from damage. If it is necessary to carry
cables some distance from the machines, run the cables overhead, if possible, and use
adequate supporting devices
v. Inflammable materials shall not be carried by welders when engaged in work
Following precautions and safe practices shall be adopted while using air-operated tools:
i. Air-operated tools shall never be pointed at another person
ii. Air-operated power tools shall be secured to the hose by a positive means to prevent the
tools from becoming accidentally disconnected
iii. Employees shall wear appropriate PPE when exposed to hazards created by dust, metal
cuttings or other substances being blown from equipment, materials or structures by the
use of compressed air, compressed gases or steam
iv. The manufacturer’s safe operating pressure for hoses, pipes, valves, filters and other
fittings shall not be exceeded
v. Air-operated tools shall only be operated in accordance with manufacturers’ instructions
vi. Metal-reinforced hoses shall not be used near energized equipment
vii. Air-operated power tools shall not be used in the proximity of energized lines or apparatus
The Safety Officer shall maintain First Aid Kits at work places and employees shall be familiar with
their location and contents. First aid is intended to be a simple, practical guide for effective action
in time of emergency. Except for minor injuries, professional medical treatment should be
sought.
The work site injuries and mishaps are required to be prevented as far as possible by taking
precautionary measures such as use of PPE. However, if such incidents are unavoidable resulting
in any mishaps, then such incidents shall be immediately reported to the Safety Officer.
References
We sincerely acknowledged all the officials who were involved in bringing first Operation and
Maintenance Manual of Dagachhu Hydro Power Corporation Limited. We also want to thank the
management of Dagachhu Hydro Power Corporation Limited for giving us this opportunity for
bringing up this first Operation and Maintenance Manual. We acknowledge the efforts and
commitments of following officials:
1. Mr. Karma Phuntsho, Chief Executive Officer,
2. Mr. Tashi Dorji, Head, Operation Unit,
3. Sonam Gyamtsho, Assistant Engineer (Mechanical)
4. Pema Wangchuk, Junior Engineer (Electrical),
5. Sonam Tenzin, Junior Engineer (Mechanical),
6. Choedra, Junior Engineer (Electrical),
7. Mon Raj Rai, Junior Engineer (Electrical),
8. Sonam Tshering, Sr. Section Officer (Mechanical),
9. Karma Dorji, Sr. Section Officer (Electrical),
10. Ugyen Tshering, Sr. Section Officer (Electrical),
11. Sherab Thaye, Sr. Section Officer (Electrical),
12. Chening Dorji, Sr. Section Officer (Electrical),
13. Tshechik Wangdi, Sr. Foreman (Mechanical),
14. Pema Dendup, Sr. Foreman (Electrical),
15. Sithar Wangdi, Foreman (Mechanical),
16. Thinley Phuntsho, Foreman (Mechanical),
17. Pema Gyeltshen, Electrician
If there are any discrepancies/ shortfalls/ mistakes/ practical issues in the manual, we would
appreciate if you keep note of it, so that we can incorporate in next the revision.