You are on page 1of 17

Energy 135 (2017) 413e429

Contents lists available at ScienceDirect

Energy
journal homepage: www.elsevier.com/locate/energy

Techno-economics and environmental analysis of energy storage for a


student residence under a South African time-of-use tariff rate
S.O. Masebinu a, *, E.T. Akinlabi a, E. Muzenda b, A.O. Aboyade c
a
Department of Mechanical Engineering Science, University of Johannesburg, South Africa
b
Department of Chemical Engineering Technology, University of Johannesburg, South Africa
c
Faculty of Engineering and the Built Environment, University of Johannesburg, South Africa

a r t i c l e i n f o a b s t r a c t

Article history: Time-of-Use has been introduced in South Africa as part of demand side management measures. Battery
Received 3 August 2016 energy storage (BES) can take advantage of energy price arbitrage under favourable pricing regimes.
Received in revised form However, the challenge is to what extent will the introduced policy favour the installation of BES at
9 May 2017
residential accommodations? The tools to assess suitability of installing BES exist but they come at a cost.
Accepted 20 June 2017
Available online 23 June 2017
In this study, we improved upon existing methodology and implemented it in Microsoft Excel to assess
techno-economic viability and environmental benefits of using BES. The approach showed that none of
the three BES technologies investigated was economically viable at the prevailing average rate of 0.1442
Keywords:
Demand side management
$/kWh for peak electricity. The Monte Carlo simulation implemented suggests that the minimum mean
Energy storage price of peak needed for the BES system to break even range between 0.2560 e 0.2919 $/kWh. At 50%
Environment discount in storage medium cost and 100% increase in the price of peak, the BES will only break even
Probabilistic simulation when the average price of peak is 0.2043 $/kWh at maximum cycling cost that range between 0.1077 e
Techno-economics 0.1560 $/kWh. The study concluded that reduction in the cost of storage medium has more impact on
Time-of-use economic viability than increasing only peak price of electricity.
© 2017 Elsevier Ltd. All rights reserved.

1. Introduction strategies. The first of these strategies was to build new baseload
power plants, as well as re-commission and upgrade old power
Emerging economies will account for about 90% of the global net stations where feasible, to support peaking power plant re-
energy demand growth by 2035 [1]. Electricity demand will be quirements. The second strategy focused on implementing con-
higher among other forms of energy in the emerging economies [1]. sumer demand reduction through integrated demand management
This projected growth has increased the interest in improved en- (IDM) [5e7]. The target of the first strategy was to add 17,000 MW
ergy efficiency to limit the risk and environmental impact of the to electricity generating capacity by the end of 2019 [6]. Efforts
sources of energy which are mostly from fossil fuel [2,3]. South under that strategy led to 3655 MW added to the grid in 2013 and
Africa's economy, identified as an emerging economy, is energy another 9564 MW is expected by the end of 2017 from two coal
intensive and in recent years, economic growth coupled with power plants [7]. Also, 1600 MW of renewable sourced energy was
increased access to electricity by previously unserved communities, added to the grid in 2014 as part of the first strategy [8]. The second
has led to an increased demand for electricity, that at some point in strategy, IDM, aimed to increase energy efficiency and was made up
2008, exceeded generation capacity [2,4]. This situation forced of a series of demand side management (DSM) programmes
Eskom, the state-owned utility which accounts for more than 95% namely; energy efficient DSM; demand response and energy con-
of electricity generated and distributed nationwide [5], into servation [5]. With the implementation of the IDM, 19 GWh
controlled load shedding with an estimated economic impact of annualised energy savings was achieved in 2013/14 [7]. The suc-
about US$268 million [5]. To avoid a repeat of that magnitude of cesses achieved on the two strategies, are under threat due to
load shedding, Eskom embarked on two major mitigating Eskom's aging fleet. The utility reported that two-third of its power
stations are beyond the mid-point of their expected life span [7].
This is indicative that continued expansion and upgrading of the
* Corresponding author. country's power generation and grid infrastructure is required, to
E-mail address: masebinity@gmail.com (S.O. Masebinu). ensure that generation keeps pace with demand in the medium to

http://dx.doi.org/10.1016/j.energy.2017.06.118
0360-5442/© 2017 Elsevier Ltd. All rights reserved.
414 S.O. Masebinu et al. / Energy 135 (2017) 413e429

Nomenclature gk Yearly inflation rate for cost of component k [%]


i Annual interest rate [%]
NPCO&M Net present cost for operation and maintenance
Acronyms [$/kW-yr]
LD and HD Refers to low demand (summer) and high demand costO&M Unit operation and maintenance cost [$/kW]
(winter) gO&M Yearly operation and maintenance cost inflation rate
PrElpeak Price of electricity at peak TOU [$/kWh] [%]
PrElstand Price of electricity at standard TOU [$/kWh] gPrEl Yearly inflation rate for price of electricity [%]
PrEloffpeak Price of electricity at offpeak TOU [$/kWh] NPCwoutES Net present cost for system without battery energy
Epeak Summation of AC energy consumed during peak [kWh] storage [$]
Estand Summation of AC energy consumed during standard NPCwithES Net present cost for system with battery energy
period [kWh] storage [$]
Eoffpeak Summation of AC energy consumed during offpeak NPVsavings Net present saving [$]
period [kWh] LCOE Levelized cost of electricity [$/kWh]
Ibatt ðtÞ The current in/out of the battery [A] IRR Internal rate of return [%]
Imax Maximum current to charge the battery without costfixed year Annual fixed service and demand charges [$/yr]
damage [A] d Day of the year [1e365]
SOC State of charge of the battery t Hour of the year [0e8759]
Capbatt The battery capacity [kWh] h Hour of the day [0e23]
Pmax Maximum absorbable power from the AC grid [kW] Dt Time step of simulation [1 h used]
Pload ðtÞ Average demand over hour t [kW] NPCall comp The sum of NPC of all k components and the O&M
hAC AC-DC converter, the rectifier, efficiency [%] cost [$]
DC

hDC DC-AC converter, the inverter, efficiency [%} NPCE from batt The NPC of energy to charge the battery [$]
vh
AC
Hourly noise factor
hbattch Battery charging efficiency [%]
vd Daily noise factor
hbattdisch Battery discharging efficiency [%]
Elquality Life time benefit for electricity quality [$]
Pbi dir The rated power of the bi-directional converter [kW]
Gridcap ut Life time benefit for grid capacity utilization [$]
VDC The DC bus voltage [V]
CSavings Coal savings [kg]
Pfrombatt ðtÞThe load demand met by the battery during peak hours
Ccons peak Coal consumption during peak [kg]
[kW]
Ppeakdir ðtÞ The load demand not met by battery during peak hours Ccons offpeak Coal consumption during offpeak [kg]
[kW] CO2; Avoided CO2 avoided [kg]
d Self-discharge rate COAvoided CO avoided [kg]
lifek Life of component k [years] SO2; Avoided SO2 avoided [kg]
lifepro Life of project [years] NOx; Avoided NOx avoided [kg]
DoD Depth of discharge Sar Rate of sulphur removal [%]
Rk Number of replacement of component k within project ts Percentage of SO2 emission out of sulphur in coal [%]
life [#] hs Desulphurisation rate [%]
NPCk Net present cost of component k [$] NN Mass fraction of nitrogen in coal [%]
Ncycles @ %DoD Number cycles at depth of discharge [#] hn Efficiency of nitrogen to be converted into NOx [%]
Efrombatt Load met by the battery [kWh/day] g Percentage of NOx from the fuel out of the total
costk Cost of component k [$] amounts of NOX emissions [%]
Epeak dir Daily load during peak hours not met by the battery hN Nitrogen removal efficiency [%]
purchased from the grid [kWh/day]

long term. However, South Africa's international and domestic The ToU tariff system has been introduced by Eskom in some
commitments to climate change mitigation means that a significant part of the country. It is an element within the IDM, and has been
part of any new generation infrastructure, needs to be based on introduced to reduce peak demand aside a yearly increase in tariff.
sources “cleaner” than coal. However, cleaner, renewable sources A ToU allows for flexibility of demand deferment with potential to
like wind and solar that forms the major part of the renewable reduce customer electricity bill. It can reduce whole market prices
energy independent power producer procurement (REIPPP) are of electricity, avoid or defer capacity investment, give utility an
intermittent and thus present challenges to grid stability and grid opportunity to operate with more level demand curve, increase the
management, especially at high penetration levels. It is widely integration of distributed energy sources, and decrease environ-
recognised that energy storage is one of the major ways to address mental pollution by avoiding the need for operating a power plant
this challenge. But energy storage technologies are still relatively at peak period [9,10]. Deployment of energy storage (ES) can be
expensive, requiring policy and regulatory interventions that advantageous due to the different pricing regimes for end cus-
improve the commercial viability of their implementation. The tomers. ES system assists in storing energy during low electric price
time-of-use (ToU) tariff system is one such regulatory tool. ToU regimes and discharge the stored energy when the applicable
pricing divides a day into two or three segments with different charge is at peak ToU, usually with a high tariff. This DSM strategy
prices that remain fixed day-to-day over a season. helps to reschedule energy consumption over a period of time and
S.O. Masebinu et al. / Energy 135 (2017) 413e429 415

thus, the end user can reduce the overall cost of electricity by However, they also stated that ES becomes highly important when
shaving consumption, exploiting energy price differential or by emission cut is constrained close to zero without any other
matching demand to supply [11e16]. The use of ES, from a dispatchable-zero-carbon source allowed within the grid. In the
perspective of the consumer owing the ES, will be economical if the work of Kaldellis et al. [25], NaS and PbA, are two batteries with an
total life cycle cost of the ES is less than the total savings in the economic prospect for small to medium scale applications for a
consumer's electricity bill. At grid level, ES can assist in load small island. Whereas, PHES and CAES are more suitable for large
balancing, power quality improvement and bridging of the power scale applications. Hessami and Bowly [30] investigated the eco-
gap [12,15,17e21]. At present, Eskom is exploring battery ES (BES) nomic performance of different ES. They concluded that CAES is
at large scale under the program “Large Scale Energy Storage” more economically viable than batteries for large scale applica-
portfolio (LSES). At Eskom's LSES facility, lithium ion phosphate tion. From the reviewed literature, different methodologies and
battery and sodium nickel chloride battery technologies are being input parameters determine which technology is more appro-
tested and there are plans to install two more flow battery systems priate and economically viable. The literature suggests that while
[22]. The testing period is expected to last over three years with PbA, NaS, and Li-ion are closely competitive, however, the degree
over 1000 nameplate cycles anticipated [22]. While these tests are of uncertainty around their key economic parameters such as the
being conducted for large scale systems, peak shaving at consumer cost of storage, cycle life and efficiency, makes it difficult to decide
side which can immediately reduce peak demand also needs par- on the most appropriate technology with high degree of
allel investigation. confidence.
The technologies for ES are numerous and have been exten- This study aims to contribute to the body of knowledge on ES by
sively discussed in literature [11,23]. The technologies include using a student residence in an academic institution as a case study
mechanical ES; pumped hydro (PHES), compressed air (CAES), and in emerging economies like South Africa that is sometimes faced
flywheel; chemical; zinc bromide (ZnBr), vanadium redox flow with persistent load shedding problems, partly influenced by high
battery (VRFB), lead acid (PbA), sodium sulphur (NaS), nickel energy demand from student residences at peak periods. It is thus a
cadmium(NieCd), iron chrome (FeCr), lithium ion (Li-ion) and good example of a load center where BES could be employed for
hydrogen; electrochemical; capacitors and supercapacitor; and peak shaving as part of IDM. The energy consumption profile of
electromagnetic; superconducting magnetic [11,23]. PHES and student residences tends to follow similar consumption profile on a
CAES are the most cost effective ES for large scale capacity while daily basis, hence combining BES with the implementation of a ToU
batteries are dominating on small to medium scale applications regime might proffer some technical and economic advantages
[23e25]. Of the battery technologies, PbA, NaS, and Li-ion are the both to the grid operator and to the consumer. The tools to assess
most suitable for residential, commercial and industrial applica- the technical and economic suitability of installing BES for resi-
tions, due to technology maturity, high efficiency and low main- dential accommodation exist but they come at a cost and require
tenance cost [26,27]. In recent times, flow batteries have also been expert training to use them. The development of a simple, adapt-
deployed at medium scale level. A pilot project using vanadium able and open access tool to help determine the commercial
redox flow battery has been implemented in South Africa with feasibility of BES deployment would therefore be useful, not just for
reported energy production cost that ranges between 0.3506 and energy managers of these institutions, but also for policy makers. In
0.5409 $/kWh1 [28]. this work, we have improved upon existing methodology and
There has been a number of studies investigating the com- develop a system that helps to address South Africa's specific ToU
mercial viability of BES under ToU regimes. Yan et al. [27] inves- regime. Also, the proposed set of equations has been implemented
tigated BES for commercial buildings considering two ToU in a widely assessable tool, Microsoft Excel Visual Basic Application,
regimes, peak and off peak, and concluded that PbA holds more with a spreadsheet front end for data input. The tool can be used for
economic prospect than NaS and Li-ion batteries. Dufo-Lopez and a deterministic calculation without any additional add-in. To cater
Bernal-Agustin [26] simulated PbA and Li-ion for grid connected for the uncertainty in input parameter, Palisade @Risk add-in was
residential ES under a three regime ToU tariff structure. The study used. The developed tool (downloadable from https://goo.gl/
concluded that at the present high cost of batteries, both PbA and iem29T) was then used to assess the technical and economic ben-
Li-ion are not economical. However, Li-ion holds more economic efits of implementing BES to take advantage of the ToU tariff system
prospect due to higher efficiency. The critical economic elements in South Africa. This study can therefore be useful in shaping future
for the profitability of the system are dependent on the unit cost of policy frameworks for encouraging ES as a grid management and
storage medium and number of cycle to failure. Battke et al. [11] peak shaving mechanism. A further exploration of the emissions
conducted a probabilistic analysis on lifecycle cost of four batte- avoided due to peak shaving is also included to emphasize the
ries across six applications. They concluded that the cost perfor- environmental benefits of ES.
mance of NaS, PbA and Li-ion are close over the applications
investigated, hence, no clear leading technology was identified. 2. System description
Zakeri and Syri [23] expanded on the technologies considered by
Battke et al. [11] and showed the economic performance of The economic viability of peak demand smoothing using BES
different ES scenarios. The study concluded that the cost of the compared to the cost of a system without BES using the City of
storage medium, replacement cost, interest rate, electricity prices Johannesburg's City Power ToU (CoJ-ToU) tariff structure was
and discharge time has higher impact on the levelized cost of investigated in this study. In the CoJ-ToU tariff system, the price of
energy (LCOE) than other parameters. They also reported that the electricity varies for the different time of weekdays (Monday to
effect of uncertainties in techno-economic data can affect evalu- Friday), weekends, low demand season (September to May) and
ation results by 5e17%. Safaei and Keith [29] assessed ES from a high demand season (June to August) as shown in Fig. 1. The
perspective of decarbonisation. The study proposed that only a applicable three ToU structures are:
small proportion of ES is needed to decarbonise electricity as low
priced natural gas provides much more of grid management. 1. Peak-period when demand is expected to be highest, requiring
high electricity production cost via peaking plants, thus the
highest price of electricity. The price of electricity during this
1
1 USD ¼ R14.49 18th April 2016. period is denoted as PrElpeak ;
416 S.O. Masebinu et al. / Energy 135 (2017) 413e429

Fig. 1. CoJ applicable TOU regime for different conditions.

2. Standard-period when demand is expected to be normal or to 2000hr. The corresponding CoJ-ToU pricing regimes for boarding
moderate. The price of electricity during this period is denoted houses, flats, and student commune for weekdays is presented in
as PrElstand ; Fig. 2. On Saturday only off peak and standard TOU are applicable
3. Off peak-period when electricity demand is expected to be low and for Sunday it is an all day off peak.
and less expensive to produce. The price of electricity during The methodology used to size the BES, to simulate the charge
this period is denoted as PrEloffpeak . and discharge sequence, and develop the economic model for using
BES and a system without BES is presented in the next section. The
For weekdays during low demand season in Fig. 1, off-peak TOU metric to assess the economic benefit of using BES could be through
(indicated by the green segment) starts from 2200hr and ends by a number of approaches, including the net present value or cost
0600hr of the next day. It is followed by an hour standard TOU from (NPV/C), the LCOE, internal rate of return (IRR) and the payback
0600 to 0700hr (mid-peak indicated by the yellow segment) and period. All metrics except the payback were used to assess the
thereafter, a peak TOU from 0700 to 1000hr. Then a standard TOU profitability of the system described in this study. Payback does not
continues from 1000 to 1800hr, followed by a peak TOU from 1800 account for benefit that occur after break even and therefore it does

Fig. 2. CoJ price of electricity under a TOU for weekdays.1.


S.O. Masebinu et al. / Energy 135 (2017) 413e429 417

Fig. 3. Power demand for 17th April 2016.

not measure profitability adequately. It is only applicable if at the average hourly load profile produced from the simulation is
end of a project life, the net cash inflow outweighs the net cash shown in Fig. 4. The boxplot shows the aggregated minimum, first
outflow. Also, due to replacement of storage medium there is a quartile, mean, third quartile and maximum energy consumption
possibility of recording more than one payback period. Therefore, it for 24-h. The outliers are represented by black dots and are
has not been considered in this study. excluded from the calculation. Electrical loads tend to be noisy as
their energy consumption and time of use are not constant at
3. Methodology every time step. Therefore, to simulate consumption of energy
over a year from the two months' data collected, some degree of
3.1. Description of case study variability termed as noise were introduced into the average daily
energy consumption data. The noise analysis was introduced to
A residence with 17 rooms occupied by students from the Uni- account for hourly, daily and seasonal variation as presented in
versity of Johannesburg was used as the reference for this study. Equation (1). The hour (t) for a particular day, d, in the year is
Energy consumption data for the residence was logged using an calculated in Equation (2).
Engage Efergy energy data logger. The energy data logger consists
of three current transformer (CT) clamps, a transmitter, receiving Pload ðtÞ ¼ Pavg *ð1 þ vh vd Þ (1)
hub and a router. The power demand data for a typical weekday is
shown in Fig. 3. t ¼ ½ðd  1Þ*24 þ h (2)

3.2. Load data and energy consumption where t is each hour for the year from 0 to 8759, d is days of the
year from 1 to 365, and h is hours for a day from 0 to 23. Matlab
The load data retrieved from the data logger over the month of was used to simulate and generate the yearly data from the logged
April and May 2016 was the basis for the yearly simulation. The data as shown in Fig. 5 according to procedure presented by

Fig. 4. Summarised hourly energy consumption for April 2016.


418 S.O. Masebinu et al. / Energy 135 (2017) 413e429

Fig. 5. Simulated load data.

Okundamiya et al. [31]. Column ðh  1Þ matrix is the hourly load, affect the stability, and reliability of electricity supply as well as
Pload ðtÞ [kW], can be represented as a ðh  dÞ matrix by multi- the utilization rate of generating plant capacity. All of these can
plying Pavg with a row ð1  dÞ matrix of ones. The hourly noise be minimised with the implementation of BES which will
function, vh , is a ðh  1Þ matrix whereas the daily noise function, shift peak load to off-peak period and reduce the peak to valley
vd , is a ð1  dÞ matrix. The hourly and daily noise input values are gap.
randomly generated from a normal distribution. The normal dis- The average daily Eoffpeak, Estand and Epeak as calculated
tribution has an average of zero and a standard deviation equal to according to Equation (3) were 105.88, 102.26 and 55.23 kWh
the hourly and daily noise factors respectively [32e34]. These respectively. The applicable ToU hours and tariffs were presented
factors are considered here as 0.8 and 0.1 respectively, which were in Figs. 1 and 2. The tariffs are for 2015/2016 CoJ-ToU rates for a
calibrated from the real-time load data using regression tech- hostel, large commune, and flats. These tariffs are also applicable
niques [35]. The annual consumption under the three TOU re- over the weekend except that there are no peak charges.
gimes was then calculated from the simulated Pload ðtÞ as shown in Hence, the battery is constrained not to discharge over week-
Equation (3) ends. Other technical and economic inputs are presented in
Table 1. The fixed cost in Table 1 represents both service and
X
8759  demand charges.
ETOU ¼ Pload LD ðtÞ þ Pload HD ðtÞ (3)
t¼0

The average daily energy consumption of the residence was 3.3. BES sizing
256.59 kWh from the logged dataset. However, the simulated
data with noise inclusion and seasonal variation, the average The average energy required from the batteries was 22.09 kWh,
daily consumption is 263.37 kWh. The peak to valley ratio of the 40% of the average daily peak energy. The decision for 40% of peak
simulated data was 5.12 and the minimum daily load factor was was to cater for lightings and other low power appliances, while all
0.19. The small daily load factor and huge peak to valley ratio other heating appliances in the residence such as electric geyser,
cooker and flat iron are covered by the grid. The capacity of the
batteries, Capbatt , chosen were 32.54, 30.95 and 29.22 kWh for PbA,
Table 1
Techno-economic input parameters. NaS, and Li-ion respectively based on their mean round trip effi-
ciency presented in Fig. 8. With SOCmin of 20%, the available ca-
Parameters (unit) Values
pacity were 26.03, 24.75 and 23.38 kWh for PbA, NaS and Li-ion
Fixed cost ($/yr) 439 battery respectively. The Efrom batt was the product of the avail-
SOCmin (%) 20
able capacity with the battery discharge efficiency and the DC-to-
Life of project (yr) 25
Life of bi-directional converter (yr) 10 AC inverter efficiency. Equal battery charge and discharge effi-
Unit cost of bi-directional converter ($/kW) 345 ciency was considered. These were calculated by taking the square
Direct current voltage (V) 48 root of the round-trip efficiency [36]. With a VDC ¼ 48 V, the Ah
Time step (hr) 1
capacity required is 678, 645, and 609 Ah for PbA, NaS and Li-ion
Component inflation (%) 2
O&M escalation rate (%) 2
respectively. The choice of battery that can be implemented var-
Electricity escalation rate (%) 9 ies, for example, PbA battery in South Africa cost on average 162
Interest rate (%) 9 $/kWh [37]. The Trojan L16HC model, 420 Ah/6 V, can be used (2
AC-to-DC and DC-to-AC efficiency (%) 98 parallel strings of 8 in series). Similar considerations were also
given to NaS and Li-ion BES.
S.O. Masebinu et al. / Energy 135 (2017) 413e429 419

Fig. 6. Grid connected ES system.

3.4. Sequence of operation for the BES voltage. Taking a time step, Dt , of 1 h, the SOC rises from
SOCðt  DtÞ to SOCmax . The SOC at any time t, SOCðtÞ, is calculated
The methodology presented by Dufo-Lopez and Bernal-Agustin using Equation (5) [36]. During the charging duration, the battery
[26] serves as the basis for analysis. The BES system schematic does not supply any power to meet load. That is both Pfrom batt ðtÞ
presented in Fig. 6 consists of a battery bank and power conversion and Ppeak dir ðtÞ are zero. All load requirements are met by the AC
system (PCS) that includes the following: battery charger (AC-to- grid.
DC), inverter (DC-to-AC) and charge/discharge controller for the

"  #
ðSOCmax  SOCðt  1ÞÞ*Capbatt *1000 Pmax  ðPload ðtÞ*1000ÞÞ*hAC=DC P
VDC bi dir
Ibatt ðtÞ ¼ min Imax ; ; ; (4)
Dt VDC VDC

battery. The PCS could be a single bi-directional unit as assumed in


this paper while the control can be configured to suit the consumer
Ibatt ðtÞ*Dt*hbatt
need. The BES will be used to provide part of the peak load. The SOCðtÞ ¼ SOCðt  DtÞ þ ch
(5)
accrued benefit is derived from arbitrage; buying electricity during Capbatt *1000
VDC
off peak period at PrEloffpeak to charge the battery and discharging
During standard period: the AC grid satisfies all load
during peak period at PrElpeak . The BES in this case is grid connected
requirement of the residence. Switch 1 and 2 are open, hence no
and is charged by a conventional energy source. It is assumed that current flows into the battery, that is Ibatt ðtÞ is zero, and the bat-
the control strategy presented in Fig. 6 is ideal and component tery do not discharge to meet load, Pfrom batt ðtÞ is zero. The
efficiency is constant over each charge and discharge cycle. The
available capacity of the battery is the difference between the
technical charging and discharging constraints imposed on the
SOCmax and any self-discharge (d) during an idle period as calcu-
system is described below (flowchart Fig. 7);
lated in Equation (6).
During off-peak period: switch 1 is closed while switch 2 is
open. If the battery is at a SOC lower than the SOCmax , current Ibatt ðtÞ
[A] flows into the battery through the rectifier to charge the battery. SOCðtÞ ¼ SOCðt  DtÞ*ð1  dÞ (6)
From Equation (4) [36,38], the current Ibatt ðtÞ flowing into the During peak period: switch 1 is open, switch 2 is closed and
battery is the minimum current required to charge the battery to a current, Ibatt ðtÞ, flows through the closed switch Equation (7) [39].
SOCmax over the offpeak hours, in this case, it is 6 h, Pmax is the The battery discharges to meet all load Pload ðtÞ or part of it
maximum absorbable power from the AC grid and VDC is the DC bus depending on the discharge constraint. The discharge constraint
420 S.O. Masebinu et al. / Energy 135 (2017) 413e429

Fig. 7. Flow chart of the charging and discharging of the BES.

implemented in this study, was that the BES should deplete its load satisfied by the AC grid Ppeak dir ðtÞ is the difference between
capacity to SOCmin over the 5 h peak period. Therefore, the power the load Pload ðtÞ and the load satisfied by the battery, Pfrom batt ðtÞ
from the battery, Pfrombatt ðtÞ, can be calculated from Equation (8). calculated from Equation (10).
The SOC reduces from SOCðtÞ to SOCmin each day Equation (9). The
S.O. Masebinu et al. / Energy 135 (2017) 413e429 421

Fig. 8. MCS input parameters.

"  #
SOCðt  1Þ  SOCmin Þ*ðCapbatt
VDC
*1000Þ
P ðtÞ*a*1000 Pbi dir
Ibatt ðtÞ ¼ min Imax ; D ; load ; (7)
Dt VDC *hDC=AC VDC *hDC=AC

investigation, the battery will discharge at high current and once


Ibatt ðtÞ*hDC=AC *VDC SOCmin is achieved, in about 2 h, the charging of the battery com-
Pfrombatt ðtÞ ¼ (8)
1000 mences. Therefore, the most critical consideration in estimating the
battery life for this case is the degradation caused by the energy
Ibatt ðtÞ*h Dt cycled [26]. Other factors which can also impact on the life of the
SOCðtÞ ¼ SOCðt  DtÞ  batt disch
(9) battery but has not been considered are handling and storage
Capbatt *1000
VDC condition, operating temperature, battery chemistry and corrosion.
The life of bi-directional converters is dependent on the manufac-
Ppeak dir ðtÞ ¼ Pload ðtÞ  Pfrom batt ðtÞ (10) turer's quality control, quality of installation, exposed environ-
mental conditions and usage. Generally, it is between 8 and 15
Having known the load satisfied by the BES and that not met by
years [26,40]. The average of 10 years will be used for the bi-
it, the annual energy from the BES and part of the peak purchased
directional converter while the battery life will be calculated from
from the grid can be calculated from Equation (11) and Equation
Equation (13) as adapted from Ref. [36].
(12) respectively.
Capbatt *DoD*Ncycles @ %DoD
X
8759  Lifebatt ¼   (13)
Efrombatt
Efrom batt ¼ Pfrom batt LD ðtÞ þ Pfrom batt HD ðtÞ (11) hbattdisch *hDC=AC
t¼0

X
8759 
Epeak direct ¼ Ppeak dir LD ðtÞ þ Ppeak dir HD ðtÞ (12) 3.5.2. Component replacement
t¼0
The number of replacement for each component k within the
project is the integer value obtained by dividing the project life,
Lifepro , by the component life, Lifek , as shown in Equation (14).

3.5. Cycle life and replacement of components  


Lifepro
Rk ¼ integer (14)
Lifek
3.5.1. Life of components
If the life of component k, Lifek , is less than the project life,
Lifepro , there will be a need to replace component k. We only
focused on the storage medium and the bi-directional converter for 3.6. Economic modelling
replacement though other components like fuse and switches
might also need replacement. The life of a battery can be estimated The net present cost of component k, NPCk , is the cost of acquiring
either by the number of cycles to failure or lifetime throughput the component, plus the cost of replacement due to failure or end of
energy before failure [40]. Due to the case study under component's life over the project lifetime minus the value of the
422 S.O. Masebinu et al. / Energy 135 (2017) 413e429

remaining component's life that has not been used at the end of the NPCwout BES is the sum of the fixed service charge with the sum-
project. NPCk is calculated by Equation (15). The first term is the cost mation of the product of the total energy consumed during each
of the component, the second term is the cost of replacement of the ToU by the applicable ToU tariff. The NPCwith BES calculates in
component over project life and the third term is the value of the addition to the cost of acquiring the BES and energy cost for
component not used at the end of the project life. charging the BES, the cost of the energy not met by the BES,
Epeak direct , for both low and high demand seasons. If the NPCwith BES
0 !
X
Rk
ð1 þ gk Þj*lifek is less than the NPCwout BES , implementing BES hold some prospect
NPCk ¼ costk þ @ costk * for further investigation. The NPCwout BES , is calculated by Equation
j¼1 ð1 þ iÞj*lifek (20) and NPCwith BES , by Equation (21).
!1
costk ð1 þ gk Þlifepro A "
 *½lifek *ð1 þ Rk Þ* (15) X
lifepro  
lifek ð1 þ iÞlifepro NPCwout BES ¼ PrElpeak LD *Epeak LD þ PrElpeak HD *Epeak HD
j¼1
Added to the NPC for all components is the net present operation  
þ PrElstand LD *Estand LD þ PrElstand HD *Estand HD
and maintenance cost for all components, NPCO&M , within the  
project life. þ PrEloffpeak LD *Eoffpeak LD þ PrEloffpeak HD *Eoffpeak HD
The NPCO&M is calculated by Equation (16) [41]. Hence the #
 ð1 þ g Þj
PrEl
overall NPC and O&M cost for all components over the project life is þ costfixed year *
given by Equation (17). ð1 þ iÞj
(20)
!
X
life pro
ð1 þ gO&M Þ j
NPCO&M ¼ costO&M * (16) NPCwith BES ¼ NPCall comp þ NPCE from batt
j¼1 ð1 þ iÞj "
X
lifepro 

þ PrElpeak LD *Epeakdirect
X LD
NPCall comp ¼ ðNPCk Þ þ NPCO&M (17) j¼1
 
k þ PrElpeak HD *Epeak direct HD þ PrElstand LD *Estand LD
The energy from the BES, which was earlier purchased from the  
þ PrElstand HD *Estand HD þ PrEloffpeak LD *Eoffpeak LD
grid is discharged during peak hours. Net present cost of energy

from the BES, NPCE from batt , is calculated by Equation (18) [36]. þ PrEloffpeak HD *Eoffpeak HD
Equation (18) sums up the total energy to charge the BES during #
 ð1 þ g Þj
low demand season and multiply it by PrEloffpeak LD. Similarly, the PrEl
þ costfixed year *
sum of the energy to charge the BES during high demand season is ð1 þ iÞj
multiplied by PrEloffpeak HD. The sum of both energy cost is calcu- (21)
lated over the life of the project including the charging and dis-
charging efficiencies and the AC-DC and DC-AC efficiencies. The If the difference between NPCwout BES and NPCwith BES is positive, i.e
result is then discounted to calculate the NPCE from batt . greater than zero, then deploying BES is said to be profitable. The
difference for the saving accrued for exploiting BES is presented in

2P8759  P
8759
 3
X batt LD ðtÞ*PrEloffpeak LD þ t¼0 Pfrm batt HD ðtÞ*PrEloffpeak HD
life Pfrm
pro
4
t¼0 ð1 þ gPrEl Þj 5
NPCE from batt ¼ * (18)
AC *hbatt
hDC ch *hbatt disch *hDC ð1 þ iÞj
j¼1 AC

Having known the NPCall comp , NPCE from batt and Efrombatt , the peak Equation (22)
price of electricity needed, PrElpeak needed , to evaluate the profit-
ability of deploying BES can be calculated as presented in Equation NPVsavings ¼ NPCwout BES  NPCwith BES (22)
(19). The numerator term gives the life cycle cost of acquiring the
The percentage of NPV saving for using BES with respect to case
BES while the denominator term gives the lifetime energy pro-
without BES is given by Equation (23).
duction of the BES. If the PrElpeak needed is less than the prevailing
weighted average PrElpeak , then making use of BES will be profit-
NPVsavings
able. The weighted average price of peak caters for different peak %NPVsavings ¼ *100% (23)
prices for the different seasons within the year. NPCwout BES
Another metric for economic evaluation is the LCOE for
NPCall comp þ NPCE from batt deploying BES. The LCOE aggregates the lifetime cost of the system
PrElpeak ¼  (19) and the lifetime energy production to determine the minimum
needed Plifepro ð1þgPrEl Þj
j¼1
Efrom batt * j price ($/kWh) at which energy generated by any system must be
ð1þiÞ
sold to break even over the life time of the project. It is desirable to
To further assess the profitability of utilising BES, comparing the have a selling price above the minimum LCOE. If the LCOE of a
NPC of a system without BES, NPCwout BES , to that with BES, system with BES, LCOEwith BES , is less than the LCOE of a system
NPCwith BES , is another metric for economic comparison. The without ES, LCOEwout BES , then the deployment of BES is said to be
S.O. Masebinu et al. / Energy 135 (2017) 413e429 423

profitable. The LCOEwout BES is calculated by Equation (24) while Notwithstanding the exclusion of RE sources in this present study,
LCOEwith BES is calculated by Equation (25) [42]. The difference be- other techno-economic and environmental benefits of using ES
tween the LCOEwith BES and PrElpeak needed lies in the additional cost include improved electricity quality, maximizing grid capacity
of the unmet load by the ES system purchased from the grid that and reduction in associated air pollution from conventional en-
was included in the LCOEwith BES . ergy sources.

NPCwout BES 3.8.1. Improved electricity quality


LCOEwout BES ¼ P  (24)
8759 BES system can flatten out sudden short-duration surges on
t¼0 Pload ðtÞ *lifepro
waveform caused by variation in voltage, frequency, harmonics,
and power factor to improve power quality and protect the cus-
NPCwith BES
LCOEwith BES ¼ P  (25) tomer's sensitive processes and load [50e53]. Also, BES can provide
8759
t¼0 Pload ðtÞ *lifepro an uninterrupted power supply to support customer load during
power disruptions and assist in resynchronization of load with the
Another econometrics for investment decision making is the grid when power is restored [17,47,54,55]. According to Schoenung
internal rate of return (IRR) of an investment. It is the discounting and Eyer [56], the annual benefit for improving electricity quality is
rate that equates the NPV of the negative and positive cash flows. about 750 $/kW. Equation (27) gives the project lifetime benefit for
That is, the discounting rate at which the total NPVsavings is zero. This improving electricity quality, Elquality .
is given by Equation (26) and iteratively calculated by changing i.
Efrom batt
IRR ¼ i; when NPVsavings ðiÞ ¼ 0 (26) Elquality ¼ *lifepro *750 (27)
hdisch dur

3.8.2. Improved grid capacity utilization


3.7. Probabilistic approach BES system can reduce the urgency or defer the need for
investing in new transmission and distribution facilities and sub-
Known to BES are the lack of consistent data on technical and stations by storing energy until there is less stress on the grid
economic parameters, uncertainties about feasible uses, and ul- [11,51]. BES systems are used to avoid congestion-related charges
timately cost competitiveness. Although, an extensive review of that occur during high demand period when cheap energy cannot
literature exists for technical characteristics and cost details be delivered to some loads due to transmission facilities peaking
[23,43e49], the degree of variability of such reviews are high. during such period. According to Schoenung and Eyer [56], the
Despite the variability associated with the technical and economic annual benefit for grid capacity utilization, Gridcap ut , is about 650
parameters for BES, there is still a need to appropriately match
$/kW. The project life time benefit is given in Equation (28).
pairs of technology and application towards a cost-effective de-
cision making. To cater for the uncertainties, a probabilistic Efrom batt
approach through Monte Carlo Simulation (MCS) was employed. Gridcap ut ¼ *lifepro *650 (28)
hdisch dur
MCS is governed by the law of large numbers around the mean
distribution. The MCS model requires an adequate number of
simulation to achieve the distinctive calculation accuracy. 10,000
iterations as proposed by Baumann et al. [24] was therefore 3.8.3. Reduced emission of grid power generating source
implemented in this study. The reference technical values used for South Africa is the fifth largest coal producing country in the
simulation were derived from Baumann et al. [24] while the cost world and third largest exporter of the commodity [57]. 77% of its
of storage medium was retrieved from Sustainable [37]. Fig. 8 energy needs is being met by coal and about 90% of electricity
shows the minimum, first quartile, mean, third quartile and generation is from coal-fired plants [7,57]. By making use of BES,
maximum input parameters for the MCS of each BES technology emissions from coal-fired plant during peak period can be reduced
investigated. Fig. 8aed are the number of cycle life at 80% depth of due to peak demand shifting. The emissions include CO2, SO2, NOx,
discharge, round trip efficiency, battery acquisition cost and and CO.
operation and maintenance cost of each BES technology respec- The coal required to manufacture the BES is calculated based on
tively. High variability was observed in the data as presented in the battery medium weight and equivalent CO2 emitted presented
Fig. 8. The MCS was conducted using Program Evaluation and in Equation (29) according to [58]. The CO2 emission (kg CO2,eq./kg
Review Technique (PERT) distribution based on a beta distribution of battery weight), SCO2 , is given as 0.9, 1.2 and 12.5 while energy
as proposed by Battke et al. [11]. The PERT is insensitive to density, En denbatt , is given as 0.04, 0.2, and 0.13 kWh/kg for PbA,
extreme value unlike the triangular distribution and requires NaS and Li-ion respectively [58]. On average, 2.6 ton of CO2 is
three inputs; the minimum, mode (most likely parameter) and emitted per ton of coal combusted [27]. The coal savings, CSavings , for
maximum values for each parameter. The mean has been using BES is given by Equation (30) [27]. It is estimated by finding
considered as the most likely parameter in this study. The factors the difference between the mass of coal consumed to charge the
considered for MCS, which is assumed to be mutually uncorre- BES during off peak hours, Ccons offpeak , mass of coal avoided for
lated, are cycle life, round trip efficiency, storage cost, and oper- using BES during the peak period, Ccons peak and mass of coal
ation and maintenance cost. required to manufacture the BES. Other emissions are calculated
based on the CSavings . The avoided CO2 emission from the CSavings ,
3.8. Other benefits of BES CO2; Avoided , is given by Equation (31).

In this study, only conventional electrical energy source was Capbatt


* SCO2
En denbatt
considered to charge the BES. The use of BES supports the inte- Crequired ¼ (29)
gration of renewable energy (RE) sources, which will be consid- 2:6
ered as part of a more sustainable project in the future.
424 S.O. Masebinu et al. / Energy 135 (2017) 413e429

Table 3
  Deterministic viability result.
CSavings ¼ Efrom batt *Ccons peak
Base Case Result Lead Acid NaS Li-ion
! !
X
8759 Cycles @ 80% DoD [#] 775 2659 3752
 Pbidir *tchar *Ccons offpeak *Lifepro  Crequired Round trip efficiency [%] 75 83 93
Storage Cost [$/kWh] 162 395 643
t¼0
O&M Cost [$/kW-yr] 9.39 17.94 10.21
(30) Results
Battery life 2.99 10.72 16.29
NPC Comp [$] 26,866 22,964 26,219
CO2;Avoided ¼ 2:6*CSavings (31)
NPC E-From Bat [$] 10,748 9271 7683
Price of Peak needed [$/kWh] 0.2620 0.2353 0.2595
Methodologies for estimating CO, SO2 and NOx emission from
Cost of battery [$/kWh Cycled] 0.2616 0.1859 0.2139
power generating plants are immature according to Yan et al. [27]. NPC w/o BES [$] 187,963 187,963 187,963
A recent approach presented by Yan et al. [27] for CO, estimated NPC with BES [$] 209,085 204,456 207,247
that on average, 0.23 kg of CO is emitted per ton coal, Equation (32). NPV Saving [$] 21,122 16,493 19,284
The avoided SO2 and NOx emission were estimated by Equation (33) LCOE w/o BES [$/kWh] 0.0782 0.0782 0.0782
LCOE with BES [$/kWh] 0.0870 0.0851 0.0862
and Equation (34) respectively [27]. In Equation (33), the ratio 64/ %NPV Saving 11.24% 8.77% 10.26%
32 represents SO2 molecular weight with respect to elemental Minimum daily load factor 0.2126 0.2206 0.2324
sulphur molecular weight while in Equation (34), the ratio 30.8/14 Peak to valley ratio 4.7045 4.5323 4.3020
represents NOx molecular weight to elemental nitrogen molecular Reduction in peak [%] 8.16% 11.52% 16.02%
weight. Other parameters have been defined in the nomenclature
list and the constants used is presented in Table 2 according to [27].
The results of the simulation are presented in Table 3. The re-
CSavings sults show that none of the BES yielded any positive return on
COAvoided ¼ 0:23* (32)
1000 investment over the 25 years project life at the current ToU tariff
rates. Of the three, NaS had the highest likelihood of profitability
64 with the least PrElpeak needed . However, the PrElpeak needed was 63%
SO2; Avoided ¼ *C *Sar *ts *ð1  hs Þ (33)
32 Savings higher than the average PrElpeak . As earlier presented, for a system
with BES to be profitable, either the NPCwith BES < NPCwout BES or
30:8 h LCOEwith BES < LCOEwout BES or the calculated
NOx;Avoided ¼ *CSavings *NN * n *ð1  hN Þ (34)
14 g PrElpeak needed < PrElpeak . None of the BES technologies had their
NPC or LCOE below the system without BES nor their
PrElpeak needed below the average selling price of peak of 0.1442
$/kWh. The NPVsavings of the three technologies were higher than
4. Results and discussion that of a system without BES by 11.24%, 8.77% and 10.26% for PbA,
NaS and Li-ion respectively. Considering PbA with a low storage
4.1. Simulation of BES medium cost, but also a low life cycle and low cycling efficiency,
these resulted in high cycling cost 0.2616 $/kWh/cycled, high
After supplying all needed parameters into the developed number of replacement with associated cost (NPCk ) as well as the
spreadsheet, we simulated the operation of the system. Fig. 9 shows high cost of the energy produced (NPCE from batt ). On the other
the mean demand (P_load [kW] No Storage) from the simulated hand, Li-ion had the highest storage medium cost but with a high
data extracted from the mean data logged, as well as charge, cycle life and efficiency which both saw to it low energy cycling
discharge and state of charge profile for PbA. The resulting peak to cost of 0.2139 $/kWh/cycled with high technical benefit of
valley ratio decreased from 5.12 to 4.70, 4.53, and 4.30 for PbA, NaS, reduction in peak yet its PrElpeak needed was higher than the
and Li-ion BES respectively as shown in Table 3. The minimum daily
average PrElpeak by 80% when compared to 63% of NaS and 82% of
load factor also increased from 0.19 to 0.21, 0.22, and 0.23. The
PbA.
increase in load factor, though not significant due to the size of BES
and percentage peak covered, notwithstanding, this indicates bet- Since the deterministic approach is not sufficient to truly assess
the impact of uncertainties in econometric analysis, as explained in
ter utilization of generating capacity. This is particularly important
where demand during off-peak without BES falls significantly section 3.7, a probabilistic approach was considered. Fig. 10 and
below base load. The valley created can be harnessed to charge the Fig. 11 show the mean PrElpeak needed and mean LCOE with 95% error
BES. Also, the reduction in peak to valley ratio due to BES ensures bar taking into consideration uncertainties in input parameters.
power quality stability and improvement such that the generating The 95% error bar indicates the range in which 95% of the results
plant ramping rate to cover short peaks is reduced. generated by the MCS lie. The average selling PrElpeak considering
summer and winter price differential and the LCOE of the system
without BES is represented by the dotted line. For a BES technology
Table 2 with a mean price below the dotted line, such BES is said to be
Environmental benefit Constants.
economically viable. The uncertainty analysis showed that the most
Parameters values financially viable technology is NaS with the least PrElpeak needed of
Sar 1% 0.2560 $/kWh (0.2160 $/kWh/cycled) while PbA is the least
ts 95% economically viable technology as shown in Fig. 10. The
hs 80%
PrElpeak needed for Li-ion and PbA were 0.2795 and 0.2954 $/kWh
NN 32%
hn 1.5% respectively. Factors that aided NaS economic performance were
g 99% the moderately low cost of storage medium compared to Li-ion, its
hN 0.8% high cycle life, and cycling efficiency. After consideration of
S.O. Masebinu et al. / Energy 135 (2017) 413e429 425

Fig. 9. Charge discharge sequence after implementing BES.

uncertainties, the PrElpeak needed deviated from the deterministic 4.2. Sensitivity analysis
price by 26.29%, 8.87% and 7.56% with a wide range of lower and
upper bound for PbA, NaS and Li-ion batteries respectively as In the past two years, an annual increase in the price of elec-
shown in Fig. 10. The lower and upper bound for each BES tech- tricity has been observed. Both peak and off peak prices are affected
nology shows that the impact of uncertainties in cost and technical by the increase. Since none of the three BES technologies is
data exceed by far the differences in the mean PrElpeak needed across economically viable based on their current technical performance
technologies. Furthermore, the LCOE in Fig. 11 shows that despite characteristics and average PrElpeak , we investigated varying
the variation in PrElpeak needed , a strong competition exists between PrElpeak as well a reduction in the cost of the storage medium on the
NaS and Li-ion BES for peak shaving application as the degree of profitability of using BES. Sensitivity analysis was conducted within
variation was minimal in both BES technologies. the MCS framework to find the combination of the economic pa-
rameters within control of policy makers to make the system

Fig. 10. Price of peak needed compared to the average price of electricity.
426 S.O. Masebinu et al. / Energy 135 (2017) 413e429

Fig. 11. LCOE with BES compared to LCOE without BES.

profitable. The results reported are the mean values after 10,000 In all scenarios where the PrElpeak only was increased without a
iterations of the MCS for each of the eleven scenarios considered. decrease in cost of storage, the PrElpeak needed remained the same.
The scenarios are presented below; This is valid because only parameters of production cost such as
PrEloffpeak , costk etc. will alter the price of peak needed while the
A - 25% increase in both summer and winter peak prices
selling price PrElpeak will only affect the return on investment. At
B - 50% increase in both summer and winter peak prices
scenario A, B, and C, increasing the PrElpeak did not lower the price
C - 100% increase in both summer and winter prices
D - 25% decrease in cost of storage medium only of peak needed but increased the accrued NPVsavings by reducing the
E - 50% decrease in cost of storage medium only margin between NPCwout BES and NPCwith BES as shown in Fig. 12. A
F - 25% decrease in cost of storage medium þ50% increase in similar trend was also observed for the LCOE in Fig. 13. NPVsavings for
both peak prices using BES with 100% reduction in the price of peak compared to a
G - 25% decrease in cost of storage medium þ100% increase in system without BES increased by 63.68%, 81.26% and 69.92% for
both peak prices PbA, NaS and Li-ion respectively as shown Fig. 14.
H - 50% decrease in cost of storage medium þ50% increase in Aside increasing PrElpeak , consideration was given to reduction
both peak prices in the cost of storage, scenario D and E. This could be implemented
I - 50% decrease in cost of storage medium þ100% increase in through a subsidy programme. Conversely to scenario A, B, and C, a
summer peak price only reduction in cost of storage did not alter the average PrElpeak rather
J - 50% decrease in cost of storage medium þ100% increase in it lowered the PrElpeak needed for each BES technology. The response
summer peak price þ50% increase in winter peak price of these economic indicators to change in parameters are useful as a
K - 50% decrease in cost of storage medium þ100% increase in guide to policy makers as two different approaches could be
both summer and winter peak price employed to drive the profitability of the system. At 50% reduction

Fig. 12. Sensitivity analysis on price of peak needed.


S.O. Masebinu et al. / Energy 135 (2017) 413e429 427

Fig. 13. Sensitivity analysis on LCOE.

Fig. 14. Effect of scenarios on NPV savings.

in cost of the storage medium, the cycled energy cost ($/kWh/cycle) summer period by 100% with 50% discount on storage cost, scenario
were 0.1960 for PbA, 0.1077 for NaS and 0.1201 Li-ion BES. NPVsavings I. At this condition, only NaS yielded a positive return on invest-
of the system increased by 54.81%, 57.29% and 59.68% compared to ment with a NPVsavings of 0.2%. Increasing winter PrElpeak by 50%,
50% increase in PrElpeak with the NPVsavings as 31.89%, 40.57% and scenario J, the three BES technologies yielded a positive return on
34.97% for PbA, NaS and Li-ion respectively. Cost reduction strongly investment. Prevailing PrElpeak was 0.2036 $/kWh while the
favours high technical performing technologies like Li-ion towards PrElpeak needed for PbA was 0.1960, NaS was 0.1753 and Li-ion was
profitability as seen by the 59.68% increase in savings. 0.1808 representing 0.47% (1088 $), 1.69% (3938 $), and 1.28% (2973
Scenario F and G investigated 25% reduction on storage medium $) savings respectively. The IRR at this scenario was 10.06%, 14.1%
cost with 50% and 100% increase in the PrElpeak . At 100% increase, and 11.72% for PbA, NaS and Li-ion respectively. At 50% storage cost
the price of peak was 0.2298 $/kWh while PrElpeak needed for PbA, reduction and 100% increase in both price of peaks, scenario k,
NaS and Li-ion were 0.2457, 0.2160 and 0.2305 $/kWh. Only NaS PrElpeak increased to 0.2298 $/kWh resulting in 1.93% (4745 $),
was profitable at this condition with its PrElpeak needed < PrElpeak . At 3.02% (7457 $) and 2.56% (6301 $) savings with IRR of 12.09%,
50% storage medium cost reduction with 50% increase in the price 16.92% and 14% for PbA, NaS, and Li-ion respectively. From this
of peak, scenario H, the BES cycled energy cost were 0.1560 $/kWh/ analysis, it can be deduced that though the system showed a pos-
cycle for the least efficient BES, PbA, 0.1077 $/kWh/cycle for NaS itive return on investment, the savings were not quite huge.
and 0.1201 $/kWh/cycle for Li-ion. At these cycled costs, the Reduction in storage cost and increase in average PrElpeak are
LCOEwout BES was 0.0904 $/kWh while for NaS with the highest needed for the profitability of implementing BES.
likelihood of profitability, the LCOE was 0.0905 $/kWh which was From the sensitivity analysis conducted above, the driving fac-
not sufficient to break even as the LCOEwith BES > LCOEwout BES . tors for the economic viability of implemented technologies were
Since summer ToU tariff accounts for 273 days of the year, its the prevailing cost of storage, the cycle life, cycling efficiency and
long duration impacts on the economics evaluation. We therefore cycled cost. This study shows that the present average PrElpeak
investigated the impact of increasing the selling price of peak over 0.1442 $/kWh is below the PrElpeak needed to encourage the use of
428 S.O. Masebinu et al. / Energy 135 (2017) 413e429

grid-tied BES. For BES to be economically viable, the cycling cost of is because the disposal of BES can account as benefit derived from
storage medium should be less than 0.1560 $/kWh for PbA, 0.1077 recycling the BES. This cost/benefit for the end of life of the BES vary
$/kWh for NaS and 0.1201 $/kWh for Li-ion. At these energy cycling depending on the location where the disposal is performed. We
costs, an average PrElpeak of 0.2042 $/kWh is required. A price above therefore assume that the cost benefit of disposing the BES negates
the PrElpeak is needed if the deployment of grid-tied BES is to be the environmental cost to the consumer.
encouraged. Where no discount of the storage medium is provided,
that is at the current technology rate, the PrElpeak needed to break 5. Conclusion
even were 0.2919 $/kWh, 0.2560 $/kWh and 0.2795 $/kWh for PbA,
NaS and Li-ion respectively. In Denmark and Germany with rela- The technical and economic performance of three BES, PbA, NaS
tively developed ES markets, the average price of electricity is and Li-ion batteries was investigated under a South African ToU
0.3485 $/kWh in Denmark and 0.3382 $/kWh in Germany. The tariff rate. The study concluded that the prevailing average PrElpeak
average cost of electricity across Europe is 0.2422 $/kWh [59]. This is not favourable for the deployment of BES to take advantage of
shows that the present PrElpeak is relatively cheap and thus energy arbitrage. The study proposed a minimum average PrElpeak
implementing BES is not economically viable. To support the up- of 0.2043 $/kWh with cycling cost of 0.1560 $/kWh for PbA, 0.1077
take of BES as a demand side management solution, thereby $/kWh for NaS and 0.1201 $/kWh for Li-ion. The proposed costs are
reducing peaks, it might be feasible to support the investment of the minimum if the BES system is to break even during it life time,
consumers on the uptake of storage technologies. Such investment however, a PrElpeak above the minimum and energy cycling cost
coupled with high deployment rate will accelerate development below the proposed are desirable. Assessing the environmental
and technology improvement through research, create more performance of the system, Li-ion battery yielded superior envi-
competition within the storage market and eventually drive the ronmental performance due to high round trip efficiency though
cost of storage downward. This will make storage financially lagged on economic evaluation where NaS leads. Considering both
attractive even without subsidy in the long run. While we strongly the technical and environmental performance of the three tech-
encourage some form of investment on storage cost through sub- nologies, a close competition between NaS and Li-ion exist but Li-
sidy, the scheme should ensure that the peak load being avoided is ion leads on environmental consideration. PbA will compete
well managed in such a way the network benefit. Uncoordinated closely with the other two technologies if its cycle life and effi-
charging of storage system can have a negative effect on grid ciency are improved upon.
balancing itself and therefore negate the motive behind this The constant price of peak needed for scenarios A, B and C
proposition. suggests that increasing the PrElpeak only was not sufficient to move
the system into profitability but lowering PrEloffpeak or securing a
4.3. Other benefits of BES cheaper source of charging the BES might be required to further
improve on the prospect of profitability. The option of lowering
Peak shaving using BES provides other techno-economic and PrEloffpeak , which might not suffice as a policy tool, calls for
environmental benefits. The environmental benefit majorly lies in consideration of alternative sources of energy which might be
the avoided high coal consumption required during the peak period cheaper to charge the BES and also meet load demand during peak.
and the environmental pollution associated. For using BES to shave For this, the authors recommend considerations of solar PV and
40% peak of the student residence under study, the life time benefit wind energy. The current rate of technology improvement of these
to the grid for power quality management was 8577 $ and for RE sources, reduction in the cost of acquiring them and increase in
transmission and distribution deferral was 74,332 $. The lifetime PrElpeak in South Africa suggest that grid parity between conven-
benefit for the three BES are the same as they are designed to tional and RE sources is imminent.
produce 22.09 kWh of energy irrespective of their construction
chemistry. However, the three technologies offer different envi- Acknowledgement
ronmental benefits with Li-ion having the highest environmental
benefit, that is 24.07 ton CSavings , 62.58 ton CO2; Avoided , 5.54 kg The authors wish to acknowledge the University of Johannes-
COAvoided , 19.25 kg SO2; Avoided and 3.18 kg NOx; Avoided though it had burg-University Research Committee for providing grants for this
the highest emission during manufacturing based on a 12.5 kg research work [UJ-URC-201339837].
CO2,eq./kg weight of battery. The high net environmental perfor-
mance of Li-ion BES is due to its high cycling efficiency, as it re- References
quires less energy from the grid to charge the battery to the
[1] IEA. Worl energy outlook. France: International Energy Agency; 2013.
required capacity. On the other hand, PbA battery had the least [2] Becker B, Fischer D. Promoting renewable electricity generation in emerging
environmental benefit as shown in Table 4. The environmental economies. Energy Policy 5//2013;56:446e55.
impact of disposal of the BES was not considered in this study. This [3] Aboyade AO, Carrier M, Meyer EL, Knoetze H, Go € rgens JF. Slow and pressur-
ized co-pyrolysis of coal and agricultural residues. Energy Convers Manag 1//
2013;65:198e207.
[4] National Treasury. Electricity. Pretoria, South Africa: Department of National
Table 4 Treasury; 2011.
Technical and environmental Benefit of peak shaving. [5] Pegels A. Renewable energy in South Africa: potentials, barriers and options
for support. Energy Policy May 2010;38:10.
PbA NaS Li-ion
[6] Eskom. Integrated report 2012. Johannesburg: Eskom; 2012.
Elquality ($) 8577 8577 8577 [7] Eskom. Integrated report 2014. Johannesburg: Eskom; 2014.
Gridcap_ut ($) 74,332 74,332 74,332 [8] DoE. State of renewable energy in South Africa. Pretoria: Department of En-
Coal Required (ton) 0.31 0.07 1.1 ergy; 2015.
Coal Saving (ton) 7.11 16.37 24.07 [9] Yang P, Tang G, Nehorai A. A game-theoretic approach for optimal time-of-use
electricity pricing. IEEE Trans Power Syst 2013;28:9.
Reduced CO2 emission (ton) 18.48 42.57 62.58
[10] Badtke-Berkow M, Centore M, Mohlin K, Spiller B. Making the most of time-
Reduced CO emission (kg) 1.63 3.77 5.54
variant electricity pricing. Environmental Defense Fund, Environmental
Reduced SO2 emission (kg) 5.69 13.10 19.25
Defence Fund; 2015.
Reduced NOx emission (kg) 0.94 2.16 3.18 [11] Battke B, Schmidt TS, Grosspietsch D, Hoffmann VH. A review and probabi-
listic model of lifecycle costs of stationary batteries in multiple applications.
S.O. Masebinu et al. / Energy 135 (2017) 413e429 429

Renew Sustain Energy Rev 9//2013;25:240e50. [36] Dufo-Lopez R, Bernal-Agustín JL. Techno-economic analysis of grid-connected
[12] Palizban O, Kauhaniemi K. Energy storage systems in modern gridsdmatrix of battery storage. Energy Convers Manag 2//2015;91:394e404.
technologies and applications. J Energy Storage 5//2016;6:248e59. [37] Sustainable. Solar power, online eco store. 1/05/2016. 2016. Available:, http://
[13] Aneke M, Wang M. Energy storage technologies and real life applications e a www.sustainable.co.za/.
state of the art review. Appl Energy 10/1/2016;179:350e77. [38] Dufo-Lopez R, Bernal-Agustin JL. Design and control strategies of PV-Diesel
[14] Zafirakis D, Elmasides C, Sauer DU, Leuthold M, Merei G, Kaldellis JK, et al. The systems using genetic algorithms. Sol Energy 2005;79:14.
multiple role of energy storage in the industrial sector: evidence from a Greek [39] Dufo-Lopez R. Optimisation of size and control of grid-connected storage
industrial facility. Energy Procedia 01/01 2014;46:178e85. under real time electricity pricing conditions. Appl Energy 2015;140:14.
[15] Lin B, Wu W. Economic viability of battery energy storage and grid strategy: a [40] Okundamiya MS, Emagbetere JO, Ogujo EA. Techno-Economic analysis of a
special case of China electricity market. Energy 4/1/2017;124:423e34. grid-connected hybrid energy system for developing regions. Iran J Energy
[16] Tong S, Fung T, Klein MP, Weisbach DA, Park JW. Demonstration of reusing Environ 31 Aug 2015;6:12.
electric vehicle battery for solar energy storage and demand side manage- [41] Dufo-Lopez R, Bernal-Agustin JL. A comparative assessment of net metering
ment. J Energy Storage 6//2017;11:200e10. and net billing policies. Study cases for Spain. Energy 2015;84:10.
[17] Aguado JA, de la Torre S, Trivin ~ o A. Battery energy storage systems in trans- [42] Darling SB, You F, Veselka T, Velosa A. Assumptions and the levelized cost of
mission network expansion planning. Electr Power Syst Res 4//2017;145: energy for photovoltaics. Energy Environ Sci 2011;4:3133.
63e72. [43] Chen H, Cong TN, Yang W, Tan C, Li Y, Ding Y. Progress in electrical energy
[18] Kerdphol T, Qudaih Y, Mitani Y. Optimum battery energy storage system using storage system: a critical review. Progr. Nat Sci 3/10/2009;19:291e312.
PSO considering dynamic demand response for microgrids. Int J Electr Power [44] Díaz-Gonza lez F, Sumper A, Gomis-Bellmunt O, Villaf afila-Robles R. A review
& Energy Syst 12//2016;83:58e66. of energy storage technologies for wind power applications. Renew Sustain
[19] Kyriakopoulos GL, Arabatzis G. Electrical energy storage systems in electricity Energy Rev 5//2012;16:2154e71.
generation: energy policies, innovative technologies, and regulatory regimes. [45] Evans A, Strezov V, Evans TJ. Assessment of utility energy storage options for
Renew Sustain Energy Rev 4//2016;56:1044e67. increased renewable energy penetration. Renew Sustain Energy Rev 8//
[20] Barbour E, Wilson IAG, Radcliffe J, Ding Y, Li Y. A review of pumped hydro 2012;16:4141e7.
energy storage development in significant international electricity markets. [46] Hadjipaschalis I, Poullikkas A, Efthimiou V. Overview of current and future
Renew Sustain Energy Rev 8//2016;61:421e32. energy storage technologies for electric power applications. Renew Sustain
[21] Mandelli S, Brivio C, Leonardi M, Colombo E, Molinas M, Park E, et al. The role Energy Rev 8//2009;13:1513e22.
of electrical energy storage in sub-Saharan Africa. J Energy Storage 11// [47] Ibrahim H, Ilinca A. Techno-economic analysis of different energy storage
2016;8:287e99. technologies. In: Zobaa AF, editor. Energy storage, technology and application.
[22] Langley P. Eskom LSES facility. In: Africa utility week: clean power Africa. Cape InTech; 2013. p. 40.
Town, South Africa: Eskom; 2015. p. 20. [48] Ibrahim H, Ilinca A, Perron J. Energy storage systemsdcharacteristics and
[23] Zakeri B, Syri S. Electrical energy storage systems: a comparative life cycle cost comparisons. Renew Sustain Energy Rev 6//2008;12:1221e50.
analysis. Renew Sustain Energy Rev 7 Nov 2015;42:28. [49] Karellas S, Tzouganatos N. Comparison of the performance of compressed-air
[24] Baumann M, Zimmermann B, Dura H, Simon B, Weil M. A comparative and hydrogen energy storage systems: karpathos island case study. Renew
probabilistic economic analysis of selected stationary battery systems for grid Sustain Energy Rev 1//2014;29:865e82.
applications. IEEE Electr Power Energy Conf 2013:6. [50] Makansi J, Abboud J. Energy storage: the missing link in the electricity value
[25] Kaldellis JK, Zafirakis D, Kavadias K. Techno-economic comparison of energy chain. Energy Storage Council; 2002.
storage systems for island autonomous electrical networks. Renew Sustain [51] Parker CD. Leadeacid battery energy-storage systems for electricity supply
Energy Rev 2//2009;13:378e92. networks. J Power Sources 11/30/2001;100:18e28.
[26] Dufo-Lopez R, Bernal-Agustin JL. Techno-economic analysis fo grid-connected [52] Dubarry M, Devie A, Stein K, Tun M, Matsuura M, Rocheleau R. Battery Energy
battery storage. Energy Convers Manag 2015;2015:11. Storage System battery durability and reliability under electric utility grid
[27] Yan X, Zhang X, Chen H, Xu Y, Tan C. Techno-economic and social analysis of operations: analysis of 3 years of real usage. J Power Sources 1/15/2017;338:
energy storage for commercial buildings. Energy Convers Manag 2//2014;78: 65e73.
125e36. [53] Mahela OP, Shaik AG. Power quality improvement in distribution network
[28] Gildemeister. CellCube-a storage system based on vanadium redox flow using DSTATCOM with battery energy storage system. Int J Electr Power &
technology. Germany: gildemeister energy solutions GmbH; 2015. Energy Syst 12//2016;83:229e40.
[29] Safaei H, Keith D. How much bulk energy storage is needed to decarbonize [54] Koohi-Kamali S, Rahim NA. Coordinated control of smart microgrid during
electricity. Energy Environ Sci 2015;8:9. and after islanding operation to prevent under frequency load shedding using
[30] Hessami MA, Bowly DR. Economic feasibility and optimization of an energy energy storage system. Energy Convers Manag 11/1/2016;127:623e46.
storage system for Portland wind farm (Victoria, Australia). Appl Energy [55] Bakar NNA, Hassan MY, Sulaima MF, Mohd Nasir MNI, Khamis A. Microgrid
2011;2011:9. and load shedding scheme during islanded mode: a review. Renew Sustain
[31] Okundamiya MS, Emagbetere JO, Ogujo EA. Techno-Economic analysis of a Energy Rev 5//2017;71:161e9.
grid-connected hybrid energy system for developing regions. Iran J Energy [56] Schoenung SM, Eyer J. Benefit/Cost framework for evaluating modular energy
Environ 31 Aug 2015;6:12. storage. California: Sandia National Laboratories; 2008.
[32] Homer Energy. Homer Pro. version 3.7 user manual. 2016. Homer Energy. [57] Nkomo JC. Energy and economic development: challenges for South Africa.
[33] Homer Energy. Load noise. 03/04/2016. 2015. Available:, http://usersupport. J Energy South Afr 2005;16:11.
homerenergy.com/customer/en/portal/articles/2188767-load-noise. [58] McManus MC. Environmental consequences of the use of batteries in low
[34] Boait P, Advani V, Gammon R. Estimation of demand diversity and daily de- carbon systems: the impact of battery production. Appl Energy 5//2012;93:
mand profile for off-grid electrification in developing countries. Energy Sus- 288e95.
tain Dev 12//2015;29:135e41. [59] Eurostat. Electricity price statistic. 22/06/2016. 2016. Available:, http://ec.
[35] Okundamiya MS, Emagbetere JO, Ogujo EA. Evaluation of various global solar europa.eu/eurostat/statistics-explained/index.php/Electricity_price_statistics.
radiation models for Nigeria. Int J Green Energy 2016;13:8.

You might also like