In line with the above regulations we are obliged to inform the Contractor of the
abnormal risks that may be encountered in the construction of these works. As
part of the design process all the salient health & safety aspects are given full
consideration and these are observed within the designs viewed on this document.
Although considerable effort is undertaken to eliminate risks, the very nature of
2000 Footway except the project gives rise to some hazards and risks.
Road 4 1500 Footway Significant risks that cannot be eliminated by design and could not be foreseen by
675 Hard Margin 6000 Carriageway Road 14TH(Part) 3000 Footway/Cycleway a competent contractor are noted in the risk assessment boxes on the drawings.
Notes
*Crossfall direction varies depending on 1. All highway works to be constructed in accordance with the
road. Refer to road levels plan for details. South Yorkshire Design Guide and any specific requirements of
3% min, 4% max Barnsley MBC.
DETAIL 3 1 sub base 4. All public sewers are to be the subject of a Section 104
DETAIL 4 Agreement of the Water Industry Act 1991.
+
TYPICAL SECTION THROUGH ROAD 4(Part), 7(Part), 7TH(Part) and 14TH(Part) CBR values less than 2.5% will require
4.0 225 275 OR 375
1:20 further discussions with the L.A.
5-10 + OR 325 Engineer.
200 250
10-15 175 + 175 OR 250 CBR values vary across the site and
therefore further testing will be required
Greater than 150 + 150 OR 200 to confirm the actual CBR values at
15 formation level prior to construction
commencing.
*1:40 (2.5%)
3% min, 4% max
Kerb foundation
on 150mm type
1 sub base DETAIL 3 Kerb foundation
on 150mm type
1 sub base
DETAIL 6
Surface Course
Surface Course 60mm thick Brindle pencil edged Concrete Paviors to SWH Clause 1107 and BS6717-1: 2001 to be laid in 45° DETAIL 4
25mm thickness of 0/6mm Dense Bitumen Macadam herring-bone pattern bedded on 35mm thickness of naturally occuring silica sand to BS7533-3: 2005: Table D2. Channel
190 pen L/stone to BS4987-1: 2005: Clause 7.5 to be formed from 2 rows of brindle blocks laid in stretcher bond.